81_FR_71316 81 FR 71117 - Conduct of Operations

81 FR 71117 - Conduct of Operations

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 81, Issue 199 (October 14, 2016)

Page Range71117-71119
FR Document2016-24887

The U.S. Nuclear Regulatory Commission (NRC) is issuing final revisions to Section 13.6.4, ``Access Authorization--Operational Program;'' Section 13.7, ``Fitness-for-Duty;'' Section 13.7.1, ``Fitness-for-Duty--Operational Program;'' Section 13.7.2, ``Fitness for Duty--Construction;'' and Section 13.6.3, ``Physical Security-- Operational Program--Early Site Permits and Reactor Siting Criteria;'' of NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR Edition.''

Federal Register, Volume 81 Issue 199 (Friday, October 14, 2016)
[Federal Register Volume 81, Number 199 (Friday, October 14, 2016)]
[Notices]
[Pages 71117-71119]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-24887]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2012-0314; NRC-2013-0149; NRC-2014-0099; NRC-2014-0101]


Conduct of Operations

AGENCY: Nuclear Regulatory Commission.

ACTION: Standard review plan--final section revision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing final 
revisions to Section 13.6.4, ``Access Authorization--Operational 
Program;'' Section 13.7, ``Fitness-for-Duty;'' Section 13.7.1, 
``Fitness-for-Duty--Operational Program;'' Section 13.7.2, ``Fitness 
for Duty--Construction;'' and Section 13.6.3, ``Physical Security--
Operational Program--Early Site Permits and Reactor Siting Criteria;'' 
of NUREG-0800, ``Standard Review Plan for the Review of Safety Analysis 
Reports for Nuclear Power Plants: LWR Edition.''

DATES: The effective date of these SRP section revisions is November 
14, 2016.

ADDRESSES: Please refer to Docket IDs NRC-2012-0314 for SRP Section 
13.6.4, NRC-2013-0149 for SRP Sections 13.7 and 13.7.1, NRC-2014-0099 
for SRP Section 13.7.2, and NRC-2014-0101 for SRP Section 13.6.3 when 
contacting the NRC about the availability of information regarding this 
document. You may obtain publicly-available information related to this 
document using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket IDs NRC-2012-0314 (for SRP 
Section 13.6.4), NRC-2013-0149 (for SRP Sections 13.7 and 13.7.1), NRC-
2014-0099 (for SRP Section 13.7.2), and NRC-2014-0101 (for SRP Section 
13.6.3). Address questions about NRC dockets to Carol Gallagher; 
telephone: 301-415-3463; email: [email protected]. For technical 
questions, contact the individuals listed in the FOR FURTHER 
INFORMATION CONTACT section of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the

[[Page 71118]]

ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced in this document 
(if that document is available in ADAMS) is provided the first time 
that a document is referenced. For the convenience of the reader, the 
ADAMS accession numbers are provided in a table in the ``Availability 
of Documents'' section of this document. The NUREG-0800 is available on 
the NRC's public Web site at http://www.nrc.gov/reading-rm/doc-collections/nuregs/staff/sr0800/.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Mark Notich, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-3053; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Background

    On December 31, 2012 (77 FR 77117), the NRC published for public 
comment the proposed revision to Section 13.6.4, ``Access 
Authorization--Operational Program'' (ADAMS Accession No. ML12125A098). 
On July 16, 2013 (78 FR 42558), the NRC published for public comment 
the proposed revision to Section 13.7, ``Fitness-for-Duty;'' and 
Section 13.7.1, ``Fitness-for-Duty--Operational Program'' (ADAMS 
Accession Nos. ML113250516 and ML113250541, respectively). On May 5, 
2014 (79 FR 25627), the NRC published for public comment the proposed 
revision to Section 13.6.3, ``Physical Security--Early Site Permit and 
Reactor Siting Criteria'' (ADAMS Accession No. ML13059A367). Also on 
May 5, 2014 (79 FR 25628), the NRC published for public comment the 
proposed revision to Section 13.7.2, ``Fitness-for-Duty--Construction'' 
(ADAMS Accession No. ML113270035).
    The NRC staff received comments on the proposed revision to SRP 
Section 13.6.4. A summary of the comments and the NRC staff's 
disposition of the comments are available in a separate document 
entitled, ``Response to Public Comments on Draft Standard Review Plan 
(SRP) 13.6.4: Access Authorization--Operational Program'' (ADAMS 
Accession No. ML13270A111). Therefore, the NRC is issuing this revised 
section of the SRP in final form for use.
    The NRC did not receive comments on the proposed revisions to SRP 
Sections 13.6.3, 13.7, 13.7.1, and 13.7.2. Therefore, the NRC is 
issuing these revised sections of the SRP in final form for use.
    There have been minor editorial changes to these sections since 
their issuance in proposed form for public comment. Details on the 
specific changes are included in the redline strikeout documents 
referenced in Section IV, ``Availability of Documents,'' of this 
document.

II. Backfitting and Issue Finality

    Issuance of these revised SRP sections does not constitute 
backfitting as defined in Sec.  50.109 of title 10 of the Code of 
Federal Regulations (10 CFR), ``Backfitting,'' (the Backfit Rule) or 
otherwise be inconsistent with the issue finality provisions in 10 CFR 
part 52. The NRC's position is based upon the following considerations:
    1. The SRP positions do not constitute backfitting, inasmuch as the 
SRP is internal guidance directed at the NRC staff with respect to 
their regulatory responsibilities.
    The SRP provides guidance to the NRC staff on how to review an 
application for NRC regulatory approval in the form of licensing. 
Changes in internal NRC staff guidance are not matters for which either 
nuclear power plant applicants or licensees are protected under either 
the Backfit Rule or the issue finality provisions of 10 CFR part 52.
    2. The NRC staff has no intention to impose the SRP positions on 
existing nuclear power plant licenses or regulatory approvals either 
now or in the future (absent a voluntary request for change from the 
licensee, holder of a regulatory approval, or a design certification 
applicant).
    The NRC staff does not intend to impose or apply the positions 
described in the SRP to existing (already issued) licenses and 
regulatory approvals. Therefore, the issuance of a final SRP--even if 
considered guidance that is within the purview of the issue finality 
provisions in 10 CFR part 52--need not be evaluated as if it were a 
backfit or as being inconsistent with issue finality provisions. If, in 
the future, the NRC staff seeks to impose a position in the SRP on 
holders of already issued licenses in a manner which does not provide 
issue finality as described in the applicable issue finality provision, 
then the NRC staff must make the showing as set forth in the Backfit 
Rule or address the criteria for avoiding issue finality as described 
in the applicable issue finality provision.
    3. Backfitting and issue finality--with limited exceptions not 
applicable here--do not protect current or future applicants.
    Applicants and potential applicants are not, with certain 
exceptions, protected by either the Backfit Rule or any issue finality 
provisions under 10 CFR part 52. This is because neither the Backfit 
Rule nor the issue finality provisions under 10 CFR part 52--with 
certain exclusions discussed in the next paragraph--were intended to 
apply to every NRC action which substantially changes the expectations 
of current and future applicants.
    The exceptions to the general principle are applicable whenever an 
applicant references a 10 CFR part 52 license (e.g., an early site 
permit) and/or NRC regulatory approval (e.g., a design certification 
rule) with specified issue finality provisions. The NRC staff does not 
currently intend to impose the positions represented in these SRP 
sections in a manner that is inconsistent with any issue finality 
provisions. If, in the future, the NRC staff seeks to impose a position 
in the SRP in a manner which does not provide issue finality as 
described in the applicable issue finality provision, then the NRC 
staff must address the criteria for avoiding issue finality as 
described in the applicable issue finality provision.

III. Congressional Review Act

    These SRP section revisions are a rule as defined in the 
Congressional Review Act (5 U.S.C. 801-808). However, the Office of 
Management and Budget has not found it to be a major rule as defined in 
the Congressional Review Act.

IV. Availability of Documents

    The documents identified in the following table are available to 
interested persons as indicated.

[[Page 71119]]



----------------------------------------------------------------------------------------------------------------
                                                           Final revision     Current draft    Redline strikeout
                      SRP section                         ADAMS accession     revision ADAMS    ADAMS accession
                                                                No.           accession No.           No.
----------------------------------------------------------------------------------------------------------------
13.6.3.................................................        ML15061A471        ML13059A367        ML15226A059
13.6.4.................................................        ML15226A009        ML12125A098        ML15111A201
13.7...................................................        ML15111A091        ML113250516        ML15111A057
13.7.1.................................................        ML15111A036        ML113250541        ML15226A098
13.7.2.................................................        ML15111A034        ML113270035        ML15226A168
----------------------------------------------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 6th day of October 2016.

    For the Nuclear Regulatory Commission.
Joseph Colaccino,
Chief, New Reactor Rulemaking and Guidance Branch, Division of 
Engineering, Infrastructure, and Advanced Reactors, Office of New 
Reactors.
[FR Doc. 2016-24887 Filed 10-13-16; 8:45 am]
 BILLING CODE 7590-01-P



                                                                             Federal Register / Vol. 81, No. 199 / Friday, October 14, 2016 / Notices                                               71117

                                               I. Background                                           regulatory approvals. Hence, the                        For the Nuclear Regulatory Commission.
                                                  On May 27, 2015 (80 FR 30285), the                   issuance of this SRP—even if                          Joseph Colaccino,
                                               NRC published for public comment a                      considered guidance within the purview                Chief, New Reactor Rulemaking and
                                               proposed revision of Section 2.0, ‘‘Site                of the issue finality provisions in 10                Guidance Branch, Division of Engineering,
                                               Characteristics and Site Parameters’’ of                CFR part 52—does not need to be                       Infrastruture and Advanced Reactors, Office
                                               NUREG–0800, ‘‘Standard Review Plan                      evaluated as if it were a backfit or as               of New Reactors.
                                               (SRP) for the Review of Safety Analysis                 being inconsistent with issue finality                [FR Doc. 2016–24859 Filed 10–13–16; 8:45 am]
                                               Reports for Nuclear Power Plants: LWR                   provisions. If, in the future, the NRC                BILLING CODE 7590–01–P
                                               Edition.’’ The staff received comments                  staff seeks to impose a position in the
                                               on the draft section. After consideration               SRP on holders of already issued
                                               of comments received on the proposed                    licenses in a manner that does not                    NUCLEAR REGULATORY
                                               revision, the NRC staff reformatted                     provide issue finality as described in the            COMMISSION
                                               guidance for the review of nonsafety-                   applicable issue finality provision, then             [NRC–2012–0314; NRC–2013–0149; NRC–
                                               related structures, systems, and                        the staff must make the showing as set                2014–0099; NRC–2014–0101]
                                               components (SSCs) into a tabular                        forth in the Backfit Rule or address the
                                               format, and separated it from the core                  criteria for avoiding issue finality as               Conduct of Operations
                                               review guidance used for review of                      described in the applicable issue finality            AGENCY:  Nuclear Regulatory
                                               safety-related SSCs. A summary of                       provision.                                            Commission.
                                               comments received and the staff’s
                                               disposition of the comments are                            3. Backfitting and issue finality do               ACTION: Standard review plan—final
                                               available in a separate document                        not—with limited exceptions not                       section revision; issuance.
                                               entitled, ‘‘Response to Public Comments                 applicable here—protect current or
                                                                                                       future applicants.                                    SUMMARY:    The U.S. Nuclear Regulatory
                                               on Draft Standard Review Plan, Section                                                                        Commission (NRC) is issuing final
                                               2, ‘Site Characteristics and Site                          Applicants and potential applicants                revisions to Section 13.6.4, ‘‘Access
                                               Parameters’’’ (ADAMS Accession No.                      are not, with certain exceptions,                     Authorization—Operational Program;’’
                                               ML15279A093).                                           protected by either the Backfit Rule or               Section 13.7, ‘‘Fitness-for-Duty;’’
                                               II. Backfitting and Issue Finality                      any issue finality provisions under 10                Section 13.7.1, ‘‘Fitness-for-Duty—
                                                                                                       CFR part 52. Neither the Backfit Rule                 Operational Program;’’ Section 13.7.2,
                                                  Section 2 provides guidance to the                   nor the issue finality provisions under               ‘‘Fitness for Duty—Construction;’’ and
                                               staff for reviewing applications for a                  10 CFR part 52—with certain                           Section 13.6.3, ‘‘Physical Security—
                                               construction permit and an operating
                                                                                                       exclusions—were intended to apply to                  Operational Program—Early Site
                                               license under part 50 of title 10 of the
                                                                                                       every NRC action that substantially                   Permits and Reactor Siting Criteria;’’ of
                                               Code of Federal Regulations (10 CFR)
                                                                                                       changes the expectations of current and               NUREG–0800, ‘‘Standard Review Plan
                                               with respect to systems associated with
                                                                                                       future applicants.                                    for the Review of Safety Analysis
                                               site characteristics and site parameters.
                                                                                                          The exceptions to the general                      Reports for Nuclear Power Plants: LWR
                                               SRP Section 2 also provides guidance
                                                                                                       principle are applicable whenever an                  Edition.’’
                                               for reviewing an application for a
                                               standard design approval, a standard                    applicant references a 10 CFR part 52                 DATES: The effective date of these SRP
                                               design certification, a combined license,               license (e.g., an early site permit) or               section revisions is November 14, 2016.
                                               and a manufacturing license under 10                    NRC regulatory approval (e.g., a design               ADDRESSES: Please refer to Docket IDs
                                               CFR part 52 with respect to the same                    certification rule) with specified issue              NRC–2012–0314 for SRP Section 13.6.4,
                                               subject matters.                                        finality provisions. The NRC staff does               NRC–2013–0149 for SRP Sections 13.7
                                                  Issuance of this SRP section revision                not, at this time, intend to impose the               and 13.7.1, NRC–2014–0099 for SRP
                                               does not constitute backfitting as                      positions represented in the SRP in a                 Section 13.7.2, and NRC–2014–0101 for
                                               defined in 10 CFR 50.109 (the Backfit                   manner that is inconsistent with any                  SRP Section 13.6.3 when contacting the
                                               Rule) nor is it inconsistent with the                   issue finality provisions. If, in the                 NRC about the availability of
                                               issue finality provisions in 10 CFR part                future, the staff seeks to impose a                   information regarding this document.
                                               52. The NRC’s position is based upon                                                                          You may obtain publicly-available
                                                                                                       position in the SRP section in a manner
                                               the following considerations.                                                                                 information related to this document
                                                                                                       that does not provide issue finality as
                                                  1. The SRP positions would not                                                                             using any of the following methods:
                                                                                                       described in the applicable issue finality
                                               constitute backfitting, inasmuch as the                                                                          • Federal Rulemaking Web site: Go to
                                                                                                       provision, then the staff must address                http://www.regulations.gov and search
                                               SRP is internal guidance to NRC staff.
                                                  The SRP provides internal guidance                   the criteria for avoiding issue finality as           for Docket IDs NRC–2012–0314 (for SRP
                                               to the NRC staff on how to review an                    described in the applicable issue finality            Section 13.6.4), NRC–2013–0149 (for
                                               application for NRC regulatory approval                 provision.                                            SRP Sections 13.7 and 13.7.1), NRC–
                                               in the form of licensing. Changes in                    III. Congressional Review Act                         2014–0099 (for SRP Section 13.7.2), and
                                               internal staff guidance are not matters                                                                       NRC–2014–0101 (for SRP Section
                                               for which either nuclear power plant                       This action is a rule as defined in the            13.6.3). Address questions about NRC
                                               applicants or licensees are protected                   Congressional Review Act (5 U.S.C.                    dockets to Carol Gallagher; telephone:
                                               under either the Backfit Rule or the                    801–808). However, the Office of                      301–415–3463; email: Carol.Gallagher@
                                               issue finality provisions of 10 CFR part                Management and Budget has not found                   nrc.gov. For technical questions, contact
rmajette on DSK2TPTVN1PROD with NOTICES




                                               52.                                                     it to be a major rule as defined in the               the individuals listed in the FOR
                                                  2. The NRC staff has no intention to                 Congressional Review Act.                             FURTHER INFORMATION CONTACT section of
                                               impose the SRP positions on existing                                                                          this document.
                                                                                                         Dated at Rockville, Maryland, this 11th day
                                               licensees either now or in the future.                                                                           • NRC’s Agencywide Documents
                                                                                                       of October 2016.
                                                  The NRC staff does not intend to                                                                           Access and Management System
                                               impose or apply the positions described                                                                       (ADAMS): You may obtain publicly-
                                               in the SRP to existing licenses and                                                                           available documents online in the


                                          VerDate Sep<11>2014   14:29 Oct 13, 2016   Jkt 241001   PO 00000   Frm 00079   Fmt 4703   Sfmt 4703   E:\FR\FM\14OCN1.SGM   14OCN1


                                               71118                         Federal Register / Vol. 81, No. 199 / Friday, October 14, 2016 / Notices

                                               ADAMS Public Documents collection at                    comments are available in a separate                  provisions in 10 CFR part 52—need not
                                               http://www.nrc.gov/reading-rm/                          document entitled, ‘‘Response to Public               be evaluated as if it were a backfit or as
                                               adams.html. To begin the search, select                 Comments on Draft Standard Review                     being inconsistent with issue finality
                                               ‘‘ADAMS Public Documents’’ and then                     Plan (SRP) 13.6.4: Access                             provisions. If, in the future, the NRC
                                               select ‘‘Begin Web-based ADAMS                          Authorization—Operational Program’’                   staff seeks to impose a position in the
                                               Search.’’ For problems with ADAMS,                      (ADAMS Accession No. ML13270A111).                    SRP on holders of already issued
                                               please contact the NRC’s Public                         Therefore, the NRC is issuing this                    licenses in a manner which does not
                                               Document Room (PDR) reference staff at                  revised section of the SRP in final form              provide issue finality as described in the
                                               1–800–397–4209, 301–415–4737, or by                     for use.                                              applicable issue finality provision, then
                                               email to pdr.resource@nrc.gov. The                         The NRC did not receive comments                   the NRC staff must make the showing as
                                               ADAMS accession number for each                         on the proposed revisions to SRP                      set forth in the Backfit Rule or address
                                               document referenced in this document                    Sections 13.6.3, 13.7, 13.7.1, and 13.7.2.            the criteria for avoiding issue finality as
                                               (if that document is available in                       Therefore, the NRC is issuing these                   described in the applicable issue finality
                                               ADAMS) is provided the first time that                  revised sections of the SRP in final form             provision.
                                               a document is referenced. For the                       for use.                                                 3. Backfitting and issue finality—with
                                               convenience of the reader, the ADAMS                       There have been minor editorial                    limited exceptions not applicable here—
                                               accession numbers are provided in a                     changes to these sections since their                 do not protect current or future
                                               table in the ‘‘Availability of Documents’’              issuance in proposed form for public                  applicants.
                                               section of this document. The NUREG–                    comment. Details on the specific
                                               0800 is available on the NRC’s public                                                                            Applicants and potential applicants
                                                                                                       changes are included in the redline                   are not, with certain exceptions,
                                               Web site at http://www.nrc.gov/reading-                 strikeout documents referenced in
                                               rm/doc-collections/nuregs/staff/sr0800/.                                                                      protected by either the Backfit Rule or
                                                                                                       Section IV, ‘‘Availability of                         any issue finality provisions under 10
                                                  • NRC’s PDR: You may examine and                     Documents,’’ of this document.
                                               purchase copies of public documents at                                                                        CFR part 52. This is because neither the
                                               the NRC’s PDR, Room O1–F21, One                         II. Backfitting and Issue Finality                    Backfit Rule nor the issue finality
                                               White Flint North, 11555 Rockville                         Issuance of these revised SRP sections             provisions under 10 CFR part 52—with
                                               Pike, Rockville, Maryland 20852.                        does not constitute backfitting as                    certain exclusions discussed in the next
                                               FOR FURTHER INFORMATION CONTACT:                        defined in § 50.109 of title 10 of the                paragraph—were intended to apply to
                                               Mark Notich, Office of New Reactors,                    Code of Federal Regulations (10 CFR),                 every NRC action which substantially
                                               U.S. Nuclear Regulatory Commission,                     ‘‘Backfitting,’’ (the Backfit Rule) or                changes the expectations of current and
                                               Washington, DC 20555–0001; telephone:                   otherwise be inconsistent with the issue              future applicants.
                                               301–415–3053; email: Mark.Notich@                       finality provisions in 10 CFR part 52.                   The exceptions to the general
                                               nrc.gov.                                                The NRC’s position is based upon the                  principle are applicable whenever an
                                                                                                       following considerations:                             applicant references a 10 CFR part 52
                                               SUPPLEMENTARY INFORMATION:
                                                                                                          1. The SRP positions do not constitute             license (e.g., an early site permit) and/
                                               I. Background                                           backfitting, inasmuch as the SRP is                   or NRC regulatory approval (e.g., a
                                                  On December 31, 2012 (77 FR 77117),                  internal guidance directed at the NRC                 design certification rule) with specified
                                               the NRC published for public comment                    staff with respect to their regulatory                issue finality provisions. The NRC staff
                                               the proposed revision to Section 13.6.4,                responsibilities.                                     does not currently intend to impose the
                                               ‘‘Access Authorization—Operational                         The SRP provides guidance to the                   positions represented in these SRP
                                               Program’’ (ADAMS Accession No.                          NRC staff on how to review an                         sections in a manner that is inconsistent
                                               ML12125A098). On July 16, 2013 (78 FR                   application for NRC regulatory approval               with any issue finality provisions. If, in
                                               42558), the NRC published for public                    in the form of licensing. Changes in                  the future, the NRC staff seeks to impose
                                               comment the proposed revision to                        internal NRC staff guidance are not                   a position in the SRP in a manner which
                                               Section 13.7, ‘‘Fitness-for-Duty;’’ and                 matters for which either nuclear power                does not provide issue finality as
                                               Section 13.7.1, ‘‘Fitness-for-Duty—                     plant applicants or licensees are                     described in the applicable issue finality
                                               Operational Program’’ (ADAMS                            protected under either the Backfit Rule               provision, then the NRC staff must
                                               Accession Nos. ML113250516 and                          or the issue finality provisions of 10                address the criteria for avoiding issue
                                               ML113250541, respectively). On May 5,                   CFR part 52.                                          finality as described in the applicable
                                               2014 (79 FR 25627), the NRC published                      2. The NRC staff has no intention to               issue finality provision.
                                               for public comment the proposed                         impose the SRP positions on existing                  III. Congressional Review Act
                                               revision to Section 13.6.3, ‘‘Physical                  nuclear power plant licenses or
                                               Security—Early Site Permit and Reactor                  regulatory approvals either now or in                   These SRP section revisions are a rule
                                               Siting Criteria’’ (ADAMS Accession No.                  the future (absent a voluntary request                as defined in the Congressional Review
                                               ML13059A367). Also on May 5, 2014                       for change from the licensee, holder of               Act (5 U.S.C. 801–808). However, the
                                               (79 FR 25628), the NRC published for                    a regulatory approval, or a design                    Office of Management and Budget has
                                               public comment the proposed revision                    certification applicant).                             not found it to be a major rule as
                                               to Section 13.7.2, ‘‘Fitness-for-Duty—                     The NRC staff does not intend to                   defined in the Congressional Review
                                               Construction’’ (ADAMS Accession No.                     impose or apply the positions described               Act.
                                               ML113270035).                                           in the SRP to existing (already issued)               IV. Availability of Documents
                                                  The NRC staff received comments on                   licenses and regulatory approvals.
rmajette on DSK2TPTVN1PROD with NOTICES




                                               the proposed revision to SRP Section                    Therefore, the issuance of a final SRP—                 The documents identified in the
                                               13.6.4. A summary of the comments and                   even if considered guidance that is                   following table are available to
                                               the NRC staff’s disposition of the                      within the purview of the issue finality              interested persons as indicated.




                                          VerDate Sep<11>2014   14:29 Oct 13, 2016   Jkt 241001   PO 00000   Frm 00080   Fmt 4703   Sfmt 4703   E:\FR\FM\14OCN1.SGM   14OCN1


                                                                                         Federal Register / Vol. 81, No. 199 / Friday, October 14, 2016 / Notices                                                                       71119

                                                                                                                                                                                     Final revision          Current draft     Redline strikeout
                                                                                                     SRP section                                                                   ADAMS accession         revision ADAMS     ADAMS accession
                                                                                                                                                                                          No.               accession No.            No.

                                               13.6.3 .........................................................................................................................        ML15061A471            ML13059A367         ML15226A059
                                               13.6.4 .........................................................................................................................        ML15226A009            ML12125A098         ML15111A201
                                               13.7 ............................................................................................................................       ML15111A091            ML113250516         ML15111A057
                                               13.7.1 .........................................................................................................................        ML15111A036            ML113250541         ML15226A098
                                               13.7.2 .........................................................................................................................        ML15111A034            ML113270035         ML15226A168



                                                  Dated at Rockville, Maryland, this 6th day                                   • Federal Rulemaking Web site: Go to                                   For the Nuclear Regulatory Commission.
                                               of October 2016.                                                             http://www.regulations.gov and search                                Kriss M. Kennedy,
                                                  For the Nuclear Regulatory Commission.                                    for Docket ID NRC–2016–0211. Address                                 Regional Administrator.
                                               Joseph Colaccino,                                                            questions about NRC dockets to Carol
                                                                                                                                                                                                 ATTACHMENT—CONFIRMATORY ORDER
                                               Chief, New Reactor Rulemaking and                                            Gallagher; telephone: 301–415–3463;                                  MODIFYING LICENSE
                                               Guidance Branch, Division of Engineering,                                    email: Carol.Gallagher@nrc.gov. For
                                               Infrastructure, and Advanced Reactors, Office                                questions about the Order, contact the                               UNITED STATES OF AMERICA
                                               of New Reactors.
                                                                                                                            individual listed in the FOR FURTHER                                 NUCLEAR REGULATORY COMMISSION
                                               [FR Doc. 2016–24887 Filed 10–13–16; 8:45 am]
                                                                                                                            INFORMATION CONTACT section of this                                  In the Matter of Power Resources, Inc.
                                               BILLING CODE 7590–01–P
                                                                                                                            document.
                                                                                                                                                                                                 [Docket No. 040–08964; License No. SUA–
                                                                                                                               • NRC’s Agencywide Documents                                      1548]
                                               NUCLEAR REGULATORY                                                           Access and Management System
                                                                                                                                                                                                 EA–16–051
                                               COMMISSION                                                                   (ADAMS): You may obtain publicly-
                                                                                                                            available documents online in the                                    CONFIRMATORY ORDER MODIFYING
                                                                                                                            ADAMS Public Documents collection at                                 LICENSE
                                               [Docket No. 040–08964; License No. SUA–
                                               1548; EA–16–051; NRC–2016–0211]                                              http://www.nrc.gov/reading-rm/                                       (EFFECTIVE UPON ISSUANCE)
                                                                                                                            adams.html. To begin the search, select
                                               In the Matter of Power Resources, Inc.                                                                                                            I
                                                                                                                            ‘‘ADAMS Public Documents’’ and then
                                                                                                                                                                                                   Power Resources, Inc. (PRI or Licensee), is
                                               AGENCY:  Nuclear Regulatory                                                  select ‘‘Begin Web-based ADAMS
                                                                                                                                                                                                 the holder of Source Material License SUA–
                                               Commission.                                                                  Search.’’ For problems with ADAMS,                                   1548 issued on May 8, 2001, by the U.S.
                                                                                                                            please contact the NRC’s Public                                      Nuclear Regulatory Commission (NRC or
                                               ACTION: Confirmatory order; issuance.
                                                                                                                            Document Room (PDR) reference staff at                               Commission) pursuant to Part 40 of Title 10
                                               SUMMARY:    The U.S. Nuclear Regulatory                                      1–800–397–4209, 301–415–4737, or by                                  of the Code of Federal Regulations (10 CFR).
                                                                                                                            email to pdr.resource@nrc.gov. The                                   The license authorizes the operation of PRI’s
                                               Commission (NRC) is issuing a
                                                                                                                                                                                                 North Butte satellite facility in accordance
                                               confirmatory order to Power Resources,                                       ADAMS accession number for each
                                                                                                                                                                                                 with conditions specified therein. The
                                               Inc., confirming agreements reached in                                       document referenced (if it is available in                           facility is located on the licensee’s site in
                                               an alternative dispute resolution                                            ADAMS) is provided the first time that                               Campbell County, Wyoming.
                                               mediation session held on September                                          it is mentioned in this document.                                      This Confirmatory Order is the result of an
                                               22, 2016. As part of the agreement,                                                                                                               agreement reached during an alternative
                                                                                                                               • NRC’s PDR: You may examine and
                                               Power Resources, Inc., will conduct                                                                                                               dispute resolution (ADR) mediation session
                                                                                                                            purchase copies of public documents at                               conducted on September 22, 2016.
                                               annual meetings among key                                                    the NRC’s PDR, Room O1–F21, One
                                               management, radiation safety officer,                                        White Flint North, 11555 Rockville                                   II
                                               facility managers, and other appropriate                                                                                                             On June 27, 2014, the NRC’s Office of
                                                                                                                            Pike, Rockville, Maryland 20852.
                                               technical personnel to provide                                                                                                                    Investigations (OI), initiated an investigation
                                               assurance that management understands                                        FOR FURTHER INFORMATION CONTACT: John                                (OI Case No. 4–2014–034) at PRI’s North
                                               the requirements of a radiation                                              Kramer, Region IV, U.S. Nuclear                                      Butte satellite facility. Based on the evidence
                                               protection program are being met; will                                       Regulatory Commission, 1600 E. Lamar                                 developed during its investigation, the NRC
                                               provide training which will emphasize                                                                                                             identified apparent violations of 10 CFR
                                                                                                                            Blvd., Arlington, TX 76011–4511;
                                               the importance of complete and                                                                                                                    20.1501, ‘‘Surveys and Monitoring—
                                                                                                                            telephone: 817–200–1121; email:                                      General,’’ and 10 CFR 40.9, ‘‘Completeness
                                               accurate information for all required                                        John.Kramer@nrc.gov.                                                 and accuracy of information,’’ as well as, two
                                               records, correspondence, and                                                                                                                      apparent violations of License Condition 9.3
                                               communications with the NRC and its                                          SUPPLEMENTARY INFORMATION:                             The text of   of License SUA 1548, Amendment 18, dated
                                               staff; and will have a qualified member                                      the Order is attached.                                               March 27, 2013, which includes the
                                               of the heath physics staff available at                                        Dated at Arlington, Texas, this 30th day of                        requirement that the licensee conduct its
                                               any of its facilities when equipment is                                      September 2016.                                                      operations in accordance with Volume 1,
                                               being released from a radiologically-                                                                                                             Chapter 9, ‘‘Management Control
                                               controlled are to an unrestricted area.                                                                                                           Procedures,’’ of the licensee’s application
                                                                                                                                                                                                 dated May 6, 2003, as amended based on
                                               DATES: The confirmatory order was                                                                                                                 letter dated March 20, 2008. In addition,
                                               issued on September 30, 2016.                                                                                                                     based on OI’s investigative results, the NRC
rmajette on DSK2TPTVN1PROD with NOTICES




                                               ADDRESSES: Please refer to Docket ID                                                                                                              is concerned that willfulness may be
                                               NRC–2016–0211 when contacting the                                                                                                                 associated with the apparent violation
                                                                                                                                                                                                 involving the failure to maintain accurate
                                               NRC about the availability of                                                                                                                     records of contamination exit surveys. By
                                               information regarding this document.                                                                                                              letter dated August 24, 2016, the NRC
                                               You may obtain publicly-available                                                                                                                 notified PRI of the results of the investigation
                                               information related to this document                                                                                                              and provided an opportunity to: (1) Provide
                                               using any of the following methods:                                                                                                               a response in writing, (2) attend a



                                          VerDate Sep<11>2014          14:29 Oct 13, 2016         Jkt 241001       PO 00000        Frm 00081       Fmt 4703       Sfmt 4703        E:\FR\FM\14OCN1.SGM    14OCN1



Document Created: 2016-10-14 00:01:24
Document Modified: 2016-10-14 00:01:24
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionStandard review plan--final section revision; issuance.
DatesThe effective date of these SRP section revisions is November 14, 2016.
ContactMark Notich, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3053; email: [email protected]
FR Citation81 FR 71117 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR