81_FR_8225 81 FR 8193 - Clark Canyon Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

81 FR 8193 - Clark Canyon Hydro, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 32 (February 18, 2016)

Page Range8193-8194
FR Document2016-03335

Federal Register, Volume 81 Issue 32 (Thursday, February 18, 2016)
[Federal Register Volume 81, Number 32 (Thursday, February 18, 2016)]
[Notices]
[Pages 8193-8194]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-03335]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14677-001]


Clark Canyon Hydro, LLC; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Original License for a Major Water Power 
Project at an Existing Dam, 5 Megawatts or Less.
    b. Project No.: 14677-001.
    c. Date filed: November 23, 2015.
    d. Applicant: Clark Canyon Hydro, LLC.
    e. Name of Project: Clark Canyon Dam Hydroelectric Project.
    f. Location: On the Beaverhead River, in the Town of Dillon, 
Beaverhead County, Montana. The project would occupy 62.1 acres of land 
owned by the U.S. Bureau of Reclamation and 0.2 acres of land owned by 
the U.S. Bureau of Land Management.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: John Gangemi, (406) 249-3972, email at 
[email protected].
    i. FERC Contact: Kelly Wolcott, (202) 502-6480, email at 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 30 days from the issuance date of this 
notice; reply comments are due 75 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the

[[Page 8194]]

Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14677-001.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. The Clark Canyon Dam Hydroelectric Project would utilize the 
U.S. Bureau of Reclamation's Clark Canyon Dam and outlet works 
including an intake structure and concrete conduit in the reservoir. 
The project would consist of the following new facilities: (1) A 360-
foot-long, 8-foot-diameter steel penstock within the existing concrete 
conduit, ending in a trifurcation; (2) two 35-foot-long, 8-foot-
diameter penstocks extending from the trifurcation to the powerhouse, 
transitioning to 6-foot-diameter before entering the powerhouse; (3) a 
10-foot-long, 8-foot-diameter steel penstock leaving the trifurcation 
and ending in a 7-foot-diameter cone valve and reducer to control 
discharge into the existing outlet stilling basin; (4) a 65-foot-long, 
46-foot-wide reinforced concrete powerhouse containing two vertical 
Francis-type turbine/generator units with a total capacity of 4.7 
megawatts; (5) two 25-foot-long steel draft tubes transitioning to 
concrete draft tube/tailrace section; (6) a 17-foot-long, 15-foot-
diameter tailrace channel connecting with the existing spillway 
stilling basin; (7) a 45-foot-long, 10-foot-wide aeration basin 
downstream of the powerhouse with three frames containing 330 
diffusers; (8) a 1,100-foot-long, 4.16-kilovolt (kV) buried 
transmission line from the powerhouse to a substation; (9) a substation 
containing step-up transformers and switchgear; (10) a 7.9-mile-long, 
69-kV transmission line extending from the project substation to the 
Peterson Flat substation (the point of interconnection); and (11) 
appurtenant facilities. The estimated annual generation of the Clark 
Canyon Dam Project would be 15.4 gigawatt-hours. All project facilities 
would be located on federal lands owned by the U.S. Bureau of 
Reclamation and the U.S. Bureau of Land Management. The applicant 
proposes to operate the project as run-of-release.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must (1) bear in all capital letters the title 
``COMMENTS'', ``REPLY COMMENTS'', ``RECOMMENDATIONS,'' ``TERMS AND 
CONDITIONS,'' or ``PRESCRIPTIONS;'' (2) set forth in the heading the 
name of the applicant and the project number of the application to 
which the filing responds; (3) furnish the name, address, and telephone 
number of the person submitting the filing; and (4) otherwise comply 
with the requirements of 18 CFR 385.2001 through 385.2005. All 
comments, recommendations, terms and conditions or prescriptions must 
set forth their evidentiary basis and otherwise comply with the 
requirements of 18 CFR 4.34(b). Agencies may obtain copies of the 
application directly from the applicant. Each filing must be 
accompanied by proof of service on all persons listed on the service 
list prepared by the Commission in this proceeding, in accordance with 
18 CFR 4.34(b), and 385.2010.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. Public notice of the filing of the initial development 
application, which has already been given, established the due date for 
filing competing applications or notices of intent. Under the 
Commission's regulations, any competing development application must be 
filed in response to and in compliance with public notice of the 
initial development application. No competing applications or notices 
of intent may be filed in response to this notice.
    o. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) A copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: February 11, 2016.
Nathaniel J. Davis, Sr.,
 Deputy Secretary.
[FR Doc. 2016-03335 Filed 2-17-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 81, No. 32 / Thursday, February 18, 2016 / Notices                                                 8193

                                                     Additional information about the                        Docket Numbers: ER16–711–001.                      Protests may be considered, but
                                                  Project is available from the                              Applicants: Pio Pico Energy Center,                intervention is necessary to become a
                                                  Commission’s Office of External Affairs                 LLC.                                                  party to the proceeding.
                                                  at (866) 208–FERC or on the FERC Web                       Description: Tariff Amendment:                        eFiling is encouraged. More detailed
                                                  site (www.ferc.gov). Using the                          Amendment to MBR to be effective 3/1/                 information relating to filing
                                                  ‘‘eLibrary’’ link, select ‘‘General Search’’            2016.                                                 requirements, interventions, protests,
                                                  from the eLibrary menu, enter the                          Filed Date: 2/11/16.                               service, and qualifying facilities filings
                                                  selected date range and ‘‘Docket                           Accession Number: 20160211–5093.                   can be found at: http://www.ferc.gov/
                                                  Number’’ excluding the last three digits                   Comments Due: 5 p.m. ET 3/3/16.                    docs-filing/efiling/filing-req.pdf. For
                                                  (i.e., CP15–18 or CP15–498), and follow                    Docket Numbers: ER16–922–000.                      other information, call (866) 208–3676
                                                  the instructions. For assistance with                      Applicants: Southern California                    (toll free). For TTY, call (202) 502–8659.
                                                  access to eLibrary, the helpline can be                 Edison Company.                                         Dated: February 11, 2016.
                                                  reached at (866) 208–3676, TTY (202)                       Description: § 205(d) Rate Filing:                 Nathaniel J. Davis, Sr.,
                                                  502–8659, or at FERCOnlineSupport@                      Amendment of LGIA, Service                            Deputy Secretary.
                                                  ferc.gov. The eLibrary link on the FERC                 Agreement No. 157 to be effective 4/11/               [FR Doc. 2016–03320 Filed 2–17–16; 8:45 am]
                                                  Web site also provides access to the                    2016.
                                                                                                                                                                BILLING CODE 6717–01–P
                                                  texts of formal documents issued by the                    Filed Date: 2/10/16.
                                                  Commission, such as orders, notices,                       Accession Number: 20160210–5168.
                                                  and rule makings.                                          Comments Due: 5 p.m. ET 3/2/16.
                                                     Additional information about the                                                                           DEPARTMENT OF ENERGY
                                                                                                             Docket Numbers: ER16–923–000.
                                                  White Oak and System Reliability                                                                              Federal Energy Regulatory
                                                                                                             Applicants: Puget Sound Energy, Inc.
                                                  Projects can be obtained by contacting                                                                        Commission
                                                                                                             Description: § 205(d) Rate Filing:
                                                  the environmental project manager,
                                                                                                          OATT EIM Changes to be effective 4/1/                 [Project No. 14677–001]
                                                  Gertrude Johnson, by telephone at (202)
                                                                                                          2012.
                                                  502–6692 or by electronic mail at
                                                                                                             Filed Date: 2/10/16.                               Clark Canyon Hydro, LLC; Notice of
                                                  gertrude.fernandez.johnson@ferc.gov.
                                                                                                             Accession Number: 20160210–5196.                   Application Ready for Environmental
                                                    Dated: February 10, 2016.                                Comments Due: 5 p.m. ET 3/2/16.                    Analysis and Soliciting Comments,
                                                  Nathaniel J. Davis, Sr.,                                   Docket Numbers: ER16–924–000.                      Recommendations, Terms and
                                                  Deputy Secretary.                                          Applicants: Portland General Electric              Conditions, and Prescriptions
                                                  [FR Doc. 2016–03323 Filed 2–17–16; 8:45 am]             Company.
                                                  BILLING CODE 6717–01–P                                     Description: Initial rate filing: Service             Take notice that the following
                                                                                                          Agreement Under Portland General                      hydroelectric application has been filed
                                                                                                          Electric Companys OATT to be effective                with the Commission and is available
                                                  DEPARTMENT OF ENERGY                                    3/1/2016.                                             for public inspection.
                                                                                                             Filed Date: 2/11/16.                                  a. Type of Application: Original
                                                  Federal Energy Regulatory                                  Accession Number: 20160211–5000.                   License for a Major Water Power Project
                                                  Commission                                                 Comments Due: 5 p.m. ET 3/3/16.                    at an Existing Dam, 5 Megawatts or Less.
                                                                                                                                                                   b. Project No.: 14677–001.
                                                  Combined Notice of Filings #1                              Docket Numbers: ER16–925–000.
                                                                                                                                                                   c. Date filed: November 23, 2015.
                                                                                                             Applicants: New York Independent
                                                     Take notice that the Commission                                                                               d. Applicant: Clark Canyon Hydro,
                                                                                                          System Operator, Inc.
                                                  received the following electric rate                                                                          LLC.
                                                                                                             Description: § 205(d) Rate Filing:
                                                  filings:                                                                                                         e. Name of Project: Clark Canyon Dam
                                                                                                          LGIA (SA No. 2260) between NMPC and
                                                                                                                                                                Hydroelectric Project.
                                                     Docket Numbers: ER10–1484–012.                       Indeck-Corinth to be effective 11/19/
                                                     Applicants: Shell Energy North                                                                                f. Location: On the Beaverhead River,
                                                                                                          2015.
                                                  America (US), L.P.                                                                                            in the Town of Dillon, Beaverhead
                                                                                                             Filed Date: 2/11/16.
                                                     Description: Supplement to November                                                                        County, Montana. The project would
                                                                                                             Accession Number: 20160211–5001.
                                                  11, 2015 Notice of Non-Material Change                                                                        occupy 62.1 acres of land owned by the
                                                                                                             Comments Due: 5 p.m. ET 3/3/16.
                                                  in Status of Shell Energy North America                                                                       U.S. Bureau of Reclamation and 0.2
                                                                                                             Docket Numbers: ER16–926–000.                      acres of land owned by the U.S. Bureau
                                                  (US), L.P.                                                 Applicants: Southwest Power Pool,
                                                     Filed Date: 2/10/16.                                                                                       of Land Management.
                                                     Accession Number: 20160210–5204.                     Inc.                                                     g. Filed Pursuant to: Federal Power
                                                     Comments Due: 5 p.m. ET 3/2/16.                         Description: § 205(d) Rate Filing: 3164            Act 16 U.S.C. 791(a)–825(r).
                                                                                                          Aksamit Resource Management, LLC                         h. Applicant Contact: John Gangemi,
                                                     Docket Numbers: ER15–1332–004;
                                                                                                          GIA to be effective 1/19/2016.                        (406) 249–3972, email at john.gangemi@
                                                  ER10–2397–003; ER10–2403–005;
                                                                                                             Filed Date: 2/11/16.                               erm.com.
                                                  ER10–2425–005; ER15–1020–002;
                                                                                                             Accession Number: 20160211–5038.                      i. FERC Contact: Kelly Wolcott, (202)
                                                  ER15–1333–004.
                                                     Applicants: Arbuckle Mountain Wind                      Comments Due: 5 p.m. ET 3/3/16.                    502–6480, email at kelly.wolcott@
                                                  Farm LLC, Arlington Wind Power                             The filings are accessible in the                  ferc.gov.
                                                  Project LLC, Cloud County Wind Farm,                    Commission’s eLibrary system by                          j. Deadline for filing comments,
                                                  LLC, Pioneer Prairie Wind Farm I, LLC,                  clicking on the links or querying the                 recommendations, terms and
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  Rising Tree Wind Farm III LLC, Waverly                  docket number.                                        conditions, and prescriptions: 30 days
                                                  Wind Farm LLC.                                             Any person desiring to intervene or                from the issuance date of this notice;
                                                     Description: Notice of Non-Material                  protest in any of the above proceedings               reply comments are due 75 days from
                                                  Change in Status of Arbuckle Mountain                   must file in accordance with Rules 211                the issuance date of this notice.
                                                  Wind Farm LLC, et al.                                   and 214 of the Commission’s                              The Commission strongly encourages
                                                     Filed Date: 2/10/16.                                 Regulations (18 CFR 385.211 and                       electronic filing. Please file comments,
                                                     Accession Number: 20160210–5212.                     385.214) on or before 5:00 p.m. Eastern               recommendations, terms and
                                                     Comments Due: 5 p.m. ET 3/2/16.                      time on the specified comment date.                   conditions, and prescriptions using the


