81_FR_84799 81 FR 84573 - Dominion Carolina Gas Transmission, LLC; Notice of Request Under Blanket Authorization

81 FR 84573 - Dominion Carolina Gas Transmission, LLC; Notice of Request Under Blanket Authorization

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 226 (November 23, 2016)

Page Range84573-84574
FR Document2016-28158

Federal Register, Volume 81 Issue 226 (Wednesday, November 23, 2016)
[Federal Register Volume 81, Number 226 (Wednesday, November 23, 2016)]
[Notices]
[Pages 84573-84574]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-28158]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-12-000]


Dominion Carolina Gas Transmission, LLC; Notice of Request Under 
Blanket Authorization

    Take notice that on November 9, 2016, Dominion Carolina Gas 
Transmission, LLC (DCG), 121 Moore Hopkins Lane, Columbia, South 
Carolina 29210, filed in Docket No. CP17-12-000, a prior notice request 
pursuant to sections 157.205 and 157.216 of the Commission's 
regulations under the Natural Gas Act (NGA). DCG seeks authorization to 
abandon in place and disconnect an 11.01 mile segment of its Line L in 
Kershaw County, South Carolina.
    DCG proposes to perform these activities under its blanket 
certificate authority issued in Docket No. CP06-72-000, all as more 
fully set forth in the application which is on file with the Commission 
and open to public inspection.
    The filing may be viewed on the web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at FERCOnlineSupport@ferc.gov or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions regarding this application should be directed to 
Richard D. Jessee, Gas Transmission Certificates Program Manager, 
Dominion Carolina Gas Transmission, LLC, 707 East Main Street, 
Richmond, VA 23219, or by calling (804) 771-3704. (telephone), 
Richard.Jessee@dom.com,
    Any person or the Commission's Staff may, within 60 days after the 
issuance of the instant notice by the Commission, file pursuant to Rule 
214 of the Commission's Procedural Rules (18 CFR 385.214) a motion to 
intervene or notice of intervention and, pursuant to section 157.205 of 
the Commission's

[[Page 84574]]

Regulations under the NGA (18 CFR 157.205) a protest to the request. If 
no protest is filed within the time allowed therefore, the proposed 
activity shall be deemed to be authorized effective the day after the 
time allowed for protest. If a protest is filed and not withdrawn 
within 30 days after the time allowed for filing a protest, the instant 
request shall be treated as an application for authorization pursuant 
to section 7 of the NGA.
    Pursuant to Section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding, or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commenters will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commenters will not be required to serve copies of filed 
documents on all other parties. However, the non-party commenters will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests, and interventions via the internet in lieu of paper. See 18 
CFR 385.2001(a) (1) (iii) and the instructions on the Commission's Web 
site (www.ferc.gov) under the ``e-Filing'' link. Persons unable to file 
electronically should submit an original and 5 copies of the protest or 
intervention to the Federal Energy Regulatory Commission, 888 First 
Street, NE., Washington, DC 20426.

    Dated: November 16, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-28158 Filed 11-22-16; 8:45 am]
 BILLING CODE 6717-01-P



                                                                          Federal Register / Vol. 81, No. 226 / Wednesday, November 23, 2016 / Notices                                                 84573

                                                  Galveston Block 391 to Brazos Block                     to the proceedings for this project                   and five copies of the protest or
                                                  538, Offshore, Texas, and related                       should, on or before the comment date                 intervention to the Federal Energy
                                                  metering facilities, all as more fully set              stated below, file with the Federal                   Regulatory Commission, 888 First Street
                                                  forth in the application which is on file               Energy Regulatory Commission, 888                     NE., Washington, DC 20426.
                                                  with the Commission and open to                         First Street NE., Washington, DC 20426,                 Comment Date: 5:00 p.m. Eastern
                                                  public inspection.                                      a motion to intervene in accordance                   Time on December 7, 2016.
                                                     The filing may also be viewed on the                 with the requirements of the                            Dated: November 16, 2016.
                                                  Web at http://www.ferc.gov using the                    Commission’s Rules of Practice and
                                                                                                                                                                Kimberly D. Bose,
                                                  ‘‘eLibrary’’ link. Enter the docket                     Procedure (18 CFR 385.214 or 385.211)
                                                  number excluding the last three digits in                                                                     Secretary.
                                                                                                          and the Regulations under the NGA (18
                                                  the docket number field to access the                   CFR 157.10). A person obtaining party                 [FR Doc. 2016–28157 Filed 11–22–16; 8:45 am]
                                                  document. For assistance, please contact                status will be placed on the service list             BILLING CODE 6717–01–P
                                                  FERC Online Support at                                  maintained by the Secretary of the
                                                  FERCOnlineSupport@ferc.gov or toll                      Commission and will receive copies of
                                                  free at (866) 208–3676, or TTY, contact                 all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                                  (202) 502–8659.                                         by all other parties. A party must submit
                                                     Any questions concerning this                                                                              Federal Energy Regulatory
                                                                                                          five copies of filings made with the
                                                  application may be directed to Marg                                                                           Commission
                                                                                                          Commission and must mail a copy to
                                                  Camardello, Regulatory Analyst, Lead,                   the applicant and to every other party in             [Docket No. CP17–12–000]
                                                  (713) 215–3380, P.O. Box 1396,                          the proceeding. Only parties to the
                                                  Houston, Texas 77251; and Ben                           proceeding can ask for court review of                Dominion Carolina Gas Transmission,
                                                  Carranza, Manager, Rates & Regulatory,                  Commission orders in the proceeding.                  LLC; Notice of Request Under Blanket
                                                  (713) 420–5535, 1001 Louisiana Street,                     However, a person does not have to                 Authorization
                                                  Suite 1000, Houston Texas 77002.                        intervene in order to have comments
                                                     Specifically, Transco and Tennessee                                                                           Take notice that on November 9,
                                                                                                          considered. The second way to
                                                  propose to abandon four pipeline                                                                              2016, Dominion Carolina Gas
                                                                                                          participate is by filing with the
                                                  segments on Transco’s Central Texas                                                                           Transmission, LLC (DCG), 121 Moore
                                                                                                          Secretary of the Commission, as soon as
                                                  Gathering System, offshore Texas: Three                                                                       Hopkins Lane, Columbia, South
                                                                                                          possible, an original and two copies of
                                                  20-inch-diameter segments with a                        comments in support of or in opposition               Carolina 29210, filed in Docket No.
                                                  combined length of 40.45-miles                          to this project. The Commission will                  CP17–12–000, a prior notice request
                                                  connecting Transco Platform BA538 to                    consider these comments in                            pursuant to sections 157.205 and
                                                  Platform GA393, and 16-inch-diameter                    determining the appropriate action to be              157.216 of the Commission’s regulations
                                                  5.87-mile-long segment immediately                      taken, but the filing of a comment alone              under the Natural Gas Act (NGA). DCG
                                                  downstream of Transco Platform                          will not serve to make the filer a party              seeks authorization to abandon in place
                                                  GA393. Transco states that due to the                   to the proceeding. The Commission’s                   and disconnect an 11.01 mile segment
                                                  minimal flow on the Laterals, it would                  rules require that persons filing                     of its Line L in Kershaw County, South
                                                  not be operationally feasible to pig these              comments in opposition to the project                 Carolina.
                                                  facilities in order to maintain their                   provide copies of their protests only to                 DCG proposes to perform these
                                                  integrity. The requested order date is                  the party or parties directly involved in             activities under its blanket certificate
                                                  March 1, 2017. The project cost is                      the protest.                                          authority issued in Docket No. CP06–
                                                  estimated at $2.28 million.                                Persons who wish to comment only                   72–000, all as more fully set forth in the
                                                     Pursuant to section 157.9 of the                     on the environmental review of this                   application which is on file with the
                                                  Commission’s rules, 18 CFR 157.9,                       project should submit an original and                 Commission and open to public
                                                  within 90 days of this Notice the                       two copies of their comments to the                   inspection.
                                                  Commission staff will either: Complete                  Secretary of the Commission.                             The filing may be viewed on the web
                                                  its environmental assessment (EA) and                   Environmental commentors will be                      at http://www.ferc.gov using the
                                                  place it into the Commission’s public                   placed on the Commission’s                            ‘‘eLibrary’’ link. Enter the docket
                                                  record (eLibrary) for this proceeding; or               environmental mailing list, will receive              number excluding the last three digits in
                                                  issue a Notice of Schedule for                          copies of the environmental documents,                the docket number field to access the
                                                  Environmental Review. If a Notice of                    and will be notified of meetings                      document. For assistance, contact FERC
                                                  Schedule for Environmental Review is                    associated with the Commission’s                      at FERCOnlineSupport@ferc.gov or call
                                                  issued, it will indicate, among other                   environmental review process.                         toll-free, (886) 208–3676 or TYY, (202)
                                                  milestones, the anticipated date for the                Environmental commentors will not be                  502–8659.
                                                  Commission staff’s issuance of the EA                   required to serve copies of filed                        Any questions regarding this
                                                  for this proposal. The filing of the EA                 documents on all other parties.                       application should be directed to
                                                  in the Commission’s public record for                   However, the non-party commentors                     Richard D. Jessee, Gas Transmission
                                                  this proceeding or the issuance of a                    will not receive copies of all documents              Certificates Program Manager, Dominion
                                                  Notice of Schedule for Environmental                    filed by other parties or issued by the               Carolina Gas Transmission, LLC, 707
                                                  Review will serve to notify federal and                 Commission (except for the mailing of                 East Main Street, Richmond, VA 23219,
                                                  state agencies of the timing for the                    environmental documents issued by the                 or by calling (804) 771–3704.
                                                  completion of all necessary reviews, and                Commission) and will not have the right               (telephone), Richard.Jessee@dom.com,
                                                  the subsequent need to complete all                     to seek court review of the                              Any person or the Commission’s Staff
mstockstill on DSK3G9T082PROD with NOTICES




                                                  federal authorizations within 90 days of                Commission’s final order.                             may, within 60 days after the issuance
                                                  the date of issuance of the Commission                     The Commission strongly encourages                 of the instant notice by the Commission,
                                                  staff’s EA.                                             electronic filings of comments, protests              file pursuant to Rule 214 of the
                                                     There are two ways to become                         and interventions in lieu of paper using              Commission’s Procedural Rules (18 CFR
                                                  involved in the Commission’s review of                  the ‘‘eFiling’’ link at http://                       385.214) a motion to intervene or notice
                                                  this project. First, any person wishing to              www.ferc.gov. Persons unable to file                  of intervention and, pursuant to section
                                                  obtain legal status by becoming a party                 electronically should submit original                 157.205 of the Commission’s


                                             VerDate Sep<11>2014   18:04 Nov 22, 2016   Jkt 241001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\23NON1.SGM   23NON1


                                                  84574                   Federal Register / Vol. 81, No. 226 / Wednesday, November 23, 2016 / Notices

                                                  Regulations under the NGA (18 CFR                       protest or intervention to the Federal                   Applicants: Southwest Power Pool,
                                                  157.205) a protest to the request. If no                Energy Regulatory Commission, 888                     Inc.
                                                  protest is filed within the time allowed                First Street, NE., Washington, DC 20426.                 Description: § 205(d) Rate Filing:
                                                  therefore, the proposed activity shall be                 Dated: November 16, 2016.
                                                                                                                                                                Revisions to Prospectively Require All
                                                  deemed to be authorized effective the                                                                         VERs to Register as DVERs to be
                                                                                                          Kimberly D. Bose,
                                                  day after the time allowed for protest. If                                                                    effective 1/15/2017.
                                                                                                          Secretary.                                               Filed Date: 11/16/16.
                                                  a protest is filed and not withdrawn
                                                  within 30 days after the time allowed                   [FR Doc. 2016–28158 Filed 11–22–16; 8:45 am]             Accession Number: 20161116–5132.
                                                  for filing a protest, the instant request               BILLING CODE 6717–01–P                                   Comments Due: 5 p.m. ET 12/7/16.
                                                  shall be treated as an application for                                                                           Docket Numbers: ER17–367–000.
                                                  authorization pursuant to section 7 of                                                                           Applicants: PJM Interconnection,
                                                  the NGA.                                                DEPARTMENT OF ENERGY                                  L.L.C.
                                                     Pursuant to Section 157.9 of the                                                                              Description: § 205(d) Rate Filing:
                                                                                                          Federal Energy Regulatory                             Revisions to the OATT and RAA RE:
                                                  Commission’s rules, 18 CFR 157.9,
                                                                                                          Commission                                            Enhanced Aggregation and Seasonal
                                                  within 90 days of this Notice the
                                                  Commission staff will either: Complete                                                                        Capacity to be effective 1/19/2017.
                                                                                                          Combined Notice of Filings #1                            Filed Date: 11/17/16.
                                                  its environmental assessment (EA) and
                                                  place it into the Commission’s public                      Take notice that the Commission                       Accession Number: 20161117–5003.
                                                  record (eLibrary) for this proceeding, or               received the following electric corporate                Comments Due: 5 p.m. ET 12/8/16.
                                                  issue a Notice of Schedule for                          filings:                                                 Docket Numbers: ER17–368–000.
                                                  Environmental Review. If a Notice of                                                                             Applicants: Southwest Power Pool,
                                                                                                             Docket Numbers: EC17–34–000.
                                                  Schedule for Environmental Review is                                                                          Inc.
                                                                                                             Applicants: Great Western Wind                        Description: § 205(d) Rate Filing:
                                                  issued, it will indicate, among other                   Energy, LLC.
                                                  milestones, the anticipated date for the                                                                      3114R1 Resale Power Group of Iowa
                                                                                                             Description: Application for                       NITSA NOA to be effective 11/1/2016.
                                                  Commission staff’s issuance of the final                Authorization under Section 203 of the                   Filed Date: 11/17/16.
                                                  environmental impact statement (FEIS)                   Federal Power Act and Request for                        Accession Number: 20161117–5021.
                                                  or EA for this proposal. The filing of the              Expedited Consideration and                              Comments Due: 5 p.m. ET 12/8/16.
                                                  EA in the Commission’s public record                    Confidential Treatment of Great Western                  The filings are accessible in the
                                                  for this proceeding or the issuance of a                Wind Energy, LLC.                                     Commission’s eLibrary system by
                                                  Notice of Schedule for Environmental                       Filed Date: 11/16/16.                              clicking on the links or querying the
                                                  Review will serve to notify federal and                    Accession Number: 20161116–5159.                   docket number.
                                                  state agencies of the timing for the                       Comments Due: 5 p.m. ET 12/7/16.                      Any person desiring to intervene or
                                                  completion of all necessary reviews, and                   Take notice that the Commission                    protest in any of the above proceedings
                                                  the subsequent need to complete all                     received the following electric rate                  must file in accordance with Rules 211
                                                  federal authorizations within 90 days of                filings:                                              and 214 of the Commission’s
                                                  the date of issuance of the Commission                     Docket Numbers: ER10–2881–014;                     Regulations (18 CFR 385.211 and
                                                  staff’s FEIS or EA.                                     ER10–2641–014; ER10–2663–014;                         385.214) on or before 5:00 p.m. Eastern
                                                     Persons who wish to comment only
                                                                                                          ER10–2882–014; ER10–2883–014;                         time on the specified comment date.
                                                  on the environmental review of this
                                                                                                          ER10–2884–014; ER10–2885–014;                         Protests may be considered, but
                                                  project should submit an original and
                                                                                                          ER13–1101–009; ER13–1541–008;                         intervention is necessary to become a
                                                  two copies of their comments to the
                                                                                                          ER14–787–002; EL15–39–000.                            party to the proceeding.
                                                  Secretary of the Commission.                                                                                     eFiling is encouraged. More detailed
                                                                                                             Applicants: Alabama Power
                                                  Environmental commenters will be                                                                              information relating to filing
                                                                                                          Company; Southern Power Company;
                                                  placed on the Commission’s
                                                                                                          Mississippi Power Company; Georgia                    requirements, interventions, protests,
                                                  environmental mailing list, will receive
                                                                                                          Power Company; Gulf Power Company;                    service, and qualifying facilities filings
                                                  copies of the environmental documents,
                                                                                                          Oleander Power Project, Limited                       can be found at: http://www.ferc.gov/
                                                  and will be notified of meetings
                                                                                                          Partnership; Southern Company—                        docs-filing/efiling/filing-req.pdf. For
                                                  associated with the Commission’s
                                                                                                          Florida LLC; Southern Turner Cimarron                 other information, call (866) 208–3676
                                                  environmental review process.
                                                                                                          I, LLC; Spectrum Nevada Solar, LLC;                   (toll free). For TTY, call (202) 502–8659.
                                                  Environmental commenters will not be
                                                  required to serve copies of filed                       Campo Verde Solar, LLC; Macho                           Dated: November 17, 2016.
                                                  documents on all other parties.                         Springs Solar, LLC.                                   Nathaniel J. Davis, Sr.,
                                                  However, the non-party commenters                          Description: Comments of Southern                  Deputy Secretary.
                                                  will not receive copies of all documents                Companies on the EQR Analysis of
                                                                                                                                                                [FR Doc. 2016–28196 Filed 11–22–16; 8:45 am]
                                                  filed by other parties or issued by the                 Hour-Ahead Transactions in accordance
                                                                                                                                                                BILLING CODE 6717–01–P
                                                  Commission (except for the mailing of                   to the August 9, 2016 and October 13,
                                                  environmental documents issued by the                   2016 Orders.
                                                  Commission) and will not have the right                    Filed Date: 10/28/16.                              DEPARTMENT OF ENERGY
                                                  to seek court review of the                                Accession Number: 20161028–5192.
                                                  Commission’s final order.                                  Comments Due: 5 p.m. ET 11/18/16.                  Federal Energy Regulatory
                                                     The Commission strongly encourages                      Docket Numbers: ER17–272–000.                      Commission
                                                  electronic filings of comments, protests,                  Applicants: Startrans IO, LLC.
mstockstill on DSK3G9T082PROD with NOTICES




                                                  and interventions via the internet in lieu                 Description: Errata to November 1,                 Combined Notice of Filings
                                                  of paper. See 18 CFR 385.2001(a) (1) (iii)              2016 Startrans IO, LLC tariff filing                    Take notice that the Commission has
                                                  and the instructions on the                             (Exhibit ST–03).                                      received the following Natural Gas
                                                  Commission’s Web site (www.ferc.gov)                       Filed Date: 11/16/16.                              Pipeline Rate and Refund Report filings:
                                                  under the ‘‘e-Filing’’ link. Persons                       Accession Number: 20161116–5149.
                                                  unable to file electronically should                       Comments Due: 5 p.m. ET 12/7/16.                   Filings Instituting Proceedings
                                                  submit an original and 5 copies of the                     Docket Numbers: ER17–366–000.                        Docket Numbers: RP17–178–000.


                                             VerDate Sep<11>2014   18:04 Nov 22, 2016   Jkt 241001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\23NON1.SGM   23NON1



Document Created: 2016-11-23 05:30:42
Document Modified: 2016-11-23 05:30:42
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 84573 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR