The U.S. Army Corps of Engineers (Corps) Seattle District has prepared a Draft Environmental Impact Statement (EIS) to analyze the direct, indirect, and cumulative effects of an action proposed by Millennium Bulk Terminals--Longview, LLC (MBTL) involving the Columbia River and adjacent waters of the United States. The Proposed Action is to construct and operate a shipping terminal to export up to 44 million metric tons of coal per year. Construction of the terminal and support facilities would result in the permanent loss of 29.3 acres of waters of the United States, consisting of 24.1 acres of wetlands and 5.2 acres of ditches and other waters. The proposed work requires Department of the Army authorization from the Corps under Section 10 of the Rivers and Harbors Act and Section 404 of the Clean Water Act. The permit applicant is Millennium Bulk Terminals--Longview, LLC. This Draft EIS was prepared in accordance with the National Environmental Policy Act (NEPA) of 1969, as amended, and Corps regulations for implementing NEPA (33 Code of Federal Regulations [CFR] Part 230 and Part 325, Appendix B). The Corps' Seattle District, is the lead federal agency, with the Environmental Protection Agency and U.S. Coast Guard participating as cooperating agencies. Information contained in this EIS will support a future decision regarding issuance of a Department of the Army permit under Sections 10 and 404. This EIS also provides information for state, local, and other Federal agencies having jurisdictional responsibility for the affected resources.

Federal Register, Volume 81 Issue 195 (Friday, October 7, 2016)
[Federal Register Volume 81, Number 195 (Friday, October 7, 2016)]
[Notices]
[Page 69803]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-24312]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army, Corps of Engineers


Notice of Availability of the Draft Environmental Impact 
Statement for Millennium Bulk Terminals--Longview, LLC Shipping 
Terminal, in the Columbia River, Near Longview, Cowlitz County, 
Washington

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: The U.S. Army Corps of Engineers (Corps) Seattle District has 
prepared a Draft Environmental Impact Statement (EIS) to analyze the 
direct, indirect, and cumulative effects of an action proposed by 
Millennium Bulk Terminals--Longview, LLC (MBTL) involving the Columbia 
River and adjacent waters of the United States. The Proposed Action is 
to construct and operate a shipping terminal to export up to 44 million 
metric tons of coal per year. Construction of the terminal and support 
facilities would result in the permanent loss of 29.3 acres of waters 
of the United States, consisting of 24.1 acres of wetlands and 5.2 
acres of ditches and other waters. The proposed work requires 
Department of the Army authorization from the Corps under Section 10 of 
the Rivers and Harbors Act and Section 404 of the Clean Water Act. The 
permit applicant is Millennium Bulk Terminals--Longview, LLC.
    This Draft EIS was prepared in accordance with the National 
Environmental Policy Act (NEPA) of 1969, as amended, and Corps 
regulations for implementing NEPA (33 Code of Federal Regulations [CFR] 
Part 230 and Part 325, Appendix B). The Corps' Seattle District, is the 
lead federal agency, with the Environmental Protection Agency and U.S. 
Coast Guard participating as cooperating agencies. Information 
contained in this EIS will support a future decision regarding issuance 
of a Department of the Army permit under Sections 10 and 404. This EIS 
also provides information for state, local, and other Federal agencies 
having jurisdictional responsibility for the affected resources.

DATES: Written comments on the Draft EIS will be accepted thru November 
29, 2016. Oral and/or written comments may also be presented at Public 
Hearings to be held Monday, October 24, 2016 at the Cowlitz County 
Regional Conference Center, 1900 7th Avenue, Longview, Washington and 
on Tuesday, October 25, 2016 at the Clark County Event Center, 17402 NE 
Delfel Road, Ridgefield, Washington. Each hearing is scheduled for 1:00 
p.m. to 9:00 p.m., with a one-hour break between 4:00 p.m. and 5:00 
p.m.

ADDRESSES: Send written comments regarding the Proposed Action and 
Draft EIS to Ms. Danette L. Guy, U.S. Army Corps of Engineers, 
Millennium Bulk Terminals--Longview NEPA EIS, c/o ICF International, 
710 Second Avenue, Suite 550, Seattle, WA 98104. Comments may also be 
submitted online at http://www.millenniumbulkeiswa.gov/submit-comments.html.

FOR FURTHER INFORMATION CONTACT: Ms. Danette L. Guy, Project Manager, 
U.S. Army Corps of Engineers, Seattle District, Regulatory Branch by 
email at [email protected] or by telephone at (206) 316-3048.

SUPPLEMENTARY INFORMATION: The purpose of the Draft EIS is to provide 
decision makers and the public information pertaining to the Proposed 
Action, including alternatives, environmental impacts, and mitigation 
measures that could reduce impacts of the action.
    An electronic copy of the Draft EIS may be obtained by visiting the 
project Web site at http://www.millenniumbulkeiswa.gov/.

    Dated: September 30, 2016.
John G. Buck,
Colonel, Corps of Engineers, District Engineer, Seattle District.
[FR Doc. 2016-24312 Filed 10-6-16; 8:45 am]
 BILLING CODE 3720-58-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesWritten comments on the Draft EIS will be accepted thru November 29, 2016. Oral and/or written comments may also be presented at Public Hearings to be held Monday, October 24, 2016 at the Cowlitz County Regional Conference Center, 1900 7th Avenue, Longview, Washington and on Tuesday, October 25, 2016 at the Clark County Event Center, 17402 NE Delfel Road, Ridgefield, Washington. Each hearing is scheduled for 1:00 p.m. to 9:00 p.m., with a one-hour break between 4:00 p.m. and 5:00 p.m.
ContactMs. Danette L. Guy, Project Manager, U.S. Army Corps of Engineers, Seattle District, Regulatory Branch by email at [email protected] or by telephone at (206) 316-3048.
FR Citation81 FR 69803 

2024 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR