The Coast Guard has issued a temporary deviation from the operating schedule that governs the Montlake Bridge across the Lake Washington Ship Canal, mile 5.2, at Seattle, WA. The Montlake Bridge is a double leaf bascule bridge. The deviation is necessary to allow work crews to replace bridge decking. This deviation allows a single leaf opening with a one hour advance notice during the day, and remains in the closed-to-navigation position at night.

Federal Register, Volume 81 Issue 173 (Wednesday, September 7, 2016)
[Federal Register Volume 81, Number 173 (Wednesday, September 7, 2016)]
[Rules and Regulations]
[Pages 61615-61616]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-21448]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2016-0847]


Drawbridge Operation Regulation; Lake Washington Ship Canal, 
Seattle, WA

AGENCY: Coast Guard, DHS.

ACTION: Notice of deviation from drawbridge regulation.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard has issued a temporary deviation from the 
operating schedule that governs the Montlake Bridge across the Lake 
Washington Ship Canal, mile 5.2, at Seattle, WA. The Montlake Bridge is 
a double leaf bascule bridge. The deviation is necessary to allow work 
crews to replace bridge decking. This deviation allows a single leaf 
opening with a one hour advance notice during the day, and remains in 
the closed-to-navigation position at night.

DATES: This deviation is effective from 6 a.m. on September 24, 2016 to 
6 a.m. on September 26, 2016.

ADDRESSES: The docket for this deviation, [USCG-2016-0847] is available 
at http://www.regulations.gov. Type the docket number in the ``SEARCH'' 
box and click ``SEARCH.'' Click on Open Docket Folder on the line 
associated with this deviation.

FOR FURTHER INFORMATION CONTACT: If you have questions on this 
temporary deviation, call or email Mr. Steven Fischer, Bridge 
Administrator, Thirteenth Coast Guard District; telephone 206-220-7282, 
email [email protected].

SUPPLEMENTARY INFORMATION: Washington Department of Transportation has 
requested a temporary deviation from the operating schedule for the 
Montlake Bridge across the Lake Washington Ship Canal, at mile 5.2, at 
Seattle, WA. The deviation is necessary to accommodate work crews to 
conduct timely bridge deck

[[Page 61616]]

repairs. The Montlake Bridge in the closed position provides 30 feet of 
vertical clearance throughout the navigation channel, and 46 feet of 
vertical clearance throughout the center 60 feet of the bridge; 
vertical clearance references to the Mean Water Level of Lake 
Washington. When half the span is open, single leaf, 46 feet of 
vertical clearance will be reduced throughout the center to 30 feet of 
the bridge. To facilitate this event, the north half of the bridge span 
will open with at least a one hour advance notice provided to the 
bridge operator from 6 a.m. to 6 p.m. From 6 p.m. to 6 a.m., the 
Montlake Bridge span will remain in the closed-to-navigation position, 
or full closure.
    The deviation period is from 6 a.m. until 6 p.m. on September 24, 
2016 (north single leaf opening if a one hour notice is given); from 6 
p.m. on September 24, 2016 until 6 a.m. on September 25, 2016 (span 
remain in the closed-to-navigation position); from 6 a.m. until 6 p.m. 
on September 25, 2016 (north single leaf opening if a one hour notice 
is given); from 6 p.m. on September 25, 2016 until 6 a.m. on September 
26, 2016 (span remain in the closed-to-navigation position). The normal 
operating schedule for the Montlake Bridge operates in accordance with 
33 CFR 117.1051(e).
    Waterway usage on the Lake Washington Ship Canal ranges from 
commercial tug and barge to small pleasure craft. Vessels able to pass 
through the bridge in the closed-to-navigation position may do so at 
any time. The bridge will be able to open for emergency vessels in 
route to a call when an hour notice is given to the bridge operator, 
and a single leaf opening will be provided. The Lake Washington Ship 
Canal has no immediate alternate route for vessels to pass. The Coast 
Guard will also inform the users of the waterways through our Local and 
Broadcast Notices to Mariners of the change in operating schedule for 
the bridge so that vessels can arrange their transits to minimize any 
impact caused by the temporary deviation.
    In accordance with 33 CFR 117.35(e), the drawbridge must return to 
its regular operating schedule immediately at the end of the designated 
time period. This deviation from the operating regulations is 
authorized under 33 CFR 117.35.

    Dated: August 25, 2016.
Steven M. Fischer,
Bridge Administrator, Thirteenth Coast Guard District.
[FR Doc. 2016-21448 Filed 9-6-16; 8:45 am]
 BILLING CODE 9110-04-P



                                                        Federal Register / Vol. 81, No. 173 / Wednesday, September 7, 2016 / Rules and Regulations                                               61615

                                           sureties’ reliance on a cash-flow basis to              DEPARTMENT OF DEFENSE                                   (6) * * *
                                           cover the cost of reclamation when their                                                                        (i) APF is not used to reimburse their
                                           bonds are forfeited.                                    Office of the Secretary                               salaries and benefits.
                                             We believe that carefully considered                                                                        *     *    *     *     *
                                           revisions to our regulations will better                32 CFR Part 252
                                                                                                                                                           Dated: August 30, 2016.
                                           (1) ensure the completion of the                        [Docket ID: DOD–2012–OS–0170]
                                           reclamation plan as required in section                                                                       Aaron Siegel,
                                           509(a) of SMCRA, 30 U.S.C. 1259(a), (2)                 RIN 0790–AI98                                         Alternate OSD Federal Register Liaison
                                           guarantee that an applicant                                                                                   Officer, Department of Defense.
                                           demonstrates a history of financial                     Professional U.S. Scouting                            [FR Doc. 2016–21254 Filed 9–6–16; 8:45 am]
                                           solvency and continuous operation                       Organization Operations at U.S.                       BILLING CODE 5001–06–P
                                           sufficient for authorization to self-insure             Military Installations Overseas;
                                           as required in section 509(c) of SMCRA,                 Technical Amendment
                                           30 U.S.C. 1259(c), and (3) assure that                  AGENCY:  Under Secretary of Defense for               DEPARTMENT OF HOMELAND
                                           surface coal mining operations are                      Personnel and Readiness, DoD.                         SECURITY
                                           conducted to protect the environment,                   ACTION: Final rule; technical
                                           30 U.S.C. 1202(d).                                                                                            Coast Guard
                                                                                                   amendment.
                                             As we begin to examine broader
                                           regulatory changes, we will seek                        SUMMARY:   On January 25, 2016, the                   33 CFR Part 117
                                           specific input from the many                            Department of Defense published a final               [Docket No. USCG–2016–0847]
                                           stakeholders about their ideas of how to                rule, 81 FR 3959–3962, titled
                                           improve our regulations. The state RAs                  Professional U.S. Scouting Organization               Drawbridge Operation Regulation;
                                           have many years of experience with                      Operations at U.S. Military Installations             Lake Washington Ship Canal, Seattle,
                                           self-bonding and we will ask that they                  Overseas. DoD is making a technical                   WA
                                           provide specific suggestions on how to                  amendment due to the discovery of a
                                           improve our regulations to ensure they                                                                        AGENCY: Coast Guard, DHS.
                                                                                                   mistake regarding the use of
                                           have adequate financial assurance to                    nonappropriated funds. A paragraph in                 ACTION:Notice of deviation from
                                           complete reclamation of each mine.                      the final rule incorrectly stated                     drawbridge regulation.
                                           VI. Procedural Matters and                              nonappropriated funds cannot be used                  SUMMARY:  The Coast Guard has issued a
                                           Determinations                                          to reimburse salaries and benefits of                 temporary deviation from the operating
                                                                                                   qualified scouting organization                       schedule that governs the Montlake
                                              This document is not a proposed or                   employees. Nonappropriated funds may
                                           final rule, policy, or guidance.                                                                              Bridge across the Lake Washington Ship
                                                                                                   be used to reimburse salaries and                     Canal, mile 5.2, at Seattle, WA. The
                                           Therefore, it is not subject to the                     benefits of employees of qualified
                                           Regulatory Flexibility Act, the Small                                                                         Montlake Bridge is a double leaf bascule
                                                                                                   scouting organizations for periods                    bridge. The deviation is necessary to
                                           Business Regulatory Enforcement                         during which their professional
                                           Fairness Act, the Paperwork Reduction                                                                         allow work crews to replace bridge
                                                                                                   scouting employees perform services in                decking. This deviation allows a single
                                           Act, the Unfunded Mandates Reform                       overseas areas in direct support of DoD
                                           Act, or Executive Orders 12866, 13563,                                                                        leaf opening with a one hour advance
                                                                                                   personnel and their families.                         notice during the day, and remains in
                                           12630, 13132, 12988, 13175, and 13211.                  DATES: This rule is effective September
                                           We will conduct the analyses required                                                                         the closed-to-navigation position at
                                                                                                   7, 2016.                                              night.
                                           by these laws and executive orders
                                                                                                   FOR FURTHER INFORMATION CONTACT: Ms.
                                           when we develop a proposed rule.                                                                              DATES: This deviation is effective from
                                              In developing this document, we did                  Patricia Toppings, 571–372–0485.                      6 a.m. on September 24, 2016 to 6 a.m.
                                           not conduct or use a study, experiment,                 SUPPLEMENTARY INFORMATION: This                       on September 26, 2016.
                                           or survey requiring peer review under                   technical amendment amends 32 CFR                     ADDRESSES: The docket for this
                                           the Information Quality Act (Pub. L.                    part 252 to read as set forth in the                  deviation, [USCG–2016–0847] is
                                           106–554, section 15).                                   amendatory language in this final rule.               available at http://www.regulations.gov.
                                              This document is not subject to the                  List of Subjects in 32 CFR Part 252                   Type the docket number in the
                                           requirement to prepare an                                                                                     ‘‘SEARCH’’ box and click ‘‘SEARCH.’’
                                           Environmental Assessment or                               Military installations, Military
                                                                                                                                                         Click on Open Docket Folder on the line
                                           Environmental Impact Statement under                    personnel, Scout organizations.
                                                                                                                                                         associated with this deviation.
                                           the National Environmental Policy Act                     Accordingly 32 CFR part 252 is
                                                                                                                                                         FOR FURTHER INFORMATION CONTACT: If
                                           (NEPA), 42 U.S.C. 4332(2)(C), because                   amended as follows:
                                                                                                                                                         you have questions on this temporary
                                           no proposed action, as described in 40                                                                        deviation, call or email Mr. Steven
                                           CFR 1508.18(a) and (b), yet exists. This                PART 252—PROFESSIONAL U.S.
                                                                                                   SCOUTING ORGANIZATION                                 Fischer, Bridge Administrator,
                                           document only announces the Director’s                                                                        Thirteenth Coast Guard District;
                                           decision to grant a petition and initiate               OPERATIONS AT U.S. MILITARY
                                                                                                   INSTALLATIONS OVERSEAS                                telephone 206–220–7282, email d13-pf-
                                           rulemaking. We will prepare the                                                                               d13bridges@uscg.mil.
                                           appropriate NEPA compliance
                                                                                                   ■ 1. The authority citation for part 252              SUPPLEMENTARY INFORMATION:
                                           documents as part of the rulemaking
                                                                                                   continues to read as follows:                         Washington Department of
                                           process.
                                                                                                     Authority: E.O. 12715, May 3, 1990, 55 FR           Transportation has requested a
ehiers on DSK5VPTVN1PROD with RULES




                                             Dated: August 19, 2016.                               19051; 10 U.S.C. 2606, 2554, and 2555.                temporary deviation from the operating
                                           Glenda H. Owens,                                                                                              schedule for the Montlake Bridge across
                                                                                                   ■ 2. Amend § 252.6 by revising
                                           Assistant Director, Office of Surface Mining            paragraph (a)(6)(i) to read as follows:               the Lake Washington Ship Canal, at
                                           Reclamation and Enforcement.                                                                                  mile 5.2, at Seattle, WA. The deviation
                                           [FR Doc. 2016–21440 Filed 9–6–16; 8:45 am]              § 252.6   Procedures.                                 is necessary to accommodate work
                                           BILLING CODE 4310–05–P                                      (a) * * *                                         crews to conduct timely bridge deck


                                      VerDate Sep<11>2014   14:50 Sep 06, 2016   Jkt 238001   PO 00000   Frm 00033   Fmt 4700   Sfmt 4700   E:\FR\FM\07SER1.SGM   07SER1


                                           61616        Federal Register / Vol. 81, No. 173 / Wednesday, September 7, 2016 / Rules and Regulations

                                           repairs. The Montlake Bridge in the                     DEPARTMENT OF HOMELAND                                (d), during the enforcement period, no
                                           closed position provides 30 feet of                     SECURITY                                              vessel may not enter, remain in, or
                                           vertical clearance throughout the                                                                             transit through the safety zone without
                                           navigation channel, and 46 feet of                      Coast Guard                                           approval from the Captain of the
                                           vertical clearance throughout the center                                                                      Hampton Roads (COTP) or a COTP
                                           60 feet of the bridge; vertical clearance               33 CFR Part 165                                       designated representative. The Coast
                                           references to the Mean Water Level of                   [Docket No. USCG–2016–0745]                           Guard may be assisted by other Federal,
                                           Lake Washington. When half the span is                                                                        state or local law enforcement agencies
                                           open, single leaf, 46 feet of vertical                  Safety Zone; North Atlantic Ocean,                    in enforcing this regulation.
                                           clearance will be reduced throughout                    Virginia Beach, VA                                       This notice of enforcement is issued
                                           the center to 30 feet of the bridge. To                                                                       under authority of 33 CFR 165.506(d)
                                           facilitate this event, the north half of the            AGENCY:  Coast Guard, DHS.                            and 5 U.S.C. 552 (a). In addition to this
                                           bridge span will open with at least a one               ACTION: Notice of enforcement of                      notice of enforcement in the Federal
                                           hour advance notice provided to the                     regulation.                                           Register, the Coast Guard plans to
                                           bridge operator from 6 a.m. to 6 p.m.                                                                         provide notification of this enforcement
                                                                                                   SUMMARY:    The Coast Guard will enforce              period via the Local Notice to Mariners
                                           From 6 p.m. to 6 a.m., the Montlake
                                                                                                   safety zone regulations for a fireworks               and marine information broadcasts.
                                           Bridge span will remain in the closed-
                                                                                                   display taking place offshore the
                                           to-navigation position, or full closure.                                                                        Dated: August 17, 2016.
                                                                                                   Virginia Beach oceanfront in the
                                              The deviation period is from 6 a.m.                  vicinity of the 20th Street, Virginia                 Richard J. Wester,
                                           until 6 p.m. on September 24, 2016                      Beach, VA, on October 1, 2016. This                   Captain, U.S. Coast Guard, Captain of the
                                           (north single leaf opening if a one hour                action is necessary to ensure safety of               Port, Hampton Roads, VA.
                                           notice is given); from 6 p.m. on                        life on navigable waters during this                  [FR Doc. 2016–21476 Filed 9–6–16; 8:45 am]
                                           September 24, 2016 until 6 a.m. on                      event. Our regulation for Recurring                   BILLING CODE 9110–04–P
                                           September 25, 2016 (span remain in the                  Marine Events within the Fifth Coast
                                           closed-to-navigation position); from 6                  Guard District identifies the regulated
                                           a.m. until 6 p.m. on September 25, 2016                 area for this fireworks display event.                DEPARTMENT OF HOMELAND
                                           (north single leaf opening if a one hour                During the enforcement period, no                     SECURITY
                                           notice is given); from 6 p.m. on                        person or vessel may enter, transit
                                           September 25, 2016 until 6 a.m. on                      through, anchor in, or remain within the              Coast Guard
                                           September 26, 2016 (span remain in the                  regulated area without approval from
                                           closed-to-navigation position). The                     the Captain of the Port Hampton Roads                 33 CFR Part 165
                                           normal operating schedule for the                       or a designated representative.                       [Docket No. USCG- 2016–0788]
                                           Montlake Bridge operates in accordance                  DATES: From 8:30 p.m. through 10 p.m.
                                           with 33 CFR 117.1051(e).                                on October 1, 2016, the regulations in 33             Eighth Coast Guard District Annual
                                                                                                   CFR 165.506 will be enforced for the                  Safety Zones; Pittsburgh Pirates
                                              Waterway usage on the Lake
                                                                                                   safety zone regulated area listed in row              Fireworks; Allegheny River Mile 0.2 to
                                           Washington Ship Canal ranges from
                                                                                                   (c) 9 of the table to § 165.506.                      0.8
                                           commercial tug and barge to small
                                           pleasure craft. Vessels able to pass                    FOR FURTHER INFORMATION CONTACT: If                   AGENCY:  Coast Guard, DHS.
                                           through the bridge in the closed-to-                    you have questions about this notice of               ACTION: Notice of enforcement of
                                           navigation position may do so at any                    enforcement, call or email ENS Chandra                regulation.
                                           time. The bridge will be able to open for               Saunders, U.S. Coast Guard Sector
                                           emergency vessels in route to a call                    Hampton Roads (WWM); telephone                        SUMMARY:   The Coast Guard will enforce
                                           when an hour notice is given to the                     757–668–5582, email                                   a safety zone for the Pittsburgh Pirates
                                           bridge operator, and a single leaf                      Chandra.M.Saunders@uscg.mil.                          Fireworks on the Allegheny River, from
                                           opening will be provided. The Lake                      SUPPLEMENTARY INFORMATION: The Coast                  mile 0.2 to 0.8, to protect vessels
                                           Washington Ship Canal has no                            Guard will enforce the safety zone                    transiting the area and event spectators
                                           immediate alternate route for vessels to                regulations in 33 CFR 165.506 from 8:30               from the hazards associated with the
                                           pass. The Coast Guard will also inform                  p.m. until 10 p.m. on October 1, 2016,                Pittsburgh Pirates land-based fireworks
                                           the users of the waterways through our                  for the safety zone regulated area listed             displays following certain home games
                                           Local and Broadcast Notices to Mariners                 in row (c) 9 of the table to § 165.506.               throughout the season. During the
                                           of the change in operating schedule for                 This enforcement is related to a                      enforcement period, entry into,
                                           the bridge so that vessels can arrange                  fireworks display that is part of the                 transiting, or anchoring in the safety
                                           their transits to minimize any impact                   Virginia Beach Neptune Festival, on the               zone is prohibited to all vessels not
                                           caused by the temporary deviation.                      North Atlantic Ocean, Virginia Beach,                 registered with the sponsor as
                                              In accordance with 33 CFR 117.35(e),                 VA. This action is being taken to                     participants or official patrol vessels,
                                           the drawbridge must return to its regular               provide for the safety of life on                     unless specifically authorized by the
                                           operating schedule immediately at the                   navigable waterways during this event.                Captain of the Port (COTP) Pittsburgh or
                                           end of the designated time period. This                    Our regulation for Recurring Marine                a designated representative.
                                           deviation from the operating regulations                Events within the Fifth Coast Guard                   DATES: The regulations in 33 CFR
                                           is authorized under 33 CFR 117.35.                      District, § 165.506, specifies the location           165.801 Table 1, Sector Ohio Valley, No.
                                                                                                   of the regulated area for this safety zone            1 will be enforced from 8:00 p.m. until
ehiers on DSK5VPTVN1PROD with RULES




                                             Dated: August 25, 2016.                                                                                     11:30 p.m., on September 10, 2016 with
                                                                                                   within a 1000 yard radius of the center
                                           Steven M. Fischer,                                      located near the shoreline at                         a rain date to occur within 48 hours of
                                           Bridge Administrator, Thirteenth Coast Guard            approximate position latitude 36°51′12″               the scheduled date.
                                           District.                                               N., longitude 075°58′06″ W., located off              FOR FURTHER INFORMATION CONTACT: If
                                           [FR Doc. 2016–21448 Filed 9–6–16; 8:45 am]              Virginia Beach, VA between 17th and                   you have questions about this notice of
                                           BILLING CODE 9110–04–P                                  31st streets. As specified in § 165.506               enforcement, call or email MST1


                                      VerDate Sep<11>2014   14:50 Sep 06, 2016   Jkt 238001   PO 00000   Frm 00034   Fmt 4700   Sfmt 4700   E:\FR\FM\07SER1.SGM   07SER1



Document Created: 2016-09-07 11:50:34
Document Modified: 2016-09-07 11:50:34
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionRules and Regulations
ActionNotice of deviation from drawbridge regulation.
DatesThis deviation is effective from 6 a.m. on September 24, 2016 to 6 a.m. on September 26, 2016.
ContactIf you have questions on this temporary deviation, call or email Mr. Steven Fischer, Bridge Administrator, Thirteenth Coast Guard District; telephone 206-220-7282, email [email protected]
FR Citation81 FR 61615 