81_FR_65137 81 FR 64954 - Nuclear Power Plant Instrumentation for Earthquakes

81 FR 64954 - Nuclear Power Plant Instrumentation for Earthquakes

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 81, Issue 183 (September 21, 2016)

Page Range64954-64955
FR Document2016-22743

The U.S. Nuclear Regulatory Commission (NRC) is issuing for public comment draft regulatory guide (DG)-1332, ``Nuclear Power Plant Instrumentation for Earthquakes.'' This DG is proposed Revision 3 of Regulatory Guide 1.12, ``Nuclear Power Plant Instrumentation for Earthquakes.'' The NRC proposes to revise the guide to incorporate advances in seismic instrumentation and operating experience since Revision 2 of RG 1.12 was issued in 1997. The proposed revision describes the seismic instrumentation criteria, including instrumentation type, locations, characteristics, and maintenance, that the NRC staff considers acceptable for nuclear power plants.

Federal Register, Volume 81 Issue 183 (Wednesday, September 21, 2016)
[Federal Register Volume 81, Number 183 (Wednesday, September 21, 2016)]
[Notices]
[Pages 64954-64955]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-22743]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2016-0201]


Nuclear Power Plant Instrumentation for Earthquakes

AGENCY: Nuclear Regulatory Commission.

ACTION: Draft regulatory guide; request for comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing for 
public comment draft regulatory guide (DG)-1332, ``Nuclear Power Plant 
Instrumentation for Earthquakes.'' This DG is proposed Revision 3 of 
Regulatory Guide 1.12, ``Nuclear Power Plant Instrumentation for 
Earthquakes.'' The NRC proposes to revise the guide to incorporate 
advances in seismic instrumentation and operating experience since 
Revision 2 of RG 1.12 was issued in 1997. The proposed revision 
describes the seismic instrumentation criteria, including 
instrumentation type, locations, characteristics, and maintenance, that 
the NRC staff considers acceptable for nuclear power plants.

DATES: Submit comments by November 21, 2016. Comments received after 
this date will be considered if it is practical to do so, but the NRC 
is able to ensure consideration only for comments received on or before 
this date. Although a time limit is given, comments and suggestions in 
connection with items for inclusion in guides currently being developed 
or improvements in all published guides are encouraged at any time.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0201. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     Mail comments to: Cindy Bladey, Office of Administration, 
Mail Stop: OWFN-12H08, U.S. Nuclear Regulatory Commission, Washington, 
DC 20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: Sarah Tabatabai, telephone: 301-415-
2982, email: [email protected]; and Edward O'Donnell, telephone: 
301-415-3317, email: [email protected]. Both are staff of the 
Office of Nuclear Regulatory Research of the U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001.

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2016-0201 when contacting the NRC 
about the availability of information regarding this action. You may 
obtain publically-available information related to this action by any 
of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2016-0201.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
DG is available in ADAMS under Accession No. ML16104A220.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

B. Submitting Comments

    Please include Docket ID NRC-2016-0201 in your comment submission.
    The NRC cautions you not to include identifying or contact 
information that you do not want to be publicly disclosed in your 
comment submission. The NRC posts all comment submissions at http://www.regulations.gov as well as enters the comment submissions into 
ADAMS. The NRC does not routinely edit comment submissions to remove 
identifying or contact information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Additional Information

    The NRC is issuing for public comment a DG in the NRC's 
``Regulatory Guide'' series. This series was developed to describe and 
make

[[Page 64955]]

available to the public information regarding methods that are 
acceptable to the NRC staff for implementing specific parts of the 
NRC's regulations, techniques that the staff uses in evaluating 
specific issues or postulated events, and data that the staff needs in 
its review of applications for permits and licenses.
    The DG entitled, ``Nuclear Power Plant Instrumentation for 
Earthquakes,'' is proposed Revision 3 of RG 1.12, ``Nuclear Power Plant 
Instrumentation for Earthquakes.'' The DG is temporarily identified by 
its task number, DG-1332. The guide proposes revised guidance for the 
seismic instrumentation criteria, including instrumentation type, 
locations, characteristics, and maintenance, that the NRC staff 
considers acceptable for nuclear power plants. The current revision of 
RG 1.12 dates to 1997 and significant technological advances in seismic 
instrumentation have since been made. Lessons learned from the recent 
earthquakes that impacted the North Anna and Fukushima-Dai-ichi nuclear 
power plants indicate a need to update seismic instrumentation guidance 
relative to instrument characteristics, locations, installation, and 
maintenance. In addition, the guide needs to be reformatted to align 
with the current program guidance for regulatory guides.

III. Backfitting and Issue Finality

    This DG describes the seismic instrumentation criteria, including 
instrumentation type, locations, characteristics, and maintenance, that 
the NRC staff considers acceptable for nuclear power plants. Issuance 
of this DG, if finalized, would not constitute backfitting as defined 
in Sec.  50.109 of title 10 of the Code of Federal Regulations (10 CFR) 
(the Backfit Rule) and would not otherwise be inconsistent with the 
issue finality provisions in 10 CFR part 52. As discussed in the 
``Implementation'' section of this DG, the NRC has no current intention 
to impose this guide, if finalized, on holders of current operating 
licenses or combined licenses.
    This DG may be applied to applications for operating licenses, 
combined licenses, early site permits, and certified design rules 
docketed by the NRC as of the date of issuance of the final guide, as 
well as future applications submitted after the issuance of the guide. 
Such action would not constitute backfitting as defined in the Backfit 
Rule or be otherwise inconsistent with the applicable issue finality 
provision in 10 CFR part 52, inasmuch as such applicants or potential 
applicants are not within the scope of entities protected by the 
Backfit Rule or the relevant issue finality provisions in 10 CFR part 
52.

    Dated at Rockville, Maryland, this 16th day of September, 2016.

    For the Nuclear Regulatory Commission.
Thomas H. Boyce,
Chief, Regulatory Guidance and Generic Issues Branch, Division of 
Engineering, Office of Nuclear Regulatory Research.
[FR Doc. 2016-22743 Filed 9-20-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                  64954                    Federal Register / Vol. 81, No. 183 / Wednesday, September 21, 2016 / Notices

                                                  17–19, 2016). OWCP will post your                       ACTION:Draft regulatory guide; request                I. Obtaining Information and
                                                  comments on the Advisory Board Web                      for comment.                                          Submitting Comments
                                                  site and provide your submissions to
                                                                                                          SUMMARY:   The U.S. Nuclear Regulatory                A. Obtaining Information
                                                  Advisory Board members.
                                                     Because of security-related                          Commission (NRC) is issuing for public                   Please refer to Docket ID NRC–2016–
                                                  procedures, receipt of submissions by                   comment draft regulatory guide (DG)–                  0201 when contacting the NRC about
                                                  regular mail may experience significant                 1332, ‘‘Nuclear Power Plant                           the availability of information regarding
                                                  delays.                                                 Instrumentation for Earthquakes.’’ This               this action. You may obtain publically-
                                                     Requests to speak and speaker                        DG is proposed Revision 3 of Regulatory               available information related to this
                                                  presentations: If you want to address the               Guide 1.12, ‘‘Nuclear Power Plant                     action by any of the following methods:
                                                  Advisory Board at the meeting you must                  Instrumentation for Earthquakes.’’ The                   • Federal Rulemaking Web site: Go to
                                                  submit a request to speak, as well as any               NRC proposes to revise the guide to                   http://www.regulations.gov and search
                                                  written or electronic presentation, by                  incorporate advances in seismic                       for Docket ID NRC–2016–0201.
                                                  October 7, 2016, using one of the                       instrumentation and operating                            • NRC’s Agencywide Documents
                                                  methods listed in the ADDRESSES                         experience since Revision 2 of RG 1.12                Access and Management System
                                                  section. Your request may include:                      was issued in 1997. The proposed                      (ADAMS): You may obtain publicly-
                                                     • The amount of time requested to                    revision describes the seismic                        available documents online in the
                                                  speak;                                                  instrumentation criteria, including                   ADAMS Public Documents collection at
                                                     • The interest you represent (e.g.,                  instrumentation type, locations,                      http://www.nrc.gov/reading-rm/
                                                  business, organization, affiliation), if                characteristics, and maintenance, that                adams.html. To begin the search, select
                                                  any; and                                                the NRC staff considers acceptable for                ‘‘ADAMS Public Documents’’ and then
                                                     • A brief outline of the presentation.               nuclear power plants.                                 select ‘‘Begin Web-based ADAMS
                                                     PowerPoint presentations and other                   DATES: Submit comments by November
                                                                                                                                                                Search.’’ For problems with ADAMS,
                                                  electronic materials must be compatible                 21, 2016. Comments received after this                please contact the NRC’s Public
                                                  with PowerPoint 2010 and other                          date will be considered if it is practical            Document Room (PDR) reference staff at
                                                  Microsoft Office 2010 formats. The                      to do so, but the NRC is able to ensure               1–800–397–4209, 301–415–4737, or by
                                                  Advisory Board Chair may grant                          consideration only for comments                       email to pdr.resource@nrc.gov. The DG
                                                  requests to address the Board as time                   received on or before this date.                      is available in ADAMS under Accession
                                                  and circumstances permit.                               Although a time limit is given,                       No. ML16104A220.
                                                     Electronic copies of this Federal                                                                             • NRC’s PDR: You may examine and
                                                                                                          comments and suggestions in
                                                  Register notice are available at http://                                                                      purchase copies of public documents at
                                                                                                          connection with items for inclusion in
                                                  www.regulations.gov. This notice, as                                                                          the NRC’s PDR, Room O1–F21, One
                                                                                                          guides currently being developed or
                                                  well as news releases and other relevant                                                                      White Flint North, 11555 Rockville
                                                                                                          improvements in all published guides
                                                  information, are also available on the                                                                        Pike, Rockville, Maryland 20852.
                                                                                                          are encouraged at any time.
                                                  Advisory Board’s Web page at http://
                                                                                                          ADDRESSES: You may submit comments                    B. Submitting Comments
                                                  www.dol.gov/owcp/energy/regs/
                                                  compliance/AdvisoryBoard.htm.                           by any of the following methods:                        Please include Docket ID NRC–2016–
                                                  FOR FURTHER INFORMATION CONTACT: You                      • Federal Rulemaking Web site: Go to                0201 in your comment submission.
                                                  may contact Antonio Rios, Designated                    http://www.regulations.gov and search                   The NRC cautions you not to include
                                                  Federal Officer, Advisory Board on                      for Docket ID NRC–2016–0201. Address                  identifying or contact information that
                                                  Toxic Substances and Worker Health,                     questions about NRC dockets to Carol                  you do not want to be publicly
                                                  Office of Workers’ Compensation                         Gallagher; telephone: 301–415–3463;                   disclosed in your comment submission.
                                                  Programs, at rios.antonio@dol.gov, or                   email: Carol.Gallagher@nrc.gov. For                   The NRC posts all comment
                                                  Carrie Rhoads, Office of Workers’                       technical questions, contact the                      submissions at http://
                                                  Compensation Programs, at                               individuals listed in the FOR FURTHER                 www.regulations.gov as well as enters
                                                  rhoads.carrie@dol.gov, U.S. Department                  INFORMATION CONTACT section of this                   the comment submissions into ADAMS.
                                                  of Labor, 200 Constitution Ave. NW.,                    document.                                             The NRC does not routinely edit
                                                  Suite S–3524, Washington, DC 20210,                       • Mail comments to: Cindy Bladey,                   comment submissions to remove
                                                  telephone (202) 343–5580. This is not a                 Office of Administration, Mail Stop:                  identifying or contact information.
                                                                                                          OWFN–12H08, U.S. Nuclear Regulatory                     If you are requesting or aggregating
                                                  toll-free number.
                                                                                                          Commission, Washington, DC 20555–                     comments from other persons for
                                                    Signed at Washington, DC, this 15th day of                                                                  submission to the NRC, then you should
                                                                                                          0001.
                                                  September, 2016.                                                                                              inform those persons not to include
                                                                                                            For additional direction on obtaining
                                                  Leonard J. Howie III,                                                                                         identifying or contact information that
                                                                                                          information and submitting comments,
                                                  Director, Office of Workers’ Compensation                                                                     they do not want to be publicly
                                                                                                          see ‘‘Obtaining Information and
                                                  Programs.                                                                                                     disclosed in their comment submission.
                                                                                                          Submitting Comments’’ in the
                                                  [FR Doc. 2016–22712 Filed 9–20–16; 8:45 am]
                                                                                                          SUPPLEMENTARY INFORMATION section of                  Your request should state that the NRC
                                                  BILLING CODE 4510–24–P
                                                                                                          this document.                                        does not routinely edit comment
                                                                                                                                                                submissions to remove such information
                                                                                                          FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                before making the comment
                                                                                                          Sarah Tabatabai, telephone: 301–415–                  submissions available to the public or
                                                  NUCLEAR REGULATORY
                                                                                                          2982, email: Sarah.Tabatabai@nrc.gov;
mstockstill on DSK3G9T082PROD with NOTICES




                                                  COMMISSION                                                                                                    entering the comment submissions into
                                                                                                          and Edward O’Donnell, telephone: 301–                 ADAMS.
                                                  [NRC–2016–0201]                                         415–3317, email: Edward.ODonnell@
                                                                                                          nrc.gov. Both are staff of the Office of              II. Additional Information
                                                  Nuclear Power Plant Instrumentation                     Nuclear Regulatory Research of the U.S.
                                                  for Earthquakes                                                                                                  The NRC is issuing for public
                                                                                                          Nuclear Regulatory Commission,                        comment a DG in the NRC’s ‘‘Regulatory
                                                  AGENCY:Nuclear Regulatory                               Washington, DC 20555–0001.                            Guide’’ series. This series was
                                                  Commission.                                             SUPPLEMENTARY INFORMATION:                            developed to describe and make


                                             VerDate Sep<11>2014   18:19 Sep 20, 2016   Jkt 238001   PO 00000   Frm 00086   Fmt 4703   Sfmt 4703   E:\FR\FM\21SEN1.SGM   21SEN1


                                                                          Federal Register / Vol. 81, No. 183 / Wednesday, September 21, 2016 / Notices                                           64955

                                                  available to the public information                     not within the scope of entities                      Gallagher; telephone: 301–415–3463;
                                                  regarding methods that are acceptable to                protected by the Backfit Rule or the                  email: Carol.Gallagher@nrc.gov. For
                                                  the NRC staff for implementing specific                 relevant issue finality provisions in 10              technical questions, contact the
                                                  parts of the NRC’s regulations,                         CFR part 52.                                          individuals listed in the FOR FURTHER
                                                  techniques that the staff uses in                          Dated at Rockville, Maryland, this 16th day        INFORMATION CONTACT section of this
                                                  evaluating specific issues or postulated                of September, 2016.                                   document.
                                                  events, and data that the staff needs in                   For the Nuclear Regulatory Commission.               • Mail comments to: Cindy Bladey,
                                                  its review of applications for permits                                                                        Office of Administration, Mail Stop:
                                                                                                          Thomas H. Boyce,
                                                  and licenses.                                                                                                 OWFN–12–H08, U.S. Nuclear
                                                     The DG entitled, ‘‘Nuclear Power                     Chief, Regulatory Guidance and Generic
                                                                                                          Issues Branch, Division of Engineering, Office        Regulatory Commission, Washington,
                                                  Plant Instrumentation for Earthquakes,’’                                                                      DC 20555–0001.
                                                                                                          of Nuclear Regulatory Research.
                                                  is proposed Revision 3 of RG 1.12,                                                                              For additional direction on obtaining
                                                                                                          [FR Doc. 2016–22743 Filed 9–20–16; 8:45 am]
                                                  ‘‘Nuclear Power Plant Instrumentation                                                                         information and submitting comments,
                                                  for Earthquakes.’’ The DG is temporarily                BILLING CODE 7590–01–P
                                                                                                                                                                see ‘‘Obtaining Information and
                                                  identified by its task number, DG–1332.                                                                       Submitting Comments’’ in the
                                                  The guide proposes revised guidance for                                                                       SUPPLEMENTARY INFORMATION section of
                                                  the seismic instrumentation criteria,                   NUCLEAR REGULATORY
                                                                                                          COMMISSION                                            this document.
                                                  including instrumentation type,
                                                  locations, characteristics, and                                                                               FOR FURTHER INFORMATION CONTACT:
                                                                                                          [NRC–2016–0189]
                                                  maintenance, that the NRC staff                                                                               Glenn Tuttle, Office of Nuclear Material
                                                  considers acceptable for nuclear power                  Shipping, Receiving, and Internal                     Safety and Safeguards, 301–415–7230,
                                                  plants. The current revision of RG 1.12                 Transfer of Special Nuclear Material                  email: Glenn.Tuttle@nrc.gov, or
                                                  dates to 1997 and significant                                                                                 Mekonen Bayssie, Office of Nuclear
                                                                                                          AGENCY: Nuclear Regulatory                            Regulatory Research, 301–415–1699,
                                                  technological advances in seismic                       Commission.
                                                  instrumentation have since been made.                                                                         email: Mekonen.Bayssie@nrc.gov, U.S.
                                                                                                          ACTION: Draft regulatory guide; request               Nuclear Regulatory Commission,
                                                  Lessons learned from the recent
                                                  earthquakes that impacted the North                     for comment.                                          Washington, DC 20555–0001.
                                                  Anna and Fukushima-Dai-ichi nuclear                     SUMMARY:   The U.S. Nuclear Regulatory                SUPPLEMENTARY INFORMATION:
                                                  power plants indicate a need to update                  Commission (NRC) is issuing for public                I. Obtaining Information and
                                                  seismic instrumentation guidance                        comment Draft Regulatory Guide (DG)                   Submitting Comments
                                                  relative to instrument characteristics,                 DG–5051, ‘‘Shipping, Receiving, and
                                                  locations, installation, and maintenance.               Internal Transfer of Special Nuclear                  A. Obtaining Information
                                                  In addition, the guide needs to be                      Material.’’ This DG would consolidate                    Please refer to Docket ID NRC–2016–
                                                  reformatted to align with the current                   in one document NRC guidance                          0189 when contacting the NRC about
                                                  program guidance for regulatory guides.                 concerning the material control and                   the availability of information for this
                                                  III. Backfitting and Issue Finality                     accounting requirements pertaining to                 action. You may obtain publicly-
                                                     This DG describes the seismic                        shipments, receipts, and internal                     available information related to this
                                                  instrumentation criteria, including                     transfers of special nuclear material.                action by any of the following methods:
                                                  instrumentation type, locations,                        The DG is part of the NRC’s ‘‘Regulatory                 • Federal rulemaking Web site: Go to
                                                  characteristics, and maintenance, that                  Guide’’ series. This series was                       http://www.regulations.gov and search
                                                  the NRC staff considers acceptable for                  developed to describe and make                        for Docket ID NRC–2016–0189.
                                                  nuclear power plants. Issuance of this                  available to the public information                      • NRC’s Agencywide Documents
                                                  DG, if finalized, would not constitute                  regarding methods that are acceptable to              Access and Management System
                                                  backfitting as defined in § 50.109 of title             the NRC staff for implementing specific               (ADAMS): You may obtain publicly-
                                                  10 of the Code of Federal Regulations                   parts of the NRC’s regulations,                       available documents online in the
                                                  (10 CFR) (the Backfit Rule) and would                   techniques that the staff uses in                     ADAMS Public Documents collection at
                                                  not otherwise be inconsistent with the                  evaluating specific issues or postulated              http://www.nrc.gov/reading-rm/
                                                  issue finality provisions in 10 CFR part                events, and data that the staff needs in              adams.html. To begin the search, select
                                                  52. As discussed in the                                 its review of applications for permits                ‘‘ADAMS Public Documents’’ and then
                                                  ‘‘Implementation’’ section of this DG,                  and licenses.                                         select ‘‘Begin Web-based ADAMS
                                                  the NRC has no current intention to                     DATES: Submit comments by October 21,                 Search. ’’ For problems with ADAMS,
                                                  impose this guide, if finalized, on                     2016. Comments received after this date               please contact the NRC’s Public
                                                  holders of current operating licenses or                will be considered if it is practical to do           Document Room (PDR) reference staff at
                                                  combined licenses.                                      so, but the NRC is able to ensure                     1–800–397–4209, 301–415–4737, or by
                                                     This DG may be applied to                            consideration only for comments                       email to pdr.resource@nrc.gov. The
                                                  applications for operating licenses,                    received on or before this date.                      ADAMS accession number for each
                                                  combined licenses, early site permits,                  Although a time limit is given,                       document referenced (if it is available in
                                                  and certified design rules docketed by                  comments and suggestions in                           ADAMS) is provided the first time that
                                                  the NRC as of the date of issuance of the               connection with items for inclusion in                it is mentioned in this document.
                                                  final guide, as well as future                          guides currently being developed or                      • NRC’s PDR: You may examine and
                                                  applications submitted after the                        improvements in all published guides                  purchase copies of public documents at
mstockstill on DSK3G9T082PROD with NOTICES




                                                  issuance of the guide. Such action                      are encouraged at any time.                           the NRC’s PDR, Room O1–F21, One
                                                  would not constitute backfitting as                     ADDRESSES: You may submit comments                    White Flint North, 11555 Rockville
                                                  defined in the Backfit Rule or be                       by any of the following methods:                      Pike, Rockville, Maryland 20852.
                                                  otherwise inconsistent with the                            • Federal Rulemaking Web site: Go to
                                                  applicable issue finality provision in 10                                                                     B. Submitting Comments
                                                                                                          http://www.regulations.gov and search
                                                  CFR part 52, inasmuch as such                           for Docket ID NRC–2016–0189. Address                    Please include Docket ID NRC–2016–
                                                  applicants or potential applicants are                  questions about NRC dockets to Carol                  0189 in your comment submission.


                                             VerDate Sep<11>2014   18:19 Sep 20, 2016   Jkt 238001   PO 00000   Frm 00087   Fmt 4703   Sfmt 4703   E:\FR\FM\21SEN1.SGM   21SEN1



Document Created: 2016-09-21 01:31:12
Document Modified: 2016-09-21 01:31:12
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDraft regulatory guide; request for comment.
DatesSubmit comments by November 21, 2016. Comments received after this date will be considered if it is practical to do so, but the NRC is able to ensure consideration only for comments received on or before this date. Although a time limit is given, comments and suggestions in connection with items for inclusion in guides currently being developed or improvements in all published guides are encouraged at any time.
ContactSarah Tabatabai, telephone: 301-415- 2982, email: [email protected]; and Edward O'Donnell, telephone: 301-415-3317, email: [email protected] Both are staff of the Office of Nuclear Regulatory Research of the U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001.
FR Citation81 FR 64954 

2025 Federal Register | Disclaimer | Privacy Policy