The U.S. Nuclear Regulatory Commission (NRC) has granted the request of the Omaha Public Power District (the licensee) to withdraw its license amendment application dated April 4, 2016, for a proposed amendment to Renewed Facility Operating License No. DPR-40 for the Fort Calhoun Station, Unit No. 1 (FCS). The proposed amendment would have modified License Condition D, Fire Protection Program, by withdrawing the commitments in REC-119 and REC-120 to implement certain plant modifications as stated in License Condition Paragraph 3.D.(3)(b).

Federal Register, Volume 81 Issue 168 (Tuesday, August 30, 2016)
[Federal Register Volume 81, Number 168 (Tuesday, August 30, 2016)]
[Notices]
[Pages 59669-59670]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-20807]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-285; NRC-2016-0096]


Omaha Public Power District; Fort Calhoun Station, Unit No. 1

AGENCY: Nuclear Regulatory Commission.

ACTION: License amendment application; withdrawal by applicant.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has granted the 
request of the Omaha Public Power District (the licensee) to withdraw 
its license amendment application dated April 4, 2016, for a proposed 
amendment to Renewed Facility Operating License No. DPR-40 for the Fort 
Calhoun Station, Unit No. 1 (FCS). The proposed amendment would have 
modified License Condition D, Fire Protection Program, by withdrawing 
the commitments in REC-119 and REC-120 to implement certain plant 
modifications as stated in License Condition Paragraph 3.D.(3)(b).

DATES: The license amendment was withdrawn by the licensee on August 
18, 2016.

ADDRESSES: Please refer to Docket ID NRC-2016-0096 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0096. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Carl F. Lyon, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2296, email: [email protected].

SUPPLEMENTARY INFORMATION: The NRC has granted the request of the 
licensee to withdraw its April 4, 2016, license amendment application 
(ADAMS Accession No. ML16103A348), for a proposed amendment to Renewed 
Facility Operating License No. DPR-40 for the FCS, located in 
Washington County, Nebraska.
    The proposed amendment would have modified License Condition D, 
Fire Protection Program, by withdrawing the commitments in REC-119 and 
REC-120 to implement certain plant modifications as stated in License 
Condition Paragraph 3.D.(3)(b), due to the fact that they are not 
necessary to meet the performance requirements of the risk-informed 
fire protection standard.
    This proposed amendment was noticed in the Federal Register on June 
7, 2016 (81 FR 36605). By letter dated August 18, 2016 (ADAMS Accession 
No. ML16231A512), the licensee withdrew its license amendment 
application.

    Dated at Rockville, Maryland, this 24th day of August 2016.


[[Page 59670]]


    For the Nuclear Regulatory Commission.
Carl F. Lyon,
Project Manager, Plant Licensing Branch IV-1, Division of Operating 
Reactor Licensing, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-20807 Filed 8-29-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                                               Federal Register / Vol. 81, No. 168 / Tuesday, August 30, 2016 / Notices                                             59669

                                                    Renewed Facility Operating License                      Renewed Facility Operating License                     • Federal Rulemaking Web site: Go to
                                                  Nos. NPF–68 and NPF–81: Amendments                      No. NPF–42. The amendment revised                     http://www.regulations.gov and search
                                                  revised the Renewed Facility Operating                  the Operating License and Technical                   for Docket ID NRC–2016–0096. Address
                                                  Licenses and Technical Specifications.                  Specifications.                                       questions about NRC dockets to Carol
                                                    Date of initial notice in Federal                       Date of initial notice in Federal                   Gallagher; telephone: 301–415–3463;
                                                  Register: May 24, 2016 (81 FR 32809).                   Register: April 12, 2016 (81 FR 21603).               email: Carol.Gallagher@nrc.gov. For
                                                    The Commission’s related evaluation                   The supplemental letter dated May 19,                 technical questions, contact the
                                                  of the amendment is contained in a                      2016, provided additional information                 individual listed in the FOR FURTHER
                                                  Safety Evaluation dated August 4, 2016.                 that clarified the application, did not               INFORMATION CONTACT section of this
                                                    No significant hazards consideration                  expand the scope of the application as                document.
                                                  comments received: No.                                  originally noticed, and did not change                   • NRC’s Agencywide Documents
                                                                                                          the staff’s original proposed no                      Access and Management System
                                                  Southern Nuclear Operating Company,                     significant hazards consideration                     (ADAMS): You may obtain publicly-
                                                  Docket Nos. 50–348 and 50–364, Joseph                   determination as published in the                     available documents online in the
                                                  M. Farley Nuclear Plant, Units 1 and 2,                 Federal Register.                                     ADAMS Public Documents collection at
                                                  Houston County, Alabama                                   The Commission’s related evaluation                 http://www.nrc.gov/reading-rm/
                                                     Date of amendment request: March                     of the amendment is contained in a                    adams.html. To begin the search, select
                                                  16, 2016.                                               Safety Evaluation dated August 3, 2016.               ‘‘ADAMS Public Documents’’ and then
                                                     Brief description of amendments: The                   No significant hazards consideration                select ‘‘Begin Web-based ADAMS
                                                  amendments revised the Technical                        comments received: No.                                Search.’’ For problems with ADAMS,
                                                  Specifications to allow the use of                        Dated at Rockville, Maryland, this 18th day         please contact the NRC’s Public
                                                  Optimized ZIRLOTM as an approved fuel                   of August 2016.                                       Document Room (PDR) reference staff at
                                                  rod cladding.                                             For the Nuclear Regulatory Commission.              1–800–397–4209, 301–415–4737, or by
                                                     Date of issuance: August 4, 2016.                    Anne T. Boland,                                       email to pdr.resource@nrc.gov. The
                                                     Effective date: As of the date of                    Director, Division of Operating Reactor               ADAMS accession number for each
                                                  issuance and shall be implemented                       Licensing, Office of Nuclear Reactor                  document referenced (if it is available in
                                                  within 90 days of issuance.                             Regulation.                                           ADAMS) is provided the first time that
                                                     Amendment Nos.: 204 (Unit 1) and                     [FR Doc. 2016–20391 Filed 8–29–16; 8:45 am]           it is mentioned in this document.
                                                  200 (Unit 2). A publicly-available                      BILLING CODE 7590–01–P                                   • NRC’s PDR: You may examine and
                                                  version is in ADAMS under Accession                                                                           purchase copies of public documents at
                                                  No. ML16179A386; documents related                                                                            the NRC’s PDR, Room O1–F21, One
                                                  to these amendments are listed in the                   NUCLEAR REGULATORY                                    White Flint North, 11555 Rockville
                                                  Safety Evaluation enclosed with the                     COMMISSION                                            Pike, Rockville, Maryland 20852.
                                                  amendments.                                             [Docket No. 50–285; NRC–2016–0096]                    FOR FURTHER INFORMATION CONTACT: Carl
                                                     Renewed Facility Operating License                                                                         F. Lyon, Office of Nuclear Reactor
                                                  Nos. NPF–2 and NPF–8: Amendments                        Omaha Public Power District; Fort                     Regulation, U.S. Nuclear Regulatory
                                                  revised the Renewed Facility Operating                  Calhoun Station, Unit No. 1                           Commission, Washington, DC 20555–
                                                  Licenses and Technical Specifications.                                                                        0001; telephone: 301–415–2296, email:
                                                     Date of initial notice in Federal                    AGENCY:  Nuclear Regulatory
                                                                                                          Commission.                                           Fred.Lyon@nrc.gov.
                                                  Register: May 24, 2016 (81 FR 32808).
                                                     The Commission’s related evaluation                  ACTION: License amendment application;                SUPPLEMENTARY INFORMATION: The NRC
                                                  of the amendment is contained in a                      withdrawal by applicant.                              has granted the request of the licensee
                                                  Safety Evaluation dated August 4, 2016.                                                                       to withdraw its April 4, 2016, license
                                                     No significant hazards consideration                 SUMMARY:    The U.S. Nuclear Regulatory               amendment application (ADAMS
                                                  comments received: No.                                  Commission (NRC) has granted the                      Accession No. ML16103A348), for a
                                                                                                          request of the Omaha Public Power                     proposed amendment to Renewed
                                                  Wolf Creek Nuclear Operating                            District (the licensee) to withdraw its               Facility Operating License No. DPR–40
                                                  Corporation, Docket No. 50–482, Wolf                    license amendment application dated                   for the FCS, located in Washington
                                                  Creek Generating Station, Coffey                        April 4, 2016, for a proposed                         County, Nebraska.
                                                  County, Kansas                                          amendment to Renewed Facility                            The proposed amendment would
                                                     Date of amendment request: January                   Operating License No. DPR–40 for the                  have modified License Condition D, Fire
                                                  27, 2016, as supplemented by letter                     Fort Calhoun Station, Unit No. 1 (FCS).               Protection Program, by withdrawing the
                                                  dated May 19, 2016.                                     The proposed amendment would have                     commitments in REC–119 and REC–120
                                                     Brief description of amendment: The                  modified License Condition D, Fire                    to implement certain plant
                                                  amendment revised the Technical                         Protection Program, by withdrawing the                modifications as stated in License
                                                  Specifications to allow the use of                      commitments in REC–119 and REC–120                    Condition Paragraph 3.D.(3)(b), due to
                                                  Optimized ZIRLOTM as an approved                        to implement certain plant                            the fact that they are not necessary to
                                                  fuel rod cladding.                                      modifications as stated in License                    meet the performance requirements of
                                                     Date of issuance: The amendment is                   Condition Paragraph 3.D.(3)(b).                       the risk-informed fire protection
                                                  effective upon issuance and shall be                    DATES: The license amendment was                      standard.
                                                  implemented within 90 days of the date                  withdrawn by the licensee on August                      This proposed amendment was
                                                  of issuance.                                            18, 2016.                                             noticed in the Federal Register on June
mstockstill on DSK3G9T082PROD with NOTICES




                                                     Effective date: August 3, 2016.                      ADDRESSES: Please refer to Docket ID                  7, 2016 (81 FR 36605). By letter dated
                                                     Amendment No.: 216. A publicly-                      NRC–2016–0096 when contacting the                     August 18, 2016 (ADAMS Accession
                                                  available version is in ADAMS under                     NRC about the availability of                         No. ML16231A512), the licensee
                                                  Accession No. ML16179A293;                              information regarding this document.                  withdrew its license amendment
                                                  documents related to this amendment                     You may obtain publicly-available                     application.
                                                  are listed in the Safety Evaluation                     information related to this document                    Dated at Rockville, Maryland, this 24th day
                                                  enclosed with the amendment.                            using any of the following methods:                   of August 2016.



                                             VerDate Sep<11>2014   20:04 Aug 29, 2016   Jkt 238001   PO 00000   Frm 00073   Fmt 4703   Sfmt 4703   E:\FR\FM\30AUN1.SGM   30AUN1


                                                  59670                        Federal Register / Vol. 81, No. 168 / Tuesday, August 30, 2016 / Notices

                                                     For the Nuclear Regulatory Commission.               ADAMS Public Documents collection at                  which is the case for CCNPP.
                                                  Carl F. Lyon,                                           http://www.nrc.gov/reading-rm/                        Consequently, since CCNPP is a multi-
                                                  Project Manager, Plant Licensing Branch IV–             adams.html. To begin the search, select               unit facility with a single shared USFAR
                                                  1, Division of Operating Reactor Licensing,             ‘‘ADAMS Public Documents’’ and then                   and a staggered refueling outage
                                                  Office of Nuclear Reactor Regulation.                   select ‘‘Begin Web-based ADAMS                        schedule, the phrase ‘‘each refueling
                                                  [FR Doc. 2016–20807 Filed 8–29–16; 8:45 am]             Search.’’ For problems with ADAMS,                    outage’’ in 10 CFR 50.71(e)(4) does not
                                                  BILLING CODE 7590–01–P                                  please contact the NRC’s Public                       decrease the regulatory burden on the
                                                                                                          Document Room (PDR) reference staff at                licensee as was the intent of the rule.
                                                                                                          1–800–397–4209, 301–415–4737, or by                   II. Request/Action
                                                  NUCLEAR REGULATORY                                      email to pdr.resource@nrc.gov. The
                                                  COMMISSION                                              ADAMS accession number for each                          Pursuant to 10 CFR 50.12, ‘‘Specific
                                                                                                          document referenced (if it available in               exemptions,’’ the licensee has, by
                                                  [Docket Nos. 50–317 and 50–318; NRC–
                                                  2016–0181]                                              ADAMS) is provided the first time that                application dated January 29, 2016
                                                                                                          a document is referenced.                             (ADAMS Accession No. ML16033A048),
                                                  Exelon Generation Company, LLC;                            • NRC’s PDR: You may examine and                   requested an exemption from the
                                                  Calvert Cliffs Nuclear Power Plant,                     purchase copies of public documents at                requirements of 10 CFR 50.71,
                                                  Units 1 and 2; Update Schedule for                      the NRC’s PDR, Room O1–F21, One                       ‘‘Maintenance of records, making of
                                                  Updated Final Safety Analysis Report                    White Flint North, 11555 Rockville                    reports,’’ paragraph (e)(4), related to the
                                                                                                          Pike, Rockville, Maryland 20852.                      schedule for submitting periodic
                                                  AGENCY:  Nuclear Regulatory                                                                                   updates to the CCNPP UFSAR. Pursuant
                                                  Commission.                                             FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                to 10 CFR 50.12(a), the NRC may, upon
                                                  ACTION: Exemption; issuance.
                                                                                                          Richard V. Guzman, Office of Nuclear
                                                                                                                                                                application by any interested person or
                                                                                                          Reactor Regulation, U.S. Nuclear
                                                                                                                                                                upon its own initiative, grant
                                                  SUMMARY:   The U.S. Nuclear Regulatory                  Regulatory Commission, Washington,
                                                                                                                                                                exemptions from the requirements of
                                                  Commission (NRC) is issuing an                          DC 20555–0001; telephone: 301–415–
                                                                                                                                                                the regulations of this part, which are
                                                  exemption in response to a January 29,                  1030, email: Richard.Guzman@nrc.gov.
                                                                                                                                                                authorized by law, will not present an
                                                  2016, application from Exelon                           SUPPLEMENTARY INFORMATION:                            undue risk to the public health and
                                                  Generation Company, LLC (Exelon), the
                                                                                                          I. Background                                         safety, and are consistent with the
                                                  licensee for Calvert Cliffs Nuclear Power
                                                                                                                                                                common defense and security and when
                                                  Plant (CCNPP), Units 1 and 2, for                          The CCNPP is a two-unit plant, both                special circumstances are present.
                                                  Renewed Facility Operating License                      units of which share an UFSAR. A strict
                                                  Nos. DPR–53 and DPR–60, which                           interpretation of the language contained              III. Discussion
                                                  requested an exemption from the                         in 50.71(e)(4) of title 10 of the Code of                Pursuant to 10 CFR 50.12, the NRC
                                                  updated final safety analysis report                    Federal Regulations (10 CFR), would                   may, upon application by any interested
                                                  (UFSAR) update schedule requirements                    require Exelon to update this single                  person or upon its own initiative, grant
                                                  in the NRC’s regulations. The NRC staff                 UFSAR within 6 months after each                      exemptions from the requirements of 10
                                                  reviewed this request and is granting an                unit’s refueling outage. In August 1992,              CFR part 50, including 10 CFR
                                                  exemption from the requirement that an                  the NRC promulgated a rule change                     50.71(e)(4) when: (1) The exemptions
                                                  update to the UFSAR be submitted 6                      entitled ‘‘Reducing the Regulatory                    are authorized by law, will not present
                                                  months after the refueling outage for                   Burden on Nuclear Licensees,’’ which                  an undue risk to the public health or
                                                  each unit. The exemption allows the                     affected 10 CFR 50.71(e)(4). This rule                safety, and are consistent with the
                                                  update to the CCNPP UFSAR to be                         change was published in the Federal                   common defense and security; and (2)
                                                  submitted within 6 months following                     Register on August 31, 1992 (57 FR                    when special circumstances are present.
                                                  the completion of each CCNPP Unit 2                     39358), with an effective date of October             Under 10 CFR 50.12(a)(2), special
                                                  refueling outage, not to exceed 24                      1, 1992, and was intended to provide a                circumstances include, among other
                                                  months from the last submittal.                         reduction in regulatory burden by, in                 things, when application of the specific
                                                  DATES: The exemption was issued on                      part, providing licensees with the                    regulation in the particular
                                                  August 18, 2016.                                        option to submit UFSAR updates once                   circumstances would not serve, or is not
                                                  ADDRESSES: Please refer to Docket ID                    per refueling outage, not to exceed 24                necessary to achieve, the underlying
                                                  NRC–2016–0181 when contacting the                       months between successive updates,                    purpose of the rule.
                                                  NRC about the availability of                           instead of annually. However, when a
                                                                                                          single UFSAR is shared between the                    Authorized by Law
                                                  information regarding this document.
                                                  You may obtain publicly-available                       units of a multi-unit plant and those                   In accordance with 10 CFR 50.12, the
                                                  information related to this document                    units have staggered refueling outages                NRC may grant an exemption from the
                                                  using any of the following methods:                     (i.e., one unit a year on alternating                 requirements of 10 CFR part 50 if the
                                                     • Federal Rulemaking Web site: Go to                 years), as is the case with CCNPP, 10                 exemption is authorized by law. The
                                                  http://www.regulations.gov and search                   CFR 50.71(e)(4) has the net effect of still           exemption requested in this instance is
                                                  for Docket ID NRC–2016–0181. Address                    requiring that the UFSAR be updated                   authorized by law because no other
                                                  questions about NRC dockets to Carol                    annually. Therefore, as written, the                  prohibition of law exists to preclude the
                                                  Gallagher; telephone: 301–415–3463;                     burden reduction provided by 10 CFR                   activities which would be authorized by
                                                  email: Carol.Gallagher@nrc.gov. For                     50.71(e)(4) of providing licensees with               the exemption. Additionally, even with
                                                  technical questions, contact the                        the option to submit UFSAR updates                    the granting of the exemption, the
mstockstill on DSK3G9T082PROD with NOTICES




                                                  individual listed in the FOR FURTHER                    each refueling outage instead of                      underlying purpose of the regulation
                                                  INFORMATION CONTACT section of this                     annually can only be realized by single-              will continue to be served. The
                                                  document.                                               unit facilities, by multi-unit facilities             underlying purpose of 10 CFR
                                                     • NRC’s Agencywide Documents                         that maintain separate UFSARs for each                50.71(e)(4) is to ensure that licensees
                                                  Access and Management System                            unit, or by multi-unit facilities that                periodically update their UFSARs to
                                                  (ADAMS): You may obtain publicly-                       share a single UFSAR and have non-                    assure that the UFSARs remain up-to-
                                                  available documents online in the                       staggered refueling outages—none of                   date such that they accurately reflect the


                                             VerDate Sep<11>2014   20:04 Aug 29, 2016   Jkt 238001   PO 00000   Frm 00074   Fmt 4703   Sfmt 4703   E:\FR\FM\30AUN1.SGM   30AUN1



Document Created: 2018-02-09 11:42:32
Document Modified: 2018-02-09 11:42:32
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionLicense amendment application; withdrawal by applicant.
DatesThe license amendment was withdrawn by the licensee on August 18, 2016.
ContactCarl F. Lyon, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2296, email: [email protected]
FR Citation81 FR 59669 