82_FR_15107 82 FR 15051 - Southern Natural Gas Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Fairburn Expansion Project and Request for Comments on Environmental Issues

82 FR 15051 - Southern Natural Gas Company, LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Fairburn Expansion Project and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 56 (March 24, 2017)

Page Range15051-15053
FR Document2017-05844

Federal Register, Volume 82 Issue 56 (Friday, March 24, 2017)
[Federal Register Volume 82, Number 56 (Friday, March 24, 2017)]
[Notices]
[Pages 15051-15053]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-05844]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-46-000]


Southern Natural Gas Company, LLC; Notice of Intent To Prepare an 
Environmental Assessment for the Proposed Fairburn Expansion Project 
and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Fairburn Expansion Project 
involving construction and operation of facilities by Southern Natural 
Gas Company, LLC (Southern) in Clayton, Cobb, Fayette, Fulton, and 
Monroe Counties, Georgia. The Commission will use this EA in its 
decision-making process to determine whether the project is in the 
public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before April 19, 2017.
    If you sent comments on this project to the Commission before the 
opening of this docket on February 3, 2017, you will need to file those 
comments in Docket No. CP17-46-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.
    If you are a landowner receiving this notice, a pipeline company 
representative may contact you about the acquisition of an easement to 
construct, operate, and maintain the proposed facilities. The company 
would seek to negotiate a mutually acceptable agreement. However, if 
the Commission approves the project, that approval conveys with it the 
right of eminent domain. Therefore, if easement negotiations fail to 
produce an agreement, the pipeline company could initiate condemnation 
proceedings where compensation would be determined in accordance with 
state law.
    Southern provided landowners with a fact sheet prepared by the FERC 
entitled ``An Interstate Natural Gas Facility On My Land? What Do I 
Need To Know?''. This fact sheet addresses a number of typically-asked 
questions, including the use of eminent domain and how to participate 
in the Commission's proceedings. It is also available for

[[Page 15052]]

viewing on the FERC Web site (www.ferc.gov).

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow these 
instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP17-46-000) with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Southern proposes to provide approximately 343 million cubic feet 
per day of new firm transportation capacity to delivery points in 
Southern's Zone 2 and Zone 3 systems from a new interconnection with an 
existing Transcontinental Gas Pipe Line Company pipeline in Fayette 
County, Georgia. Southern plans to begin construction of the project in 
early 2018 for an anticipated in-service date of October 2018. The 
Fairburn Expansion project would include the following facilities:
     One new 4.9-mile-long 30-inch-diameter Fairburn Lateral 
from the Transcontinental Gas Pipeline Company interconnect in Fayette 
County, Georgia, to the proposed Fairburn Compressor Station in Fulton 
County, Georgia;
     one 1.6-mile-long 30-inch-diameter South Main 2nd Loop 
Line Extension looping \1\ along with pig \2\ receiver from mileposts 
(MP) 373.6 to 375.2 on Southern's existing South Main Line System in 
Monroe County, Georgia;
---------------------------------------------------------------------------

    \1\ A pipeline loop is a segment of pipe constructed parallel to 
an existing pipeline to increase capacity.
    \2\ A ``pig'' is a tool that the pipeline company inserts into 
and pushes through the pipeline for cleaning the pipeline, 
conducting internal inspections, or other purposes.
---------------------------------------------------------------------------

     acquisition of the 19.7-mile-long 30-inch-diameter 
McDonough Lateral that extends from Southern's existing SNG-to-
McDonough Meter Station in Fulton County, Georgia to the proposed Plant 
McDonough Meter Station in Cobb County, Georgia;
     a new Plant McDonough Meter Station in Cobb County, 
Georgia, a SNG-to-McDonough Meter Station modification in Fulton 
County, Georgia; and a new UPS Meter Station in Fulton County, Georgia, 
all located on the McDonough Lateral;
     one new Transco-to-SNG Meter Station with pig launcher in 
Fayette County, Georgia,
     one new 18,000-horsepower electric Fairburn Compressor 
Station with pig receiver in Fulton County, Georgia; and
     modification of the Jonesboro Meter Station in Clayton 
County, Georgia.
    A map depicting the general location of the project facilities is 
included in appendix 1.\3\
---------------------------------------------------------------------------

    \3\ The appendices referenced in this notice are not being 
printed in the Federal Register. Copies of appendices were sent to 
all those receiving this notice in the mail and are available at 
www.ferc.gov using the link called ``eLibrary'' or from the 
Commission's Public Reference Room, 888 First Street NE., 
Washington, DC 20426, or call (202) 502-8371. For instructions on 
connecting to eLibrary, refer to the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Southern proposes to use 170 acres of land for construction of the 
project, and would retain 59 acres of new permanent right-of-way for 
operations. The Fairburn Lateral would require 65 acres for 
construction, comprised of 34 acres of temporary right-of-way to be 
restored and allowed to revert to former uses, and 31 acres of new 
permanent right-of-way retained for operations. The South Main 2nd Loop 
Line Extension would require 21 acres for construction, comprised of 16 
acres of temporary right-of-way and 5 acres of new permanent right-of-
way. The Fairburn Compressor Station would require 28 acres for 
construction, comprised of 13 acres of temporary workspace and 15 acres 
of new permanent operational workspace. The five meter stations would 
require 4.3 acres for construction and Columbia would retain all of 
this acreage within its proposed permanent pipeline right-of-way for 
operations. Columbia would require six new permanent access roads 
totaling 4.5 acres for construction and operation. Columbia would 
require 8.5 acres of temporary access roads and three contractor yards 
totaling 39 acres for construction, all of which would revert to 
previous use following construction.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\4\ to discover and address concerns the public may have about 
proposals. This process is referred to as ``scoping.'' The main goal of 
the scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \4\ ``We,'' ``us,'' and ``our'' refer to the environmental staff 
of the Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss impacts that could occur as a result of 
the construction and operation of the proposed project under these 
general headings:
     Geology and soils;
     water resources, fisheries, and wetlands;
     cultural resources;
     vegetation, wildlife, threatened and endangered species, 
and migratory birds;
     land use and socioeconomics;
     air quality and noise;
     public safety; and
     cumulative impacts.
    We will also evaluate reasonable alternatives to the project or 
portions of the project, and make recommendations on how to lessen or 
avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments received during the scoping process, we may also publish 
and distribute the EA to the public for an allotted comment period. We 
will consider all comments on the EA before making our recommendations 
to the Commission. To ensure we have the opportunity to consider and 
address your comments, please carefully follow the instructions in the 
Public Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/

[[Page 15053]]

or special expertise with respect to the environmental issues of this 
project to formally cooperate with us in the preparation of the EA.\5\ 
Agencies that would like to request cooperating agency status should 
follow the instructions for filing comments provided under the Public 
Participation section of this notice. Currently, the U.S. Army Corps of 
Engineers has expressed intention to participate as a cooperating 
agency in the preparation of the EA to satisfy its NEPA 
responsibilities related to this project.
---------------------------------------------------------------------------

    \5\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Consultations Under Section 106 of the National Historic Preservation 
Act

    In accordance with the Advisory Council on Historic Preservation's 
implementing regulations for section 106 of the National Historic 
Preservation Act, we are using this notice to initiate consultation 
with applicable State Historic Preservation Office (SHPO), and to 
solicit their views and those of other government agencies, interested 
Indian tribes, and the public on the project's potential effects on 
historic properties.\6\ We will define the project-specific Area of 
Potential Effects (APE) in consultation with the SHPO as the project 
develops. On natural gas facility projects, the APE at a minimum 
encompasses all areas subject to ground disturbance (examples include 
construction right-of-way, contractor/pipe storage yards, compressor 
stations, and access roads). Our EA for this project will document our 
findings on the impacts on historic properties and summarize the status 
of consultations under section 106.
---------------------------------------------------------------------------

    \6\ The Advisory Council on Historic Preservation's regulations 
are at Title 36, Code of Federal Regulations, Part 800. Those 
regulations define historic properties as any prehistoric or 
historic district, site, building, structure, or object included in 
or eligible for inclusion in the National Register of Historic 
Places.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American Tribes; other 
interested parties; and local libraries and newspapers. This list also 
includes all affected landowners (as defined in the Commission's 
regulations) who are potential right-of-way grantors, whose property 
may be used temporarily for project purposes, or who own homes within 
certain distances of aboveground facilities, and anyone who submits 
comments on the project. We will update the environmental mailing list 
as the analysis proceeds to ensure that we send the information related 
to this environmental review to all individuals, organizations, and 
government entities interested in and/or potentially affected by the 
proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an ``intervenor'' which is an official party to the 
Commission's proceeding. Intervenors play a more formal role in the 
process and are able to file briefs, appear at hearings, and be heard 
by the courts if they choose to appeal the Commission's final ruling. 
An intervenor formally participates in the proceeding by filing a 
request to intervene. Instructions for becoming an intervenor are in 
the ``Document-less Intervention Guide'' under the ``e-filing'' link on 
the Commission's Web site. Motions to intervene are more fully 
described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the ``eLibrary'' link. Click on the 
eLibrary link, click on ``General Search'' and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP17-
46). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription, which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, public meetings or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: March 20, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-05844 Filed 3-23-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                  Federal Register / Vol. 82, No. 56 / Friday, March 24, 2017 / Notices                                         15051

                                                     Accession Number: 20170320–5155.                        Description: Macquarie Sierra                      the Fairburn Expansion Project
                                                     Comments Due: 5 p.m. ET 4/10/17.                     Investment Holdings, Inc., et. al.                    involving construction and operation of
                                                     Docket Numbers: ER17–1248–000.                       submits FERC 65–B Waiver Notification.                facilities by Southern Natural Gas
                                                     Applicants: Southern California                         Filed Date: 3/17/17.                               Company, LLC (Southern) in Clayton,
                                                  Edison Company.                                            Accession Number: 20170317–5200.                   Cobb, Fayette, Fulton, and Monroe
                                                     Description: § 205(d) Rate Filing:                      Comments Due: 5 p.m. ET 4/7/17.                    Counties, Georgia. The Commission will
                                                  Amended and Restated Service                               Take notice that the Commission                    use this EA in its decision-making
                                                  Agreements with City of Victorville to                  received the following electric                       process to determine whether the
                                                  be effective 4/1/2017.                                  reliability filings:                                  project is in the public convenience and
                                                     Filed Date: 3/17/17.                                    Docket Numbers: RD17–5–000.                        necessity.
                                                     Accession Number: 20170317–5179.                        Applicants: North American Electric                   This notice announces the opening of
                                                     Comments Due: 5 p.m. ET 4/7/17.                      Reliability Corporation.                              the scoping process the Commission
                                                                                                             Description: Joint Petition of the                 will use to gather input from the public
                                                     Docket Numbers: ER17–1257–000.
                                                                                                          North American Electric Reliability                   and interested agencies on the project.
                                                     Applicants: Southern California
                                                                                                          Corporation and Western Electricity                   You can make a difference by providing
                                                  Edison Company.
                                                                                                          Coordinating Council for Approval of                  us with your specific comments or
                                                     Description: § 205(d) Rate Filing: DSA
                                                                                                          Proposed Regional Reliability Standard                concerns about the project. Your
                                                  for Decade Dairy Digester Project, SA
                                                                                                          VAR–501–WECC–3.                                       comments should focus on the potential
                                                  No. 952 to be effective 5/22/2017.                                                                            environmental effects, reasonable
                                                     Filed Date: 3/20/17.                                    Filed Date: 3/10/17.
                                                                                                             Accession Number: 20170310–5318.                   alternatives, and measures to avoid or
                                                     Accession Number: 20170320–5154.                                                                           lessen environmental impacts. Your
                                                     Comments Due: 5 p.m. ET 4/10/17.                        Comments Due: 5 p.m. ET 4/19/17.
                                                                                                             The filings are accessible in the                  input will help the Commission staff
                                                     Docket Numbers: ER17–1258–000.                                                                             determine what issues they need to
                                                     Applicants: Canadian Wood Products-                  Commission’s eLibrary system by
                                                                                                          clicking on the links or querying the                 evaluate in the EA. To ensure that your
                                                  Montreal, Inc.                                                                                                comments are timely and properly
                                                     Description: Tariff Cancellation:                    docket number.
                                                                                                             Any person desiring to intervene or                recorded, please send your comments so
                                                  Cancellation filing to be effective                                                                           that the Commission receives them in
                                                  3/21/2017.                                              protest in any of the above proceedings
                                                                                                          must file in accordance with Rules 211                Washington, DC on or before April 19,
                                                     Filed Date: 3/20/17.                                                                                       2017.
                                                     Accession Number: 20170320–5169.                     and 214 of the Commission’s
                                                                                                                                                                   If you sent comments on this project
                                                     Comments Due: 5 p.m. ET 4/10/17.                     Regulations (18 CFR 385.211 and
                                                                                                                                                                to the Commission before the opening of
                                                                                                          385.214) on or before 5:00 p.m. Eastern               this docket on February 3, 2017, you
                                                     Docket Numbers: ER17–1259–000.
                                                                                                          time on the specified comment date.                   will need to file those comments in
                                                     Applicants: ITC Midwest LLC.
                                                                                                          Protests may be considered, but                       Docket No. CP17–46–000 to ensure they
                                                     Description: § 205(d) Rate Filing:
                                                                                                          intervention is necessary to become a                 are considered as part of this
                                                  Filing of a Joint Use Agreement to be
                                                                                                          party to the proceeding.                              proceeding.
                                                  effective 5/19/2017.
                                                                                                             eFiling is encouraged. More detailed                  This notice is being sent to the
                                                     Filed Date: 3/20/17.
                                                                                                          information relating to filing                        Commission’s current environmental
                                                     Accession Number: 20170320–5182.
                                                                                                          requirements, interventions, protests,                mailing list for this project. State and
                                                     Comments Due: 5 p.m. ET 4/10/17.
                                                                                                          service, and qualifying facilities filings            local government representatives should
                                                     Docket Numbers: ER17–1260–000.                       can be found at: http://www.ferc.gov/
                                                     Applicants: Wisconsin Public Service                                                                       notify their constituents of this
                                                                                                          docs-filing/efiling/filing-req.pdf. For               proposed project and encourage them to
                                                  Corporation.                                            other information, call (866) 208–3676
                                                     Description: § 205(d) Rate Filing:                                                                         comment on their areas of concern.
                                                                                                          (toll free). For TTY, call (202) 502–8659.               If you are a landowner receiving this
                                                  Wisconsin Public Service Corporation’s
                                                  Annual PEB/PBOP Filing to be effective                    Dated: March 20, 2017.                              notice, a pipeline company
                                                  4/1/2017.                                               Nathaniel J. Davis, Sr.,                              representative may contact you about
                                                     Filed Date: 3/20/17.                                 Deputy Secretary.                                     the acquisition of an easement to
                                                     Accession Number: 20170320–5184.                     [FR Doc. 2017–05847 Filed 3–23–17; 8:45 am]
                                                                                                                                                                construct, operate, and maintain the
                                                     Comments Due: 5 p.m. ET 4/10/17.                                                                           proposed facilities. The company would
                                                                                                          BILLING CODE 6717–01–P
                                                                                                                                                                seek to negotiate a mutually acceptable
                                                     Docket Numbers: ER17–1261–000.                                                                             agreement. However, if the Commission
                                                     Applicants: Otter Tail Power                                                                               approves the project, that approval
                                                  Company.                                                DEPARTMENT OF ENERGY
                                                                                                                                                                conveys with it the right of eminent
                                                     Description: § 205(d) Rate Filing:                                                                         domain. Therefore, if easement
                                                                                                          Federal Energy Regulatory
                                                  Filing of Certificate of Concurrence to be                                                                    negotiations fail to produce an
                                                                                                          Commission
                                                  effective 1/25/2017.                                                                                          agreement, the pipeline company could
                                                     Filed Date: 3/20/17.                                 [Docket No. CP17–46–000]
                                                                                                                                                                initiate condemnation proceedings
                                                     Accession Number: 20170320–5193.                                                                           where compensation would be
                                                     Comments Due: 5 p.m. ET 4/10/17.                     Southern Natural Gas Company, LLC;
                                                                                                          Notice of Intent To Prepare an                        determined in accordance with state
                                                     Take notice that the Commission                                                                            law.
                                                  received the following public utility                   Environmental Assessment for the
                                                                                                          Proposed Fairburn Expansion Project                      Southern provided landowners with a
                                                  holding company filings:                                                                                      fact sheet prepared by the FERC entitled
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                                                                          and Request for Comments on
                                                     Docket Numbers: PH17–12–000.                         Environmental Issues                                  ‘‘An Interstate Natural Gas Facility On
                                                     Applicants: Macquarie Sierra                                                                               My Land? What Do I Need To Know?’’.
                                                  Investment Holdings, In, Electrodes                       The staff of the Federal Energy                     This fact sheet addresses a number of
                                                  Holdings, LLC, Watt Battery Holdings,                   Regulatory Commission (FERC or                        typically-asked questions, including the
                                                  LLC, Battery Storage Holdings, LLC,                     Commission) will prepare an                           use of eminent domain and how to
                                                  Sparks Battery Holdings, LLC, Sparks                    environmental assessment (EA) that will               participate in the Commission’s
                                                  Battery Holdings 2, LLC.                                discuss the environmental impacts of                  proceedings. It is also available for


                                             VerDate Sep<11>2014   13:56 Mar 23, 2017   Jkt 241001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\24MRN1.SGM   24MRN1


                                                  15052                           Federal Register / Vol. 82, No. 56 / Friday, March 24, 2017 / Notices

                                                  viewing on the FERC Web site                            looping 1 along with pig 2 receiver from                 Columbia would require six new
                                                  (www.ferc.gov).                                         mileposts (MP) 373.6 to 375.2 on                         permanent access roads totaling 4.5
                                                                                                          Southern’s existing South Main Line                      acres for construction and operation.
                                                  Public Participation                                    System in Monroe County, Georgia;                        Columbia would require 8.5 acres of
                                                    For your convenience, there are three                   • acquisition of the 19.7-mile-long 30-                temporary access roads and three
                                                  methods you can use to submit your                      inch-diameter McDonough Lateral that                     contractor yards totaling 39 acres for
                                                  comments to the Commission. The                         extends from Southern’s existing SNG-                    construction, all of which would revert
                                                                                                          to-McDonough Meter Station in Fulton                     to previous use following construction.
                                                  Commission encourages electronic filing
                                                  of comments and has expert staff                        County, Georgia to the proposed Plant                    The EA Process
                                                  available to assist you at (202) 502–8258               McDonough Meter Station in Cobb
                                                                                                          County, Georgia;                                            The National Environmental Policy
                                                  or efiling@ferc.gov. Please carefully                                                                            Act (NEPA) requires the Commission to
                                                                                                            • a new Plant McDonough Meter
                                                  follow these instructions so that your                                                                           take into account the environmental
                                                                                                          Station in Cobb County, Georgia, a SNG-
                                                  comments are properly recorded.                                                                                  impacts that could result from an action
                                                                                                          to-McDonough Meter Station
                                                     (1) You can file your comments                       modification in Fulton County, Georgia;                  whenever it considers the issuance of a
                                                  electronically using the eComment                       and a new UPS Meter Station in Fulton                    Certificate of Public Convenience and
                                                  feature on the Commission’s Web site                    County, Georgia, all located on the                      Necessity. NEPA also requires us 4 to
                                                  (www.ferc.gov) under the link to                        McDonough Lateral;                                       discover and address concerns the
                                                  Documents and Filings. This is an easy                    • one new Transco-to-SNG Meter                         public may have about proposals. This
                                                  method for submitting brief, text-only                  Station with pig launcher in Fayette                     process is referred to as ‘‘scoping.’’ The
                                                  comments on a project;                                  County, Georgia,                                         main goal of the scoping process is to
                                                                                                            • one new 18,000-horsepower electric                   focus the analysis in the EA on the
                                                     (2) You can file your comments                                                                                important environmental issues. By this
                                                  electronically by using the eFiling                     Fairburn Compressor Station with pig
                                                                                                          receiver in Fulton County, Georgia; and                  notice, the Commission requests public
                                                  feature on the Commission’s Web site                                                                             comments on the scope of the issues to
                                                  (www.ferc.gov) under the link to                          • modification of the Jonesboro Meter
                                                                                                          Station in Clayton County, Georgia.                      address in the EA. We will consider all
                                                  Documents and Filings. With eFiling,                                                                             filed comments during the preparation
                                                  you can provide comments in a variety                     A map depicting the general location
                                                                                                          of the project facilities is included in                 of the EA.
                                                  of formats by attaching them as a file                                                                              In the EA we will discuss impacts that
                                                  with your submission. New eFiling                       appendix 1.3
                                                                                                                                                                   could occur as a result of the
                                                  users must first create an account by                   Land Requirements for Construction                       construction and operation of the
                                                  clicking on ‘‘eRegister.’’ If you are filing                                                                     proposed project under these general
                                                                                                             Southern proposes to use 170 acres of
                                                  a comment on a particular project,                                                                               headings:
                                                                                                          land for construction of the project, and
                                                  please select ‘‘Comment on a Filing’’ as                                                                            • Geology and soils;
                                                                                                          would retain 59 acres of new permanent
                                                  the filing type; or                                                                                                 • water resources, fisheries, and
                                                                                                          right-of-way for operations. The
                                                     (3) You can file a paper copy of your                                                                         wetlands;
                                                                                                          Fairburn Lateral would require 65 acres                     • cultural resources;
                                                  comments by mailing them to the                         for construction, comprised of 34 acres                     • vegetation, wildlife, threatened and
                                                  following address. Be sure to reference                 of temporary right-of-way to be restored                 endangered species, and migratory
                                                  the project docket number (CP17–46–                     and allowed to revert to former uses,                    birds;
                                                  000) with your submission: Kimberly D.                  and 31 acres of new permanent right-of-                     • land use and socioeconomics;
                                                  Bose, Secretary, Federal Energy                         way retained for operations. The South                      • air quality and noise;
                                                  Regulatory Commission, 888 First Street                 Main 2nd Loop Line Extension would                          • public safety; and
                                                  NE., Room 1A, Washington, DC 20426.                     require 21 acres for construction,                          • cumulative impacts.
                                                                                                          comprised of 16 acres of temporary                          We will also evaluate reasonable
                                                  Summary of the Proposed Project                                                                                  alternatives to the project or portions of
                                                                                                          right-of-way and 5 acres of new
                                                    Southern proposes to provide                          permanent right-of-way. The Fairburn                     the project, and make recommendations
                                                  approximately 343 million cubic feet                    Compressor Station would require 28                      on how to lessen or avoid impacts on
                                                  per day of new firm transportation                      acres for construction, comprised of 13                  the various resource areas.
                                                                                                          acres of temporary workspace and 15                         The EA will present our independent
                                                  capacity to delivery points in Southern’s
                                                                                                          acres of new permanent operational                       analysis of the issues. The EA will be
                                                  Zone 2 and Zone 3 systems from a new
                                                                                                          workspace. The five meter stations                       available in the public record through
                                                  interconnection with an existing
                                                                                                          would require 4.3 acres for construction                 eLibrary. Depending on the comments
                                                  Transcontinental Gas Pipe Line
                                                                                                          and Columbia would retain all of this                    received during the scoping process, we
                                                  Company pipeline in Fayette County,
                                                                                                          acreage within its proposed permanent                    may also publish and distribute the EA
                                                  Georgia. Southern plans to begin
                                                                                                          pipeline right-of-way for operations.                    to the public for an allotted comment
                                                  construction of the project in early 2018
                                                                                                                                                                   period. We will consider all comments
                                                  for an anticipated in-service date of                     1 A pipeline loop is a segment of pipe constructed     on the EA before making our
                                                  October 2018. The Fairburn Expansion                    parallel to an existing pipeline to increase capacity.   recommendations to the Commission.
                                                  project would include the following                       2 A ‘‘pig’’ is a tool that the pipeline company
                                                                                                                                                                   To ensure we have the opportunity to
                                                  facilities:                                             inserts into and pushes through the pipeline for
                                                                                                                                                                   consider and address your comments,
                                                                                                          cleaning the pipeline, conducting internal
                                                    • One new 4.9-mile-long 30-inch-                      inspections, or other purposes.                          please carefully follow the instructions
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                  diameter Fairburn Lateral from the                        3 The appendices referenced in this notice are not     in the Public Participation section,
                                                  Transcontinental Gas Pipeline Company                   being printed in the Federal Register. Copies of         beginning on page 2.
                                                  interconnect in Fayette County, Georgia,                appendices were sent to all those receiving this            With this notice, we are asking
                                                                                                          notice in the mail and are available at www.ferc.gov
                                                  to the proposed Fairburn Compressor                     using the link called ‘‘eLibrary’’ or from the           agencies with jurisdiction by law and/
                                                  Station in Fulton County, Georgia;                      Commission’s Public Reference Room, 888 First
                                                    • one 1.6-mile-long 30-inch-diameter                  Street NE., Washington, DC 20426, or call (202)            4 ‘‘We,’’ ‘‘us,’’ and ‘‘our’’ refer to the

                                                                                                          502–8371. For instructions on connecting to              environmental staff of the Commission’s Office of
                                                  South Main 2nd Loop Line Extension                      eLibrary, refer to the last page of this notice.         Energy Projects.



                                             VerDate Sep<11>2014   13:56 Mar 23, 2017   Jkt 241001   PO 00000   Frm 00033   Fmt 4703   Sfmt 4703   E:\FR\FM\24MRN1.SGM     24MRN1


                                                                                   Federal Register / Vol. 82, No. 56 / Friday, March 24, 2017 / Notices                                                 15053

                                                  or special expertise with respect to the                  comments on the project. We will                       Finally, public meetings or site visits
                                                  environmental issues of this project to                   update the environmental mailing list as             will be posted on the Commission’s
                                                  formally cooperate with us in the                         the analysis proceeds to ensure that we              calendar located at www.ferc.gov/
                                                  preparation of the EA.5 Agencies that                     send the information related to this                 EventCalendar/EventsList.aspx along
                                                  would like to request cooperating                         environmental review to all individuals,             with other related information.
                                                  agency status should follow the                           organizations, and government entities                 Dated: March 20, 2017.
                                                  instructions for filing comments                          interested in and/or potentially affected
                                                                                                                                                                 Kimberly D. Bose,
                                                  provided under the Public Participation                   by the proposed project.
                                                                                                              If we publish and distribute the EA,               Secretary.
                                                  section of this notice. Currently, the
                                                  U.S. Army Corps of Engineers has                          copies will be sent to the environmental             [FR Doc. 2017–05844 Filed 3–23–17; 8:45 am]
                                                  expressed intention to participate as a                   mailing list for public review and                   BILLING CODE 6717–01–P
                                                  cooperating agency in the preparation of                  comment. If you would prefer to receive
                                                  the EA to satisfy its NEPA                                a paper copy of the document instead of
                                                  responsibilities related to this project.                 the CD version or would like to remove               DEPARTMENT OF ENERGY
                                                                                                            your name from the mailing list, please
                                                  Consultations Under Section 106 of the                    return the attached Information Request              Federal Energy Regulatory
                                                  National Historic Preservation Act                        (appendix 2).                                        Commission
                                                    In accordance with the Advisory
                                                                                                            Becoming an Intervenor                               Combined Notice of Filings #1
                                                  Council on Historic Preservation’s
                                                  implementing regulations for section                         In addition to involvement in the EA                 Take notice that the Commission
                                                  106 of the National Historic                              scoping process, you may want to                     received the following electric rate
                                                  Preservation Act, we are using this                       become an ‘‘intervenor’’ which is an                 filings:
                                                  notice to initiate consultation with                      official party to the Commission’s
                                                  applicable State Historic Preservation                    proceeding. Intervenors play a more                    Docket Numbers: ER17–1173–000.
                                                  Office (SHPO), and to solicit their views                 formal role in the process and are able                Applicants: Midcontinent
                                                  and those of other government agencies,                   to file briefs, appear at hearings, and be           Independent System Operator, Inc.,
                                                  interested Indian tribes, and the public                  heard by the courts if they choose to                Ameren Illinois Company.
                                                  on the project’s potential effects on                     appeal the Commission’s final ruling.                  Description: § 205(d) Rate Filing:
                                                  historic properties.6 We will define the                  An intervenor formally participates in               2017–03–13_SA 2010 Amended
                                                  project-specific Area of Potential Effects                the proceeding by filing a request to                Ameren-SIPC WDS to be effective
                                                  (APE) in consultation with the SHPO as                    intervene. Instructions for becoming an              2/9/2017.
                                                  the project develops. On natural gas                      intervenor are in the ‘‘Document-less                  Filed Date: 3/13/17.
                                                  facility projects, the APE at a minimum                   Intervention Guide’’ under the ‘‘e-filing’’
                                                                                                                                                                   Accession Number: 20170313–5262.
                                                  encompasses all areas subject to ground                   link on the Commission’s Web site.
                                                  disturbance (examples include                             Motions to intervene are more fully                    Comments Due: 5 p.m. ET 4/3/17.
                                                  construction right-of-way, contractor/                    described at http://www.ferc.gov/                      Docket Numbers: ER17–1174–000.
                                                  pipe storage yards, compressor stations,                  resources/guides/how-to/intervene.asp.                 Applicants: Southern California
                                                  and access roads). Our EA for this                                                                             Edison Company.
                                                                                                            Additional Information
                                                  project will document our findings on
                                                                                                               Additional information about the                    Description: § 205(d) Rate Filing:
                                                  the impacts on historic properties and
                                                                                                            project is available from the                        Amended IFA and Amended DSA
                                                  summarize the status of consultations
                                                                                                            Commission’s Office of External Affairs,             Between SCE and AEPCO, SA Nos. 179
                                                  under section 106.
                                                                                                            at (866) 208–FERC, or on the FERC Web                & 180 to be effective 4/1/2017.
                                                  Environmental Mailing List                                site at www.ferc.gov using the                         Filed Date: 3/13/17.
                                                     The environmental mailing list                         ‘‘eLibrary’’ link. Click on the eLibrary               Accession Number: 20170313–5306.
                                                  includes federal, state, and local                        link, click on ‘‘General Search’’ and                  Comments Due: 5 p.m. ET 4/3/17.
                                                  government representatives and                            enter the docket number, excluding the
                                                  agencies; elected officials;                              last three digits in the Docket Number                  The filings are accessible in the
                                                  environmental and public interest                         field (i.e., CP17–46). Be sure you have              Commission’s eLibrary system by
                                                  groups; Native American Tribes; other                     selected an appropriate date range. For              clicking on the links or querying the
                                                  interested parties; and local libraries                   assistance, please contact FERC Online               docket number.
                                                  and newspapers. This list also includes                   Support at FercOnlineSupport@ferc.gov                   Any person desiring to intervene or
                                                  all affected landowners (as defined in                    or toll free at (866) 208–3676, or for               protest in any of the above proceedings
                                                  the Commission’s regulations) who are                     TTY, contact (202) 502–8659. The                     must file in accordance with Rules 211
                                                  potential right-of-way grantors, whose                    eLibrary link also provides access to the            and 214 of the Commission’s
                                                  property may be used temporarily for                      texts of formal documents issued by the              Regulations (18 CFR 385.211 and
                                                  project purposes, or who own homes                        Commission, such as orders, notices,                 385.214) on or before 5:00 p.m. Eastern
                                                  within certain distances of aboveground                   and rulemakings.                                     time on the specified comment date.
                                                  facilities, and anyone who submits                           In addition, the Commission offers a              Protests may be considered, but
                                                                                                            free service called eSubscription, which             intervention is necessary to become a
                                                    5 The Council on Environmental Quality
                                                                                                            allows you to keep track of all formal               party to the proceeding.
                                                  regulations addressing cooperating agency                 issuances and submittals in specific                    eFiling is encouraged. More detailed
jstallworth on DSK7TPTVN1PROD with NOTICES




                                                  responsibilities are at Title 40, Code of Federal
                                                  Regulations, Part 1501.6.                                 dockets. This can reduce the amount of               information relating to filing
                                                    6 The Advisory Council on Historic Preservation’s       time you spend researching proceedings               requirements, interventions, protests,
                                                  regulations are at Title 36, Code of Federal              by automatically providing you with                  service, and qualifying facilities filings
                                                  Regulations, Part 800. Those regulations define           notification of these filings, document              can be found at: http://www.ferc.gov/
                                                  historic properties as any prehistoric or historic
                                                  district, site, building, structure, or object included
                                                                                                            summaries, and direct links to the                   docs-filing/efiling/filing-req.pdf. For
                                                  in or eligible for inclusion in the National Register     documents. Go to www.ferc.gov/docs-                  other information, call (866) 208–3676
                                                  of Historic Places.                                       filing/esubscription.asp.                            (toll free). For TTY, call (202) 502–8659.


                                             VerDate Sep<11>2014    13:56 Mar 23, 2017   Jkt 241001   PO 00000   Frm 00034   Fmt 4703   Sfmt 4703   E:\FR\FM\24MRN1.SGM   24MRN1



Document Created: 2018-02-01 15:11:02
Document Modified: 2018-02-01 15:11:02
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 15051 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR