82_FR_1333 82 FR 1330 - WBI Energy Transmission, Inc.; Supplemental Notice of Intent To Prepare an Environmental Assessment for the Planned Valley Expansion Project and Request for Comments on Environmental Issues

82 FR 1330 - WBI Energy Transmission, Inc.; Supplemental Notice of Intent To Prepare an Environmental Assessment for the Planned Valley Expansion Project and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 3 (January 5, 2017)

Page Range1330-1332
FR Document2016-32025

Federal Register, Volume 82 Issue 3 (Thursday, January 5, 2017)
[Federal Register Volume 82, Number 3 (Thursday, January 5, 2017)]
[Notices]
[Pages 1330-1332]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2016-32025]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. PF16-10-000]


WBI Energy Transmission, Inc.; Supplemental Notice of Intent To 
Prepare an Environmental Assessment for the Planned Valley Expansion 
Project and Request for Comments on Environmental Issues

    On November 23, 2016, the Commission issued a ``Notice of Intent to 
Prepare an Environmental Assessment for the Planned Valley Expansion 
Project and Request for Comments on Environmental Issues'' (NOI) and an 
Errata Notice for the NOI on November 28, 2016. It has come to our 
attention that the environmental mailing list was not provided copies 
of the NOI or the Errata Notice; therefore, we are issuing this 
Supplemental NOI to extend the scoping period and provide additional 
time for interested parties to file comments on environmental issues.
    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Valley Expansion Project 
involving construction and operation of facilities by WBI Energy 
Transmission, Inc. (WBI Energy) in Clay County, Minnesota and Cass, 
Burleigh, Stutsman, and Barnes Counties, North Dakota. The Commission 
will use this EA in its decision-making process to determine whether 
the project is in the public convenience and necessity.
    You can make a difference by providing us with your specific 
comments or concerns about the project. Your comments should focus on 
the potential environmental effects, reasonable alternatives, and 
measures to avoid or lessen environmental impacts. Your input will help 
the Commission staff determine what issues they need to evaluate in the 
EA. The NOI identified

[[Page 1331]]

December 23, 2016 as the close of the scoping period. Please note that 
the scoping period is now extended and will close on January 27, 2017.
    If you sent comments on this project to the Commission before the 
opening of this docket on October 17, 2016, you will need to file those 
comments in Docket No. PF16-10-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this planned 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the planned facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    A fact sheet prepared by the FERC entitled ``An Interstate Natural 
Gas Facility On My Land? What Do I Need To Know?'' is available for 
viewing on the FERC Web site (www.ferc.gov). This fact sheet addresses 
a number of typically asked questions, including the use of eminent 
domain and how to participate in the Commission's proceedings.

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(PF16-10-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Planned Project

    WBI Energy plans to construct 38 miles of new 16-inch-diameter 
pipeline between Mapleton, North Dakota and Felton, Minnesota. WBI 
Energy also plans to construct a new 2,600-horsepower electric-driven 
compressor station in Cass County, North Dakota, farm taps, valve 
settings, and ancillary facilities. Additionally, WBI Energy plans to 
replace two existing town border station delivery points and construct 
one regulator station in Burleigh, Stutsman, and Barnes Counties, North 
Dakota in order to increase in the maximum allowable operating pressure 
of a portion of its Line Section 24. According to WBI Energy, the 
project would provide an additional 40 million cubic feet per day of 
firm transportation on its system.
    The general location of the project facilities is shown in appendix 
1.\1\
---------------------------------------------------------------------------

    \1\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of the appendices were sent to all 
those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the project would affect a total of about 530 acres 
of land, including the pipeline construction right-of-way, additional 
temporary workspace, staging areas, temporary and permanent access 
roads, and aboveground facilities. The total acreage required for 
operation of the project is approximately 235 acres, including the new 
permanent pipeline easement, permanent access roads, and permanent 
aboveground facilities' footprint.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\2\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \2\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA, we will discuss impacts that could occur as a result of 
the construction and operation of the planned project under these 
general headings:
     Geology and soils;
     water resources, fisheries, and wetlands;
     vegetation and wildlife;
     endangered and threatened species;
     cultural resources;
     socioeconomics;
     land use;
     air quality and noise;
     public safety; and
     cumulative impacts.
    We will also evaluate possible alternatives to the planned project 
or portions of the project, and make recommendations on how to lessen 
or avoid impacts on the various resource areas.
    Although no formal application has been filed, we have already 
initiated our NEPA review under the Commission's pre-filing process. 
The purpose of the pre-filing process is to encourage early involvement 
of interested stakeholders and to identify and resolve issues before 
the FERC receives an application. As part of our pre-filing review, we 
have begun to contact some federal and state agencies to discuss their 
involvement in the scoping process and the preparation of the EA.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before we make our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the

[[Page 1332]]

environmental issues related to this project to formally cooperate with 
us in the preparation of the EA.\3\ Agencies that would like to request 
cooperating agency status should follow the instructions for filing 
comments provided under the Public Participation section of this 
notice.
---------------------------------------------------------------------------

    \3\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with the applicable State Historic Preservation Offices (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\4\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPOs as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \4\ The Advisory Council on Historic Preservation regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Currently Identified Environmental Issues

    We have already identified several issues that we think deserve 
attention based on a preliminary review of the planned facilities and 
the environmental information provided by WBI Energy. This preliminary 
list of issues may change based on your comments and our analysis, but 
currently includes:
     Drain tiles;
     deep topsoil and poor quality subsoils (salinity/sodium or 
lime);
     prime farm land;
     federally listed species, including the whooping crane, 
gray wolf, Dakota skipper, northern long-eared bat, western prairie 
fringed orchid, and the powershiek skipperling;
     cultural resources; and
     crossing methods of the Rush River, Red River of the 
North, and the Buffalo River.

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; Native 
American Tribes; other interested parties; and local libraries and 
newspapers. This list also includes all affected landowners (as defined 
in the Commission's regulations) who are potential right-of-way 
grantors, whose property may be used temporarily for project purposes, 
or who own homes within certain distances of aboveground facilities, 
and anyone who submits comments on the project. We will update the 
environmental mailing list as the analysis proceeds to ensure that we 
send the information related to this environmental review to all 
individuals, organizations, and government entities interested in and/
or potentially affected by the planned project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    Once WBI Energy files its application with the Commission, you may 
want to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Motions to intervene are more fully described at 
http://www.ferc.gov/resources/guides/how-to/intervene.asp. Instructions 
for becoming an intervenor are in the ``Document-less Intervention 
Guide'' under the ``e-filing'' link on the Commission's Web site. 
Please note that the Commission will not accept requests for intervenor 
status at this time. You must wait until the Commission receives a 
formal application for the project.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., PF16-
10). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription, which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: December 28, 2016.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2016-32025 Filed 1-4-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                  1330                             Federal Register / Vol. 82, No. 3 / Thursday, January 5, 2017 / Notices

                                                                     Docket No.                             File date                                         Presenter or requester

                                                       2. ER17–217–000 ..............................       12–12–2016      U.S. House Representative Frank Pallone, Jr.
                                                       3. CP14–96–000 ................................      12–13–2016      U.S. Senator Elizabeth Warren.
                                                       4. CP16–10–000 ................................      12–13–2016      U.S. Senator Bill Nelson.
                                                       5. ER17–217–000 ..............................       12–14–2016      U.S. House Representative Frank Pallone, Jr.
                                                       6. CP16–454–000, CP16–455–000 ...                    12–19–2016      FERC Staff.2
                                                       7. CP15–138–000 ..............................       12–20–2016      State of Pennsylvania House Representative Bryan          Cutler.
                                                       8. CP15–138–000 ..............................       12–20–2016      State of Pennsylvania House Representative Bryan          Cutler.
                                                       9. CP15–138–000 ..............................       12–20–2016      State of Pennsylvania House Representative Bryan          Cutler.
                                                       10. CP15–138–000 ............................        12–20–2016      State of Pennsylvania House Representative Bryan          Cutler.
                                                       11. CP16–10–000 ..............................       12–22–2016      FERC Staff.3
                                                     1 Threeletters have been sent to FERC Commissioners and staff under this docket number.
                                                     2 Conference  call notes from December 6, 2016 call with Rio Grande LNG, LLC and Rio Bravo Pipeline, LLC.
                                                     3 Memo forwarding letter dated December 21, 2016 from Advisory Council on Historic Preservation.




