Page Range | 22280-22280 | |
FR Document | 2017-09724 |
[Federal Register Volume 82, Number 92 (Monday, May 15, 2017)] [Rules and Regulations] [Page 22280] From the Federal Register Online [www.thefederalregister.org] [FR Doc No: 2017-09724] ======================================================================= ----------------------------------------------------------------------- DEPARTMENT OF HOMELAND SECURITY Coast Guard 33 CFR Part 117 [Docket No. USCG-2017-0395] Drawbridge Operation Regulation; Willamette River at Portland, OR AGENCY: Coast Guard, DHS. ACTION: Notice of deviation from drawbridge regulation. ----------------------------------------------------------------------- SUMMARY: The Coast Guard has issued a temporary deviation from the operating schedule that governs the Burnside Bridge across the Willamette River, mile 12.4, at Portland, OR. This deviation is necessary to accommodate the annual Rose Festival Grand Floral Parade event. The deviation allows the bridge to remain in the closed-to- navigation position to allow safe roadway movement of event participants. DATES: This deviation is effective from 7 a.m. to 2 p.m. on June 10, 2017. ADDRESSES: The docket for this deviation, USCG-2017-00395 is available at http://www.regulations.gov. Type the docket number in the ``SEARCH'' box and click ``SEARCH.'' Click on Open Docket Folder on the line associated with this deviation. FOR FURTHER INFORMATION CONTACT: If you have questions on this temporary deviation, call or email Mr. Steven Fischer, Bridge Administrator, Thirteenth Coast Guard District; telephone 206-220-7282, email [email protected]. SUPPLEMENTARY INFORMATION: Multnomah County owns the Burnside Bridge, crossing the Willamette River, mile 12.4, at Portland, OR, and has requested a temporary deviation from the operating schedule. The requested deviation is to accommodate the Rose Festival Grand Floral Parade event. To facilitate this event, the draw of this bridge will be allowed to be kept in the closed-to-navigation position to marine traffic from 7 a.m. to 2 p.m. on June 10, 2017. The Burnside Bridge provides a vertical clearance of 41 feet in the closed-to-navigation position referenced to Columbia River Datum 0.0. The normal operating schedule is in 33 CFR 117.897. Waterway usage on this part of the Willamette River includes vessels ranging from commercial tug and barge to small pleasure craft. The Coast Guard contacted all known users of the Willamette River for comment, and we received no objections for this deviation. Vessels able to pass through the bridge in the closed-to-navigation position may do so at any time. The bridge will be able to open for emergencies, and there is no immediate alternate route for vessels to pass. The Coast Guard will inform the users of the waterway, through our Local and Broadcast Notices to Mariners, of the change in operating schedule for the bridges so that vessels can arrange their transits to minimize any impact caused by the temporary deviation. In accordance with 33 CFR 117.35(e), the drawbridge must return to its regular operating schedules immediately at the end of the effective period of this temporary deviation. This deviation from the operating regulations is authorized under 33 CFR 117.35. Dated: May 10, 2017. Steven M. Fischer, Bridge Administrator, Thirteenth Coast Guard District. [FR Doc. 2017-09724 Filed 5-12-17; 8:45 am] BILLING CODE 9110-04-P
Category | Regulatory Information | |
Collection | Federal Register | |
sudoc Class | AE 2.7: GS 4.107: AE 2.106: | |
Publisher | Office of the Federal Register, National Archives and Records Administration | |
Section | Rules and Regulations | |
Action | Notice of deviation from drawbridge regulation. | |
Dates | This deviation is effective from 7 a.m. to 2 p.m. on June 10, 2017. | |
Contact | If you have questions on this temporary deviation, call or email Mr. Steven Fischer, Bridge Administrator, Thirteenth Coast Guard District; telephone 206-220-7282, email [email protected] | |
FR Citation | 82 FR 22280 |