81_FR_66454 81 FR 66267 - Columbia Gas Transmission, LLC; Notice of Application

81 FR 66267 - Columbia Gas Transmission, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 187 (September 27, 2016)

Page Range66267-66268
FR Document2016-23233

Federal Register, Volume 81 Issue 187 (Tuesday, September 27, 2016)
[Federal Register Volume 81, Number 187 (Tuesday, September 27, 2016)]
[Notices]
[Pages 66267-66268]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-23233]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP16-498-000; PF16-4-000]


Columbia Gas Transmission, LLC; Notice of Application

    Take notice that on September 9, 2016, Columbia Gas Transmission, 
LLC (Columbia), 5151 San Felipe, Suite 2500, Houston, Texas 77056, 
filed an application pursuant to sections 7(b) and 7(c) of the Natural 
Gas Act (NGA) requesting authorization to: (i) Abandon in place 17.5 
miles of its Line B-105, (ii) replace 14 miles of its Line B-111, (iii) 
replace 0.1 miles of its Line B-121, (iv) replace 0.5 miles of its Line 
B-130, (v) install 7.6 miles of Line K-270 pipeline, and (vi) remove or 
install various appurtenances, all located in Fairfield and Franklin 
Counties, Ohio. Columbia states that there will be no change in 
certificated capacity. Columbia estimates the cost of the proposed 
project to be approximately $182,773,707, all as more fully set forth 
in the application which is on file with the Commission and open to 
public inspection. The filing is available for review at the Commission 
in the Public Reference Room or may be viewed on the Commission's Web 
site web at http://www.ferc.gov using the ``eLibrary'' link. Enter the 
docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
FERCOnlineSupport@ferc.gov or call toll-free, (886) 208-3676 or TYY, 
(202) 502-8659.
    Any questions concerning these applications may be directed to 
Tyler R. Brown, Senior Counsel, Columbia Gas Transmission, LLC, 5151 
San Felipe, Suite 2500, Houston, Texas 77056, by telephone at (713) 
386-3797.
    On March 10, 2016, the Commission staff granted Columbia's request 
to utilize the Pre-Filing Process and assigned Docket No. PF16-4-000 to 
staff activities involved in the above referenced project. Now, as of 
the filing of the September 9, 2016 application, the Pre-Filing Process 
for this project has ended. From this time forward, this proceeding 
will be conducted in Docket No. CP16-498-000 as noted in the caption of 
this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit seven copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 7 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: October 12, 2016.


[[Page 66268]]


    Dated: September 21, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-23233 Filed 9-26-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 81, No. 187 / Tuesday, September 27, 2016 / Notices                                          66267

                                                    protests must be filed on or before the                 the Commission and open to public                     CFR 157.10). A person obtaining party
                                                    comment date. On or before the                          inspection. The filing is available for               status will be placed on the service list
                                                    comment date, it is not necessary to                    review at the Commission in the Public                maintained by the Secretary of the
                                                    serve motions to intervene or protests                  Reference Room or may be viewed on                    Commission and will receive copies of
                                                    on persons other than the Applicant.                    the Commission’s Web site web at                      all documents filed by the applicant and
                                                       The Commission encourages                            http://www.ferc.gov using the                         by all other parties. A party must submit
                                                    electronic submission of protests and                   ‘‘eLibrary’’ link. Enter the docket                   seven copies of filings made in the
                                                    interventions in lieu of paper using the                number excluding the last three digits in             proceeding with the Commission and
                                                    ‘‘eFiling’’ link at http://www.ferc.gov.                the docket number field to access the                 must mail a copy to the applicant and
                                                    Persons unable to file electronically                   document. For assistance, contact FERC
                                                                                                                                                                  to every other party. Only parties to the
                                                    should submit an original and 5 copies                  at FERCOnlineSupport@ferc.gov or call
                                                                                                                                                                  proceeding can ask for court review of
                                                    of the protest or intervention to the                   toll-free, (886) 208–3676 or TYY, (202)
                                                                                                            502–8659.                                             Commission orders in the proceeding.
                                                    Federal Energy Regulatory Commission,
                                                    888 First Street NE., Washington, DC                       Any questions concerning these                        However, a person does not have to
                                                    20426.                                                  applications may be directed to Tyler R.              intervene in order to have comments
                                                       This filing is accessible on-line at                 Brown, Senior Counsel, Columbia Gas                   considered. The second way to
                                                    http://www.ferc.gov, using the                          Transmission, LLC, 5151 San Felipe,                   participate is by filing with the
                                                    ‘‘eLibrary’’ link and is available for                  Suite 2500, Houston, Texas 77056, by                  Secretary of the Commission, as soon as
                                                    review in the Commission’s Public                       telephone at (713) 386–3797.                          possible, an original and two copies of
                                                    Reference Room in Washington, DC.                          On March 10, 2016, the Commission                  comments in support of or in opposition
                                                    There is an ‘‘eSubscription’’ link on the               staff granted Columbia’s request to                   to this project. The Commission will
                                                    Web site that enables subscribers to                    utilize the Pre-Filing Process and                    consider these comments in
                                                    receive email notification when a                       assigned Docket No. PF16–4–000 to staff
                                                                                                                                                                  determining the appropriate action to be
                                                    document is added to a subscribed                       activities involved in the above
                                                                                                                                                                  taken, but the filing of a comment alone
                                                    docket(s). For assistance with any FERC                 referenced project. Now, as of the filing
                                                                                                            of the September 9, 2016 application,                 will not serve to make the filer a party
                                                    Online service, please email                                                                                  to the proceeding. The Commission’s
                                                    FERCOnlineSupport@ferc.gov, or call                     the Pre-Filing Process for this project
                                                                                                            has ended. From this time forward, this               rules require that persons filing
                                                    (866) 208–3676 (toll free). For TTY, call                                                                     comments in opposition to the project
                                                    (202) 502–8659.                                         proceeding will be conducted in Docket
                                                                                                            No. CP16–498–000 as noted in the                      provide copies of their protests only to
                                                       Comment Date: 5:00 p.m. Eastern                                                                            the party or parties directly involved in
                                                    Time on October 11, 2016.                               caption of this Notice.
                                                                                                               Pursuant to section 157.9 of the                   the protest.
                                                      Dated: September 20, 2016.                            Commission’s rules, 18 CFR 157.9,                        Persons who wish to comment only
                                                    Kimberly D. Bose,                                       within 90 days of this Notice the                     on the environmental review of this
                                                    Secretary.                                              Commission staff will either: Complete                project should submit an original and
                                                    [FR Doc. 2016–23238 Filed 9–26–16; 8:45 am]             its environmental assessment (EA) and
                                                                                                                                                                  two copies of their comments to the
                                                                                                            place it into the Commission’s public
                                                    BILLING CODE 6717–01–P                                                                                        Secretary of the Commission.
                                                                                                            record (eLibrary) for this proceeding; or
                                                                                                            issue a Notice of Schedule for                        Environmental commentors will be
                                                                                                            Environmental Review. If a Notice of                  placed on the Commission’s
                                                    DEPARTMENT OF ENERGY
                                                                                                            Schedule for Environmental Review is                  environmental mailing list, will receive
                                                    Federal Energy Regulatory                               issued, it will indicate, among other                 copies of the environmental documents,
                                                    Commission                                              milestones, the anticipated date for the              and will be notified of meetings
                                                                                                            Commission staff’s issuance of the EA                 associated with the Commission’s
                                                    [Docket Nos. CP16–498–000; PF16–4–000]
                                                                                                            for this proposal. The filing of the EA               environmental review process.
                                                    Columbia Gas Transmission, LLC;                         in the Commission’s public record for                 Environmental commentors will not be
                                                    Notice of Application                                   this proceeding or the issuance of a                  required to serve copies of filed
                                                                                                            Notice of Schedule for Environmental                  documents on all other parties.
                                                      Take notice that on September 9,                      Review will serve to notify federal and               However, the non-party commentors
                                                    2016, Columbia Gas Transmission, LLC                    state agencies of the timing for the                  will not receive copies of all documents
                                                    (Columbia), 5151 San Felipe, Suite                      completion of all necessary reviews, and              filed by other parties or issued by the
                                                    2500, Houston, Texas 77056, filed an                    the subsequent need to complete all                   Commission (except for the mailing of
                                                    application pursuant to sections 7(b)                   federal authorizations within 90 days of              environmental documents issued by the
                                                    and 7(c) of the Natural Gas Act (NGA)                   the date of issuance of the Commission                Commission) and will not have the right
                                                    requesting authorization to: (i) Abandon                staff’s EA.                                           to seek court review of the
                                                    in place 17.5 miles of its Line B–105, (ii)                There are two ways to become
                                                                                                                                                                  Commission’s final order.
                                                    replace 14 miles of its Line B–111, (iii)               involved in the Commission’s review of
                                                    replace 0.1 miles of its Line B–121, (iv)               this project. First, any person wishing to               The Commission strongly encourages
                                                    replace 0.5 miles of its Line B–130, (v)                obtain legal status by becoming a party               electronic filings of comments, protests
                                                    install 7.6 miles of Line K–270 pipeline,               to the proceedings for this project                   and interventions in lieu of paper using
                                                    and (vi) remove or install various                      should, on or before the comment date                 the ‘‘eFiling’’ link at http://
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    appurtenances, all located in Fairfield                 stated below file with the Federal                    www.ferc.gov. Persons unable to file
                                                    and Franklin Counties, Ohio. Columbia                   Energy Regulatory Commission, 888                     electronically should submit an original
                                                    states that there will be no change in                  First Street NE., Washington, DC 20426,               and 7 copies of the protest or
                                                    certificated capacity. Columbia                         a motion to intervene in accordance                   intervention to the Federal Energy
                                                    estimates the cost of the proposed                      with the requirements of the                          regulatory Commission, 888 First Street
                                                    project to be approximately                             Commission’s Rules of Practice and                    NE., Washington, DC 20426.
                                                    $182,773,707, all as more fully set forth               Procedure (18 CFR 385.214 or 385.211)
                                                                                                                                                                     Comment Date: October 12, 2016.
                                                    in the application which is on file with                and the Regulations under the NGA (18


                                               VerDate Sep<11>2014   17:08 Sep 26, 2016   Jkt 238001   PO 00000   Frm 00015   Fmt 4703   Sfmt 4703   E:\FR\FM\27SEN1.SGM   27SEN1


                                                    66268                     Federal Register / Vol. 81, No. 187 / Tuesday, September 27, 2016 / Notices

                                                      Dated: September 21, 2016.                            FERCOnlineSupport@ferc.gov, or call                   reduced with the implementation of
                                                    Kimberly D. Bose,                                       (866) 208–3676 (toll free). For TTY, call             Mountain Valley’s and Equitrans’
                                                    Secretary.                                              (202) 502–8659.                                       proposed mitigation measures, and the
                                                    [FR Doc. 2016–23233 Filed 9–26–16; 8:45 am]               Comment Date: 5:00 p.m. Eastern                     additional measures recommended by
                                                    BILLING CODE 6717–01–P
                                                                                                            Time on October 11, 2016.                             the FERC staff in the EIS.
                                                                                                              Dated: September 19, 2016.                             The United States Department of
                                                                                                            Kimberly D. Bose,                                     Agriculture Forest Service (FS), U.S.
                                                    DEPARTMENT OF ENERGY                                                                                          Army Corps of Engineers (COE), U.S.
                                                                                                            Secretary.
                                                                                                                                                                  Environmental Protection Agency, U.S.
                                                    Federal Energy Regulatory                               [FR Doc. 2016–23235 Filed 9–26–16; 8:45 am]
                                                                                                                                                                  Department of the Interior Bureau of
                                                    Commission                                              BILLING CODE 6717–01–P
                                                                                                                                                                  Land Management (BLM), U.S.
                                                    [Docket No. ID–8008–000]
                                                                                                                                                                  Department of Transportation, West
                                                                                                                                                                  Virginia Department of Environmental
                                                                                                            DEPARTMENT OF ENERGY
                                                    Hastings, Michael W.; Notice of Filing                                                                        Protection, and West Virginia Division
                                                                                                            Federal Energy Regulatory                             of Natural Resources participated as
                                                       Take notice that on September 19,                                                                          cooperating agencies in the preparation
                                                                                                            Commission
                                                    2016, Michael W. Hastings submitted                                                                           of the EIS. Cooperating agencies have
                                                    for filing, an application for authority to             [Docket No. CP16–10–000; Docket No.                   jurisdiction by law or special expertise
                                                    hold interlocking positions, pursuant to                CP16–13–000]                                          with respect to resources potentially
                                                    section 305(b) of the Federal Power Act                                                                       affected by the proposals and
                                                    (FPA), 16 U.S.C. 825d(b), Part 45 of the                Mountain Valley Pipeline LLC,                         participated in the NEPA analysis. The
                                                    Federal Energy Regulatory                               Equitrans LP; Notice of Availability of               BLM, COE, and FS may adopt and use
                                                    Commission’s (Commission) Rules of                      the Draft Environmental Impact                        the EIS when they consider the issuance
                                                    Practice and Procedure, 18 CFR part 45,                 Statement for the Proposed Mountain                   of a Right-of-Way Grant to Mountain
                                                    and Order No. 664.1                                     Valley Project and Equitrans                          Valley for the portion of the MVP that
                                                       Any person desiring to intervene or to               Expansion Project                                     would cross federal lands. Further, the
                                                    protest this filing must file in                           The staff of the Federal Energy                    FS may use the EIS when it considers
                                                    accordance with Rules 211 and 214 of                    Regulatory Commission (FERC or                        amendments to its Land and Resource
                                                    the Commission’s Rules of Practice and                  Commission) has prepared a draft                      Management Plan (LRMP) for the
                                                    Procedure (18 CFR 385.211, 385.214).                    environmental impact statement (EIS)                  proposed crossing of the Jefferson
                                                    Protests will be considered by the                      for the projects proposed by Mountain                 National Forest. Although the
                                                    Commission in determining the                           Valley Pipeline LLC (Mountain Valley)                 cooperating agencies provided input to
                                                    appropriate action to be taken, but will                and Equitrans LP (Equitrans) in the                   the conclusions and recommendations
                                                    not serve to make protestants parties to                above-referenced dockets. Mountain                    presented in the draft EIS, the agencies
                                                    the proceeding. Any person wishing to                   Valley requests authorization to                      will present their own conclusions and
                                                    become a party must file a notice of                    construct and operate certain interstate              recommendations in their respective
                                                    intervention or motion to intervene, as                 natural gas facilities in West Virginia               permit authorizations and Records of
                                                    appropriate. Such notices, motions, or                  and Virginia, known as the Mountain                   Decision (ROD) for the projects.
                                                    protests must be filed on or before the                 Valley Project (MVP) in Docket Number
                                                    comment date. On or before the                                                                                Proposed Facilities
                                                                                                            CP16–10–000. The MVP is designed to
                                                    comment date, it is not necessary to                    transport about 2 billion cubic feet per                The draft EIS addresses the potential
                                                    serve motions to intervene or protests                  day (Bcf/d) of natural gas from                       environmental effects of the
                                                    on persons other than the Applicant.                    production areas in the Appalachian                   construction and operation of the
                                                       The Commission encourages                            Basin to markets in the Mid-Atlantic                  proposed facilities. For the MVP,
                                                    electronic submission of protests and                   and Southeastern United States.                       facilities include:
                                                    interventions in lieu of paper using the                Equitrans requests authorization to                     • About 301 miles of new 42-inch-
                                                    ‘‘eFiling’’ link at http://www.ferc.gov.                construct and operate certain natural gas             diameter pipeline extending from the
                                                    Persons unable to file electronically                   facilities in Pennsylvania and West                   new Mobley Interconnect in Wetzel
                                                    should submit an original and 5 copies                  Virginia, known as the Equitrans                      County, West Virginia to the existing
                                                    of the protest or intervention to the                   Expansion Project (EEP) in Docket No.                 Transcontinental Gas Pipe Line
                                                    Federal Energy Regulatory Commission,                   CP16–13–000. The EEP is designed to                   Company LLC (Transco) Station 165 in
                                                    888 First Street NE., Washington, DC                    transport about 0.4 Bcf/d of natural gas,             Pittsylvania County, Virginia;
                                                    20426.                                                  to improve system flexibility and                       • 3 new compressor stations
                                                       This filing is accessible on-line at                 reliability, and serve markets in the                 (Bradshaw, Harris, Stallworth) in West
                                                    http://www.ferc.gov, using the                          Northeast, Mid-Atlantic, and Southeast,               Virginia, totaling about 171,600
                                                    ‘‘eLibrary’’ link and is available for                  through interconnections with various                 horsepower (hp);
                                                    electronic review in the Commission’s                   other interstate systems, including the                 • 4 new meter and regulation stations
                                                    Public Reference Room in Washington,                    proposed MVP.                                         and interconnections (Mobley,
                                                    DC. There is an ‘‘eSubscription’’ link on                  The draft EIS assesses the potential               Sherwood, WB, and Transco);
                                                    the Web site that enables subscribers to                environmental effects of the                            • 2 new taps (Webster and Roanoke);
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    receive email notification when a                       construction and operation of the MVP                   • 5 pig 1 launchers and receivers; and
                                                    document is added to a subscribed                       and EEP in accordance with the                          • 36 mainline block valves.
                                                    docket(s). For assistance with any FERC                 requirements of the National                            For the EEP, facilities include:
                                                    Online service, please email                            Environmental Policy Act (NEPA). The                    • About 8 miles total of new various
                                                      1 Commission Authorization to Hold Interlocking
                                                                                                            FERC staff concludes that approval of                 diameter pipelines in six segments;
                                                    Positions, 112 FERC ¶ 61,298 (2005) (Order No.
                                                                                                            the MVP and EEP would have some
                                                    664); order on reh’g, 114 FERC ¶ 61,142 (2006)          adverse environmental impacts;                          1 A ‘‘pig’’ is a device used to clean or inspect the

                                                    (Order No. 664–A).                                      however, these impacts would be                       interior of a pipeline.



                                               VerDate Sep<11>2014   17:08 Sep 26, 2016   Jkt 238001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\27SEN1.SGM   27SEN1



Document Created: 2016-09-27 01:19:09
Document Modified: 2016-09-27 01:19:09
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesOctober 12, 2016.
FR Citation81 FR 66267 

2025 Federal Register | Disclaimer | Privacy Policy