81_FR_70303 81 FR 70107 - Moriah Hydro Corporation; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests

81 FR 70107 - Moriah Hydro Corporation; Notice of Application Accepted for Filing and Soliciting Motions To Intervene and Protests

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 196 (October 11, 2016)

Page Range70107-70108
FR Document2016-24471

Federal Register, Volume 81 Issue 196 (Tuesday, October 11, 2016)
[Federal Register Volume 81, Number 196 (Tuesday, October 11, 2016)]
[Notices]
[Pages 70107-70108]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-24471]



[[Page 70107]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No.: P-12635-002]


Moriah Hydro Corporation; Notice of Application Accepted for 
Filing and Soliciting Motions To Intervene and Protests

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original Major License.
    b. Project No.: P-12635-002.
    c. Date filed: February 13, 2015.
    d. Applicant: Moriah Hydro Corporation.
    e. Name of Project: Mineville Energy Storage Project.
    f. Location: The project would be located in an abandoned 
subterranean mine complex \1\ in the town of Moriah, Essex County, New 
York. No federal lands are occupied by project works or located within 
the project boundary.
---------------------------------------------------------------------------

    \1\ The existing mine complex is composed of the interconnected 
Old Bed, Bonanza open pit, and Harmony mines.
---------------------------------------------------------------------------

    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: James A. Besha, President, Moriah Hydro 
Corporation, c/o Albany Engineering Corporation, 5 Washington Square, 
Albany, New York 12205, (518) 456-7712.
    i. FERC Contact: Chris Millard (202) 502-8256 or 
[email protected].
    j. Deadline for filing motions to intervene and protests: 60 days 
from the issuance date of this notice.
    The Commission strongly encourages electronic filing. Please file 
motions to intervene and protests using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. For assistance, please 
contact FERC Online Support at [email protected], (866) 208-
3676 (toll free), or (202) 502-8659 (TTY). In lieu of electronic 
filing, please send a paper copy to: Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426. The 
first page of any filing should include docket number P-12635-002.
    The Commission's Rules of Practice and Procedures require all 
intervenors filing documents with the Commission to serve a copy of 
that document on each person on the official service list for the 
project. Further, if an intervenor files comments or documents with the 
Commission relating to the merits of an issue that may affect the 
responsibilities of a particular resource agency, they must also serve 
a copy of the document on that resource agency.
    k. This application has been accepted for filing, but is not ready 
for environmental analysis at this time.
    l. The proposed project consists of: (1) An upper reservoir located 
within the upper portion of the mine between elevations 495 and 1,095 
feet above mean seal level (msl), with a surface area of 4 acres and a 
storage capacity of 2,448 acre-feet; (2) a lower reservoir in the lower 
portion of the mine between elevations -1,075 and -1,555 feet msl, with 
a surface area of 5.1 acres and a storage capacity of 2,448 acre-feet; 
(3) a 14-foot-diameter and 2,955-foot-long upper reservoir shaft 
connecting the upper reservoir to the high-pressure penstock located 
below the powerhouse chamber floor; (4) a 14-foot-diameter and 2,955-
foot-long lower reservoir shaft connecting the lower reservoir and the 
lower reservoir ventilation tunnel; (5) two 6-foot-diameter emergency 
evacuation shafts located between the powerhouse chamber and the 
electrical equipment chamber; (6) a 25-foot-diameter main shaft 
extending 2,955 feet from the surface down to the powerhouse chamber; 
(7) 15-foot-diameter high- and low-pressure steel penstocks embedded 
beneath the powerhouse chamber floor; (8) a 320-foot-long by 80-foot-
wide powerhouse chamber, containing 100 reversible pump-turbine units, 
each with a nameplate generating capacity of 2.4 megawatts; (9) a 274-
foot-long by 36-foot-wide underground electrical equipment chamber 
adjacent to the powerhouse chamber; (10) an inclined electrical tunnel 
connecting the electrical equipment chamber to a new 115-kilovolt (kV) 
substation constructed adjacent to an existing single circuit 115-kV 
transmission line located about one horizontal mile from the 
underground powerhouse chamber; and (11) appurtenant facilities. The 
project would operate as a closed-loop system to meet energy demands 
and grid control requirements. The project would have an average annual 
generation of 421 gigawatt-hours (GWh). The average pumping power used 
by the project would be 554 GWh.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    Register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Any qualified applicant desiring to file a competing application 
must submit to the Commission, on or before the specified intervention 
deadline date, a competing development application, or a notice of 
intent to file such an application. Submission of a timely notice of 
intent allows an interested person to file the competing development 
application no later than 120 days after the specified intervention 
deadline date. Applications for preliminary permits will not be 
accepted in response to this notice.
    A notice of intent must specify the exact name, business address, 
and telephone number of the prospective applicant, and must include an 
unequivocal statement of intent to submit a development application. A 
notice of intent must be served on the applicant(s) named in this 
public notice.
    Anyone may submit a protest, or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210, .211, and .214. In determining the appropriate action to take, 
the Commission will consider all protests filed, but only those who 
file a motion to intervene in accordance with the Commission's Rules 
may become a party to the proceeding. Any comments, protests, or 
motions to intervene must be received on or before the specified 
comment date for the particular application.
    When the application is ready for environmental analysis, the 
Commission will issue a public notice requesting comments, 
recommendations, terms and conditions, or prescriptions.
    All filings must (1) bear in all capital letters the title 
``PROTEST'' or ``MOTION TO INTERVENE,'' ``NOTICE OF INTENT TO FILE 
COMPETING APPLICATION,'' or ``COMPETING APPLICATION;'' (2) set forth in 
the heading the name of the applicant and the project number of the 
application to which the filing responds; (3) furnish the name, 
address, and telephone number of the person protesting or intervening; 
and (4) otherwise comply with the requirements of 18 CFR 385.2001 
through 385.2005. Agencies may obtain copies of the application 
directly from the applicant. A copy of any protest or motion to 
intervene must be served upon each representative of

[[Page 70108]]

the applicant specified in the particular application.

    Dated: October 4, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-24471 Filed 10-7-16; 8:45 am]
BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 81, No. 196 / Tuesday, October 11, 2016 / Notices                                           70107

                                                    DEPARTMENT OF ENERGY                                    issue that may affect the responsibilities            for inspection and reproduction at the
                                                                                                            of a particular resource agency, they                 address in item h above.
                                                    Federal Energy Regulatory                               must also serve a copy of the document                   Register online at http://
                                                    Commission                                              on that resource agency.                              www.ferc.gov/docs-filing/
                                                                                                               k. This application has been accepted              esubscription.asp to be notified via
                                                    [Project No.: P–12635–002]
                                                                                                            for filing, but is not ready for                      email of new filings and issuances
                                                    Moriah Hydro Corporation; Notice of                     environmental analysis at this time.                  related to this or other pending projects.
                                                    Application Accepted for Filing and                        l. The proposed project consists of: (1)           For assistance, contact FERC Online
                                                    Soliciting Motions To Intervene and                     An upper reservoir located within the                 Support.
                                                    Protests                                                upper portion of the mine between                        n. Any qualified applicant desiring to
                                                                                                            elevations 495 and 1,095 feet above                   file a competing application must
                                                       Take notice that the following                       mean seal level (msl), with a surface                 submit to the Commission, on or before
                                                    hydroelectric application has been filed                area of 4 acres and a storage capacity of             the specified intervention deadline date,
                                                    with the Commission and is available                    2,448 acre-feet; (2) a lower reservoir in             a competing development application,
                                                    for public inspection.                                  the lower portion of the mine between                 or a notice of intent to file such an
                                                       a. Type of Application: Original Major               elevations ¥1,075 and ¥1,555 feet msl,                application. Submission of a timely
                                                    License.                                                with a surface area of 5.1 acres and a                notice of intent allows an interested
                                                       b. Project No.: P–12635–002.                         storage capacity of 2,448 acre-feet; (3) a            person to file the competing
                                                       c. Date filed: February 13, 2015.                    14-foot-diameter and 2,955-foot-long                  development application no later than
                                                       d. Applicant: Moriah Hydro                           upper reservoir shaft connecting the                  120 days after the specified intervention
                                                    Corporation.                                            upper reservoir to the high-pressure                  deadline date. Applications for
                                                       e. Name of Project: Mineville Energy                 penstock located below the powerhouse                 preliminary permits will not be
                                                    Storage Project.                                        chamber floor; (4) a 14-foot-diameter                 accepted in response to this notice.
                                                       f. Location: The project would be                    and 2,955-foot-long lower reservoir shaft                A notice of intent must specify the
                                                    located in an abandoned subterranean                    connecting the lower reservoir and the                exact name, business address, and
                                                    mine complex 1 in the town of Moriah,                   lower reservoir ventilation tunnel; (5)               telephone number of the prospective
                                                    Essex County, New York. No federal                      two 6-foot-diameter emergency                         applicant, and must include an
                                                    lands are occupied by project works or                  evacuation shafts located between the                 unequivocal statement of intent to
                                                    located within the project boundary.                    powerhouse chamber and the electrical                 submit a development application. A
                                                       g. Filed Pursuant to: Federal Power                  equipment chamber; (6) a 25-foot-                     notice of intent must be served on the
                                                    Act 16 U.S.C. 791(a)–825(r).                            diameter main shaft extending 2,955                   applicant(s) named in this public notice.
                                                       h. Applicant Contact: James A. Besha,                feet from the surface down to the                        Anyone may submit a protest, or a
                                                    President, Moriah Hydro Corporation, c/                 powerhouse chamber; (7) 15-foot-                      motion to intervene in accordance with
                                                    o Albany Engineering Corporation, 5                     diameter high- and low-pressure steel                 the requirements of Rules of Practice
                                                    Washington Square, Albany, New York                     penstocks embedded beneath the                        and Procedure, 18 CFR 385.210, .211,
                                                    12205, (518) 456–7712.                                  powerhouse chamber floor; (8) a 320-                  and .214. In determining the appropriate
                                                       i. FERC Contact: Chris Millard (202)                 foot-long by 80-foot-wide powerhouse                  action to take, the Commission will
                                                    502–8256 or christopher.millard@                        chamber, containing 100 reversible                    consider all protests filed, but only
                                                    ferc.gov.                                               pump-turbine units, each with a                       those who file a motion to intervene in
                                                       j. Deadline for filing motions to                    nameplate generating capacity of 2.4                  accordance with the Commission’s
                                                    intervene and protests: 60 days from the                megawatts; (9) a 274-foot-long by 36-                 Rules may become a party to the
                                                    issuance date of this notice.                           foot-wide underground electrical                      proceeding. Any comments, protests, or
                                                       The Commission strongly encourages                   equipment chamber adjacent to the                     motions to intervene must be received
                                                    electronic filing. Please file motions to               powerhouse chamber; (10) an inclined                  on or before the specified comment date
                                                    intervene and protests using the                        electrical tunnel connecting the                      for the particular application.
                                                    Commission’s eFiling system at http://                  electrical equipment chamber to a new                    When the application is ready for
                                                    www.ferc.gov/docs-filing/efiling.asp. For               115-kilovolt (kV) substation constructed              environmental analysis, the
                                                    assistance, please contact FERC Online                  adjacent to an existing single circuit                Commission will issue a public notice
                                                    Support at FERCOnlineSupport@                           115-kV transmission line located about                requesting comments,
                                                    ferc.gov, (866) 208–3676 (toll free), or                one horizontal mile from the                          recommendations, terms and
                                                    (202) 502–8659 (TTY). In lieu of                        underground powerhouse chamber; and                   conditions, or prescriptions.
                                                                                                            (11) appurtenant facilities. The project                 All filings must (1) bear in all capital
                                                    electronic filing, please send a paper
                                                                                                            would operate as a closed-loop system                 letters the title ‘‘PROTEST’’ or
                                                    copy to: Secretary, Federal Energy
                                                                                                            to meet energy demands and grid                       ‘‘MOTION TO INTERVENE,’’ ‘‘NOTICE
                                                    Regulatory Commission, 888 First Street
                                                                                                            control requirements. The project would               OF INTENT TO FILE COMPETING
                                                    NE., Washington, DC 20426. The first
                                                                                                            have an average annual generation of                  APPLICATION,’’ or ‘‘COMPETING
                                                    page of any filing should include docket
                                                                                                            421 gigawatt-hours (GWh). The average                 APPLICATION;’’ (2) set forth in the
                                                    number P–12635–002.
                                                                                                            pumping power used by the project                     heading the name of the applicant and
                                                       The Commission’s Rules of Practice
                                                                                                            would be 554 GWh.                                     the project number of the application to
                                                    and Procedures require all intervenors
                                                                                                               m. A copy of the application is                    which the filing responds; (3) furnish
                                                    filing documents with the Commission
                                                                                                            available for review at the Commission                the name, address, and telephone
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    to serve a copy of that document on
                                                                                                            in the Public Reference Room or may be                number of the person protesting or
                                                    each person on the official service list
                                                                                                            viewed on the Commission’s Web site at                intervening; and (4) otherwise comply
                                                    for the project. Further, if an intervenor
                                                                                                            http://www.ferc.gov using the                         with the requirements of 18 CFR
                                                    files comments or documents with the
                                                                                                            ‘‘eLibrary’’ link. Enter the docket                   385.2001 through 385.2005. Agencies
                                                    Commission relating to the merits of an
                                                                                                            number excluding the last three digits in             may obtain copies of the application
                                                      1 The existing mine complex is composed of the        the docket number field to access the                 directly from the applicant. A copy of
                                                    interconnected Old Bed, Bonanza open pit, and           document. For assistance, contact FERC                any protest or motion to intervene must
                                                    Harmony mines.                                          Online Support. A copy is also available              be served upon each representative of


                                               VerDate Sep<11>2014   20:12 Oct 07, 2016   Jkt 241001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\11OCN1.SGM   11OCN1


                                                    70108                          Federal Register / Vol. 81, No. 196 / Tuesday, October 11, 2016 / Notices

                                                    the applicant specified in the particular                 1, 2017.1 The project would have been                     i. FERC Contact: John Ramer, (202)
                                                    application.                                              located in the Pacific Ocean between 2.5               502–8969, or email at john.ramer@
                                                      Dated: October 4, 2016.                                 and 3.0 miles off the coast of San Luis                ferc.gov.
                                                                                                              Obispo County, California, and on land                    j. Deadline for filing motions to
                                                    Kimberly D. Bose,
                                                                                                              near the town of Morro Bay.                            intervene and protests, comments, terms
                                                    Secretary.
                                                                                                                 The preliminary permit for Project                  and conditions, and recommendations:
                                                    [FR Doc. 2016–24471 Filed 10–7–16; 8:45 am]                                                                      Due to the small size and location of
                                                                                                              No. 14584 will remain in effect until the
                                                    BILLING CODE 6717–01–P
                                                                                                              close of business, November 3, 2016.                   this project and the close coordination
                                                                                                              But, if the Commission is closed on this               with state and federal agencies during
                                                                                                              day, then the permit remains in effect                 preparation of the application, the 60-
                                                    DEPARTMENT OF ENERGY                                                                                             day timeframe in 18 CFR 4.34(b) is
                                                                                                              until the close of business on the next
                                                    Federal Energy Regulatory                                 day in which the Commission is open.2                  shortened. Instead, motions to intervene
                                                                                                              New applications for this site may not                 and protests, comments, terms and
                                                    Commission
                                                                                                              be submitted until after the permit                    conditions, and recommendations are
                                                    [Project No. 14585–001]                                   surrender is effective.                                due 30 days from the issuance date of
                                                                                                                                                                     this notice. All reply comments must be
                                                    Dynegy Estero Bay Wave Park, LLC;                           Dated: October 4, 2016.
                                                                                                                                                                     filed with the Commission within 45
                                                    Notice of Surrender of Preliminary                        Kimberly D. Bose,                                      days from the issuance date of this
                                                    Permit                                                    Secretary.                                             notice.
                                                                                                              [FR Doc. 2016–24473 Filed 10–7–16; 8:45 am]               The Commission strongly encourages
                                                       Take notice that Dynegy Estero Bay                                                                            electronic filing. Please file motions to
                                                                                                              BILLING CODE 6717–01–P
                                                    Wave Park, LLC, permittee for the                                                                                intervene, protests, comments, and
                                                    proposed Estero Bay Wave Park Project,                                                                           recommendations using the
                                                    has requested that its preliminary                        DEPARTMENT OF ENERGY                                   Commission’s eFiling system at http://
                                                    permit be terminated. The permit was                                                                             www.ferc.gov/docs-filing/efiling.asp.
                                                    issued on October 28, 2014, and would                     Federal Energy Regulatory                              Commenters can submit brief comments
                                                    have expired on November 1, 2017.1                        Commission                                             up to 6,000 characters, without prior
                                                    The project would have been located in                                                                           registration, using the eComment system
                                                                                                              [Project No. 14680–002]
                                                    coastal waters between 2.5 and 3.0 miles                                                                         at http://www.ferc.gov/docs-filing/
                                                    off the coast of San Luis Obispo County,                  Water Street Land, LLC; Notice of                      ecomment.asp. You must include your
                                                    California, and on land near the town of                  Application Accepted for Filing With                   name and contact information at the end
                                                    Morro Bay.                                                the Commission, Intent To Waive                        of your comments. For assistance,
                                                       The preliminary permit for Project                     Scoping, Soliciting Motions To                         please contact FERC Online Support at
                                                    No. 14585 will remain in effect until the                 Intervene and Protests, Ready for                      FERCOnlineSupport@ferc.gov, (866)
                                                    close of business, November 3, 2016.                      Environmental Analysis, and Soliciting                 208–3676 (toll free), or (202) 502–8659
                                                    But, if the Commission is closed on this                  Comments, Terms and Conditions, and                    (TTY). In lieu of electronic filing, please
                                                    day, then the permit remains in effect                    Recommendations, and Establishing                      send a paper copy to: Secretary, Federal
                                                    until the close of business on the next                   an Expedited Schedule for Processing                   Energy Regulatory Commission, 888
                                                    day in which the Commission is open.2                                                                            First Street NE., Washington, DC 20426.
                                                    New applications for this site may not                       Take notice that the following                      The first page of any filing should
                                                    be submitted until after the permit                       hydroelectric application has been filed               include docket number P–14680–002.
                                                    surrender is effective.                                   with the Commission and is available                      The Commission’s Rules of Practice
                                                      Dated: October 4, 2016.                                 for public inspection.                                 require all intervenors filing documents
                                                    Kimberly D. Bose,                                            a. Type of Application: Exemption                   with the Commission to serve a copy of
                                                    Secretary.                                                from Licensing                                         that document on each person on the
                                                    [FR Doc. 2016–24475 Filed 10–7–16; 8:45 am]
                                                                                                                 b. Project No.: 14680–002                           official service list for the project.
                                                    BILLING CODE 6717–01–P
                                                                                                                 c. Date filed: July 13, 2016                        Further, if an intervenor files comments
                                                                                                                 d. Applicant: Water Street Land, LLC                or documents with the Commission
                                                                                                                 e. Name of Project: Natick Pond Dam                 relating to the merits of an issue that
                                                    DEPARTMENT OF ENERGY                                      Hydroelectric Project                                  may affect the responsibilities of a
                                                                                                                 f. Location: On the Pawtuxet River, in              particular resource agency, they must
                                                    Federal Energy Regulatory                                 the Towns of Warwick and West                          also serve a copy of the document on
                                                    Commission                                                Warwick, Kent County, Rhode Island.                    that resource agency.
                                                                                                              No federal lands would be occupied by                     k. This application has been accepted
                                                    [Project No. 14584–001]
                                                                                                              project works or located within the                    for filing and is now ready for
                                                    Dynegy Point Estero Wave Park, LLC;                       project boundary.                                      environmental analysis.
                                                    Notice of Surrender of Preliminary                           g. Filed Pursuant to: Public Utility                   l. The proposed Natick Pond Dam
                                                    Permit                                                    Regulatory Policies Act of 1978, 16                    Hydroelectric Project would consist of:
                                                                                                              U.S.C. 2705, 2708 (2012), amended by                   (1) An existing 265-foot-long granite
                                                      Take notice that Dynegy Point Estero                    the Hydropower Regulatory Efficiency                   block dam with a 19.3-foot-high, 166-
                                                                                                                                                                     foot-long spillway; (2) an existing 58-
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    Wave Park, LLC, permittee for the                         Act of 2013, Public Law 113–23, 127
                                                    proposed Point Estero Wave Park                           Stat. 493 (2013).                                      foot to 125.3-foot-wide, 1-foot- to 28-
                                                    Project, has requested that its                              h. Applicant Contact: Mr. Rob Cioe,                 foot-deep earth embankment; (3) an
                                                    preliminary permit be terminated. The                     Water Street Land, LLC, P.O. Box 358,                  existing 44-foot-long, 4-foot- to 20-foot-
                                                    permit was issued on October 28, 2014,                    North Kingstown, RI 02852; (480) 797–                  high south granite block training wall;
                                                    and would have expired on November                        3077.                                                  (4) an existing 1,244-foot-long, 18-foot-
                                                                                                                                                                     to 41.25-foot-high granite block and
                                                      1 149   FERC ¶ 62,059.                                    1 149   FERC ¶ 62,058.                               cobble stone north training wall; (5) an
                                                      2 18   CFR 385.2007(a)(2) (2016).                         2 18   CFR 385.2007(a)(2) (2016).                    existing 4-foot-wide, 6-foot-high granite


                                               VerDate Sep<11>2014     20:12 Oct 07, 2016   Jkt 241001   PO 00000   Frm 00024    Fmt 4703   Sfmt 4703   E:\FR\FM\11OCN1.SGM   11OCN1



Document Created: 2018-02-13 16:34:05
Document Modified: 2018-02-13 16:34:05
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 70107 