                                                    Dated: December 28, 2016.                                 intervention or motion to intervene, as                DEPARTMENT OF ENERGY
                                                  Nathaniel J. Davis, Sr.,                                    appropriate. The Respondent’s answer
                                                  Deputy Secretary.                                           and all interventions, or protests must                Federal Energy Regulatory
                                                  [FR Doc. 2016–32026 Filed 1–4–17; 8:45 am]                  be filed on or before the comment date.                Commission
                                                  BILLING CODE 6717–01–P                                      The Respondent’s answer, motions to                    [Docket No. PF16–10–000]
                                                                                                              intervene, and protests must be served
                                                                                                              on the Complainants.                                   WBI Energy Transmission, Inc.;
                                                  DEPARTMENT OF ENERGY                                                                                               Supplemental Notice of Intent To
                                                                                                                 The Commission encourages
                                                                                                                                                                     Prepare an Environmental Assessment
                                                  Federal Energy Regulatory                                   electronic submission of protests and
                                                                                                                                                                     for the Planned Valley Expansion
                                                  Commission                                                  interventions in lieu of paper using the               Project and Request for Comments on
                                                                                                              ‘‘eFiling’’ link at http://www.ferc.gov.               Environmental Issues
                                                  [Docket No. EL17–29–000]
                                                                                                              Persons unable to file electronically
                                                                                                              should submit an original and 5 copies                    On November 23, 2016, the
                                                  American Municipal Power, Inc. v.
                                                                                                              of the protest or intervention to the                  Commission issued a ‘‘Notice of Intent
                                                  Midcontinent Independent System
                                                                                                              Federal Energy Regulatory Commission,                  to Prepare an Environmental
                                                  Operator, Inc.; Notice of Complaint
                                                                                                              888 First Street, NE., Washington, DC                  Assessment for the Planned Valley
                                                     Take notice that on December 19,                         20426.                                                 Expansion Project and Request for
                                                  2016, pursuant to Rule 206 of the                                                                                  Comments on Environmental Issues’’
                                                  Federal Energy Regulatory                                      This filing is accessible on-line at                (NOI) and an Errata Notice for the NOI
                                                  Commission’s (Commission) Rules of                          http://www.ferc.gov, using the                         on November 28, 2016. It has come to
                                                  Practice and Procedure, 18 CFR 385.206                      ‘‘eLibrary’’ link and is available for                 our attention that the environmental
                                                  and sections 206 and 309 of the Federal                     electronic review in the Commission’s                  mailing list was not provided copies of
                                                  Power Act, (FPA) 1 American Municipal                       Public Reference Room in Washington,                   the NOI or the Errata Notice; therefore,
                                                  Power, Inc. (AMP or Complainant) filed                      DC. There is an ‘‘eSubscription’’ link on              we are issuing this Supplemental NOI to
                                                  a formal complaint against                                  the Web site that enables subscribers to               extend the scoping period and provide
                                                  Midcontinent Independent System                             receive email notification when a                      additional time for interested parties to
                                                  Operator, Inc. (MISO or Respondent)                         document is added to a subscribed                      file comments on environmental issues.
                                                  alleging that MISO violated its Open                        docket(s). For assistance with any FERC                   The staff of the Federal Energy
                                                  Access Transmission, Energy and                             Online service, please email                           Regulatory Commission (FERC or
                                                  Operating Reserve Markets Tariff by                         FERCOnlineSupport@ferc.gov, or call                    Commission) will prepare an
                                                  improperly charging AMP for certain                         (866) 208–3676 (toll free). For TTY, call              environmental assessment (EA) that will
                                                  congestion and scheduling fees                              (202) 502–8659.                                        discuss the environmental impacts of
                                                  associated with the transmission of                                                                                the Valley Expansion Project involving
                                                  energy from its facility, as more fully                        Comment Date: 5:00 p.m. Eastern                     construction and operation of facilities
                                                  explained in the complaint.                                 Time on January 18, 2017.                              by WBI Energy Transmission, Inc. (WBI
                                                     The Complainant certifies that a                           Dated: December 28, 2016.                            Energy) in Clay County, Minnesota and
                                                  copies of the complaint were served on                      Nathaniel J. Davis, Sr.,                               Cass, Burleigh, Stutsman, and Barnes
                                                  the contacts for MISO as listed on the                                                                             Counties, North Dakota. The
                                                                                                              Deputy Secretary.
                                                  Commission’s list of Corporate Officials.                                                                          Commission will use this EA in its
                                                                                                              [FR Doc. 2016–32020 Filed 1–4–17; 8:45 am]
                                                     Any person desiring to intervene or to                                                                          decision-making process to determine
                                                  protest this filing must file in                            BILLING CODE 6717–01–P                                 whether the project is in the public
                                                  accordance with Rules 211 and 214 of                                                                               convenience and necessity.
                                                  the Commission’s Rules of Practice and                                                                                You can make a difference by
                                                  Procedure (18 CFR 385.211, 385.214).                                                                               providing us with your specific
                                                  Protests will be considered by the                                                                                 comments or concerns about the project.
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Commission in determining the                                                                                      Your comments should focus on the
                                                  appropriate action to be taken, but will                                                                           potential environmental effects,
                                                  not serve to make protestants parties to                                                                           reasonable alternatives, and measures to
                                                  the proceeding. Any person wishing to                                                                              avoid or lessen environmental impacts.
                                                  become a party must file a notice of                                                                               Your input will help the Commission
                                                                                                                                                                     staff determine what issues they need to
                                                    1 16   U.S.C. 824(e) and 825(h).                                                                                 evaluate in the EA. The NOI identified


                                             VerDate Sep<11>2014     22:33 Jan 04, 2017   Jkt 241001     PO 00000   Frm 00021   Fmt 4703   Sfmt 4703   E:\FR\FM\05JAN1.SGM   05JAN1


                                                                                Federal Register / Vol. 82, No. 3 / Thursday, January 5, 2017 / Notices                                                      1331

                                                  December 23, 2016 as the close of the                   of formats by attaching them as a file                 Necessity. NEPA also requires us 2 to
                                                  scoping period. Please note that the                    with your submission. New eFiling                      discover and address concerns the
                                                  scoping period is now extended and                      users must first create an account by                  public may have about proposals. This
                                                  will close on January 27, 2017.                         clicking on ‘‘eRegister.’’ If you are filing           process is referred to as scoping. The
                                                    If you sent comments on this project                  a comment on a particular project,                     main goal of the scoping process is to
                                                  to the Commission before the opening of                 please select ‘‘Comment on a Filing’’ as               focus the analysis in the EA on the
                                                  this docket on October 17, 2016, you                    the filing type; or                                    important environmental issues. By this
                                                  will need to file those comments in                        (3) You can file a paper copy of your               notice, the Commission requests public
                                                  Docket No. PF16–10–000 to ensure they                   comments by mailing them to the                        comments on the scope of the issues to
                                                  are considered as part of this                          following address. Be sure to reference                address in the EA. We will consider all
                                                  proceeding.                                             the project docket number (PF16–10–                    filed comments during the preparation
                                                    This notice is being sent to the                      000) with your submission: Kimberly D.                 of the EA.
                                                  Commission’s current environmental                      Bose, Secretary, Federal Energy                           In the EA, we will discuss impacts
                                                  mailing list for this project. State and                Regulatory Commission, 888 First Street                that could occur as a result of the
                                                  local government representatives should                 NE., Room 1A, Washington, DC 20426.                    construction and operation of the
                                                  notify their constituents of this planned                                                                      planned project under these general
                                                                                                          Summary of the Planned Project
                                                  project and encourage them to comment                                                                          headings:
                                                  on their areas of concern.                                WBI Energy plans to construct 38                        • Geology and soils;
                                                    If you are a landowner receiving this                 miles of new 16-inch-diameter pipeline                    • water resources, fisheries, and
                                                  notice, a pipeline company                              between Mapleton, North Dakota and                     wetlands;
                                                  representative may contact you about                    Felton, Minnesota. WBI Energy also                        • vegetation and wildlife;
                                                  the acquisition of an easement to                       plans to construct a new 2,600-                           • endangered and threatened species;
                                                  construct, operate, and maintain the                    horsepower electric-driven compressor                     • cultural resources;
                                                  planned facilities. The company would                   station in Cass County, North Dakota,                     • socioeconomics;
                                                  seek to negotiate a mutually acceptable                 farm taps, valve settings, and ancillary                  • land use;
                                                  agreement. However, if the Commission                   facilities. Additionally, WBI Energy                      • air quality and noise;
                                                  approves the project, that approval                     plans to replace two existing town                        • public safety; and
                                                  conveys with it the right of eminent                    border station delivery points and                        • cumulative impacts.
                                                  domain. Therefore, if easement                          construct one regulator station in                        We will also evaluate possible
                                                  negotiations fail to produce an                         Burleigh, Stutsman, and Barnes                         alternatives to the planned project or
                                                  agreement, the pipeline company could                   Counties, North Dakota in order to                     portions of the project, and make
                                                  initiate condemnation proceedings                       increase in the maximum allowable                      recommendations on how to lessen or
                                                  where compensation would be                             operating pressure of a portion of its                 avoid impacts on the various resource
                                                  determined in accordance with state                     Line Section 24. According to WBI                      areas.
                                                  law.                                                    Energy, the project would provide an                      Although no formal application has
                                                    A fact sheet prepared by the FERC                     additional 40 million cubic feet per day               been filed, we have already initiated our
                                                  entitled ‘‘An Interstate Natural Gas                    of firm transportation on its system.                  NEPA review under the Commission’s
                                                  Facility On My Land? What Do I Need                       The general location of the project                  pre-filing process. The purpose of the
                                                  To Know?’’ is available for viewing on                  facilities is shown in appendix 1.1                    pre-filing process is to encourage early
                                                  the FERC Web site (www.ferc.gov). This                  Land Requirements for Construction                     involvement of interested stakeholders
                                                  fact sheet addresses a number of                                                                               and to identify and resolve issues before
                                                  typically asked questions, including the                   Construction of the project would
                                                                                                          affect a total of about 530 acres of land,             the FERC receives an application. As
                                                  use of eminent domain and how to                                                                               part of our pre-filing review, we have
                                                                                                          including the pipeline construction
                                                  participate in the Commission’s                                                                                begun to contact some federal and state
                                                                                                          right-of-way, additional temporary
                                                  proceedings.                                                                                                   agencies to discuss their involvement in
                                                                                                          workspace, staging areas, temporary and
                                                  Public Participation                                    permanent access roads, and                            the scoping process and the preparation
                                                                                                          aboveground facilities. The total acreage              of the EA.
                                                    For your convenience, there are three                                                                           The EA will present our independent
                                                  methods you can use to submit your                      required for operation of the project is
                                                                                                          approximately 235 acres, including the                 analysis of the issues. The EA will be
                                                  comments to the Commission. The                                                                                available in the public record through
                                                  Commission encourages electronic filing                 new permanent pipeline easement,
                                                                                                          permanent access roads, and permanent                  eLibrary. Depending on the comments
                                                  of comments and has expert staff                                                                               received during the scoping process, we
                                                  available to assist you at (202) 502–8258               aboveground facilities’ footprint.
                                                                                                                                                                 may also publish and distribute the EA
                                                  or efiling@ferc.gov. Please carefully                   The EA Process                                         to the public for an allotted comment
                                                  follow these instructions so that your                                                                         period. We will consider all comments
                                                                                                            The National Environmental Policy
                                                  comments are properly recorded.                                                                                on the EA before we make our
                                                    (1) You can file your comments                        Act (NEPA) requires the Commission to
                                                                                                          take into account the environmental                    recommendations to the Commission.
                                                  electronically using the eComment                                                                              To ensure we have the opportunity to
                                                  feature on the Commission’s Web site                    impacts that could result from an action
                                                                                                          whenever it considers the issuance of a                consider and address your comments,
                                                  (www.ferc.gov) under the link to                                                                               please carefully follow the instructions
                                                  Documents and Filings. This is an easy                  Certificate of Public Convenience and
                                                                                                                                                                 in the Public Participation section,
                                                  method for submitting brief, text-only
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                            1 The appendices referenced in this notice will      beginning on page 2.
                                                  comments on a project;                                  not appear in the Federal Register. Copies of the         With this notice, we are asking
                                                    (2) You can file your comments                        appendices were sent to all those receiving this       agencies with jurisdiction by law and/
                                                  electronically by using the eFiling                     notice in the mail and are available at www.ferc.gov
                                                                                                          using the link called ‘‘eLibrary’’ or from the         or special expertise with respect to the
                                                  feature on the Commission’s Web site
                                                                                                          Commission’s Public Reference Room, 888 First
                                                  (www.ferc.gov) under the link to                        Street NE., Washington, DC 20426, or call (202)          2 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the
                                                  Documents and Filings. With eFiling,                    502–8371. For instructions on connecting to            environmental staff of the Commission’s Office of
                                                  you can provide comments in a variety                   eLibrary, refer to the last page of this notice.       Energy Projects.



                                             VerDate Sep<11>2014   21:06 Jan 04, 2017   Jkt 241001   PO 00000   Frm 00022   Fmt 4703   Sfmt 4703   E:\FR\FM\05JAN1.SGM   05JAN1


                                                  1332                             Federal Register / Vol. 82, No. 3 / Thursday, January 5, 2017 / Notices

                                                  environmental issues related to this                        • crossing methods of the Rush River,               ‘‘General Search’’ and enter the docket
                                                  project to formally cooperate with us in                  Red River of the North, and the Buffalo               number, excluding the last three digits
                                                  the preparation of the EA.3 Agencies                      River.                                                in the Docket Number field (i.e., PF16–
                                                  that would like to request cooperating                                                                          10). Be sure you have selected an
                                                                                                            Environmental Mailing List
                                                  agency status should follow the                                                                                 appropriate date range. For assistance,
                                                  instructions for filing comments                             The environmental mailing list                     please contact FERC Online Support at
                                                  provided under the Public Participation                   includes federal, state, and local                    FercOnlineSupport@ferc.gov or toll free
                                                  section of this notice.                                   government representatives and                        at (866) 208–3676, or for TTY, contact
                                                                                                            agencies; elected officials; Native                   (202) 502–8659. The eLibrary link also
                                                  Consultations Under Section 106 of the                    American Tribes; other interested                     provides access to the texts of formal
                                                  National Historic Preservation Act                        parties; and local libraries and                      documents issued by the Commission,
                                                     In accordance with the Advisory                        newspapers. This list also includes all               such as orders, notices, and
                                                  Council on Historic Preservation’s                        affected landowners (as defined in the                rulemakings.
                                                  implementing regulations for section                      Commission’s regulations) who are                        In addition, the Commission offers a
                                                  106 of the National Historic                              potential right-of-way grantors, whose                free service called eSubscription, which
                                                  Preservation Act, we are using this                       property may be used temporarily for                  allows you to keep track of all formal
                                                  notice to initiate consultation with the                  project purposes, or who own homes                    issuances and submittals in specific
                                                  applicable State Historic Preservation                    within certain distances of aboveground               dockets. This can reduce the amount of
                                                  Offices (SHPO), and to solicit their                      facilities, and anyone who submits                    time you spend researching proceedings
                                                  views and those of other government                       comments on the project. We will                      by automatically providing you with
                                                  agencies, interested Indian tribes, and                   update the environmental mailing list as              notification of these filings, document
                                                  the public on the project’s potential                     the analysis proceeds to ensure that we               summaries, and direct links to the
                                                  effects on historic properties.4 We will                  send the information related to this                  documents. Go to www.ferc.gov/docs-
                                                  define the project-specific Area of                       environmental review to all individuals,              filing/esubscription.asp.
                                                  Potential Effects (APE) in consultation                   organizations, and government entities                   Finally, public meetings or site visits
                                                  with the SHPOs as the project develops.                   interested in and/or potentially affected             will be posted on the Commission’s
                                                  On natural gas facility projects, the APE                 by the planned project.                               calendar located at www.ferc.gov/
                                                  at a minimum encompasses all areas                           If we publish and distribute the EA,               EventCalendar/EventsList.aspx along
                                                  subject to ground disturbance (examples                   copies will be sent to the environmental              with other related information.
                                                  include construction right-of-way,                        mailing list for public review and
                                                                                                            comment. If you would prefer to receive                 Dated: December 28, 2016.
                                                  contractor/pipe storage yards,
                                                                                                            a paper copy of the document instead of               Nathaniel J. Davis, Sr.,
                                                  compressor stations, and access roads).
                                                                                                            the CD version or would like to remove                Deputy Secretary.
                                                  Our EA for this project will document
                                                  our findings on the impacts on historic                   your name from the mailing list, please               [FR Doc. 2016–32025 Filed 1–4–17; 8:45 am]
                                                  properties and summarize the status of                    return the attached Information Request               BILLING CODE 6717–01–P

                                                  consultations under section 106.                          (appendix 2).

                                                  Currently Identified Environmental                        Becoming an Intervenor
                                                                                                                                                                  DEPARTMENT OF ENERGY
                                                  Issues                                                       Once WBI Energy files its application
                                                                                                            with the Commission, you may want to                  Federal Energy Regulatory
                                                     We have already identified several
                                                                                                            become an ‘‘intervenor’’ which is an                  Commission
                                                  issues that we think deserve attention
                                                                                                            official party to the Commission’s
                                                  based on a preliminary review of the                                                                            [Docket No. EL17–32–000]
                                                                                                            proceeding. Intervenors play a more
                                                  planned facilities and the
                                                                                                            formal role in the process and are able               Old Dominion Electric Cooperative and
                                                  environmental information provided by
                                                                                                            to file briefs, appear at hearings, and be            Direct Energy Business, LLC on Behalf
                                                  WBI Energy. This preliminary list of
                                                                                                            heard by the courts if they choose to                 of Itself and Its Affiliate, Direct Energy
                                                  issues may change based on your
                                                                                                            appeal the Commission’s final ruling.                 Business Marketing, LLC and
                                                  comments and our analysis, but
                                                                                                            An intervenor formally participates in                American Municipal Power, Inc. v. PJM
                                                  currently includes:
                                                                                                            the proceeding by filing a request to                 Interconnection, L.L.C.; Notice of
                                                     • Drain tiles;
                                                                                                            intervene. Motions to intervene are                   Complaint
                                                     • deep topsoil and poor quality
                                                                                                            more fully described at http://
                                                  subsoils (salinity/sodium or lime);                                                                               Take notice that on December 23,
                                                                                                            www.ferc.gov/resources/guides/how-to/
                                                     • prime farm land;                                     intervene.asp. Instructions for becoming              2016, pursuant to sections 206 and 306
                                                     • federally listed species, including                  an intervenor are in the ‘‘Document-less              of the Federal Power Act, 16 U.S.C.
                                                  the whooping crane, gray wolf, Dakota                     Intervention Guide’’ under the ‘‘e-filing’’           824e, 825e, and 825h, and Rule 206 of
                                                  skipper, northern long-eared bat,                         link on the Commission’s Web site.                    the Federal Energy Regulatory
                                                  western prairie fringed orchid, and the                   Please note that the Commission will                  Commission’s (Commission) Rules of
                                                  powershiek skipperling;                                   not accept requests for intervenor status             Practice and Procedure, 18 CFR 385.206,
                                                     • cultural resources; and                              at this time. You must wait until the                 Old Dominion Electric Cooperative
                                                                                                            Commission receives a formal                          (ODEC) and Direct Energy Business,
                                                    3 The Council on Environmental Quality
                                                                                                            application for the project.                          LLC, on behalf of itself and its affiliate,
                                                  regulations addressing cooperating agency                                                                       Direct Energy Business Marketing, LLC,
mstockstill on DSK3G9T082PROD with NOTICES




                                                  responsibilities are at Title 40, Code of Federal         Additional Information
                                                  Regulations, Part 1501.6.                                                                                       and American Municipal Power, Inc.
                                                    4 The Advisory Council on Historic Preservation            Additional information about the                   (collectively, Complainants) filed a
                                                  regulations are at Title 36, Code of Federal              project is available from the                         formal complaint against PJM
                                                  Regulations, Part 800. Those regulations define           Commission’s Office of External Affairs,              Interconnection, L.L.C. (PJM or
                                                  historic properties as any prehistoric or historic
                                                  district, site, building, structure, or object included
                                                                                                            at (866) 208–FERC, or on the FERC Web                 Respondent) alleging, among other
                                                  in or eligible for inclusion in the National Register     site (www.ferc.gov) using the eLibrary                things, that certain provisions in the
                                                  of Historic Places.                                       link. Click on the eLibrary link, click on            Respondent’s Open Access


                                             VerDate Sep<11>2014    21:06 Jan 04, 2017   Jkt 241001   PO 00000   Frm 00023   Fmt 4703   Sfmt 4703   E:\FR\FM\05JAN1.SGM   05JAN1



Document Created: 2018-02-01 14:51:11
Document Modified: 2018-02-01 14:51:11
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 1330 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR