DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 81, Issue 38 (February 26, 2016)

Page Range9842-9842
FR Document2016-04146

Federal Register, Volume 81 Issue 38 (Friday, February 26, 2016)
[Federal Register Volume 81, Number 38 (Friday, February 26, 2016)]
[Notices]
[Page 9842]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-04146]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP15-552-000]


Northern Natural Gas Company; Notice of Schedule for 
Environmental Review of the Gaines County Crossover Compressor Station 
Project

    On September 9, 2015, Northern Natural Gas Company (Northern) filed 
an application in Docket No. CP15-552-000 requesting a Certificate of 
Public Convenience and Necessity pursuant to Section 7(c) of the 
Natural Gas Act to construct and operate a new compressor station in 
Gaines County, Texas. The proposed project is known as the Gaines 
County Crossover Compressor Station Project (Project), and would 
deliver an additional 210 million standard cubic feet of natural gas 
per day to supply natural gas for electrical power plants.
    On September 22, 2015, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA--May 9, 2016
90-day Federal Authorization Decision Deadline--August 7, 2016

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Project would include installation of two compressor units with 
a combined horsepower of 18,089. The suction side of the compressor 
station would be connected to Northern's existing 30-inch-diameter 
Spraberry to Plains Pipeline. The station would discharge to Northern's 
existing 30-inch-diameter Kermit to Beaver Pipeline. The proposed 
Project would also include the installation of two compressor 
buildings, a control building, an auxiliary building, associated above-
grade and below-grade piping, and valves and instrumentation.

Background

    On October 22, 2015, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Gaines County 
Crossover Compressor Station and Request for Comments on Environmental 
Issues (NOI). The NOI was sent to affected landowners; federal, state, 
and local government agencies; elected officials; environmental and 
public interest groups; Native American tribes; other interested 
parties; and local libraries and newspapers. In response to the NOI, 
the Commission received one comment from the Bureau of Indian Affairs 
recommending consultation with four different tribes with historic 
traditions in the area. No issues of environmental concern were raised 
by the commentor.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the ``eLibrary'' link, select 
``General Search'' from the eLibrary menu, enter the selected date 
range and ``Docket Number'' excluding the last three digits (i.e., 
CP15-552), and follow the instructions. For assistance with access to 
eLibrary, the helpline can be reached at (866) 208-3676, TTY (202) 502-
8659, or at [email protected]. The eLibrary link on the FERC 
Web site also provides access to the texts of formal documents issued 
by the Commission, such as orders, notices, and rule makings.

    Dated: February 19, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-04146 Filed 2-25-16; 8:45 am]
BILLING CODE 6717-01-P



                                                  9842                          Federal Register / Vol. 81, No. 38 / Friday, February 26, 2016 / Notices

                                                    Filed Date: 2/19/16.                                  DEPARTMENT OF ENERGY                                  Background
                                                    Accession Number: 20160219–5011.
                                                    Comments Due: 5 p.m. ET 3/2/16.                       Federal Energy Regulatory                                On October 22, 2015, the Commission
                                                                                                          Commission                                            issued a Notice of Intent to Prepare an
                                                    Docket Numbers: RP16–618–000.                                                                               Environmental Assessment for the
                                                    Applicants: Algonquin Gas                                                                                   Proposed Gaines County Crossover
                                                  Transmission, LLC.                                      [Docket No. CP15–552–000]
                                                                                                                                                                Compressor Station and Request for
                                                    Description: § 4(d) Rate Filing:
                                                                                                          Northern Natural Gas Company; Notice                  Comments on Environmental Issues
                                                  Bidding Requirements Waiver for State-
                                                                                                          of Schedule for Environmental Review                  (NOI). The NOI was sent to affected
                                                  Regulated Electric Reliability Programs
                                                                                                          of the Gaines County Crossover                        landowners; federal, state, and local
                                                  to be effective 4/1/2016.
                                                                                                          Compressor Station Project                            government agencies; elected officials;
                                                    Filed Date: 2/19/16.
                                                    Accession Number: 20160219–5050.                                                                            environmental and public interest
                                                                                                             On September 9, 2015, Northern
                                                    Comments Due: 5 p.m. ET 3/2/16.                                                                             groups; Native American tribes; other
                                                                                                          Natural Gas Company (Northern) filed
                                                                                                                                                                interested parties; and local libraries
                                                    Docket Numbers: RP16–619–000.                         an application in Docket No. CP15–552–
                                                                                                                                                                and newspapers. In response to the NOI,
                                                    Applicants: National Fuel Gas Supply                  000 requesting a Certificate of Public
                                                                                                          Convenience and Necessity pursuant to                 the Commission received one comment
                                                  Corporation.                                                                                                  from the Bureau of Indian Affairs
                                                    Description: § 4(d) Rate Filing: Fuel                 Section 7(c) of the Natural Gas Act to
                                                                                                          construct and operate a new compressor                recommending consultation with four
                                                  Tracker (04/01/16) to be effective 4/1/
                                                                                                          station in Gaines County, Texas. The                  different tribes with historic traditions
                                                  2016.
                                                                                                          proposed project is known as the Gaines               in the area. No issues of environmental
                                                    Filed Date: 2/19/16.
                                                                                                          County Crossover Compressor Station                   concern were raised by the commentor.
                                                    Accession Number: 20160219–5161.
                                                    Comments Due: 5 p.m. ET 3/2/16.                       Project (Project), and would deliver an               Additional Information
                                                                                                          additional 210 million standard cubic
                                                    Any person desiring to intervene or                   feet of natural gas per day to supply                    In order to receive notification of the
                                                  protest in any of the above proceedings                 natural gas for electrical power plants.              issuance of the EA and to keep track of
                                                  must file in accordance with Rules 211
                                                                                                             On September 22, 2015, the Federal                 all formal issuances and submittals in
                                                  and 214 of the Commission’s
                                                                                                          Energy Regulatory Commission                          specific dockets, the Commission offers
                                                  Regulations (18 CFR 385.211 and
                                                                                                          (Commission or FERC) issued its Notice                a free service called eSubscription. This
                                                  § 385.214) on or before 5:00 p.m. Eastern
                                                                                                          of Application for the Project. Among                 can reduce the amount of time you
                                                  time on the specified date(s). Protests
                                                                                                          other things, that notice alerted agencies            spend researching proceedings by
                                                  may be considered, but intervention is
                                                                                                          issuing federal authorizations of the                 automatically providing you with
                                                  necessary to become a party to the
                                                                                                          requirement to complete all necessary                 notification of these filings, document
                                                  proceeding.
                                                                                                          reviews and to reach a final decision on              summaries, and direct links to the
                                                  Filings in Existing Proceedings                         a request for a federal authorization                 documents. Go to www.ferc.gov/docs-
                                                     Docket Numbers: RP16–234–000.                        within 90 days of the date of issuance                filing/esubscription.asp.
                                                                                                          of the Commission staff’s Environmental
                                                     Applicants: El Paso Natural Gas                                                                               Additional information about the
                                                                                                          Assessment (EA) for the Project. This
                                                  Company, L.L.C.                                                                                               Project is available from the
                                                                                                          instant notice identifies the FERC staff’s
                                                     Description: Report Filing: Refund                                                                         Commission’s Office of External Affairs
                                                                                                          planned schedule for the completion of
                                                  Report in Docket Nos. RP16–234 and                                                                            at (866) 208–FERC or on the FERC Web
                                                                                                          the EA for the Project.
                                                  RP10–1398.                                                                                                    site (www.ferc.gov). Using the
                                                     Filed Date: 2/18/16.                                 Schedule for Environmental Review                     ‘‘eLibrary’’ link, select ‘‘General Search’’
                                                     Accession Number: 20160218–5140.                     Issuance of EA—May 9, 2016                            from the eLibrary menu, enter the
                                                     Comments Due: 5 p.m. ET 3/1/16.                                                                            selected date range and ‘‘Docket
                                                                                                          90-day Federal Authorization Decision
                                                     Any person desiring to protest in any                                                                      Number’’ excluding the last three digits
                                                                                                             Deadline—August 7, 2016
                                                  of the above proceedings must file in                                                                         (i.e., CP15–552), and follow the
                                                  accordance with Rule 211 of the                            If a schedule change becomes
                                                                                                          necessary, additional notice will be                  instructions. For assistance with access
                                                  Commission’s Regulations (18 CFR
                                                                                                          provided so that the relevant agencies                to eLibrary, the helpline can be reached
                                                  385.211) on or before 5:00 p.m. Eastern
                                                  time on the specified comment date.                     are kept informed of the Project’s                    at (866) 208–3676, TTY (202) 502–8659,
                                                     The filings are accessible in the                    progress.                                             or at FERCOnlineSupport@ferc.gov. The
                                                  Commission’s eLibrary system by                                                                               eLibrary link on the FERC Web site also
                                                                                                          Project Description                                   provides access to the texts of formal
                                                  clicking on the links or querying the
                                                  docket number.                                            The Project would include                           documents issued by the Commission,
                                                     eFiling is encouraged. More detailed                 installation of two compressor units                  such as orders, notices, and rule
                                                  information relating to filing                          with a combined horsepower of 18,089.                 makings.
                                                  requirements, interventions, protests,                  The suction side of the compressor                      Dated: February 19, 2016.
                                                  service, and qualifying facilities filings              station would be connected to
                                                                                                                                                                Nathaniel J. Davis, Sr.,
                                                  can be found at: http://www.ferc.gov/                   Northern’s existing 30-inch-diameter
                                                                                                          Spraberry to Plains Pipeline. The station             Deputy Secretary.
                                                  docs-filing/efiling/filing-req.pdf. For
mstockstill on DSK4VPTVN1PROD with NOTICES




                                                  other information, call (866) 208–3676                  would discharge to Northern’s existing                [FR Doc. 2016–04146 Filed 2–25–16; 8:45 am]

                                                  (toll free). For TTY, call (202) 502–8659.              30-inch-diameter Kermit to Beaver                     BILLING CODE 6717–01–P
                                                                                                          Pipeline. The proposed Project would
                                                    Dated: February 22, 2016.                             also include the installation of two
                                                  Nathaniel J. Davis, Sr.,                                compressor buildings, a control
                                                  Deputy Secretary.                                       building, an auxiliary building,
                                                  [FR Doc. 2016–04157 Filed 2–25–16; 8:45 am]             associated above-grade and below-grade
                                                  BILLING CODE 6717–01–P                                  piping, and valves and instrumentation.


                                             VerDate Sep<11>2014   20:41 Feb 25, 2016   Jkt 238001   PO 00000   Frm 00039   Fmt 4703   Sfmt 9990   E:\FR\FM\26FEN1.SGM   26FEN1



Document Created: 2018-02-02 14:37:25
Document Modified: 2018-02-02 14:37:25
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation81 FR 9842 