81_FR_87267 81 FR 87035 - Proposed 2018 Olmsted Power Marketing Plan

81 FR 87035 - Proposed 2018 Olmsted Power Marketing Plan

DEPARTMENT OF ENERGY
Western Area Power Administration

Federal Register Volume 81, Issue 232 (December 2, 2016)

Page Range87035-87036
FR Document2016-28976

Western Area Power Administration (WAPA), a Federal power marketing agency of the Department of Energy, is seeking comments about this Proposed Olmsted Power Marketing Plan. WAPA has responsibility for the marketing of energy from the Colorado River Storage Project (CRSP), among other projects, and operates the transmission infrastructure associated with these Federal projects.

Federal Register, Volume 81 Issue 232 (Friday, December 2, 2016)
[Federal Register Volume 81, Number 232 (Friday, December 2, 2016)]
[Notices]
[Pages 87035-87036]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-28976]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Western Area Power Administration


Proposed 2018 Olmsted Power Marketing Plan

AGENCY: Western Area Power Administration, Department of Energy (DOE).

ACTION: Notice of Proposed Olmsted Power Marketing Plan and 
announcement of public information and comment forum.

-----------------------------------------------------------------------

SUMMARY: Western Area Power Administration (WAPA), a Federal power 
marketing agency of the Department of Energy, is seeking comments about 
this Proposed Olmsted Power Marketing Plan. WAPA has responsibility for 
the marketing of energy from the Colorado River Storage Project (CRSP), 
among other projects, and operates the transmission infrastructure 
associated with these Federal projects.

DATES: The public comment period on the Proposed Olmsted Power 
Marketing Plan begins December 2, 2016 and ends March 2, 2017. To be 
assured of consideration, WAPA must receive all written comments by the 
end of the comment period. WAPA reserves the right not to consider any 
comments received after the prescribed date and time.
    WAPA will hold a public information forum about this proposed 
marketing plan on Friday, January 13, 2017, from 10 a.m. to 12 p.m. MST 
at the Bureau of Reclamation, 125 South State Street, Salt Lake City, 
Utah. The public comment forum is scheduled for the afternoon of the 
same day Friday, January 13, 2017, from 1 p.m. to 3 p.m. MST at the 
Bureau of Reclamation, 125 South State Street, Salt Lake City, Utah.

ADDRESSES: Submit written comments about this proposed marketing plan 
to: Ms. Lynn C. Jeka, CRSP Manager, CRSP Management Center, Western 
Area Power Administration, 150 East Social Hall Avenue, Suite 300, Salt 
Lake City, UT 84111-1580. Comments may also be emailed to [email protected] 
or be faxed to (801) 524-5017. All documentation developed or retained 
by WAPA for the purpose of developing the proposed marketing plan will 
be available for inspection and copying at the CRSP Management Center 
office, 150 East Social Hall Avenue, Suite 300, Salt Lake City, Utah.

FOR FURTHER INFORMATION CONTACT: Mr. Brent Osiek, CRSP Power Marketing 
Manager, [email protected], (801) 524-5495; or Mr. Steve Mullen, CRSP 
Public Utilities Specialist, [email protected], (801) 524-6383. Written 
requests for information should be mailed to CRSP Management Center, 
Western Area Power Administration, 150 East Social Hall Avenue, Suite 
300, Salt Lake City, UT 84111-1580, or faxed to (801) 524-5017.

SUPPLEMENTARY INFORMATION: The Olmsted Powerplant, located in northern 
Utah, was acquired in condemnation proceedings by the United States in 
1990 in order to secure water rights associated with the Olmsted 
Powerplant deemed essential to the Central Utah Project (CUP). The CUP 
is a participating project of the CRSP. As part of the condemnation 
proceedings, PacifiCorp continued Olmsted operations until 2015, after 
which time the operation of the facility became the responsibility of 
the Department of the Interior, Bureau of Reclamation.
    The existing Olmsted Powerplant is over 100 years old and has 
greatly exceeded its operational life. A replacement facility is being 
constructed for the generation of power and the preservation of 
associated non-consumptive water rights necessary for the CUP. On 
February 4, 2015, an Implementation Agreement (Agreement) for the 
Olmsted Powerplant Replacement Project (Project) was signed by Central 
Utah Water Conservancy District (District); Department of the Interior, 
Bureau of Reclamation; and Department of Energy, WAPA (Participants). 
The Agreement sets forth the responsibilities of the Participants and 
how the Project will be funded. The District will construct, operate, 
maintain, and replace the Olmsted facilities in connection with its CUP 
operations, including power generation.
    The Olmsted facilities are a feature of the CUP, which is a 
participating project of CRSP. WAPA markets the hydropower generated 
from the CRSP facilities as well as the participating projects of CRSP. 
In accordance with Acts of Congress approved April 11, 1956 (70 Stat. 
105); August 4, 1977 (91 Stat. 565); October 30, 1992 (106 Stat. 
46050); and Acts amendatory or supplementary to the foregoing Acts, 
WAPA will be responsible for marketing the energy from the Olmsted 
Powerplant. WAPA plans to begin marketing energy from the Olmsted

[[Page 87036]]

Powerplant in the summer of 2018. Only energy, without capacity, will 
be available for marketing (power production will be non-dispatchable 
and incidental to the delivery of water). It is expected that annual 
energy production from the replacement Olmsted Powerplant will average 
approximately 27,000,000 kWh per year.

Proposed 2018 Olmsted Power Marketing Plan

    WAPA proposes to apply the following criteria to applicants seeking 
an allocation of energy under the proposed 2018 Olmsted Power Marketing 
Plan:
    1. Contract Term: Due to the lack of actual generating data, the 
term of the contract will be limited. Service is expected to begin on 
July 1, 2018, or as soon as the Project is declared commercially 
operable; and the contract term will be effective through September 30, 
2024.
    2. Marketing Area: Due to the relatively small size of the resource 
and its operating characteristics, eligible applicants must be 
preference entities, in accordance with section 9(c) of the Reclamation 
Project Act of 1939 (43 U.S.C. 485h(c)), located within the following 
counties in Utah: Davis, Morgan, Salt Lake, Summit, Utah, Weber, and 
Wasatch.
    3. Delivery Point: 12.47-kV bus at PacifiCorp's Hale Substation or 
another substation that may be identified that can be electrically 
interconnected to the Project.
    4. Transmission: Any associated transformation/transmission beyond 
PacifiCorp's 12.47-kV bus at the Hale Substation, or other identified 
substation if delivery is not made at the Hale Substation, is the sole 
responsibility of the applicant. Applicants must have the necessary 
arrangements for transmission and/or distribution service in place by 
April 1, 2018.
    5. Eligible Applicants: WAPA will provide allocations only to 
preference entities in the marketing area. WAPA, through the public 
process, will determine the amount of energy, if any, to allocate in 
accordance with the marketing criteria and administrative discretion 
under Reclamation Law. Priority will be given to the District as the 
operator of the Olmsted Powerplant.
    6. Resource Pool: WAPA will take into consideration all existing 
Federal hydropower allocations an applicant is currently receiving when 
determining each allocation. Allocations of Olmsted energy will be 
determined solely by WAPA. Applicants who receive an allocation will be 
allocated a percentage of the annual energy output of the Powerplant.
    7. Preference Entities: Preference will be given to entities in 
accordance with section 9(c) of the Reclamation Project Act of 1939, 43 
U.S.C. 485h(c), as amended and supplemented, including Municipalities, 
Rural Cooperatives, and political subdivisions including irrigation or 
other districts, municipalities, and other governmental organizations 
that have electric utility status by April 1, 2018; and, Federally 
recognized Native American tribes as defined in the Indian Self 
Determination Act of 1975, 25 U.S.C. 5304 as amended. ``Electric 
utility status'' means that the entity has responsibility to meet load 
growth, has a distribution system, and is ready, willing, and able to 
purchase Federal power from WAPA on a wholesale basis.
    8. Ready, Willing, and Able: Eligible applicants must be ready, 
willing, and able to receive and distribute or use energy from WAPA. 
Ready, willing, and able means the applicant has the facilities needed 
for the receipt of power or has made the necessary arrangements for 
transmission and/or distribution service, and its power supply 
contracts with third parties permit the delivery of WAPA's power.
    9. Rates and Payment: Each applicant who receives an allocation 
will pay its proportional share of the annual expenses of the Project 
based on its proportional share of the energy produced. WAPA, through a 
separate public process, will establish a rate methodology for the 
Project. Rather than pay a stated rate per kWh for energy, applicants 
who receive allocations will pay their proportional shares of the 
Project's total annual OM&R expenses in return for their proportional 
shares of total marketable energy production.

Availability of Information

    Documents developed or retained by WAPA during this public process 
will be available, by appointment, for inspection and copying at the 
CRSP Management Center, located at 150 East Social Hall Avenue, Suite 
300, Salt Lake City, Utah. Written comments received as part of the 
Olmsted Marketing Plan formal public process will be available for 
viewing on WAPA's Web site after the close of the comment period.

Procedural Requirements

Environmental Compliance

    WAPA Olmsted Power Marketing Plan will comply with the National 
Environmental Policy Act (NEPA) of 1969 (42 U.S.C. 4321-4347), the 
Council on Environmental Quality Regulations (40 CFR parts 1500-1508), 
and DOE NEPA Regulations (10 CFR 1021).

Review Under the Regulatory Flexibility Act

    The Regulatory Flexibility Act of 1980 (RFA; 5 U.S.C. 601, et seq.) 
requires a Federal agency to perform a regulatory flexibility analysis 
whenever the agency is required by law to publish a general notice of 
proposed rulemaking for any proposed rule, unless the agency can 
certify that the rule will not have a significant economic impact on a 
substantial number of small entities. In defining the term ``rule,'' 
the RFA specifies that a ``rule'' does not include ``a rule of 
particular applicability relating to rates [and] services . . . or to 
valuations, costs or accounting, or practices relating to such rates 
[and] services . . .'' (5 U.S.C. 601). WAPA has determined that this 
action relates to rates or services offered by WAPA and, therefore, is 
not a rule within the purview of the Regulatory Flexibility Act.

Determination Under Executive Order 12866

    WAPA has an exemption from centralized regulatory review under 
Executive Order 12866; accordingly, no clearance of this notice by the 
Office of Management and Budget is required.

    Dated: November 23, 2016.
Mark A. Gabriel,
Administrator.
[FR Doc. 2016-28976 Filed 12-1-16; 8:45 am]
 BILLING CODE 6450-01-P



                                                                                 Federal Register / Vol. 81, No. 232 / Friday, December 2, 2016 / Notices                                          87035

                                                       Description: Compliance filing: 2016–                  Dated: November 28, 2016.                           Social Hall Avenue, Suite 300, Salt Lake
                                                    11–28_Compliance filing to address 9/                   Nathaniel J. Davis, Sr.,                              City, Utah.
                                                    28/2016 Order on Entergy Settlement to                  Deputy Secretary.                                     FOR FURTHER INFORMATION CONTACT: Mr.
                                                    be effective 12/19/2013.                                [FR Doc. 2016–28938 Filed 12–1–16; 8:45 am]           Brent Osiek, CRSP Power Marketing
                                                       Filed Date: 11/28/16.                                BILLING CODE 6717–01–P                                Manager, osiek@wapa.gov, (801) 524–
                                                       Accession Number: 20161128–5194.                                                                           5495; or Mr. Steve Mullen, CRSP Public
                                                       Comments Due: 5 p.m. ET 12/19/16.                                                                          Utilities Specialist, smullen@wapa.gov,
                                                       Docket Numbers: ER16–1956–001.                       DEPARTMENT OF ENERGY                                  (801) 524–6383. Written requests for
                                                       Applicants: Western Antelope Dry                                                                           information should be mailed to CRSP
                                                    Ranch LLC.                                              Western Area Power Administration                     Management Center, Western Area
                                                       Description: Compliance filing:                                                                            Power Administration, 150 East Social
                                                    Western Antelope Dry Ranch LLC MBR                      Proposed 2018 Olmsted Power                           Hall Avenue, Suite 300, Salt Lake City,
                                                    Tariff to be effective 6/18/2016.                       Marketing Plan                                        UT 84111–1580, or faxed to (801) 524–
                                                       Filed Date: 11/28/16.                                AGENCY: Western Area Power                            5017.
                                                       Accession Number: 20161128–5102.                     Administration, Department of Energy                  SUPPLEMENTARY INFORMATION: The
                                                       Comments Due: 5 p.m. ET 12/19/16.                    (DOE).                                                Olmsted Powerplant, located in
                                                       Docket Numbers: ER17–418–000.                        ACTION: Notice of Proposed Olmsted                    northern Utah, was acquired in
                                                       Applicants: Seward Generation, LLC.                  Power Marketing Plan and                              condemnation proceedings by the
                                                       Description: Compliance filing:                      announcement of public information                    United States in 1990 in order to secure
                                                    Reactive Rate Schedule eTariff                          and comment forum.                                    water rights associated with the
                                                    Compliance Filing to be effective 11/29/                                                                      Olmsted Powerplant deemed essential
                                                    2016.                                                   SUMMARY: Western Area Power                           to the Central Utah Project (CUP). The
                                                       Filed Date: 11/28/16.                                Administration (WAPA), a Federal                      CUP is a participating project of the
                                                       Accession Number: 20161128–5207.                     power marketing agency of the                         CRSP. As part of the condemnation
                                                       Comments Due: 5 p.m. ET 12/19/16.                    Department of Energy, is seeking                      proceedings, PacifiCorp continued
                                                       Docket Numbers: ER17–419–000.                        comments about this Proposed Olmsted                  Olmsted operations until 2015, after
                                                       Applicants: American Electric Power                  Power Marketing Plan. WAPA has                        which time the operation of the facility
                                                    Service Corporate, PJM Interconnection,                 responsibility for the marketing of                   became the responsibility of the
                                                    L.L.C.                                                  energy from the Colorado River Storage                Department of the Interior, Bureau of
                                                       Description: § 205(d) Rate Filing:                   Project (CRSP), among other projects,                 Reclamation.
                                                    Transource PA and MD submit revisions                   and operates the transmission                           The existing Olmsted Powerplant is
                                                    to OATT to add Attachments H–29 and                     infrastructure associated with these                  over 100 years old and has greatly
                                                    H–30 to be effective 2/1/2017.                          Federal projects.                                     exceeded its operational life. A
                                                       Filed Date: 11/28/16.                                DATES: The public comment period on                   replacement facility is being constructed
                                                       Accession Number: 20161128–5221.                     the Proposed Olmsted Power Marketing                  for the generation of power and the
                                                       Comments Due: 5 p.m. ET 12/19/16.                    Plan begins December 2, 2016 and ends                 preservation of associated non-
                                                       Take notice that the Commission                      March 2, 2017. To be assured of                       consumptive water rights necessary for
                                                    received the following qualifying                       consideration, WAPA must receive all                  the CUP. On February 4, 2015, an
                                                    facility filings:                                       written comments by the end of the                    Implementation Agreement (Agreement)
                                                       Docket Numbers: QF17–318–000.                        comment period. WAPA reserves the                     for the Olmsted Powerplant
                                                       Applicants: Fresh Air Energy II, LLC.                right not to consider any comments                    Replacement Project (Project) was
                                                       Description: Form 556 of Fresh Air                   received after the prescribed date and                signed by Central Utah Water
                                                    Energy II, LLC [Shoshoni PV1].                          time.                                                 Conservancy District (District);
                                                       Filed Date: 11/28/16.                                   WAPA will hold a public information                Department of the Interior, Bureau of
                                                       Accession Number: 20161128–5065.                     forum about this proposed marketing                   Reclamation; and Department of Energy,
                                                       Comments Due: 5 p.m. ET 11/28/16.                    plan on Friday, January 13, 2017, from                WAPA (Participants). The Agreement
                                                       The filings are accessible in the                    10 a.m. to 12 p.m. MST at the Bureau                  sets forth the responsibilities of the
                                                    Commission’s eLibrary system by                         of Reclamation, 125 South State Street,               Participants and how the Project will be
                                                    clicking on the links or querying the                   Salt Lake City, Utah. The public                      funded. The District will construct,
                                                    docket number.                                          comment forum is scheduled for the                    operate, maintain, and replace the
                                                       Any person desiring to intervene or                  afternoon of the same day Friday,                     Olmsted facilities in connection with its
                                                    protest in any of the above proceedings                 January 13, 2017, from 1 p.m. to 3 p.m.               CUP operations, including power
                                                    must file in accordance with Rules 211                  MST at the Bureau of Reclamation, 125                 generation.
                                                    and 214 of the Commission’s                             South State Street, Salt Lake City, Utah.               The Olmsted facilities are a feature of
                                                    Regulations (18 CFR 385.211 and                         ADDRESSES: Submit written comments                    the CUP, which is a participating project
                                                    385.214) on or before 5:00 p.m. Eastern                 about this proposed marketing plan to:                of CRSP. WAPA markets the
                                                    time on the specified comment date.                     Ms. Lynn C. Jeka, CRSP Manager, CRSP                  hydropower generated from the CRSP
                                                    Protests may be considered, but                         Management Center, Western Area                       facilities as well as the participating
                                                    intervention is necessary to become a                   Power Administration, 150 East Social                 projects of CRSP. In accordance with
                                                    party to the proceeding.                                Hall Avenue, Suite 300, Salt Lake City,               Acts of Congress approved April 11,
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                       eFiling is encouraged. More detailed                 UT 84111–1580. Comments may also be                   1956 (70 Stat. 105); August 4, 1977 (91
                                                    information relating to filing                          emailed to jeka@wapa.gov or be faxed to               Stat. 565); October 30, 1992 (106 Stat.
                                                    requirements, interventions, protests,                  (801) 524–5017. All documentation                     46050); and Acts amendatory or
                                                    service, and qualifying facilities filings              developed or retained by WAPA for the                 supplementary to the foregoing Acts,
                                                    can be found at: http://www.ferc.gov/                   purpose of developing the proposed                    WAPA will be responsible for marketing
                                                    docs-filing/efiling/filing-req.pdf. For                 marketing plan will be available for                  the energy from the Olmsted
                                                    other information, call (866) 208–3676                  inspection and copying at the CRSP                    Powerplant. WAPA plans to begin
                                                    (toll free). For TTY, call (202) 502–8659.              Management Center office, 150 East                    marketing energy from the Olmsted


                                               VerDate Sep<11>2014   17:55 Dec 01, 2016   Jkt 241001   PO 00000   Frm 00019   Fmt 4703   Sfmt 4703   E:\FR\FM\02DEN1.SGM   02DEN1


                                                    87036                        Federal Register / Vol. 81, No. 232 / Friday, December 2, 2016 / Notices

                                                    Powerplant in the summer of 2018.                       of the annual energy output of the                    (40 CFR parts 1500–1508), and DOE
                                                    Only energy, without capacity, will be                  Powerplant.                                           NEPA Regulations (10 CFR 1021).
                                                    available for marketing (power                             7. Preference Entities: Preference will
                                                                                                                                                                  Review Under the Regulatory
                                                    production will be non-dispatchable                     be given to entities in accordance with
                                                                                                                                                                  Flexibility Act
                                                    and incidental to the delivery of water).               section 9(c) of the Reclamation Project
                                                    It is expected that annual energy                       Act of 1939, 43 U.S.C. 485h(c), as                       The Regulatory Flexibility Act of 1980
                                                    production from the replacement                         amended and supplemented, including                   (RFA; 5 U.S.C. 601, et seq.) requires a
                                                    Olmsted Powerplant will average                         Municipalities, Rural Cooperatives, and               Federal agency to perform a regulatory
                                                    approximately 27,000,000 kWh per year.                  political subdivisions including                      flexibility analysis whenever the agency
                                                                                                            irrigation or other districts,                        is required by law to publish a general
                                                    Proposed 2018 Olmsted Power                                                                                   notice of proposed rulemaking for any
                                                    Marketing Plan                                          municipalities, and other governmental
                                                                                                            organizations that have electric utility              proposed rule, unless the agency can
                                                       WAPA proposes to apply the                           status by April 1, 2018; and, Federally               certify that the rule will not have a
                                                    following criteria to applicants seeking                recognized Native American tribes as                  significant economic impact on a
                                                    an allocation of energy under the                       defined in the Indian Self Determination              substantial number of small entities. In
                                                    proposed 2018 Olmsted Power                             Act of 1975, 25 U.S.C. 5304 as amended.               defining the term ‘‘rule,’’ the RFA
                                                    Marketing Plan:                                         ‘‘Electric utility status’’ means that the            specifies that a ‘‘rule’’ does not include
                                                       1. Contract Term: Due to the lack of                 entity has responsibility to meet load                ‘‘a rule of particular applicability
                                                    actual generating data, the term of the                 growth, has a distribution system, and is             relating to rates [and] services . . . or to
                                                    contract will be limited. Service is                    ready, willing, and able to purchase                  valuations, costs or accounting, or
                                                    expected to begin on July 1, 2018, or as                Federal power from WAPA on a                          practices relating to such rates [and]
                                                    soon as the Project is declared                         wholesale basis.                                      services . . .’’ (5 U.S.C. 601). WAPA has
                                                    commercially operable; and the contract                    8. Ready, Willing, and Able: Eligible              determined that this action relates to
                                                    term will be effective through                          applicants must be ready, willing, and                rates or services offered by WAPA and,
                                                    September 30, 2024.                                     able to receive and distribute or use                 therefore, is not a rule within the
                                                       2. Marketing Area: Due to the                                                                              purview of the Regulatory Flexibility
                                                                                                            energy from WAPA. Ready, willing, and
                                                    relatively small size of the resource and                                                                     Act.
                                                                                                            able means the applicant has the
                                                    its operating characteristics, eligible
                                                                                                            facilities needed for the receipt of power            Determination Under Executive Order
                                                    applicants must be preference entities,
                                                                                                            or has made the necessary arrangements                12866
                                                    in accordance with section 9(c) of the
                                                                                                            for transmission and/or distribution
                                                    Reclamation Project Act of 1939 (43                                                                             WAPA has an exemption from
                                                                                                            service, and its power supply contracts
                                                    U.S.C. 485h(c)), located within the                                                                           centralized regulatory review under
                                                                                                            with third parties permit the delivery of
                                                    following counties in Utah: Davis,                                                                            Executive Order 12866; accordingly, no
                                                                                                            WAPA’s power.
                                                    Morgan, Salt Lake, Summit, Utah,                                                                              clearance of this notice by the Office of
                                                                                                               9. Rates and Payment: Each applicant
                                                    Weber, and Wasatch.                                                                                           Management and Budget is required.
                                                       3. Delivery Point: 12.47-kV bus at                   who receives an allocation will pay its
                                                    PacifiCorp’s Hale Substation or another                 proportional share of the annual                       Dated: November 23, 2016.
                                                    substation that may be identified that                  expenses of the Project based on its                  Mark A. Gabriel,
                                                    can be electrically interconnected to the               proportional share of the energy                      Administrator.
                                                    Project.                                                produced. WAPA, through a separate                    [FR Doc. 2016–28976 Filed 12–1–16; 8:45 am]
                                                       4. Transmission: Any associated                      public process, will establish a rate                 BILLING CODE 6450–01–P
                                                    transformation/transmission beyond                      methodology for the Project. Rather than
                                                    PacifiCorp’s 12.47-kV bus at the Hale                   pay a stated rate per kWh for energy,
                                                    Substation, or other identified                         applicants who receive allocations will
                                                                                                                                                                  ENVIRONMENTAL PROTECTION
                                                    substation if delivery is not made at the               pay their proportional shares of the
                                                                                                                                                                  AGENCY
                                                    Hale Substation, is the sole                            Project’s total annual OM&R expenses in
                                                                                                            return for their proportional shares of               [ER–FRL–9030–5]
                                                    responsibility of the applicant.
                                                    Applicants must have the necessary                      total marketable energy production.
                                                                                                                                                                  Environmental Impact Statements;
                                                    arrangements for transmission and/or                    Availability of Information                           Notice of Availability
                                                    distribution service in place by April 1,
                                                                                                              Documents developed or retained by                    Responsible Agency: Office of Federal
                                                    2018.
                                                       5. Eligible Applicants: WAPA will                    WAPA during this public process will                  Activities, General Information (202)
                                                    provide allocations only to preference                  be available, by appointment, for                     564–7146 or http://www.epa.gov/nepa.
                                                    entities in the marketing area. WAPA,                   inspection and copying at the CRSP
                                                                                                                                                                  Weekly receipt of Environmental Impact
                                                    through the public process, will                        Management Center, located at 150 East
                                                                                                                                                                    Statements
                                                    determine the amount of energy, if any,                 Social Hall Avenue, Suite 300, Salt Lake              Filed 11/21/2016 Through 11/25/2016
                                                    to allocate in accordance with the                      City, Utah. Written comments received                 Pursuant to 40 CFR 1506.9.
                                                    marketing criteria and administrative                   as part of the Olmsted Marketing Plan
                                                                                                            formal public process will be available               Notice
                                                    discretion under Reclamation Law.
                                                    Priority will be given to the District as               for viewing on WAPA’s Web site after                    Section 309(a) of the Clean Air Act
                                                    the operator of the Olmsted Powerplant.                 the close of the comment period.                      requires that EPA make public its
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                       6. Resource Pool: WAPA will take                     Procedural Requirements                               comments on EISs issued by other
                                                    into consideration all existing Federal                                                                       Federal agencies. EPA’s comment letters
                                                    hydropower allocations an applicant is                  Environmental Compliance                              on EISs are available at: http://
                                                    currently receiving when determining                      WAPA Olmsted Power Marketing                        www.epa.gov/compliance/nepa/
                                                    each allocation. Allocations of Olmsted                 Plan will comply with the National                    eisdata.html.
                                                    energy will be determined solely by                     Environmental Policy Act (NEPA) of                    EIS No. 20160283, Final, NPS, FL,
                                                    WAPA. Applicants who receive an                         1969 (42 U.S.C. 4321–4347), the Council                 ADOPTION—Central Everglades
                                                    allocation will be allocated a percentage               on Environmental Quality Regulations                    Planning Program, Review Period


                                               VerDate Sep<11>2014   17:55 Dec 01, 2016   Jkt 241001   PO 00000   Frm 00020   Fmt 4703   Sfmt 4703   E:\FR\FM\02DEN1.SGM   02DEN1



Document Created: 2018-02-14 09:01:51
Document Modified: 2018-02-14 09:01:51
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of Proposed Olmsted Power Marketing Plan and announcement of public information and comment forum.
DatesThe public comment period on the Proposed Olmsted Power Marketing Plan begins December 2, 2016 and ends March 2, 2017. To be assured of consideration, WAPA must receive all written comments by the end of the comment period. WAPA reserves the right not to consider any comments received after the prescribed date and time.
ContactMr. Brent Osiek, CRSP Power Marketing Manager, [email protected], (801) 524-5495; or Mr. Steve Mullen, CRSP Public Utilities Specialist, [email protected], (801) 524-6383. Written requests for information should be mailed to CRSP Management Center, Western Area Power Administration, 150 East Social Hall Avenue, Suite 300, Salt Lake City, UT 84111-1580, or faxed to (801) 524-5017.
FR Citation81 FR 87035 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR