81_FR_59783 81 FR 59615 - Gulf South Pipeline Company, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed St. Charles Parish Expansion Project and Request for Comments on Environmental Issues

81 FR 59615 - Gulf South Pipeline Company, LP; Notice of Intent To Prepare an Environmental Assessment for the Proposed St. Charles Parish Expansion Project and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 168 (August 30, 2016)

Page Range59615-59617
FR Document2016-20752

Federal Register, Volume 81 Issue 168 (Tuesday, August 30, 2016)
[Federal Register Volume 81, Number 168 (Tuesday, August 30, 2016)]
[Notices]
[Pages 59615-59617]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-20752]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP16-478-000]


Gulf South Pipeline Company, LP; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed St. Charles Parish Expansion 
Project and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the St. Charles Parish Expansion 
Project (Project) involving construction and operation of natural gas 
pipeline and compression facilities by Gulf South Pipeline Company, LP 
(Gulf South) in St. Charles and St. John the Baptist Parishes, 
Louisiana. The Commission will use this EA in its decision-making 
process to determine whether the Project is in the public convenience 
and.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the Project. You can make a difference by providing us with 
your specific comments or concerns about the Project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before September 23, 2016.
    If you sent comments on this Project to the Commission before the 
opening of this docket July 11, 2016, you will need to file those 
comments in Docket No. CP16-478-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this Project. State and local government 
representatives should notify their constituents of this proposed 
Project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the Project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Gulf South provided landowners with a fact sheet prepared by the 
FERC entitled ``An Interstate Natural Gas Facility On My Land? What Do 
I Need To Know?'' This fact sheet addresses a number of typically asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for viewing on 
the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP16-478-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Gulf South plans to begin construction of the Project in the fall 
of 2017 and place the facilities in-service by September 1, 2018. The 
Project purpose is to provide 133,333 dekatherms per day to serve 
Entergy Louisiana, LLC's proposed natural gas-fired power plant 
facility located near Montz, Louisiana.
    Specifically, Gulf South proposes to construct:
     A new 5,000 horsepower compressor station near Montz, 
Louisiana (Montz Compressor Station);
     about 900 feet of new 16-inch-diameter pipeline; and
     auxiliary facilities.
    The proposed Montz Compressor Station would be on the border of St. 
Charles and St. John the Baptist Parishes and would include two CAT 
G3608 A4 engines and Erial JGK/6 compressor units, housed in a 
permanent building. The proposed pipeline would commence at the Montz 
Compressor Station, extend approximately 900 feet southeast, and 
terminate at Gulf South's existing Index 270-94 Lateral in St.

[[Page 59616]]

Charles Parish, Louisiana. Gulf South would co-locate the proposed 16-
inch-pipeline with its existing Index 270 pipeline right-of-way. 
Installation of the proposed pipeline would utilize a 135-foot-wide 
temporary construction right-of-way. Following construction, Gulf South 
proposes to maintain a 35-foot-wide permanent right-of-way along the 
pipeline route, adjacent to the existing Index 270 permanent right-of-
way.
    The general location of the Project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called ``eLibrary'' or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would disturb about 13.9 
acres of land for the aboveground facilities, pipeline, and two 
permanent access roads. Following construction, Gulf South would 
maintain about 3.5 acres for permanent operation of the Project's 
facilities; the remaining acreage would be restored and revert to 
former uses.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed Project under these 
general headings:
     Geology and soils;
     land use;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation and wildlife;
     air quality and noise;
     endangered and threatened species;
     public safety;
     socioeconomics; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the proposed 
Project or portions of the Project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this Project to formally cooperate with us in the preparation of the 
EA.\3\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the Project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the Project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this Project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries. This list also includes all 
affected landowners (as defined in the Commission's regulations) who 
are potential right-of-way grantors, whose property may be used 
temporarily for project purposes, or who own homes within certain 
distances of aboveground facilities, and anyone who submits comments on 
the project. We will update the environmental mailing list as the 
analysis proceeds to ensure that we send the information related to 
this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed Project.
    If we publish and distribute the EA, copies of the EA will be sent 
to the environmental mailing list for public review and comment. If you 
would prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the Project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number

[[Page 59617]]

field (i.e., CP16-478). Be sure you have selected an appropriate date 
range. For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: August 24, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-20752 Filed 8-29-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 81, No. 168 / Tuesday, August 30, 2016 / Notices                                             59615

                                                     Docket Numbers: ER16–2475–000.                       Pipeline Company, LP (Gulf South) in                  Public Participation
                                                     Applicants: Gulf Power Company.                      St. Charles and St. John the Baptist                     For your convenience, there are three
                                                     Description: Tariff Cancellation:                    Parishes, Louisiana. The Commission                   methods you can use to submit your
                                                  Termination of UPS Agreements to be                     will use this EA in its decision-making               comments to the Commission. The
                                                  effective 12/31/2011.                                   process to determine whether the                      Commission encourages electronic filing
                                                     Filed Date: 8/24/16.                                 Project is in the public convenience                  of comments and has expert staff
                                                     Accession Number: 20160824–5170.                     and.                                                  available to assist you at (202) 502–8258
                                                     Comments Due: 5 p.m. ET 9/14/16.                        This notice announces the opening of               or efiling@ferc.gov. Please carefully
                                                     Docket Numbers: ER16–2476–000.                       the scoping process the Commission                    follow these instructions so that your
                                                     Applicants: Mississippi Power                        will use to gather input from the public              comments are properly recorded.
                                                  Company.                                                and interested agencies on the Project.                  (1) You can file your comments
                                                     Description: Tariff Cancellation:                    You can make a difference by providing                electronically using the eComment
                                                  Termination of UPS Agreements to be                     us with your specific comments or                     feature on the Commission’s Web site
                                                  effective 12/31/2011.                                   concerns about the Project. Your                      (www.ferc.gov) under the link to
                                                     Filed Date: 8/24/16.                                 comments should focus on the potential                Documents and Filings. This is an easy
                                                     Accession Number: 20160824–5173.                     environmental effects, reasonable                     method for submitting brief, text-only
                                                     Comments Due: 5 p.m. ET 9/14/16.                     alternatives, and measures to avoid or                comments on a project;
                                                     The filings are accessible in the                    lessen environmental impacts. Your                       (2) You can file your comments
                                                  Commission’s eLibrary system by                         input will help the Commission staff                  electronically by using the eFiling
                                                  clicking on the links or querying the                   determine what issues they need to                    feature on the Commission’s Web site
                                                  docket number.                                          evaluate in the EA. To ensure that your               (www.ferc.gov) under the link to
                                                     Any person desiring to intervene or                  comments are timely and properly                      Documents and Filings. With eFiling,
                                                  protest in any of the above proceedings                 recorded, please send your comments so                you can provide comments in a variety
                                                  must file in accordance with Rules 211                  that the Commission receives them in                  of formats by attaching them as a file
                                                  and 214 of the Commission’s                             Washington, DC on or before September                 with your submission. New eFiling
                                                  Regulations (18 CFR 385.211 and                         23, 2016.                                             users must first create an account by
                                                  385.214) on or before 5:00 p.m. Eastern                    If you sent comments on this Project               clicking on ‘‘eRegister.’’ If you are filing
                                                  time on the specified comment date.                     to the Commission before the opening of               a comment on a particular project,
                                                  Protests may be considered, but                         this docket July 11, 2016, you will need              please select ‘‘Comment on a Filing’’ as
                                                  intervention is necessary to become a                   to file those comments in Docket No.                  the filing type; or
                                                  party to the proceeding.                                CP16–478–000 to ensure they are                          (3) You can file a paper copy of your
                                                     eFiling is encouraged. More detailed                 considered as part of this proceeding.                comments by mailing them to the
                                                  information relating to filing                                                                                following address. Be sure to reference
                                                  requirements, interventions, protests,                     This notice is being sent to the
                                                                                                          Commission’s current environmental                    the project docket number (CP16–478–
                                                  service, and qualifying facilities filings                                                                    000) with your submission: Kimberly D.
                                                  can be found at: http://www.ferc.gov/                   mailing list for this Project. State and
                                                                                                          local government representatives should               Bose, Secretary, Federal Energy
                                                  docs-filing/efiling/filing-req.pdf. For                                                                       Regulatory Commission, 888 First Street
                                                  other information, call (866) 208–3676                  notify their constituents of this
                                                                                                          proposed Project and encourage them to                NE., Room 1A, Washington, DC 20426.
                                                  (toll free). For TTY, call (202) 502–8659.
                                                                                                          comment on their areas of concern.                    Summary of the Proposed Project
                                                    Dated: August 24, 2016.
                                                                                                             If you are a landowner receiving this                 Gulf South plans to begin
                                                  Kimberly D. Bose,
                                                                                                          notice, a pipeline company                            construction of the Project in the fall of
                                                  Secretary.
                                                                                                          representative may contact you about                  2017 and place the facilities in-service
                                                  [FR Doc. 2016–20756 Filed 8–29–16; 8:45 am]             the acquisition of an easement to                     by September 1, 2018. The Project
                                                  BILLING CODE 6717–01–P                                  construct, operate, and maintain the                  purpose is to provide 133,333
                                                                                                          proposed facilities. The company would                dekatherms per day to serve Entergy
                                                                                                          seek to negotiate a mutually acceptable               Louisiana, LLC’s proposed natural gas-
                                                  DEPARTMENT OF ENERGY                                    agreement. However, if the Commission                 fired power plant facility located near
                                                  Federal Energy Regulatory                               approves the Project, that approval                   Montz, Louisiana.
                                                  Commission                                              conveys with it the right of eminent                     Specifically, Gulf South proposes to
                                                                                                          domain. Therefore, if easement                        construct:
                                                  [Docket No. CP16–478–000]                               negotiations fail to produce an                          • A new 5,000 horsepower
                                                                                                          agreement, the pipeline company could                 compressor station near Montz,
                                                  Gulf South Pipeline Company, LP;                        initiate condemnation proceedings
                                                  Notice of Intent To Prepare an                                                                                Louisiana (Montz Compressor Station);
                                                                                                          where compensation would be                              • about 900 feet of new 16-inch-
                                                  Environmental Assessment for the                        determined in accordance with state
                                                  Proposed St. Charles Parish                                                                                   diameter pipeline; and
                                                                                                          law.                                                     • auxiliary facilities.
                                                  Expansion Project and Request for
                                                  Comments on Environmental Issues                           Gulf South provided landowners with                   The proposed Montz Compressor
                                                                                                          a fact sheet prepared by the FERC                     Station would be on the border of St.
                                                    The staff of the Federal Energy                       entitled ‘‘An Interstate Natural Gas                  Charles and St. John the Baptist Parishes
                                                  Regulatory Commission (FERC or                          Facility On My Land? What Do I Need                   and would include two CAT G3608 A4
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Commission) will prepare an                             To Know?’’ This fact sheet addresses a                engines and Erial JGK/6 compressor
                                                  environmental assessment (EA) that will                 number of typically asked questions,                  units, housed in a permanent building.
                                                  discuss the environmental impacts of                    including the use of eminent domain                   The proposed pipeline would
                                                  the St. Charles Parish Expansion Project                and how to participate in the                         commence at the Montz Compressor
                                                  (Project) involving construction and                    Commission’s proceedings. It is also                  Station, extend approximately 900 feet
                                                  operation of natural gas pipeline and                   available for viewing on the FERC Web                 southeast, and terminate at Gulf South’s
                                                  compression facilities by Gulf South                    site (www.ferc.gov).                                  existing Index 270–94 Lateral in St.


                                             VerDate Sep<11>2014   20:04 Aug 29, 2016   Jkt 238001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\30AUN1.SGM   30AUN1


                                                  59616                        Federal Register / Vol. 81, No. 168 / Tuesday, August 30, 2016 / Notices

                                                  Charles Parish, Louisiana. Gulf South                      • socioeconomics; and                                  the impacts on historic properties and
                                                  would co-locate the proposed 16-inch-                      • cumulative impacts.                                  summarize the status of consultations
                                                  pipeline with its existing Index 270                       We will also evaluate reasonable                       under section 106.
                                                  pipeline right-of-way. Installation of the              alternatives to the proposed Project or
                                                                                                          portions of the Project, and make                         Environmental Mailing List
                                                  proposed pipeline would utilize a 135-
                                                  foot-wide temporary construction right-                 recommendations on how to lessen or                          The environmental mailing list
                                                  of-way. Following construction, Gulf                    avoid impacts on the various resource                     includes federal, state, and local
                                                  South proposes to maintain a 35-foot-                   areas.                                                    government representatives and
                                                  wide permanent right-of-way along the                      The EA will present our independent                    agencies; elected officials;
                                                  pipeline route, adjacent to the existing                analysis of the issues. The EA will be                    environmental and public interest
                                                  Index 270 permanent right-of-way.                       available in the public record through                    groups; Native American Tribes; other
                                                    The general location of the Project                   eLibrary. Depending on the comments                       interested parties; and local libraries.
                                                  facilities is shown in appendix 1.1                     received during the scoping process, we                   This list also includes all affected
                                                                                                          may also publish and distribute the EA                    landowners (as defined in the
                                                  Land Requirements for Construction                      to the public for an allotted comment                     Commission’s regulations) who are
                                                    Construction of the proposed facilities               period. We will consider all comments                     potential right-of-way grantors, whose
                                                  would disturb about 13.9 acres of land                  on the EA before making our                               property may be used temporarily for
                                                  for the aboveground facilities, pipeline,               recommendations to the Commission.                        project purposes, or who own homes
                                                  and two permanent access roads.                         To ensure we have the opportunity to                      within certain distances of aboveground
                                                  Following construction, Gulf South                      consider and address your comments,                       facilities, and anyone who submits
                                                  would maintain about 3.5 acres for                      please carefully follow the instructions                  comments on the project. We will
                                                  permanent operation of the Project’s                    in the Public Participation section,                      update the environmental mailing list as
                                                  facilities; the remaining acreage would                 beginning on page 2.                                      the analysis proceeds to ensure that we
                                                  be restored and revert to former uses.                     With this notice, we are asking                        send the information related to this
                                                                                                          agencies with jurisdiction by law and/                    environmental review to all individuals,
                                                  The EA Process                                          or special expertise with respect to the                  organizations, and government entities
                                                     The National Environmental Policy                    environmental issues of this Project to                   interested in and/or potentially affected
                                                  Act (NEPA) requires the Commission to                   formally cooperate with us in the                         by the proposed Project.
                                                  take into account the environmental                     preparation of the EA.3 Agencies that                        If we publish and distribute the EA,
                                                  impacts that could result from an action                would like to request cooperating                         copies of the EA will be sent to the
                                                  whenever it considers the issuance of a                 agency status should follow the                           environmental mailing list for public
                                                  Certificate of Public Convenience and                   instructions for filing comments                          review and comment. If you would
                                                  Necessity. NEPA also requires us 2 to                   provided under the Public Participation                   prefer to receive a paper copy of the
                                                  discover and address concerns the                       section of this notice.                                   document instead of the CD version or
                                                  public may have about proposals. This                   Consultations Under Section 106 of the                    would like to remove your name from
                                                  process is referred to as ‘‘scoping.’’ The              National Historic Preservation Act                        the mailing list, please return the
                                                  main goal of the scoping process is to                                                                            attached Information Request (appendix
                                                                                                            In accordance with the Advisory                         2).
                                                  focus the analysis in the EA on the
                                                                                                          Council on Historic Preservation’s
                                                  important environmental issues. By this                                                                           Becoming an Intervenor
                                                                                                          implementing regulations for section
                                                  notice, the Commission requests public
                                                                                                          106 of the National Historic                                 In addition to involvement in the EA
                                                  comments on the scope of the issues to
                                                                                                          Preservation Act, we are using this                       scoping process, you may want to
                                                  address in the EA. We will consider all
                                                                                                          notice to initiate consultation with the                  become an ‘‘intervenor’’ which is an
                                                  filed comments during the preparation
                                                                                                          applicable State Historic Preservation                    official party to the Commission’s
                                                  of the EA.
                                                                                                          Office (SHPO), and to solicit their views                 proceeding. Intervenors play a more
                                                     In the EA we will discuss impacts that
                                                                                                          and those of other government agencies,                   formal role in the process and are able
                                                  could occur as a result of the
                                                                                                          interested Indian tribes, and the public                  to file briefs, appear at hearings, and be
                                                  construction and operation of the
                                                                                                          on the Project’s potential effects on                     heard by the courts if they choose to
                                                  proposed Project under these general
                                                                                                          historic properties.4 We will define the                  appeal the Commission’s final ruling.
                                                  headings:
                                                     • Geology and soils;                                 project-specific Area of Potential Effects                An intervenor formally participates in
                                                     • land use;                                          (APE) in consultation with the SHPO as                    the proceeding by filing a request to
                                                     • water resources, fisheries, and                    the Project develops. On natural gas                      intervene. Instructions for becoming an
                                                  wetlands;                                               facility projects, the APE at a minimum                   intervenor are in the ‘‘Document-less
                                                     • cultural resources;                                encompasses all areas subject to ground                   Intervention Guide’’ under the ‘‘e-filing’’
                                                     • vegetation and wildlife;                           disturbance (examples include                             link on the Commission’s Web site.
                                                     • air quality and noise;                             construction right-of-way, contractor/                    Motions to intervene are more fully
                                                     • endangered and threatened species;                 pipe storage yards, compressor stations,                  described at http://www.ferc.gov/
                                                     • public safety;                                     and access roads). Our EA for this                        resources/guides/how-to/intervene.asp.
                                                                                                          Project will document our findings on
                                                    1 The appendices referenced in this notice will
                                                                                                                                                                    Additional Information
                                                  not appear in the Federal Register. Copies of             3 The  Council on Environmental Quality                    Additional information about the
                                                  appendices were sent to all those receiving this        regulations addressing cooperating agency                 Project is available from the
mstockstill on DSK3G9T082PROD with NOTICES




                                                  notice in the mail and are available at www.ferc.gov    responsibilities are at Title 40, Code of Federal
                                                  using the link called ‘‘eLibrary’’ or from the          Regulations, Part 1501.6.                                 Commission’s Office of External Affairs,
                                                  Commission’s Public Reference Room, 888 First             4 The Advisory Council on Historic Preservation’s       at (866) 208–FERC, or on the FERC Web
                                                  Street NE., Washington, DC 20426, or call (202)         regulations are at Title 36, Code of Federal              site at www.ferc.gov using the
                                                  502–8371. For instructions on connecting to             Regulations, Part 800. Those regulations define           ‘‘eLibrary’’ link. Click on the eLibrary
                                                  eLibrary, refer to the last page of this notice.        historic properties as any prehistoric or historic
                                                    2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the            district, site, building, structure, or object included
                                                                                                                                                                    link, click on ‘‘General Search’’ and
                                                  environmental staff of the Commission’s Office of       in or eligible for inclusion in the National Register     enter the docket number, excluding the
                                                  Energy Projects.                                        of Historic Places.                                       last three digits in the Docket Number


                                             VerDate Sep<11>2014   20:04 Aug 29, 2016   Jkt 238001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\30AUN1.SGM     30AUN1


                                                                               Federal Register / Vol. 81, No. 168 / Tuesday, August 30, 2016 / Notices                                                 59617

                                                  field (i.e., CP16–478). Be sure you have                   Description: Request of the North                  November 10, 2016, 10:00 a.m.–5:00
                                                  selected an appropriate date range. For                 American Electric Reliability                           p.m. (EST)
                                                  assistance, please contact FERC Online                  Corporation for Acceptance of its 2017                Doubletree Hotel, 5400 Computer Drive,
                                                  Support at FercOnlineSupport@ferc.gov                   Business Plan and Budget.                               Westborough, MA 01581
                                                  or toll free at (866) 208–3676, or for                     Filed Date: 8/23/16.
                                                                                                             Accession Number: 20160823–5166.                   December 2, 2016, 10:00 a.m.–5:00 p.m.
                                                  TTY, contact (202) 502–8659. The
                                                                                                             Comments Due: 5 p.m. ET 9/13/16.                     (EST)
                                                  eLibrary link also provides access to the
                                                  texts of formal documents issued by the                    The filings are accessible in the                  Colonnade Seaport Hotel, 120
                                                  Commission, such as orders, notices,                    Commission’s eLibrary system by                         Huntington Ave, Boston, MA 02116
                                                  and rulemakings.                                        clicking on the links or querying the                    Further information may be found at
                                                     In addition, the Commission offers a                 docket number.                                        www.nepool.com/IMAPP.php.
                                                  free service called eSubscription which                    Any person desiring to intervene or                   The discussion at the meeting
                                                  allows you to keep track of all formal                  protest in any of the above proceedings               described above may address matters at
                                                  issuances and submittals in specific                    must file in accordance with Rules 211                issue in the following proceedings:
                                                  dockets. This can reduce the amount of                  and 214 of the Commission’s
                                                  time you spend researching proceedings                                                                        Docket Nos. EL13–33 and EL 14–86,
                                                                                                          Regulations (18 CFR 385.211 and
                                                  by automatically providing you with                                                                             Environment Northeast et al. v.
                                                                                                          385.214) on or before 5:00 p.m. Eastern
                                                  notification of these filings, document                                                                         Bangor Hydro-Electric Company et al.
                                                                                                          time on the specified comment date.
                                                  summaries, and direct links to the                      Protests may be considered, but                       Docket No. EL16–19, ISO New England
                                                  documents. Go to www.ferc.gov/docs-                     intervention is necessary to become a                   Inc. Participating Transmission
                                                  filing/esubscription.asp.                               party to the proceeding.                                Owners Administrative Committee
                                                     Finally, public meetings or site visits                 eFiling is encouraged. More detailed               Docket No. EL16–38, Dominion Energy
                                                  will be posted on the Commission’s                      information relating to filing                          Marketing, Inc. et al. v. ISO New
                                                  calendar located at www.ferc.gov/                       requirements, interventions, protests,                  England Inc.
                                                  EventCalendar/EventsList.aspx along                     service, and qualifying facilities filings            Docket No. EL16–93, NextEra Energy
                                                  with other related information.                         can be found at: http://www.ferc.gov/                   Resources, LLC and PSEG Companies
                                                    Dated: August 24, 2016.                               docs-filing/efiling/filing-req.pdf. For                 v. ISO New England Inc.
                                                  Kimberly D. Bose,                                       other information, call (866) 208–3676                Docket No. RP16–618, Algonquin Gas
                                                  Secretary.                                              (toll free). For TTY, call (202) 502–8659.              Transmission, LLC
                                                  [FR Doc. 2016–20752 Filed 8–29–16; 8:45 am]               Dated: August 24, 2016.                             Docket No. ER12–1650, Emera Maine
                                                  BILLING CODE 6717–01–P                                  Kimberly D. Bose,                                     Docket No. ER14–1409, ISO New
                                                                                                          Secretary.                                              England Inc.
                                                                                                          [FR Doc. 2016–20751 Filed 8–29–16; 8:45 am]           Docket No. ER14–1639, ISO New
                                                  DEPARTMENT OF ENERGY                                    BILLING CODE 6717–01–P                                  England Inc. and New England Power
                                                                                                                                                                  Pool Participants Committee
                                                  Federal Energy Regulatory
                                                  Commission                                                                                                    Docket No. ER13–2266, ISO New
                                                                                                          DEPARTMENT OF ENERGY                                    England Inc.
                                                  Combined Notice of Filings #2                                                                                 Docket No. ER15–1429, Emera Maine
                                                                                                          Federal Energy Regulatory
                                                     Take notice that the Commission                      Commission                                            Docket No. ER16–551, ISO New England
                                                  received the following exempt                                                                                   Inc.
                                                  wholesale generator filings:                            Notice of Commission Staff                            Docket No. ER16–1301, ISO New
                                                     Docket Numbers: EG16–140–000.                        Attendance                                              England Inc. and Emera Maine
                                                     Applicants: Astra Wind LLC.                            The Federal Energy Regulatory                       Docket No. ER16–1041, ISO New
                                                     Description: Self-Certification of EG of             Commission (Commission) hereby gives                    England Inc.
                                                  Astra Wind LLC.                                         notice that members of the                            Docket No. ER16–1904, ISO New
                                                     Filed Date: 8/22/16.                                 Commission’s staff may attend the                       England Inc.
                                                     Accession Number: 20160822–5275.                                                                           Docket No. ER16–2126, ISO New
                                                     Comments Due: 5 p.m. ET 9/12/16.                     following meetings related to the
                                                                                                          wholesale markets of ISO New England                    England Inc. and New England Power
                                                     Take notice that the Commission                                                                              Pool Participants Committee
                                                                                                          Inc.:
                                                  received the following electric rate
                                                                                                          Integrating Markets and Public Policy                 Docket No. ER16–2215, ISO New
                                                  filings:
                                                                                                                                                                  England Inc.
                                                     Docket Numbers: ER16–2453–000.                       August 30, 2016, 10:00 a.m.–4:30 p.m.
                                                     Applicants: Brady Interconnection,                                                                         Docket No. ER16–2283, Genbright LLC
                                                                                                            (EST)
                                                  LLC.                                                                                                          Docket No. ER16–2451, ISO New
                                                                                                          Seaport Hotel, One Seaport Lane,
                                                     Description: Baseline eTariff Filing:                                                                        England Inc. and New England Power
                                                                                                            Boston, MA 02110
                                                  Brady Interconnection, LLC Application                                                                          Pool Participants Committee
                                                  for market-Based Rates to be effective                  September 14, 2016, 10:00 a.m.–5:00
                                                                                                            p.m. (EST)                                            For more information, contact
                                                  10/18/2016.                                                                                                   Michael Cackoski, Office of Energy
                                                     Filed Date: 8/19/16.                                 Doubletree Hotel, 5400 Computer Drive,
                                                                                                            Westborough, MA 01581                               Market Regulation, Federal Energy
                                                     Accession Number: 20160819–5300.
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                                                                                Regulatory Commission at (202) 502–
                                                     Comments Due: 5 p.m. ET 9/9/16.                      October 6, 2016, 10:00 a.m.–5:00 p.m.
                                                                                                                                                                6169 or Michael.Cackoski@ferc.gov.
                                                     Take notice that the Commission                        (EST)
                                                  received the following electric                         Doubletree Hotel, 5400 Computer Drive,                  Dated: August 24, 2016.
                                                  reliability filings:                                      Westborough, MA 01581                               Kimberly D. Bose,
                                                     Docket Numbers: RR16–6–000.                          October 21, 2016, 10:00 a.m.–5:00 p.m.                Secretary.
                                                     Applicants: North American Electric                    (EST)                                               [FR Doc. 2016–20754 Filed 8–29–16; 8:45 am]
                                                  Reliability Corporation.                                Location to be determined.                            BILLING CODE 6717–01–P




                                             VerDate Sep<11>2014   20:04 Aug 29, 2016   Jkt 238001   PO 00000   Frm 00021   Fmt 4703   Sfmt 9990   E:\FR\FM\30AUN1.SGM   30AUN1



Document Created: 2018-02-09 11:42:01
Document Modified: 2018-02-09 11:42:01
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 59615 