                                             VerDate Sep<11>2014   19:03 Feb 17, 2016   Jkt 238001   PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\18FEN1.SGM   18FEN1


                                                  8194                        Federal Register / Vol. 81, No. 32 / Thursday, February 18, 2016 / Notices

                                                  Commission’s eFiling system at http://                  transformers and switchgear; (10) a 7.9-              competing applications or notices of
                                                  www.ferc.gov/docs-filing/efiling.asp.                   mile-long, 69-kV transmission line                    intent may be filed in response to this
                                                  Commenters can submit brief comments                    extending from the project substation to              notice.
                                                  up to 6,000 characters, without prior                   the Peterson Flat substation (the point of               o. A license applicant must file no
                                                  registration, using the eComment system                 interconnection); and (11) appurtenant                later than 60 days following the date of
                                                  at http://www.ferc.gov/docs-filing/                     facilities. The estimated annual                      issuance of this notice: (1) A copy of the
                                                  ecomment.asp. You must include your                     generation of the Clark Canyon Dam                    water quality certification; (2) A copy of
                                                  name and contact information at the end                 Project would be 15.4 gigawatt-hours.                 the request for certification, including
                                                  of your comments. For assistance,                       All project facilities would be located               proof of the date on which the certifying
                                                  please contact FERC Online Support at                   on federal lands owned by the U.S.                    agency received the request; or (3)
                                                  FERCOnlineSupport@ferc.gov, (866)                       Bureau of Reclamation and the U.S.                    evidence of waiver of water quality
                                                  208–3676 (toll free), or (202) 502–8659                 Bureau of Land Management. The                        certification.
                                                  (TTY). In lieu of electronic filing, please             applicant proposes to operate the                       Dated: February 11, 2016.
                                                  send a paper copy to: Secretary, Federal                project as run-of-release.
                                                                                                                                                                Nathaniel J. Davis, Sr.,
                                                  Energy Regulatory Commission, 888                          m. A copy of the application is
                                                  First Street NE., Washington, DC 20426.                 available for review at the Commission                Deputy Secretary.
                                                  The first page of any filing should                     in the Public Reference Room or may be                [FR Doc. 2016–03335 Filed 2–17–16; 8:45 am]
                                                  include docket number P–14677–001.                      viewed on the Commission’s Web site at                BILLING CODE 6717–01–P
                                                     The Commission’s Rules of Practice                   http://www.ferc.gov using the
                                                  require all intervenors filing documents                ‘‘eLibrary’’ link. Enter the docket
                                                  with the Commission to serve a copy of                  number excluding the last three digits in             DEPARTMENT OF ENERGY
                                                  that document on each person on the                     the docket number field to access the
                                                  official service list for the project.                  document. For assistance, contact FERC                Federal Energy Regulatory
                                                  Further, if an intervenor files comments                Online Support. A copy is also available              Commission
                                                  or documents with the Commission                        for inspection and reproduction at the                [Docket No. ER16–915–000 ]
                                                  relating to the merits of an issue that                 address in item h above.
                                                  may affect the responsibilities of a                       All filings must (1) bear in all capital           Comanche Solar PV, LLC;
                                                  particular resource agency, they must                   letters the title ‘‘COMMENTS’’, ‘‘REPLY               Supplemental Notice That Initial
                                                  also serve a copy of the document on                    COMMENTS’’,                                           Market-Based Rate Filing Includes
                                                  that resource agency.                                   ‘‘RECOMMENDATIONS,’’ ‘‘TERMS                          Request for Blanket Section 204
                                                     k. This application has been accepted                AND CONDITIONS,’’ or                                  Authorization
                                                  and is now ready for environmental                      ‘‘PRESCRIPTIONS;’’ (2) set forth in the
                                                  analysis.                                               heading the name of the applicant and                    This is a supplemental notice in the
                                                     l. The Clark Canyon Dam                              the project number of the application to              above-referenced proceeding of
                                                  Hydroelectric Project would utilize the                 which the filing responds; (3) furnish                Comanche Solar PV, LLC’s application
                                                  U.S. Bureau of Reclamation’s Clark                      the name, address, and telephone                      for market-based rate authority, with an
                                                  Canyon Dam and outlet works including                   number of the person submitting the                   accompanying rate tariff, noting that
                                                  an intake structure and concrete conduit                filing; and (4) otherwise comply with                 such application includes a request for
                                                  in the reservoir. The project would                     the requirements of 18 CFR 385.2001                   blanket authorization, under 18 CFR
                                                  consist of the following new facilities:                through 385.2005. All comments,                       part 34, of future issuances of securities
                                                  (1) A 360-foot-long, 8-foot-diameter steel              recommendations, terms and conditions                 and assumptions of liability.
                                                  penstock within the existing concrete                   or prescriptions must set forth their                    Any person desiring to intervene or to
                                                  conduit, ending in a trifurcation; (2) two              evidentiary basis and otherwise comply                protest should file with the Federal
                                                  35-foot-long, 8-foot-diameter penstocks                 with the requirements of 18 CFR 4.34(b).              Energy Regulatory Commission, 888
                                                  extending from the trifurcation to the                  Agencies may obtain copies of the                     First Street NE., Washington, DC 20426,
                                                  powerhouse, transitioning to 6-foot-                    application directly from the applicant.              in accordance with Rules 211 and 214
                                                  diameter before entering the                            Each filing must be accompanied by                    of the Commission’s Rules of Practice
                                                  powerhouse; (3) a 10-foot-long, 8-foot-                 proof of service on all persons listed on             and Procedure (18 CFR 385.211 and
                                                  diameter steel penstock leaving the                     the service list prepared by the                      385.214). Anyone filing a motion to
                                                  trifurcation and ending in a 7-foot-                    Commission in this proceeding, in                     intervene or protest must serve a copy
                                                  diameter cone valve and reducer to                      accordance with 18 CFR 4.34(b), and                   of that document on the Applicant.
                                                  control discharge into the existing outlet              385.2010.                                                Notice is hereby given that the
                                                  stilling basin; (4) a 65-foot-long, 46-foot-               You may also register online at                    deadline for filing protests with regard
                                                  wide reinforced concrete powerhouse                     http://www.ferc.gov/docs-filing/                      to the applicant’s request for blanket
                                                  containing two vertical Francis-type                    esubscription.asp to be notified via                  authorization, under 18 CFR part 34, of
                                                  turbine/generator units with a total                    email of new filings and issuances                    future issuances of securities and
                                                  capacity of 4.7 megawatts; (5) two 25-                  related to this or other pending projects.            assumptions of liability, is March 2,
                                                  foot-long steel draft tubes transitioning               For assistance, contact FERC Online                   2016.
                                                  to concrete draft tube/tailrace section;                Support.                                                 The Commission encourages
                                                  (6) a 17-foot-long, 15-foot-diameter                       n. Public notice of the filing of the              electronic submission of protests and
                                                  tailrace channel connecting with the                    initial development application, which                interventions in lieu of paper, using the
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  existing spillway stilling basin; (7) a 45-             has already been given, established the               FERC Online links at http://
                                                  foot-long, 10-foot-wide aeration basin                  due date for filing competing                         www.ferc.gov. To facilitate electronic
                                                  downstream of the powerhouse with                       applications or notices of intent. Under              service, persons with Internet access
                                                  three frames containing 330 diffusers;                  the Commission’s regulations, any                     who will eFile a document and/or be
                                                  (8) a 1,100-foot-long, 4.16-kilovolt (kV)               competing development application                     listed as a contact for an intervenor
                                                  buried transmission line from the                       must be filed in response to and in                   must create and validate an
                                                  powerhouse to a substation; (9) a                       compliance with public notice of the                  eRegistration account using the
                                                  substation containing step-up                           initial development application. No                   eRegistration link. Select the eFiling


                                             VerDate Sep<11>2014   19:03 Feb 17, 2016   Jkt 238001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\18FEN1.SGM   18FEN1



Document Created: 2016-02-18 07:46:27
Document Modified: 2016-02-18 07:46:27
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106: