82_FR_17069 82 FR 17003 - Town of Gypsum, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

82 FR 17003 - Town of Gypsum, Colorado; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 66 (April 7, 2017)

Page Range17003-17004
FR Document2017-06934

Federal Register, Volume 82 Issue 66 (Friday, April 7, 2017)
[Federal Register Volume 82, Number 66 (Friday, April 7, 2017)]
[Notices]
[Pages 17003-17004]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-06934]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-11-000]


Town of Gypsum, Colorado; Notice of Preliminary Determination of 
a Qualifying Conduit Hydropower Facility and Soliciting Comments and 
Motions To Intervene

    On March 28, 2017, the Town of Gypsum, Colorado, filed a notice of 
intent to construct a qualifying conduit hydropower facility, pursuant 
to section 30 of the Federal Power Act (FPA), as amended by section 4 
of the Hydropower Regulatory Efficiency Act of 2013 (HREA). The 
proposed Gypsum Hydroelectric Facility Project would have a combined 
installed capacity of 85 kilowatts (kW), and would be located along two 
sections of an existing irrigation pipeline. The project would be 
located near the Town of Gypsum in Eagle County, Colorado.
    Applicant Contact: Tim Beck, 1011 Grand Ave., Glenwood Springs, CO 
81601 Phone No. (970) 945-5700, email [email protected].
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) A new powerhouse containing one turbine/
generating unit with an installed capacity of 85 kW, in an existing 8-
inch diameter raw water pipeline prior to entering an existing water 
treatment plant; (2) a bypass section through a pressure reducing 
valve; and (3) appurtenant facilities. The proposed project would have 
an estimated annual generating capacity of 650,000 kilowatt-hours.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

[[Page 17004]]



                          Table 1--Criteria for Qualifying Conduit Hydropower Facility
----------------------------------------------------------------------------------------------------------------
              Statutory provision                                 Description                    Satisfies (Y/N)
----------------------------------------------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by HREA...........  The conduit the facility uses is a tunnel,                    Y
                                                 canal, pipeline, aqueduct, flume, ditch, or
                                                 similar manmade water conveyance that is
                                                 operated for the distribution of water for
                                                 agricultural, municipal, or industrial
                                                 consumption and not primarily for the
                                                 generation of electricity.
FPA 30(a)(3)(C)(i), as amended by HREA........  The facility is constructed, operated, or                     Y
                                                 maintained for the generation of electric
                                                 power and uses for such generation only the
                                                 hydroelectric potential of a non-federally
                                                 owned conduit.
FPA 30(a)(3)(C)(ii), as amended by HREA.......  The facility has an installed capacity that                   Y
                                                 does not exceed 5 megawatts.
FPA 30(a)(3)(C)(iii), as amended by HREA......  On or before August 9, 2013, the facility is                  Y
                                                 not licensed, or exempted from the licensing
                                                 requirements of Part I of the FPA.
----------------------------------------------------------------------------------------------------------------

    Preliminary Determination: The proposed addition of the 
hydroelectric project along the existing municipal water supply 
pipeline will not alter its primary purpose. Therefore, based upon the 
above criteria, Commission staff preliminarily determines that the 
proposal satisfies the requirements for a qualifying conduit hydropower 
facility, which is not required to be licensed or exempted from 
licensing.
    Comments and Motions to Intervene: Deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice. Deadline for filing motions 
to intervene is 30 days from the issuance date of this notice. Anyone 
may submit comments or a motion to intervene in accordance with the 
requirements of Rules of Practice and Procedure, 18 CFR 385.210 and 
385.214. Any motions to intervene must be received on or before the 
specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2016).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (i.e., CD17-11) in the 
docket number field to access the document. For assistance, call toll-
free 1-866-208-3676 or email [email protected]. For TTY, call 
(202) 502-8659.

    Dated: April 3, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-06934 Filed 4-6-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 82, No. 66 / Friday, April 7, 2017 / Notices                                                  17003

                                               may close to the public a portion of any                contact CFPB_504Request@cfpb.gov,                         Take notice that during the month of
                                               meeting, for confidential discussion. If the            202–435–9EEO, 1–855–233–0362, or                        March 2017, the status of the above-
                                               Bureau closes a meeting or any portion of a             202–435–9742 (TTY) at least ten                         captioned entities as Exempt Wholesale
                                               meeting, the Bureau will issue, at least                business days prior to the meeting or                   Generators became effective by
                                               annually, a summary of the Council’s
                                               activities during such closed meetings or
                                                                                                       event to request assistance. The request                operation of the Commission’s
                                               portions of meetings.                                   must identify the date, time, location,                 regulations. 18 CFR 366.7(a) (2016).
                                                                                                       and title of the meeting or event, the                    Dated: April 3, 2017.
                                                  Section 2 of the CBAC Charter                        nature of the assistance requested, and
                                               provides: ‘‘Pursuant to the executive                                                                           Kimberly D. Bose,
                                                                                                       contact information for the requester.
                                               and administrative powers conferred on                                                                          Secretary.
                                                                                                       CFPB will strive to provide, but cannot
                                               the Bureau by section 1012 of the Dodd-                 guarantee that accommodation will be                    [FR Doc. 2017–06933 Filed 4–6–17; 8:45 am]
                                               Frank Wall Street Reform and Consumer                   provided for late requests.                             BILLING CODE 6717–01–P
                                               Protection Act (Dodd-Frank Act), the                       Individuals who wish to attend the
                                               Director established the Community                      Community Bank Advisory Council
                                               Bank Advisory Council to consult with                   meeting must RSVP to cfpb_                              DEPARTMENT OF ENERGY
                                               the Bureau in the exercise of its                       cabandcouncilsevents@cfpb.gov by
                                               functions under the Federal consumer                    noon, Monday, April 24, 2017. Members                   Federal Energy Regulatory
                                               financial laws as they pertain to                       of the public must RSVP by the due date                 Commission
                                               community banks with total assets of                    and must include ‘‘CBAC’’ in the subject
                                               $10 billion or less.’’                                  line of the RSVP.                                       [Docket No. CD17–11–000]
                                                  Section 3 of the CBAC Charter states:
                                               ‘‘(a) The CFPB supervises depository                    III. Availability                                       Town of Gypsum, Colorado; Notice of
                                               institutions and credit unions with total                  The Council’s agenda will be made                    Preliminary Determination of a
                                               assets of more than $10 billion and their               available to the public on Monday,                      Qualifying Conduit Hydropower
                                               respective affiliates, but other than the               April 10, 2017, via                                     Facility and Soliciting Comments and
                                               limited authority conferred by § 1026 of                consumerfinance.gov. Individuals                        Motions To Intervene
                                               the Dodd-Frank Act, the CFPB does not                   should express in their RSVP if they
                                               have supervisory authority regarding                    require a paper copy of the agenda.                        On March 28, 2017, the Town of
                                               credit unions and depository                               A recording and transcript of this                   Gypsum, Colorado, filed a notice of
                                               institutions with total assets of $10                   meeting will be available after the                     intent to construct a qualifying conduit
                                               billion or less. As a result, the CFPB                  meeting on the CFPB’s Web site                          hydropower facility, pursuant to section
                                               does not have regular contact with these                consumerfinance.gov.                                    30 of the Federal Power Act (FPA), as
                                               institutions, and it would therefore be                   Dated: April 3, 2017.                                 amended by section 4 of the
                                               beneficial to create a mechanism to                                                                             Hydropower Regulatory Efficiency Act
                                                                                                       Leandra English,
                                               ensure that their unique perspectives                                                                           of 2013 (HREA). The proposed Gypsum
                                                                                                       Chief of Staff, Bureau of Consumer Financial
                                               are shared with the Bureau. Small                       Protection.
                                                                                                                                                               Hydroelectric Facility Project would
                                               Business Regulatory Enforcement                                                                                 have a combined installed capacity of
                                                                                                       [FR Doc. 2017–06996 Filed 4–6–17; 8:45 am]
                                               Fairness Act (SBREFA) panels provide                                                                            85 kilowatts (kW), and would be located
                                                                                                       BILLING CODE 4810–AM–P
                                               one avenue to gather this input, but                                                                            along two sections of an existing
                                               participants from community banks                                                                               irrigation pipeline. The project would
                                               must possess no more than $175 million                                                                          be located near the Town of Gypsum in
                                                                                                       DEPARTMENT OF ENERGY                                    Eagle County, Colorado.
                                               in assets, which precludes the
                                               participation of many. (b) The Advisory                 Federal Energy Regulatory                                  Applicant Contact: Tim Beck, 1011
                                               Council shall fill this gap by providing                Commission                                              Grand Ave., Glenwood Springs, CO
                                               an interactive dialogue and exchange of                                                                         81601 Phone No. (970) 945–5700, email
                                               ideas and experiences between                           Notice of Effectiveness of Exempt                       jim@townofgypsum.com.
                                               community bankers and Bureau staff. (c)                 Wholesale Generator Status                                 FERC Contact: Robert Bell, Phone No.
                                               The Advisory Council shall advise                                                                               (202) 502–6062, email: robert.bell@
                                                                                                                                               Docket Nos.
                                               generally on the Bureau’s regulation of                                                                         ferc.gov.
                                               consumer financial products or services                 CP Bloom Wind LLC .............      EG17–37–000
                                                                                                       Darby Power, LLC .................   EG17–38–000           Qualifying Conduit Hydropower
                                               and other topics assigned to it by the
                                                                                                       Gavin Power, LLC .................   EG17–39–000        Facility Description: The proposed
                                               Director. To carry out the Advisory                     Lawrenceburg Power, LLC ....         EG17–40–000        project would consist of: (1) A new
                                               Council’s purpose, the scope of its                     Waterford Power, LLC ...........     EG17–41–000
                                                                                                                                                               powerhouse containing one turbine/
                                               activities shall include providing                      Cotton Plains Wind I, LLC .....      EG17–42–000
                                                                                                       Old Settler Wind, LLC ...........    EG17–43–000        generating unit with an installed
                                               information, analysis, and
                                                                                                       SolaireHolman 1 LLC ............     EG17–44–000        capacity of 85 kW, in an existing 8-inch
                                               recommendations to the Bureau. The                      Bayshore Solar A, LLC .........      EG17–45–000        diameter raw water pipeline prior to
                                               output of Advisory Council meetings                     Bayshore Solar B, LLC .........      EG17–46–000
                                                                                                                                                               entering an existing water treatment
                                               should serve to better inform the CFPB’s                Bayshore Solar C, LLC .........      EG17–47–000
                                                                                                       Port Comfort Power LLC .......       EG17–48–000        plant; (2) a bypass section through a
                                               policy development, rulemaking, and                     Chamon Power LLC ..............      EG17–49–000        pressure reducing valve; and (3)
                                               engagement functions.’’                                 Arkwright Summit Wind Farm           EG17–50–000        appurtenant facilities. The proposed
                                                                                                          LLC.
                                               II. Agenda                                              Quilt Block Wind Farm LLC ..         EG17–51–000        project would have an estimated annual
nlaroche on DSK30NT082PROD with NOTICES




                                                 The Community Bank Advisory                           Cube Yadkin Generation LLC           EG17–52–000        generating capacity of 650,000 kilowatt-
                                                                                                       Iron Horse Battery Storage,          EG17–53–000        hours.
                                               Council will discuss alternative data                      LLC.
                                               and consumer access to financial                        Redbed Plains Wind Farm              EG17–54–000           A qualifying conduit hydropower
                                               records.                                                   LLC.                                                 facility is one that is determined or
                                                 Persons who need a reasonable                         Meadow Lake Wind Farm V              EG17–55–000        deemed to meet all of the criteria shown
                                                                                                          LLC.
                                               accommodation to participate should                                                                             in the table below.



                                          VerDate Sep<11>2014   14:52 Apr 06, 2017   Jkt 241001   PO 00000   Frm 00015    Fmt 4703    Sfmt 4703   E:\FR\FM\07APN1.SGM   07APN1


                                               17004                              Federal Register / Vol. 82, No. 66 / Friday, April 7, 2017 / Notices

                                                                                    TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                    Satisfies
                                                        Statutory provision                                                           Description                                                    (Y/N)

                                               FPA 30(a)(3)(A), as amended             The conduit the facility uses is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar                  Y
                                                 by HREA.                                manmade water conveyance that is operated for the distribution of water for agricultural,
                                                                                         municipal, or industrial consumption and not primarily for the generation of electricity.
                                               FPA 30(a)(3)(C)(i), as amended          The facility is constructed, operated, or maintained for the generation of electric power and                   Y
                                                 by HREA.                                uses for such generation only the hydroelectric potential of a non-federally owned conduit.
                                               FPA 30(a)(3)(C)(ii), as amend-          The facility has an installed capacity that does not exceed 5 megawatts ..................................      Y
                                                 ed by HREA.
                                               FPA 30(a)(3)(C)(iii), as amend-         On or before August 9, 2013, the facility is not licensed, or exempted from the licensing re-                   Y
                                                 ed by HREA.                            quirements of Part I of the FPA.



                                                  Preliminary Determination: The                        registration, using the eComment system                   Description: Application for
                                               proposed addition of the hydroelectric                   at http://www.ferc.gov/docs-filing/                    Authorization under section 203 of the
                                               project along the existing municipal                     ecomment.asp. You must include your                    Federal Power Act and Request for
                                               water supply pipeline will not alter its                 name and contact information at the end                Waivers and Expedited Action of
                                               primary purpose. Therefore, based upon                   of your comments. For assistance,                      Invenergy TN LLC.
                                               the above criteria, Commission staff                     please contact FERC Online Support at                     Filed Date: 4/3/17.
                                               preliminarily determines that the                        FERCOnlineSupport@ferc.gov, (866)                         Accession Number: 20170403–5417.
                                               proposal satisfies the requirements for a                208–3676 (toll free), or (202) 502–8659                   Comments Due: 5 p.m. ET 4/24/17.
                                               qualifying conduit hydropower facility,                  (TTY). In lieu of electronic filing, please               Take notice that the Commission
                                               which is not required to be licensed or                  send a paper copy to: Secretary, Federal               received the following electric rate
                                               exempted from licensing.                                 Energy Regulatory Commission, 888                      filings:
                                                  Comments and Motions to Intervene:                    First Street NE., Washington, DC 20426.
                                               Deadline for filing comments contesting                                                                            Docket Numbers: ER17–1374–000.
                                                                                                        A copy of all other filings in reference
                                               whether the facility meets the qualifying                                                                          Applicants: Cube Yadkin
                                                                                                        to this application must be accompanied
                                               criteria is 45 days from the issuance                                                                           Transmission LLC.
                                                                                                        by proof of service on all persons listed
                                               date of this notice. Deadline for filing                                                                           Description: Request for Waiver of the
                                                                                                        in the service list prepared by the
                                               motions to intervene is 30 days from the                                                                        Order No. 1000, Transmission Planning
                                                                                                        Commission in this proceeding, in
                                               issuance date of this notice. Anyone                                                                            Requirements of Cube Yadkin
                                                                                                        accordance with 18 CFR 4.34(b) and
                                               may submit comments or a motion to                       385.2010.                                              Transmission LLC.
                                               intervene in accordance with the                            Locations of Notice of Intent: Copies                  Filed Date: 4/3/17.
                                               requirements of Rules of Practice and                    of the notice of intent can be obtained                   Accession Number: 20170403–5492.
                                               Procedure, 18 CFR 385.210 and 385.214.                   directly from the applicant or such                       Comments Due: 5 p.m. ET 4/24/17.
                                               Any motions to intervene must be                         copies can be viewed and reproduced at                    Docket Numbers: ER17–1375–000.
                                               received on or before the specified                      the Commission in its Public Reference                    Applicants: Wabash Valley Power
                                               deadline date for the particular                         Room, Room 2A, 888 First Street NE.,                   Association, Inc.
                                               proceeding.                                              Washington, DC 20426. The filing may                      Description: § 205(d) Rate Filing:
                                                  Filing and Service of Responsive                      also be viewed on the web at http://                   Notice of Succession to be effective
                                               Documents: All filings must (1) bear in                  www.ferc.gov/docs-filing/elibrary.asp                  5/1/2017.
                                               all capital letters the ‘‘COMMENTS                       using the ‘‘eLibrary’’ link. Enter the                    Filed Date: 4/3/17.
                                               CONTESTING QUALIFICATION FOR A                           docket number (i.e., CD17–11) in the                      Accession Number: 20170403–5494.
                                               CONDUIT HYDROPOWER FACILITY’’                            docket number field to access the                         Comments Due: 5 p.m. ET 4/24/17.
                                               or ‘‘MOTION TO INTERVENE,’’ as                           document. For assistance, call toll-free                  Docket Numbers: ER17–1376–000.
                                               applicable; (2) state in the heading the                 1–866–208–3676 or email                                   Applicants: Midcontinent
                                               name of the applicant and the project                    FERCOnlineSupport@ferc.gov. For TTY,                   Independent System Operator, Inc.
                                               number of the application to which the                   call (202) 502–8659.                                      Description: Compliance filing: 2017–
                                               filing responds; (3) state the name,                       Dated: April 3, 2017.                                04–03_Stored Energy Resource-Type II
                                               address, and telephone number of the                                                                            Compliance Filing to be effective 9/1/
                                                                                                        Kimberly D. Bose,
                                               person filing; and (4) otherwise comply                                                                         2017.
                                                                                                        Secretary.
                                               with the requirements of sections                                                                                  Filed Date: 4/3/17.
                                               385.2001 through 385.2005 of the                         [FR Doc. 2017–06934 Filed 4–6–17; 8:45 am]
                                                                                                                                                                  Accession Number: 20170403–5496.
                                               Commission’s regulations.1 All                           BILLING CODE 6717–01–P
                                                                                                                                                                  Comments Due: 5 p.m. ET 4/24/17.
                                               comments contesting Commission staff’s
                                                                                                                                                                  The filings are accessible in the
                                               preliminary determination that the
                                                                                                        DEPARTMENT OF ENERGY                                   Commission’s eLibrary system by
                                               facility meets the qualifying criteria
                                               must set forth their evidentiary basis.                                                                         clicking on the links or querying the
                                                                                                        Federal Energy Regulatory                              docket number.
                                                  The Commission strongly encourages
                                                                                                        Commission                                                Any person desiring to intervene or
                                               electronic filing. Please file motions to
nlaroche on DSK30NT082PROD with NOTICES




                                               intervene and comments using the                         Combined Notice of Filings #2                          protest in any of the above proceedings
                                               Commission’s eFiling system at http://                                                                          must file in accordance with Rules 211
                                               www.ferc.gov/docs-filing/efiling.asp.                       Take notice that the Commission                     and 214 of the Commission’s
                                               Commenters can submit brief comments                     received the following electric corporate              Regulations (18 CFR 385.211 and
                                               up to 6,000 characters, without prior                    filings:                                               385.214) on or before 5:00 p.m. Eastern
                                                                                                           Docket Numbers: EC17–100–000.                       time on the specified comment date.
                                                 1 18   CFR 385.2001–2005 (2016).                          Applicants: Invenergy TN LLC.                       Protests may be considered, but


                                          VerDate Sep<11>2014    14:52 Apr 06, 2017   Jkt 241001   PO 00000   Frm 00016   Fmt 4703   Sfmt 4703   E:\FR\FM\07APN1.SGM   07APN1



Document Created: 2017-04-06 23:49:21
Document Modified: 2017-04-06 23:49:21
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 17003 

2025 Federal Register | Disclaimer | Privacy Policy