81 FR 71696 - Dairyland Power Cooperative: Notice of Intent To Prepare an Environmental Impact Statement and Hold Public Scoping Meetings

DEPARTMENT OF AGRICULTURE
Rural Utilities Service

Federal Register Volume 81, Issue 201 (October 18, 2016)

Page Range71696-71697
FR Document2016-25132

The Rural Utilities Service (RUS) intends to prepare an Environmental Impact Statement (EIS) and hold public scoping meetings in connection with possible impacts related to the Cardinal-Hickory Creek Transmission Line Project proposed by Dairyland Power Cooperative (DPC). Other utilities participating in the Project are American Transmission Company LLC, by its corporate manager ATC Management Inc. and ITC Midwest LLC. The proposal consists of the construction of a 345-kilovolt (kV) transmission line and associated infrastructure connecting the Hickory Creek Substation in Dubuque County, Iowa, with the Cardinal Substation in the Town of Middleton, Wisconsin (near Madison, Wisconsin). The Project also includes a new intermediate 345/138-kV substation near the Village of Montfort in either Grant County or Iowa County, Wisconsin. The total length of the 345-kV transmission lines associated with the proposed project will be approximately 125 miles. DPC and the other project participants have identified proposed and alternate segments and locations for transmission lines and associated facilities and for the intermediate substation. Dairyland Power Cooperative is requesting RUS to provide financing for its portion of the proposed project.

Federal Register, Volume 81 Issue 201 (Tuesday, October 18, 2016)
[Federal Register Volume 81, Number 201 (Tuesday, October 18, 2016)]
[Notices]
[Pages 71696-71697]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-25132]


-----------------------------------------------------------------------

DEPARTMENT OF AGRICULTURE

Rural Utilities Service


Dairyland Power Cooperative: Notice of Intent To Prepare an 
Environmental Impact Statement and Hold Public Scoping Meetings

AGENCY: Rural Utilities Service, USDA.

ACTION: Notice of Intent to Prepare an Environmental Impact Statement 
and Hold Public Scoping Meetings.

-----------------------------------------------------------------------

SUMMARY: The Rural Utilities Service (RUS) intends to prepare an 
Environmental Impact Statement (EIS) and hold public scoping meetings 
in connection with possible impacts related to the Cardinal-Hickory 
Creek Transmission Line Project proposed by Dairyland Power Cooperative 
(DPC). Other utilities participating in the Project are American 
Transmission Company LLC, by its corporate manager ATC Management Inc. 
and ITC Midwest LLC.
    The proposal consists of the construction of a 345-kilovolt (kV) 
transmission line and associated infrastructure connecting the Hickory 
Creek Substation in Dubuque County, Iowa, with the Cardinal Substation 
in the Town of Middleton, Wisconsin (near Madison, Wisconsin). The 
Project also includes a new intermediate 345/138-kV substation near the 
Village of Montfort in either Grant County or Iowa County, Wisconsin. 
The total length of the 345-kV transmission lines associated with the 
proposed project will be approximately 125 miles. DPC and the other 
project participants have identified proposed and alternate segments 
and locations for transmission lines and associated facilities and for 
the intermediate substation. Dairyland Power Cooperative is requesting 
RUS to provide financing for its portion of the proposed project.

DATES: RUS will conduct four public scoping meetings in an open-house 
format at the following locations:

----------------------------------------------------------------------------------------------------------------
                Date                        Location                  Time                      Venue
----------------------------------------------------------------------------------------------------------------
October 31, 2016...................  Peosta, Iowa..........  3:00-6:00 p.m.........  Peosta Community Center,
                                                                                      7896 Burds Road, Peosta,
                                                                                      IA 53068.
November 1, 2016...................  Cassville, Wisconsin..  4:00-7:00 p.m.........  Cassville Middle School
                                                                                      Cafeteria, 715 E. Amelia
                                                                                      Street, Cassville, WI
                                                                                      53806.
November 2, 2016...................  Dodgeville, Wisconsin.  4:00-7:00 p.m.........  Dodgeville Middle School
                                                                                      Cafeteria, 951 Chapel St.,
                                                                                      Dodgeville, WI 53533.
November 3, 2016...................  Middleton, Wisconsin..  4:00-7:00 p.m.........  Madison Marriott West, 1313
                                                                                      John Q Hammons Dr.,
                                                                                      Middleton, WI 53562.
----------------------------------------------------------------------------------------------------------------


ADDRESSES: To send comments or for further information, contact Dennis 
Rankin, Environmental Protection Specialist, U.S. Department of 
Agriculture, Rural Utilities Service, 1400 Independence Avenue SW., 
Room 2244, Stop 1571, Washington, DC 20250-1571 Email: 
[email protected] Washington, DC 20250-1571.
    An Alternative Evaluation Study (AES) and Macro Corridor Study 
(MCS), prepared by Dairyland Power Cooperative, will be presented at 
the public scoping meetings. The reports are available for public 
review at the RUS address provided in this notice and at Dairyland 
Power Cooperative, 3251 East Avenue, South, La Crosse, WI 54602. In 
addition, the reports will be available at RUS' Web site, http://www.rd.usda.gov/publications/environmental-studies/impact-statements 
and at local libraries in the project area.

SUPPLEMENTARY INFORMATION: Preliminary proposed transmission line 
corridors, the siting area for the intermediate substation, and the two 
existing end-point substations have been identified. The EIS will 
address the construction, operation, and

[[Page 71697]]

management of the proposed project, which includes the following: A new 
345-kV terminal within the existing Hickory Creek Substation in Dubuque 
County, Iowa; a new intermediate 345/138-kV substation near the Village 
of Montfort in either Grant or Iowa County, Wisconsin; a new 345-kV 
terminal within the existing Cardinal Substation in the Town of 
Middleton in Dane County, Wisconsin; a new 45- to 65-mile (depending on 
the final route) 345-kV transmission line between the Hickory Creek 
Substation and the intermediate substation; a new 45- to 60-mile 
(depending on the final route) 345-kV transmission line between the 
intermediate substation and the existing Cardinal Substation; a short, 
less than one-mile, 69-kV line in Iowa; facility reinforcement needed 
in Iowa and Wisconsin; construction and maintenance of access roads for 
all proposed transmission lines and rebuild of the Turkey River 
Substation in Dubuque County, Iowa with two 161/69 kV transformers, 
four 161-kV circuit breakers, and three 69-kV circuit breakers.
    Total length of the transmission lines for the proposed project 
will be approximately 125 miles. The project study area includes part 
or all of the following counties in Iowa: Clayton and Dubuque. In 
Wisconsin, the project area includes parts of the following counties: 
Dane, Grant, Iowa, and Lafayette.
    Among the alternatives RUS will address in the EIS is the No Action 
alternative, under which the project would not be undertaken. In the 
EIS, the effects of the proposed project will be compared to the 
existing conditions in the area affected. Alternative transmission line 
corridors and the intermediate substation location will be refined as 
part of the EIS scoping process and will be addressed in the Draft EIS. 
RUS will carefully study public health and safety, environmental 
impacts, and engineering aspects of the proposed project and all 
related facilities.
    The U.S. Army Corps of Engineers (USACE) and the U.S. Fish and 
Wildlife Service (USFWS) are participating in the environmental review 
process as cooperating agencies, with RUS as the lead Federal agency.
    RUS will use input provided by government agencies, private 
organizations, and the public in the preparation of the Draft EIS. The 
Draft EIS will be available for review and comment for 45 days. A Final 
EIS that considers all comments received will subsequently be prepared. 
The Final EIS will be available for review and comment for 30 days. 
Following the 30- day comment period, RUS will prepare a Record of 
Decision (ROD). Notices announcing the availability of the Draft EIS, 
the Final EIS, and the ROD will be published in the Federal Register 
and in local newspapers.
    Any final action by RUS related to the proposed project will be 
subject to, and contingent upon, compliance with all relevant federal, 
state, and local environmental laws and regulations and completion of 
the environmental review requirements as prescribed in the RUS 
Environmental Policies and Procedures (7 CFR part 1970).

    Dated: October 12, 2016.
Kellie Kubena,
Director, Engineering and Environmental Staff, Rural Utilities Service.
[FR Doc. 2016-25132 Filed 10-17-16; 8:45 am]
BILLING CODE P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of Intent to Prepare an Environmental Impact Statement and Hold Public Scoping Meetings.
DatesRUS will conduct four public scoping meetings in an open-house format at the following locations:
FR Citation81 FR 71696 