81_FR_95372 81 FR 95124 - Portland Natural Gas Transmission System; Notice of Application

81 FR 95124 - Portland Natural Gas Transmission System; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 248 (December 27, 2016)

Page Range95124-95124
FR Document2016-31095

Federal Register, Volume 81 Issue 248 (Tuesday, December 27, 2016)
[Federal Register Volume 81, Number 248 (Tuesday, December 27, 2016)]
[Notices]
[Page 95124]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-31095]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-24-000]


Portland Natural Gas Transmission System; Notice of Application

    Take notice that on December 12, 2016, Portland Natural Gas 
Transmission System (PNGTS), 700 Louisiana Street, Suite 700, Houston, 
TX 77002-2700, filed an application pursuant to section 7(c) of the 
Natural Gas Act (NGA) and the Federal Energy Regulatory Commission's 
(Commission) regulations seeking authorization to increase the 
certificated capacity on PNGTS's wholly-owned north system from 
Pittsburg, New Hampshire, to Westbrook, Maine, by 42,000 Mcf/d, all as 
more fully described in the application which is on file with the 
Commission and open to public inspection. The filing may also be viewed 
on the web at http://www.ferc.gov using the ``eLibrary'' link. Enter 
the docket number excluding the last three digits in the docket number 
field to access the document. For assistance, contact FERC at 
[email protected] or call toll-free, (866) 208-3676 or TTY, 
(202) 502-8659.
    Additionally, pursuant to and in accordance with Section 3 of the 
NGA, 15 U.S.C. Section 717b, Part 153 of the Commission's regulations, 
18 CFR part 153, Executive Order 10485, as amended by Executive Order 
12038, and Secretary of Energy Delegation Order No. 0204-112, PNGTS 
requested authorization to increase its authorized import and export 
capacity from 178,000 Mcf/d to 210,000 Mcf/d and to amend the 
Presidential Permit issued to PNGTS on September 24, 1997, as amended 
on November 18, 2003, in Docket No. CP96-248, et, al. to reflect such 
an increase.\1\
---------------------------------------------------------------------------

    \1\ See Portland Natural Gas Transmission System, 80 FERC ] 
61,346 (1997); and 105 FERC ] 61,235 (2003).
---------------------------------------------------------------------------

    PNGTS states that the authorizations requested will satisfy the 
requirements of the Continent to Coast Expansion Project, which will 
expand gas service delivery options for the New England market. PNGTS 
proposes no construction or modifications to its existing system or 
border crossing facilities in connection with this request and as such, 
there are no costs associated with the project.
    Any questions regarding this application should be directed to 
Robert Jackson, Manager, Certificates and Regulatory Administration, 
Portland Natural Gas Transmission System, 700 Louisiana Street, Suite 
700, Houston, Texas, or call (832) 320-5487, or by email 
[email protected].
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the final environmental impact statement (FEIS) or EA for this 
proposal. The filing of the EA in the Commission's public record for 
this proceeding or the issuance of a Notice of Schedule for 
Environmental Review will serve to notify federal and state agencies of 
the timing for the completion of all necessary reviews, and the 
subsequent need to complete all federal authorizations within 90 days 
of the date of issuance of the Commission staff's FEIS or EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit 7 copies of filings made in the proceeding with the Commission 
and must mail a copy to the applicant and to every other party. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 5 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on January 10, 2017.

    Dated: December 20, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2016-31095 Filed 12-23-16; 8:45 am]
BILLING CODE 6717-01-P



                                                    95124                      Federal Register / Vol. 81, No. 248 / Tuesday, December 27, 2016 / Notices

                                                    the application for the Credit                          of the Continent to Coast Expansion                      However, a person does not have to
                                                    Enhancement for Charter School                          Project, which will expand gas service                intervene in order to have comments
                                                    Facilities Program.                                     delivery options for the New England                  considered. The second way to
                                                      Dated: December 21, 2016.                             market. PNGTS proposes no                             participate is by filing with the
                                                    Stephanie Valentine,                                    construction or modifications to its                  Secretary of the Commission, as soon as
                                                    Acting Director, Information Collection
                                                                                                            existing system or border crossing                    possible, an original and two copies of
                                                    Clearance Division, Office of the Chief Privacy         facilities in connection with this request            comments in support of or in opposition
                                                    Officer, Office of Management.                          and as such, there are no costs                       to this project. The Commission will
                                                    [FR Doc. 2016–31152 Filed 12–23–16; 8:45 am]            associated with the project.                          consider these comments in
                                                    BILLING CODE 4000–01–P
                                                                                                               Any questions regarding this                       determining the appropriate action to be
                                                                                                            application should be directed to Robert              taken, but the filing of a comment alone
                                                                                                            Jackson, Manager, Certificates and                    will not serve to make the filer a party
                                                    DEPARTMENT OF ENERGY                                    Regulatory Administration, Portland                   to the proceeding. The Commission’s
                                                                                                            Natural Gas Transmission System, 700                  rules require that persons filing
                                                    Federal Energy Regulatory                               Louisiana Street, Suite 700, Houston,
                                                                                                                                                                  comments in opposition to the project
                                                    Commission                                              Texas, or call (832) 320–5487, or by
                                                                                                                                                                  provide copies of their protests only to
                                                                                                            email robert_jackson@transcanada.com.
                                                    [Docket No. CP17–24–000]                                                                                      the party or parties directly involved in
                                                                                                               Pursuant to section 157.9 of the
                                                                                                                                                                  the protest.
                                                    Portland Natural Gas Transmission                       Commission’s rules, 18 CFR 157.9,
                                                    System; Notice of Application                           within 90 days of this Notice the                        Persons who wish to comment only
                                                                                                            Commission staff will either: Complete                on the environmental review of this
                                                       Take notice that on December 12,                     its environmental assessment (EA) and                 project should submit an original and
                                                    2016, Portland Natural Gas                              place it into the Commission’s public                 two copies of their comments to the
                                                    Transmission System (PNGTS), 700                        record (eLibrary) for this proceeding; or             Secretary of the Commission.
                                                    Louisiana Street, Suite 700, Houston,                   issue a Notice of Schedule for                        Environmental commentors will be
                                                    TX 77002–2700, filed an application                     Environmental Review. If a Notice of                  placed on the Commission’s
                                                    pursuant to section 7(c) of the Natural                 Schedule for Environmental Review is                  environmental mailing list, will receive
                                                    Gas Act (NGA) and the Federal Energy                    issued, it will indicate, among other                 copies of the environmental documents,
                                                    Regulatory Commission’s (Commission)                    milestones, the anticipated date for the              and will be notified of meetings
                                                    regulations seeking authorization to                    Commission staff’s issuance of the final              associated with the Commission’s
                                                    increase the certificated capacity on                   environmental impact statement (FEIS)
                                                    PNGTS’s wholly-owned north system                                                                             environmental review process.
                                                                                                            or EA for this proposal. The filing of the            Environmental commentors will not be
                                                    from Pittsburg, New Hampshire, to                       EA in the Commission’s public record
                                                    Westbrook, Maine, by 42,000 Mcf/d, all                                                                        required to serve copies of filed
                                                                                                            for this proceeding or the issuance of a              documents on all other parties.
                                                    as more fully described in the                          Notice of Schedule for Environmental
                                                    application which is on file with the                                                                         However, the non-party commentors
                                                                                                            Review will serve to notify federal and
                                                    Commission and open to public                                                                                 will not receive copies of all documents
                                                                                                            state agencies of the timing for the
                                                    inspection. The filing may also be                      completion of all necessary reviews, and              filed by other parties or issued by the
                                                    viewed on the web at http://                            the subsequent need to complete all                   Commission (except for the mailing of
                                                    www.ferc.gov using the ‘‘eLibrary’’ link.               federal authorizations within 90 days of              environmental documents issued by the
                                                    Enter the docket number excluding the                   the date of issuance of the Commission                Commission) and will not have the right
                                                    last three digits in the docket number                  staff’s FEIS or EA.                                   to seek court review of the
                                                    field to access the document. For                          There are two ways to become                       Commission’s final order.
                                                    assistance, contact FERC at                             involved in the Commission’s review of                   The Commission strongly encourages
                                                    FERCOnlineSupport@ferc.gov or call                      this project. First, any person wishing to            electronic filings of comments, protests
                                                    toll-free, (866) 208–3676 or TTY, (202)                 obtain legal status by becoming a party               and interventions in lieu of paper using
                                                    502–8659.                                               to the proceedings for this project
                                                       Additionally, pursuant to and in                                                                           the ‘‘eFiling’’ link at http://
                                                                                                            should, on or before the comment date                 www.ferc.gov. Persons unable to file
                                                    accordance with Section 3 of the NGA,
                                                                                                            stated below file with the Federal                    electronically should submit an original
                                                    15 U.S.C. Section 717b, Part 153 of the
                                                                                                            Energy Regulatory Commission, 888                     and 5 copies of the protest or
                                                    Commission’s regulations, 18 CFR part
                                                                                                            First Street NE., Washington, DC 20426,               intervention to the Federal Energy
                                                    153, Executive Order 10485, as
                                                                                                            a motion to intervene in accordance                   regulatory Commission, 888 First Street
                                                    amended by Executive Order 12038, and
                                                                                                            with the requirements of the                          NE., Washington, DC 20426.
                                                    Secretary of Energy Delegation Order
                                                                                                            Commission’s Rules of Practice and
                                                    No. 0204–112, PNGTS requested                                                                                    Comment Date: 5:00 p.m. Eastern
                                                                                                            Procedure (18 CFR 385.214 or 385.211)
                                                    authorization to increase its authorized                                                                      Time on January 10, 2017.
                                                                                                            and the Regulations under the NGA (18
                                                    import and export capacity from
                                                                                                            CFR 157.10). A person obtaining party                   Dated: December 20, 2016.
                                                    178,000 Mcf/d to 210,000 Mcf/d and to
                                                                                                            status will be placed on the service list             Kimberly D. Bose,
                                                    amend the Presidential Permit issued to
                                                                                                            maintained by the Secretary of the
                                                    PNGTS on September 24, 1997, as                                                                               Secretary.
                                                                                                            Commission and will receive copies of
asabaliauskas on DSK3SPTVN1PROD with NOTICES




                                                    amended on November 18, 2003, in                                                                              [FR Doc. 2016–31095 Filed 12–23–16; 8:45 am]
                                                                                                            all documents filed by the applicant and
                                                    Docket No. CP96–248, et, al. to reflect                                                                       BILLING CODE 6717–01–P
                                                                                                            by all other parties. A party must submit
                                                    such an increase.1
                                                                                                            7 copies of filings made in the
                                                       PNGTS states that the authorizations
                                                                                                            proceeding with the Commission and
                                                    requested will satisfy the requirements
                                                                                                            must mail a copy to the applicant and
                                                      1 See Portland Natural Gas Transmission System,       to every other party. Only parties to the
                                                    80 FERC ¶ 61,346 (1997); and 105 FERC ¶ 61,235          proceeding can ask for court review of
                                                    (2003).                                                 Commission orders in the proceeding.


                                               VerDate Sep<11>2014   20:45 Dec 23, 2016   Jkt 241001   PO 00000   Frm 00027   Fmt 4703   Sfmt 9990   E:\FR\FM\27DEN1.SGM   27DEN1



Document Created: 2018-02-14 09:13:46
Document Modified: 2018-02-14 09:13:46
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on January 10, 2017.
FR Citation81 FR 95124 