81 FR 59670 - Exelon Generation Company, LLC; Calvert Cliffs Nuclear Power Plant, Units 1 and 2; Update Schedule for Updated Final Safety Analysis Report

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 81, Issue 168 (August 30, 2016)

Page Range59670-59672
FR Document2016-20804

The U.S. Nuclear Regulatory Commission (NRC) is issuing an exemption in response to a January 29, 2016, application from Exelon Generation Company, LLC (Exelon), the licensee for Calvert Cliffs Nuclear Power Plant (CCNPP), Units 1 and 2, for Renewed Facility Operating License Nos. DPR-53 and DPR-60, which requested an exemption from the updated final safety analysis report (UFSAR) update schedule requirements in the NRC's regulations. The NRC staff reviewed this request and is granting an exemption from the requirement that an update to the UFSAR be submitted 6 months after the refueling outage for each unit. The exemption allows the update to the CCNPP UFSAR to be submitted within 6 months following the completion of each CCNPP Unit 2 refueling outage, not to exceed 24 months from the last submittal.

Federal Register, Volume 81 Issue 168 (Tuesday, August 30, 2016)
[Federal Register Volume 81, Number 168 (Tuesday, August 30, 2016)]
[Notices]
[Pages 59670-59672]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-20804]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-317 and 50-318; NRC-2016-0181]


Exelon Generation Company, LLC; Calvert Cliffs Nuclear Power 
Plant, Units 1 and 2; Update Schedule for Updated Final Safety Analysis 
Report

AGENCY: Nuclear Regulatory Commission.

ACTION: Exemption; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing an 
exemption in response to a January 29, 2016, application from Exelon 
Generation Company, LLC (Exelon), the licensee for Calvert Cliffs 
Nuclear Power Plant (CCNPP), Units 1 and 2, for Renewed Facility 
Operating License Nos. DPR-53 and DPR-60, which requested an exemption 
from the updated final safety analysis report (UFSAR) update schedule 
requirements in the NRC's regulations. The NRC staff reviewed this 
request and is granting an exemption from the requirement that an 
update to the UFSAR be submitted 6 months after the refueling outage 
for each unit. The exemption allows the update to the CCNPP UFSAR to be 
submitted within 6 months following the completion of each CCNPP Unit 2 
refueling outage, not to exceed 24 months from the last submittal.

DATES: The exemption was issued on August 18, 2016.

ADDRESSES: Please refer to Docket ID NRC-2016-0181 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0181. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Richard V. Guzman, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-1030, email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Background

    The CCNPP is a two-unit plant, both units of which share an UFSAR. 
A strict interpretation of the language contained in 50.71(e)(4) of 
title 10 of the Code of Federal Regulations (10 CFR), would require 
Exelon to update this single UFSAR within 6 months after each unit's 
refueling outage. In August 1992, the NRC promulgated a rule change 
entitled ``Reducing the Regulatory Burden on Nuclear Licensees,'' which 
affected 10 CFR 50.71(e)(4). This rule change was published in the 
Federal Register on August 31, 1992 (57 FR 39358), with an effective 
date of October 1, 1992, and was intended to provide a reduction in 
regulatory burden by, in part, providing licensees with the option to 
submit UFSAR updates once per refueling outage, not to exceed 24 months 
between successive updates, instead of annually. However, when a single 
UFSAR is shared between the units of a multi-unit plant and those units 
have staggered refueling outages (i.e., one unit a year on alternating 
years), as is the case with CCNPP, 10 CFR 50.71(e)(4) has the net 
effect of still requiring that the UFSAR be updated annually. 
Therefore, as written, the burden reduction provided by 10 CFR 
50.71(e)(4) of providing licensees with the option to submit UFSAR 
updates each refueling outage instead of annually can only be realized 
by single-unit facilities, by multi-unit facilities that maintain 
separate UFSARs for each unit, or by multi-unit facilities that share a 
single UFSAR and have non-staggered refueling outages--none of which is 
the case for CCNPP. Consequently, since CCNPP is a multi-unit facility 
with a single shared USFAR and a staggered refueling outage schedule, 
the phrase ``each refueling outage'' in 10 CFR 50.71(e)(4) does not 
decrease the regulatory burden on the licensee as was the intent of the 
rule.

II. Request/Action

    Pursuant to 10 CFR 50.12, ``Specific exemptions,'' the licensee 
has, by application dated January 29, 2016 (ADAMS Accession No. 
ML16033A048), requested an exemption from the requirements of 10 CFR 
50.71, ``Maintenance of records, making of reports,'' paragraph (e)(4), 
related to the schedule for submitting periodic updates to the CCNPP 
UFSAR. Pursuant to 10 CFR 50.12(a), the NRC may, upon application by 
any interested person or upon its own initiative, grant exemptions from 
the requirements of the regulations of this part, which are authorized 
by law, will not present an undue risk to the public health and safety, 
and are consistent with the common defense and security and when 
special circumstances are present.

III. Discussion

    Pursuant to 10 CFR 50.12, the NRC may, upon application by any 
interested person or upon its own initiative, grant exemptions from the 
requirements of 10 CFR part 50, including 10 CFR 50.71(e)(4) when: (1) 
The exemptions are authorized by law, will not present an undue risk to 
the public health or safety, and are consistent with the common defense 
and security; and (2) when special circumstances are present. Under 10 
CFR 50.12(a)(2), special circumstances include, among other things, 
when application of the specific regulation in the particular 
circumstances would not serve, or is not necessary to achieve, the 
underlying purpose of the rule.

Authorized by Law

    In accordance with 10 CFR 50.12, the NRC may grant an exemption 
from the requirements of 10 CFR part 50 if the exemption is authorized 
by law. The exemption requested in this instance is authorized by law 
because no other prohibition of law exists to preclude the activities 
which would be authorized by the exemption. Additionally, even with the 
granting of the exemption, the underlying purpose of the regulation 
will continue to be served. The underlying purpose of 10 CFR 
50.71(e)(4) is to ensure that licensees periodically update their 
UFSARs to assure that the UFSARs remain up-to-date such that they 
accurately reflect the

[[Page 59671]]

plant design and operation. The rule does not require that licensees 
review all of the information contained in the UFSAR for each periodic 
update. Rather, the intent of the rule is for licensees to update only 
those portions of the UFSAR that have been affected by licensee 
activities since the previous update. As required by 10 CFR 
50.71(e)(4), UFSAR updates shall be submitted within 6 months after 
each refueling outage provided that the interval between successive 
updates does not exceed 24 months. Submitting updates to the single 
shared CCNPP UFSAR 6 months after the CCNPP Unit 2 refueling outage as 
proposed and not exceeding 24 months between successive updates 
continues to meet the intent of the regulation from the perspective of 
regulatory burden reduction and maintaining UFSAR information up-to-
date. Therefore, this exemption request is authorized by law.

No Undue Risk to the Public Health and Safety

    The underlying purpose of 10 CFR 50.71(e)(4) is to ensure that 
licensees periodically update their UFSARs to assure that the UFSARs 
remain up-to-date such that they accurately reflect the plant design 
and operation. The NRC has determined by rule that an update frequency 
not exceeding 24 months between successive updates is acceptable for 
maintaining UFSAR content up-to-date. The requested exemption provides 
an equivalent level of protection to the existing requirements because 
it ensures that updates to the CCNPP UFSAR are submitted with no 
greater than 24 months between successive updates. The requested 
exemption also meets the intent of the rule for regulatory burden 
reduction. Additionally, based on the nature of the requested exemption 
and that updates will not exceed 24 months from the last submittal as 
described above, no new accident precursors are created by the 
exemption; therefore, neither the probability nor the consequences of 
postulated accidents are increased. In conclusion, the requested 
exemption does not result in any undue risk to the public health and 
safety.

Consistent With the Common Defense and Security

    The requested exemption from 10 CFR 50.71(e)(4) would allow Exelon 
to submit its periodic updates to the CCNPP UFSAR within 6 months 
following the completion of each CCNPP Unit 2 refueling outage, not to 
exceed 24 months from the last submittal. Neither the regulation nor 
the proposed exemption thereto has any relation to security issues. 
Therefore, the common defense and security is not impacted by the 
exemption.

Special Circumstances

    Special circumstances, in accordance with 10 CFR 50.12(a)(2)(ii), 
are present whenever application of the regulation in the particular 
circumstances would not serve the underlying purpose of the rule or is 
not necessary to achieve the underlying purpose of the rule. As 
explained above, the rule change promulgated in August 1992 (57 FR 
39358; August 31, 1992) was intended to provide a reduction in 
regulatory burden by providing licensees with the option to submit 
UFSAR updates once per refueling outage, not to exceed 24 months 
between successive updates, instead of annually. However, as written, 
this burden reduction can only be realized by single-unit facilities, 
by multi-unit facilities that maintain separate UFSARs for each unit, 
or by multi-unit facilities that share a single UFSAR and have non-
staggered refueling outages--none of which is the case for CCNPP. Since 
CCNPP is a dual-unit facility with a single shared UFSAR and staggered 
refueling outages, the phrase ``each refueling outage'' in 10 CFR 
50.71(e)(4) does not decrease the regulatory burden on the licensee as 
was the intent of the rule. Therefore, special circumstances exist 
under 10 CFR 50.12(a)(2)(ii) in that application of the requirements in 
these particular circumstances would not serve the underlying purpose 
of the rule and are not necessary to achieve the underlying purpose of 
the rule.

Environmental Considerations

    With respect to its impact on the quality of the human environment, 
the NRC has determined that the issuance of the exemption discussed 
herein meets the eligibility criteria for categorical exclusion set 
forth in 10 CFR 51.22(c)(25). Under 10 CFR 51.22(c)(25), the granting 
of an exemption from the requirements of any regulation of 10 CFR 
chapter I (which includes 10 CFR 50.71(e)(4)) is an action that is a 
categorical exclusion.
    The NRC staff's determination that all of the criteria for this 
categorical exclusion are met is as follows:
    I. 10 CFR 51.22(c)(25)(i): There is no significant hazards 
consideration.
    Staff Analysis: The criteria for determining whether an action 
involves a significant hazards consideration are found in 10 CFR 50.92. 
The proposed action involves only a schedule change regarding the 
submission of an update to the application. Therefore, there are no 
significant hazard considerations because granting the exemption would 
not:
    (1) Involve a significant increase in the probability or 
consequences of an accident previously evaluated; or
    (2) Create the possibility of a new or different kind of accident 
from any accident previously evaluated; or
    (3) Involve a significant reduction in a margin of safety.
    II. 10 CFR 51.22(c)(25)(ii): There is no significant change in the 
types or significant increase in the amounts of any effluents that may 
be released offsite.
    Staff Analysis: The proposed action involves only a schedule 
change, which is administrative in nature, and does not involve any 
changes in the types or significant increase in the amounts of any 
effluents that may be released offsite.
    III. 10 CFR 51.22(c)(25)(iii): There is no significant increase in 
individual or cumulative public or occupational radiation exposure.
    Staff Analysis: Since the proposed action involves only a schedule 
change, which is administrative in nature, it does not contribute to 
any significant increase in occupational or public radiation exposure.
    IV. 10 CFR 51.22(c)(25)(iv): There is no significant construction 
impact.
    Staff Analysis: Since the proposed action involves only a schedule 
change, which is administrative in nature, it does not involve any 
construction impact.
    V. 10 CFR 51.22(c)(25)(v): There is no significant increase in the 
potential for or consequences from radiological accidents.
    Staff Analysis: The proposed action involves only a schedule 
change, which is administrative in nature and does not impact the 
potential for or consequences from accidents.
    VI. 10 CFR 51.22(c)(25)(vi): The requirements from which the 
exemption is sought involve scheduling requirements and other 
requirements of an administrative, managerial, or organizational 
nature.
    Staff Analysis: The proposed action involves scheduling 
requirements and other requirements of an administrative, managerial, 
or organizational nature because it is associated with the submittal 
schedule requirements contained in 10 CFR 50.71(e)(4), which stipulate 
that revisions to the UFSAR must be filed annually or 6 months after 
each refueling outage provided the interval between successive updates 
does not exceed 24 months.
    Based on the above, the NRC staff concludes that the proposed 
exemption

[[Page 59672]]

meets the eligibility criteria for the categorical exclusion set forth 
in 10 CFR 51.22(c)(25). Therefore, in accordance with 10 CFR 51.22(b), 
no environmental impact statement or environmental assessment need be 
prepared in connection with the NRC's issuance of this exemption.

IV. Conclusions

    The NRC has determined that, pursuant to 10 CFR 50.12, the 
exemption is authorized by law, will not present an undue risk to the 
public health and safety, and is consistent with the common defense and 
security. Also, special circumstances pursuant to 10 CFR 
50.12(a)(2)(ii) are present. Therefore, the NRC hereby grants Exelon an 
exemption from the requirements of 10 CFR 50.71(e)(4) to allow Exelon 
to file its periodic updates to the CCNPP UFSAR within 6 months 
following the completion of each CCNPP Unit 2 refueling outage, not to 
exceed 24 months from the last submittal.

    Dated at Rockville, Maryland, this 22nd Day of August 2016.

    For the Nuclear Regulatory Commission.
Anne T. Boland,
Director, Division of Operating Reactor Licensing, Office of Nuclear 
Reactor Regulation.
[FR Doc. 2016-20804 Filed 8-29-16; 8:45 am]
 BILLING CODE 7590-01-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionExemption; issuance.
DatesThe exemption was issued on August 18, 2016.
ContactRichard V. Guzman, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-1030, email: [email protected]
FR Citation81 FR 59670 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR