81_FR_73358 81 FR 73153 - United States Department of the Interior; United States Geological Survey TRIGA Research Reactor

81 FR 73153 - United States Department of the Interior; United States Geological Survey TRIGA Research Reactor

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 81, Issue 205 (October 24, 2016)

Page Range73153-73154
FR Document2016-25646

The U.S. Nuclear Regulatory Commission (NRC) issued a renewal of Facility Operating License No. R-113, held by the United States Geological Survey (USGS or the licensee), for the continued operation of its USGS Training, Research, Isotope Production, General Atomics (TRIGA) research reactor (GSTR or the reactor) at a steady-state power level of 1.0 megawatt (MW) and a pulse power level as provided in the licensee's Technical Specifications, for an additional 20 years. The GSTR facility is located on the property of the Denver Federal Center in Lakewood, Colorado.

Federal Register, Volume 81 Issue 205 (Monday, October 24, 2016)
[Federal Register Volume 81, Number 205 (Monday, October 24, 2016)]
[Notices]
[Pages 73153-73154]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-25646]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket No. 50-274; NRC-2015-0284]


United States Department of the Interior; United States 
Geological Survey TRIGA Research Reactor

AGENCY: Nuclear Regulatory Commission.

ACTION: License renewal; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) issued a renewal 
of Facility Operating License No. R-113, held by the United States 
Geological Survey (USGS or the licensee), for the continued operation 
of its USGS Training, Research, Isotope Production, General Atomics 
(TRIGA) research reactor (GSTR or the reactor) at a steady-state power 
level of 1.0 megawatt (MW) and a pulse power level as provided in the 
licensee's Technical Specifications, for an additional 20 years. The 
GSTR facility is located on the property of the Denver Federal Center 
in Lakewood, Colorado.

DATES: The operating license renewal No. R-113 is effective on October 
14, 2016.

ADDRESSES: Please refer to Docket ID NRC-2015-0284 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0284. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it available in 
ADAMS) is provided the first time that a document is referenced. In 
addition, for the convenience of the reader, the ADAMS accession 
numbers are provided in a table in the ``Availability of Documents'' 
section of this document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Geoffrey A. Wertz, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-0893; email: [email protected].

SUPPLEMENTARY INFORMATION: 

I. Discussion

    The NRC has issued renewed Facility Operating License No. R-113, 
held by the USGS, which authorizes continued operation of the USGS 
GSTR, located in the Denver Federal Center in Lakewood, Colorado. The 
GSTR is heterogeneous pool-type, natural convection, light-water 
cooled, and shielded TRIGA reactor. The GSTR is licensed to operate at 
a steady-state power level of 1,000 kilowatts thermal power and to 
pulse the reactor with a maximum reactivity insertion of $3.00. The 
renewed Facility Operating License No. R-113 will expire 20 years from 
its date of issuance.
    The renewed facility operating license complies with the standards 
and requirements of the Atomic Energy Act of 1954, as amended (the 
Act), and the Commission's rules and regulations. The Commission has 
made appropriate findings as required by the Act and the Commission's 
regulations in chapter I of title 10 of the Code of Federal 
Regulations, and sets forth those findings in the renewed facility 
operating license. The NRC afforded an opportunity for hearing in the 
Notice of Opportunity for Hearing published in the Federal Register on 
February 5, 2016 (81 FR 6302). The NRC received no request for a 
hearing or petition for leave to intervene following the notice.
    The NRC staff prepared a safety evaluation report for the renewal 
of Facility Operating License No. R-113 and concluded, based on that 
evaluation, that the licensee can continue to operate the facility 
without endangering the health and safety of the public. The NRC staff 
also prepared an Environmental Assessment and Finding of No Significant 
Impact for the renewal of the facility operating license, noticed in 
the Federal Register on June 14, 2016 (81 FR 38739), and concluded that 
renewal of the facility operating license will not have a significant 
impact on the quality of the human environment.

II. Availability of Documents

    The documents identified in the following table are available to 
interested persons as indicated.

[[Page 73154]]



------------------------------------------------------------------------
                                                        ADAMS Accession
                       Document                               No.
------------------------------------------------------------------------
U.S. Geological Survey--Revised Safety Analysis              ML092120136
 Report, Technical Specifications, and Environmental
 Report to Support License Renewal (redacted
 version), dated January 5, 2009 (redacted version)..
U.S. Geological Survey--TRIGA Reactor Response to the        ML103340090
 RAI Concerning R-113 License Renewal, dated November
 24, 2010............................................
U.S. Geological Survey--Response to Letter of                ML110480046
 February 1, 2011 Concerning R-113 License Renewal,
 dated February 11, 2011.............................
U.S. Geological Survey--Response to Questions 23.1,          ML110950059
 23.2, and 23.3 of the Referenced RAI, dated March
 28, 2011............................................
U.S. Geological Survey--Response to Questions 22.1,          ML11138A027
 22,2, 25.1, 25.2, 25.3, 25.4, and 25.6 of the
 Referenced RAI, dated May 12, 2011..................
U.S. Geological Survey--Response to Request for              ML11181A305
 Additional Information for Questions 17.1 and 17.2,
 dated June 29, 2011.................................
U.S. Geological Survey--Response to Question 2 of the        ML11214A091
 Referenced RAI, dated July 27, 2011.................
U.S. Geological Survey--Response to Question 1 of the        ML112500522
 Referenced RAI, dated August 30, 2011...............
U.S. Geological Survey--Response to Request for              ML11277A013
 Additional Information to Question 20, dated
 September 26, 2011..................................
U.S. Geological Survey TRIGA Reactor--Response to            ML11314A106
 Question 6 of the Referenced RAI, dated October 31,
 2011................................................
U.S. Geological Survey--Response to NRC Request for          ML113460014
 Additional Information Questions 7 and 8, License
 Renewal, dated November 30, 2011 (redacted version).
U.S. Geological Survey--Licensee Response to NRC             ML120240003
 Request for Additional Information Question 15.3,
 dated January 3, 2012 (redacted version)............
U.S. Geological Survey TRIGA Reactor--Response to            ML12068A138
 Question 15.2 of the Request for Additional
 Information from September 29, 2010, letter, dated
 January 27, 2012....................................
U.S. Geological Survey TRIGA Reactor (GSTR)--Response        ML12039A173
 to Question 18 of a Request for Additional
 Information dated September 29, 2010, letter, dated
 January 27, 2012....................................
U.S. Geological Survey TRIGA Reactor--Response to            ML12100A097
 Request for Additional Information to Question 14,
 dated March 28, 2012................................
U.S. Geological Survey TRIGA Reactor--Response to            ML12128A429
 Question 16 of the Referenced RAI, dated April 27,
 2012................................................
U.S. Geological Survey--Responses to Questions 26 and        ML12151A407
 27 of the Referenced RAI, dated May 18, 2012........
U.S. Geological Survey--Response to Request for              ML12160A064
 Additional Information (RAI) Question 14, dated May
 31, 2012............................................
U.S. Geological Survey TRIGA Reactor--Response to            ML12200A055
 Question 3 of the Referenced RAI, dated June 29,
 2012................................................
U.S. Geological Survey TRIGA Reactor--Response to            ML12220A525
 Question 21 of the Referenced RAI dated September
 29, 2010, letter, dated July 31, 2012...............
U.S. Geological Survey--Responses to Questions 9, 10,        ML12251A231
 11, 12, 15.1, 23.4, 24, and 25.5; Along with a
 Corrected Copy of the Proposed Technical
 Specifications (Chapter 14) of the SAR, dated August
 30, 2012............................................
U.S. Geological Survey--Redacted--Response to NRC            ML12334A001
 Request for Additional Information dated October 2,
 2012, letter, dated November 16, 2012...............
U.S. Geological Survey--Responses to NRC Request for         ML13052A179
 Additional Information dated October 2, 2012 and
 Telephone Conference, dated December 20, 2012,
 letter, dated February 8, 2013 (redacted version)...
U.S. Geological Survey--Responses to RAIs, Follow-up         ML13162A662
 Safety Analysis responses from questions of phone
 conference conducted on March 21, 2013, dated May
 17, 2013 (redacted version).........................
Follow-up Safety Analysis Responses dated July 15,           ML13311A047
 2013, letter, dated October 31, 2013................
U.S. Geological Survey TRIGA Reactor (GSTR),                 ML14070A040
 Responses to Reactor Operator Requalification
 Questions, dated February 19, 2014..................
Submission of Revised Technical Specifications,              ML14325A646
 Chapter 14, November 3, 2014........................
U.S. Geological Survey TRIGA Reactor--Responses to           ML14338A196
 RAI Questions 15.3 and 28, dated November 24, 2014
 (redacted version)..................................
Revision of Proposed Technical Specifications,               ML15261A042
 September 8, 2015...................................
U.S. Geological Survey--Responses to RAI Questions           ML16042A575
 1a, 1b, and 1c, dated January 22, 2016..............
U.S. Geological Survey--Response to Request for              ML16110A008
 Additional Information for License Renewal, dated
 April 1, 2016 (redacted version)....................
U.S. Geological Survey--Responses to RAI questions,          ML16277A216
 dated September 12, 2016............................
U.S. Geological Survey--Responses to Email Questions         ML16273A304
 from Mr. Wertz date September 10, 2016, dated
 September 22, 2016..................................
------------------------------------------------------------------------


    Dated at Rockville, Maryland, this 17th day of October, 2016.
    For the Nuclear Regulatory Commission.
Alexander Adams, Jr.,
Chief, Research and Test Reactors Licensing Branch, Division of Policy 
and Rulemaking, Office of Nuclear Reactor Regulation.
[FR Doc. 2016-25646 Filed 10-21-16; 8:45 am]
BILLING CODE 7590-01-P



                                                                                  Federal Register / Vol. 81, No. 205 / Monday, October 24, 2016 / Notices                                           73153

                                                 ATTACHMENT 1—GENERAL TARGET SCHEDULE FOR PROCESSING AND RESOLVING REQUESTS FOR ACCESS TO SENSITIVE
                                                               UNCLASSIFIED NON-SAFEGUARDS INFORMATION IN THIS PROCEEDING—Continued
                                                         Day                                                                               Event/Activity

                                                A .......................   If access granted: issuance of presiding officer or other designated officer decision on motion for protective order for access
                                                                               to sensitive information (including schedule for providing access and submission of contentions) or decision reversing a
                                                                               final adverse determination by the NRC staff.
                                                A + 3 .................     Deadline for filing executed Non-Disclosure Affidavits. Access provided to SUNSI consistent with decision issuing the protec-
                                                                               tive order.
                                                A + 28 ...............      Deadline for submission of contentions whose development depends upon access to SUNSI. However, if more than 25 days
                                                                               remain between the petitioner’s receipt of (or access to) the information and the deadline for filing all other contentions (as
                                                                               established in the notice of hearing or opportunity for hearing), the petitioner may file its SUNSI contentions by that later
                                                                               deadline.
                                                A + 53 ...............      (Contention receipt +25) Answers to contentions whose development depends upon access to SUNSI.
                                                A + 60 ...............      (Answer receipt +7) Petitioner/Intervenor reply to answers.
                                                >A + 60 .............       Decision on contention admission.



                                                [FR Doc. 2016–25607 Filed 10–21–16; 8:45 am]                 technical questions, contact the                      water cooled, and shielded TRIGA
                                                BILLING CODE 7590–01–P                                       individual listed in the FOR FURTHER                  reactor. The GSTR is licensed to operate
                                                                                                             INFORMATION CONTACT section of this                   at a steady-state power level of 1,000
                                                                                                             document.                                             kilowatts thermal power and to pulse
                                                NUCLEAR REGULATORY                                              • NRC’s Agencywide Documents                       the reactor with a maximum reactivity
                                                COMMISSION                                                   Access and Management System                          insertion of $3.00. The renewed Facility
                                                [Docket No. 50–274; NRC–2015–0284]
                                                                                                             (ADAMS): You may obtain publicly-                     Operating License No. R–113 will expire
                                                                                                             available documents online in the                     20 years from its date of issuance.
                                                United States Department of the                              ADAMS Public Documents collection at                     The renewed facility operating license
                                                Interior; United States Geological                           http://www.nrc.gov/reading-rm/                        complies with the standards and
                                                Survey TRIGA Research Reactor                                adams.html. To begin the search, select               requirements of the Atomic Energy Act
                                                                                                             ‘‘ADAMS Public Documents’’ and then                   of 1954, as amended (the Act), and the
                                                AGENCY:  Nuclear Regulatory                                  select ‘‘Begin Web-based ADAMS
                                                Commission.                                                                                                        Commission’s rules and regulations.
                                                                                                             Search.’’ For problems with ADAMS,                    The Commission has made appropriate
                                                ACTION: License renewal; issuance.                           please contact the NRC’s Public                       findings as required by the Act and the
                                                                                                             Document Room (PDR) reference staff at                Commission’s regulations in chapter I of
                                                SUMMARY:     The U.S. Nuclear Regulatory
                                                                                                             1–800–397–4209, 301–415–4737, or by                   title 10 of the Code of Federal
                                                Commission (NRC) issued a renewal of
                                                                                                             email to pdr.resource@nrc.gov. The                    Regulations, and sets forth those
                                                Facility Operating License No. R–113,
                                                                                                             ADAMS accession number for each                       findings in the renewed facility
                                                held by the United States Geological
                                                                                                             document referenced (if it available in               operating license. The NRC afforded an
                                                Survey (USGS or the licensee), for the
                                                                                                             ADAMS) is provided the first time that                opportunity for hearing in the Notice of
                                                continued operation of its USGS
                                                                                                             a document is referenced. In addition,                Opportunity for Hearing published in
                                                Training, Research, Isotope Production,
                                                                                                             for the convenience of the reader, the                the Federal Register on February 5,
                                                General Atomics (TRIGA) research
                                                                                                             ADAMS accession numbers are                           2016 (81 FR 6302). The NRC received no
                                                reactor (GSTR or the reactor) at a steady-
                                                                                                             provided in a table in the ‘‘Availability             request for a hearing or petition for
                                                state power level of 1.0 megawatt (MW)
                                                                                                             of Documents’’ section of this                        leave to intervene following the notice.
                                                and a pulse power level as provided in
                                                                                                             document.
                                                the licensee’s Technical Specifications,
                                                                                                                • NRC’s PDR: You may examine and                      The NRC staff prepared a safety
                                                for an additional 20 years. The GSTR                                                                               evaluation report for the renewal of
                                                                                                             purchase copies of public documents at
                                                facility is located on the property of the                                                                         Facility Operating License No. R–113
                                                                                                             the NRC’s PDR, Room O1–F21, One
                                                Denver Federal Center in Lakewood,                                                                                 and concluded, based on that
                                                                                                             White Flint North, 11555 Rockville
                                                Colorado.                                                                                                          evaluation, that the licensee can
                                                                                                             Pike, Rockville, Maryland 20852.
                                                DATES: The operating license renewal                         FOR FURTHER INFORMATION CONTACT:                      continue to operate the facility without
                                                No. R–113 is effective on October 14,                        Geoffrey A. Wertz, Office of Nuclear                  endangering the health and safety of the
                                                2016.                                                        Reactor Regulation, U.S. Nuclear                      public. The NRC staff also prepared an
                                                ADDRESSES: Please refer to Docket ID                         Regulatory Commission, Washington,                    Environmental Assessment and Finding
                                                NRC–2015–0284 when contacting the                            DC 20555–0001; telephone: 301–415–                    of No Significant Impact for the renewal
                                                NRC about the availability of                                0893; email: Geoffrey.Wertz@nrc.gov.                  of the facility operating license, noticed
                                                information regarding this document.                                                                               in the Federal Register on June 14, 2016
                                                                                                             SUPPLEMENTARY INFORMATION:
                                                You may obtain publicly-available                                                                                  (81 FR 38739), and concluded that
                                                information related to this document                         I. Discussion                                         renewal of the facility operating license
                                                using any of the following methods:                             The NRC has issued renewed Facility                will not have a significant impact on the
                                                  • Federal Rulemaking Web site: Go to                       Operating License No. R–113, held by                  quality of the human environment.
sradovich on DSK3GMQ082PROD with NOTICES




                                                http://www.regulations.gov and search                        the USGS, which authorizes continued                  II. Availability of Documents
                                                for Docket ID NRC–2015–0284. Address                         operation of the USGS GSTR, located in
                                                questions about NRC dockets to Carol                         the Denver Federal Center in Lakewood,                  The documents identified in the
                                                Gallagher; telephone: 301–415–3463;                          Colorado. The GSTR is heterogeneous                   following table are available to
                                                email: Carol.Gallagher@nrc.gov. For                          pool-type, natural convection, light-                 interested persons as indicated.




                                           VerDate Sep<11>2014        17:42 Oct 21, 2016   Jkt 241001   PO 00000   Frm 00098   Fmt 4703   Sfmt 4703   E:\FR\FM\24OCN1.SGM   24OCN1


                                                73154                                   Federal Register / Vol. 81, No. 205 / Monday, October 24, 2016 / Notices

                                                                                                                                                                                                                                                     ADAMS Acces-
                                                                                                                                        Document                                                                                                       sion No.

                                                U.S. Geological Survey—Revised Safety Analysis Report, Technical Specifications, and Environmental Report to Support Li-
                                                  cense Renewal (redacted version), dated January 5, 2009 (redacted version) .......................................................................                                                   ML092120136
                                                U.S. Geological Survey—TRIGA Reactor Response to the RAI Concerning R–113 License Renewal, dated November 24,
                                                  2010 ...........................................................................................................................................................................................     ML103340090
                                                U.S. Geological Survey—Response to Letter of February 1, 2011 Concerning R–113 License Renewal, dated February 11,
                                                  2011 ...........................................................................................................................................................................................     ML110480046
                                                U.S. Geological Survey—Response to Questions 23.1, 23.2, and 23.3 of the Referenced RAI, dated March 28, 2011 ...........                                                                              ML110950059
                                                U.S. Geological Survey—Response to Questions 22.1, 22,2, 25.1, 25.2, 25.3, 25.4, and 25.6 of the Referenced RAI, dated
                                                  May 12, 2011 .............................................................................................................................................................................           ML11138A027
                                                U.S. Geological Survey—Response to Request for Additional Information for Questions 17.1 and 17.2, dated June 29, 2011                                                                                 ML11181A305
                                                U.S. Geological Survey—Response to Question 2 of the Referenced RAI, dated July 27, 2011 ...............................................                                                               ML11214A091
                                                U.S. Geological Survey—Response to Question 1 of the Referenced RAI, dated August 30, 2011 ..........................................                                                                  ML112500522
                                                U.S. Geological Survey—Response to Request for Additional Information to Question 20, dated September 26, 2011 ...........                                                                             ML11277A013
                                                U.S. Geological Survey TRIGA Reactor—Response to Question 6 of the Referenced RAI, dated October 31, 2011 ...............                                                                              ML11314A106
                                                U.S. Geological Survey—Response to NRC Request for Additional Information Questions 7 and 8, License Renewal, dated
                                                  November 30, 2011 (redacted version) .....................................................................................................................................                           ML113460014
                                                U.S. Geological Survey—Licensee Response to NRC Request for Additional Information Question 15.3, dated January 3,
                                                  2012 (redacted version) .............................................................................................................................................................                ML120240003
                                                U.S. Geological Survey TRIGA Reactor—Response to Question 15.2 of the Request for Additional Information from Sep-
                                                  tember 29, 2010, letter, dated January 27, 2012 ......................................................................................................................                               ML12068A138
                                                U.S. Geological Survey TRIGA Reactor (GSTR)—Response to Question 18 of a Request for Additional Information dated
                                                  September 29, 2010, letter, dated January 27, 2012 ................................................................................................................                                  ML12039A173
                                                U.S. Geological Survey TRIGA Reactor—Response to Request for Additional Information to Question 14, dated March 28,
                                                  2012 ...........................................................................................................................................................................................     ML12100A097
                                                U.S. Geological Survey TRIGA Reactor—Response to Question 16 of the Referenced RAI, dated April 27, 2012 ..................                                                                            ML12128A429
                                                U.S. Geological Survey—Responses to Questions 26 and 27 of the Referenced RAI, dated May 18, 2012 .............................                                                                        ML12151A407
                                                U.S. Geological Survey—Response to Request for Additional Information (RAI) Question 14, dated May 31, 2012 ................                                                                           ML12160A064
                                                U.S. Geological Survey TRIGA Reactor—Response to Question 3 of the Referenced RAI, dated June 29, 2012 ....................                                                                            ML12200A055
                                                U.S. Geological Survey TRIGA Reactor—Response to Question 21 of the Referenced RAI dated September 29, 2010, let-
                                                  ter, dated July 31, 2012 .............................................................................................................................................................               ML12220A525
                                                U.S. Geological Survey—Responses to Questions 9, 10, 11, 12, 15.1, 23.4, 24, and 25.5; Along with a Corrected Copy of
                                                  the Proposed Technical Specifications (Chapter 14) of the SAR, dated August 30, 2012 ......................................................                                                          ML12251A231
                                                U.S. Geological Survey—Redacted—Response to NRC Request for Additional Information dated October 2, 2012, letter,
                                                  dated November 16, 2012 .........................................................................................................................................................                    ML12334A001
                                                U.S. Geological Survey—Responses to NRC Request for Additional Information dated October 2, 2012 and Telephone Con-
                                                  ference, dated December 20, 2012, letter, dated February 8, 2013 (redacted version) ..........................................................                                                       ML13052A179
                                                U.S. Geological Survey—Responses to RAIs, Follow-up Safety Analysis responses from questions of phone conference
                                                  conducted on March 21, 2013, dated May 17, 2013 (redacted version) ..................................................................................                                                ML13162A662
                                                Follow-up Safety Analysis Responses dated July 15, 2013, letter, dated October 31, 2013 ......................................................                                                         ML13311A047
                                                U.S. Geological Survey TRIGA Reactor (GSTR), Responses to Reactor Operator Requalification Questions, dated February
                                                  19, 2014 .....................................................................................................................................................................................       ML14070A040
                                                Submission of Revised Technical Specifications, Chapter 14, November 3, 2014 ......................................................................                                                    ML14325A646
                                                U.S. Geological Survey TRIGA Reactor—Responses to RAI Questions 15.3 and 28, dated November 24, 2014 (redacted
                                                  version) .......................................................................................................................................................................................     ML14338A196
                                                Revision of Proposed Technical Specifications, September 8, 2015 ...........................................................................................                                           ML15261A042
                                                U.S. Geological Survey—Responses to RAI Questions 1a, 1b, and 1c, dated January 22, 2016 ..............................................                                                                ML16042A575
                                                U.S. Geological Survey—Response to Request for Additional Information for License Renewal, dated April 1, 2016 (re-
                                                  dacted version) ...........................................................................................................................................................................          ML16110A008
                                                U.S. Geological Survey—Responses to RAI questions, dated September 12, 2016 ..................................................................                                                         ML16277A216
                                                U.S. Geological Survey—Responses to Email Questions from Mr. Wertz date September 10, 2016, dated September 22,
                                                  2016 ...........................................................................................................................................................................................     ML16273A304



                                                  Dated at Rockville, Maryland, this 17th day                               NUCLEAR REGULATORY                                                           performance awards for NRC Senior
                                                of October, 2016.                                                           COMMISSION                                                                   Executives and Senior Level System
                                                  For the Nuclear Regulatory Commission.                                                                                                                 employees and appointments to the
                                                Alexander Adams, Jr.,                                                       [NRC–2016–0217]                                                              NRC PRB Panel responsible for making
                                                Chief, Research and Test Reactors Licensing                                                                                                              recommendations to the appointing and
                                                                                                                            Performance Review Boards for Senior
                                                Branch, Division of Policy and Rulemaking,
                                                                                                                            Executive Service                                                            awarding authorities for NRC PRB
                                                Office of Nuclear Reactor Regulation.                                                                                                                    members.
                                                [FR Doc. 2016–25646 Filed 10–21–16; 8:45 am]                                AGENCY: Nuclear Regulatory
                                                BILLING CODE 7590–01–P                                                      Commission.                                                                  DATES:       October 24, 2016.
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                            ACTION: Appointments.                                                        ADDRESSES:  Please refer to Docket ID
                                                                                                                                                                                                         NRC–2016–0217 when contacting the
                                                                                                                            SUMMARY: The Nuclear Regulatory                                              NRC about the availability of
                                                                                                                            Commission (NRC) has announced                                               information regarding this document.
                                                                                                                            appointments to the NRC Performance
                                                                                                                                                                                                         You may obtain publicly-available
                                                                                                                            Review Board (PRB) responsible for
                                                                                                                                                                                                         information related to this document
                                                                                                                            making recommendations on
                                                                                                                                                                                                         using any of the following methods:
                                                                                                                            performance appraisal ratings and


                                           VerDate Sep<11>2014         17:42 Oct 21, 2016         Jkt 241001       PO 00000        Frm 00099        Fmt 4703       Sfmt 4703       E:\FR\FM\24OCN1.SGM               24OCN1



Document Created: 2016-10-21 23:45:50
Document Modified: 2016-10-21 23:45:50
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionLicense renewal; issuance.
DatesThe operating license renewal No. R-113 is effective on October 14, 2016.
ContactGeoffrey A. Wertz, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-0893; email: [email protected]
FR Citation81 FR 73153 