82_FR_22630 82 FR 22537 - DTE Midstream Appalachia, LLC; Notice of Application for Certificate of Public Convenience and Necessity

82 FR 22537 - DTE Midstream Appalachia, LLC; Notice of Application for Certificate of Public Convenience and Necessity

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 93 (May 16, 2017)

Page Range22537-22538
FR Document2017-09805

Federal Register, Volume 82 Issue 93 (Tuesday, May 16, 2017)
[Federal Register Volume 82, Number 93 (Tuesday, May 16, 2017)]
[Notices]
[Pages 22537-22538]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-09805]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-409-000; PF17-1-000]


DTE Midstream Appalachia, LLC; Notice of Application for 
Certificate of Public Convenience and Necessity

    Take notice that on May 1, 2017, DTE Midstream Appalachia, LLC (DTE 
Midstream), 333 Technology Drive, Suite 255, Canonsburg, Pennsylvania 
15317, filed with the Federal Energy Regulatory Commission an 
abbreviated application under Section 7 of the Natural Gas Act 
requesting a Certificate of Public Convenience and Necessity 
authorizing DTE Midstream to construct, install, own, operate and 
maintain a new interstate natural gas pipeline known as the Birdsboro 
Pipeline Project. DTE Midstream requests issuance of blanket 
certificates Pursuant to Part 284, Subpart G and Part 157, Subpart F of 
the Commission's regulations.
    The project will have an initial design capacity of 79,000 
Dekatherms per day (Dth/d) and will transport natural gas from a single 
receipt point at an interconnection with a Texas Eastern Transmission 
LP (Texas Eastern) interstate pipeline to a single delivery point at a 
new gas-fired generating facility (Birdsboro Facility), all in Berks 
County, Pennsylvania. DTE Midstream proposes initial recourse rates and 
requests approval of its pro forma Tariff as well as approval of 
certain non-conforming terms in the proposed negotiated rate agreement, 
all as more fully set forth in the application which is on file with 
the Commission and open to public inspection.
    The filing may also be viewed on the Web at http://www.ferc.gov 
using the ``e-Library'' link. Enter the docket number excluding the 
last three digits in the docket number field to access the document. 
For assistance, please contact FERC Online Support at

[[Page 22538]]

[email protected] or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Questions regarding this application may be directed to Kenneth 
Magyar, DTE Midstream Appalachia, LLC, 333 Technology Drive, Suite 255, 
Canonsburg, PA 15317; Phone: (724) 416-7263.
    Specifically, DTE Midstream proposes 13.19 miles of 12-inch 
diameter pipeline; installation of a new pig receiver at the Birdsboro 
Facility; installation of one new meter site adjacent to the Texas 
Eastern right-of-way, one new pig launcher at the Texas Eastern 
interconnect; two new taps on the Texas Eastern pipeline; and four 
valves along the pipeline route spaced to meet the requirements of the 
U.S. Department of Transportation's Pipeline and Hazardous Materials 
Safety Administration. DTE Midstream requests Commission issue the 
requested authorizations by December 15, 2017, in order to meet the 
June 30, 2018, proposed in-service date. The total cost of the Project 
is estimated to be approximately $47,276,982.
    On October 28, 2016, the Commission granted DTE Midstream's request 
to utilize the Commission's Pre-Filing Process and assigned Docket 
Number PF17-1-000 to staff activities involved in the above referenced 
project. Now, as of the filing of the May 1, 2017 application, the Pre-
Filing Process for this project has ended. From this time forward, this 
proceeding will be conducted in Docket No. CP17-409-000, as noted in 
the caption of this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the eFiling link at 
http://www.ferc.gov. Persons unable to file electronically should 
submit original and five copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on May 30, 2017.

    Dated: May 9, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-09805 Filed 5-15-17; 8:45 am]
BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 82, No. 93 / Tuesday, May 16, 2017 / Notices                                                   22537

                                                additional source of natural gas to                     this project. First, any person wishing to            Persons unable to file electronically
                                                eastern North Dakota and western                        obtain legal status by becoming a party               should submit an original and 7 copies
                                                Minnesota and enhance system                            to the proceedings for this project                   of the protest or intervention to the
                                                reliability for existing and new                        should, on or before the comment date                 Federal Energy Regulatory Commission,
                                                customers, all as more fully set forth in               stated below, file with the Federal                   888 First Street NE., Washington, DC
                                                the application. The filing is available                Energy Regulatory Commission, 888                     20426.
                                                for review at the Commission in the                     First Street NE., Washington, DC 20426,                 Comment Date: 5:00 p.m. Eastern
                                                Public Reference Room or may be                         a motion to intervene in accordance                   Time on May 30, 2017.
                                                viewed on the Commission’s Web site at                  with the requirements of the                            Dated: May 9, 2017.
                                                http://www.ferc.gov using the eLibrary                  Commission’s Rules of Practice and
                                                                                                                                                              Kimberly D. Bose,
                                                link. Enter the docket number excluding                 Procedure (18 CFR 385.214 or 385.211)
                                                the last three digits in the docket                     and the Regulations under the NGA (18                 Secretary.
                                                number field to access the document.                    CFR 157.10). A person obtaining party                 [FR Doc. 2017–09804 Filed 5–15–17; 8:45 am]
                                                There is an ‘‘eSubscription’’ link on the               status will be placed on the service list             BILLING CODE 6717–01–P
                                                Web site that enables subscribers to                    maintained by the Secretary of the
                                                receive email notification when a                       Commission and will receive copies of
                                                document is added to a subscribed                       all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                                docket(s). For assistance, please contact               by all other parties. A party must submit
                                                                                                                                                              Federal Energy Regulatory
                                                FERC Online Support at                                  7 copies of filings made with the
                                                                                                                                                              Commission
                                                FERCOnlineSupport@ferc.gov or toll                      Commission and must mail a copy to
                                                free at (866) 208–3676, or for TTY,                     the applicant and to every other party in             [Docket No. CP17–409–000; PF17–1–000]
                                                contact (202) 502–8659.                                 the proceeding. Only parties to the
                                                   Any questions regarding the proposed                 proceeding can ask for court review of                DTE Midstream Appalachia, LLC;
                                                project should be directed to Lori                      Commission orders in the proceeding.                  Notice of Application for Certificate of
                                                Myerchin, Manager, Regulatory Affairs,                     However, a person does not have to                 Public Convenience and Necessity
                                                WBI Energy Transmission, Inc., 1250                     intervene in order to have comments
                                                                                                                                                                 Take notice that on May 1, 2017, DTE
                                                West Century Avenue, Bismarck, North                    considered. The second way to
                                                                                                                                                              Midstream Appalachia, LLC (DTE
                                                Dakota 58503, or at (701) 530–1563, or                  participate is by filing with the
                                                                                                        Secretary of the Commission, as soon as               Midstream), 333 Technology Drive,
                                                lori.myerchin@wbienergy.com.
                                                   On October 17, 2016, the Commission                  possible, an original and two copies of               Suite 255, Canonsburg, Pennsylvania
                                                staff granted WBI Energy’s request to                   comments in support of or in opposition               15317, filed with the Federal Energy
                                                utilize the National Environmental                      to this project. The Commission will                  Regulatory Commission an abbreviated
                                                Policy Act (NEPA) Pre-Filing Process                    consider these comments in                            application under Section 7 of the
                                                and assigned Docket No. PF16–10–000                     determining the appropriate action to be              Natural Gas Act requesting a Certificate
                                                to staff activities involving the project.              taken, but the filing of a comment alone              of Public Convenience and Necessity
                                                Now, as of the filing of this application               will not serve to make the filer a party              authorizing DTE Midstream to
                                                on April 26, 2017, the NEPA Pre-Filing                  to the proceeding. The Commission’s                   construct, install, own, operate and
                                                Process for this project has ended. From                rules require that persons filing                     maintain a new interstate natural gas
                                                this time forward, this proceeding will                 comments in opposition to the project                 pipeline known as the Birdsboro
                                                be conducted in Docket No. CP17–257–                    provide copies of their protests only to              Pipeline Project. DTE Midstream
                                                000, as noted in the caption of this                    the party or parties directly involved in             requests issuance of blanket certificates
                                                Notice.                                                 the protest.                                          Pursuant to Part 284, Subpart G and Part
                                                   Pursuant to section 157.9 of the                        Persons who wish to comment only                   157, Subpart F of the Commission’s
                                                Commission’s rules (18 CFR 157.9),                      on the environmental review of this                   regulations.
                                                within 90 days of this Notice, the                      project should submit an original and                    The project will have an initial design
                                                Commission staff will either: Complete                  two copies of their comments to the                   capacity of 79,000 Dekatherms per day
                                                its environmental impact statement                      Secretary of the Commission.                          (Dth/d) and will transport natural gas
                                                (EIS) and place it into the Commission’s                Environmental commentors will be                      from a single receipt point at an
                                                public record (eLibrary) for this                       placed on the Commission’s                            interconnection with a Texas Eastern
                                                proceeding; or issue a Notice of                        environmental mailing list, will receive              Transmission LP (Texas Eastern)
                                                Schedule for Environmental Review. If                   copies of the environmental documents,                interstate pipeline to a single delivery
                                                a Notice of Schedule for Environmental                  and will be notified of meetings                      point at a new gas-fired generating
                                                Review is issued, it will indicate, among               associated with the Commission’s                      facility (Birdsboro Facility), all in Berks
                                                other milestones, the anticipated date                  environmental review process.                         County, Pennsylvania. DTE Midstream
                                                for the Commission staff’s issuance of                  Environmental commentors will not be                  proposes initial recourse rates and
                                                the EIS for this proposal. The filing of                required to serve copies of filed                     requests approval of its pro forma Tariff
                                                the EIS in the Commission’s public                      documents on all other parties.                       as well as approval of certain non-
                                                record for this proceeding or the                       However, the non-party commentors                     conforming terms in the proposed
                                                issuance of a Notice of Schedule for                    will not receive copies of all documents              negotiated rate agreement, all as more
                                                Environmental Review will serve to                      filed by other parties or issued by the               fully set forth in the application which
                                                notify federal and state agencies of the                Commission (except for the mailing of                 is on file with the Commission and open
                                                                                                                                                              to public inspection.
sradovich on DSK3GMQ082PROD with NOTICES




                                                timing for the completion of all                        environmental documents issued by the
                                                necessary reviews, and the subsequent                   Commission) and will not have the right                  The filing may also be viewed on the
                                                need to complete all federal                            to seek court review of the                           Web at http://www.ferc.gov using the
                                                authorizations within 90 days of the                    Commission’s final order.                             ‘‘e-Library’’ link. Enter the docket
                                                date of issuance of the Commission                         The Commission strongly encourages                 number excluding the last three digits in
                                                staff’s EIS.                                            electronic filings of comments, protests              the docket number field to access the
                                                   There are two ways to become                         and interventions in lieu of paper using              document. For assistance, please contact
                                                involved in the Commission’s review of                  the eFiling link at http://www.ferc.gov.              FERC Online Support at


                                           VerDate Sep<11>2014   16:42 May 15, 2017   Jkt 241001   PO 00000   Frm 00061   Fmt 4703   Sfmt 4703   E:\FR\FM\16MYN1.SGM   16MYN1


                                                22538                          Federal Register / Vol. 82, No. 93 / Tuesday, May 16, 2017 / Notices

                                                FERCOnlineSupport@ferc.gov or toll                      obtain legal status by becoming a party               should submit original and five copies
                                                free at (866) 208–3676, or TTY, contact                 to the proceedings for this project                   of the protest or intervention to the
                                                (202) 502–8659.                                         should, on or before the comment date                 Federal Energy Regulatory Commission,
                                                   Questions regarding this application                 stated below, file with the Federal                   888 First Street NE., Washington, DC
                                                may be directed to Kenneth Magyar,                      Energy Regulatory Commission, 888                     20426.
                                                DTE Midstream Appalachia, LLC, 333                      First Street NE., Washington, DC 20426,                 Comment Date: 5:00 p.m. Eastern
                                                Technology Drive, Suite 255,                            a motion to intervene in accordance                   Time on May 30, 2017.
                                                Canonsburg, PA 15317; Phone: (724)                      with the requirements of the
                                                                                                                                                                Dated: May 9, 2017.
                                                416–7263.                                               Commission’s Rules of Practice and
                                                   Specifically, DTE Midstream proposes                                                                       Kimberly D. Bose,
                                                                                                        Procedure (18 CFR 385.214 or 385.211)
                                                13.19 miles of 12-inch diameter                         and the Regulations under the NGA (18                 Secretary.
                                                pipeline; installation of a new pig                     CFR 157.10). A person obtaining party                 [FR Doc. 2017–09805 Filed 5–15–17; 8:45 am]
                                                receiver at the Birdsboro Facility;                     status will be placed on the service list             BILLING CODE 6717–01–P
                                                installation of one new meter site                      maintained by the Secretary of the
                                                adjacent to the Texas Eastern right-of-                 Commission and will receive copies of
                                                way, one new pig launcher at the Texas                  all documents filed by the applicant and              DEPARTMENT OF ENERGY
                                                Eastern interconnect; two new taps on                   by all other parties. A party must submit
                                                the Texas Eastern pipeline; and four                    five copies of filings made with the                  Federal Energy Regulatory
                                                valves along the pipeline route spaced                  Commission and must mail a copy to                    Commission
                                                to meet the requirements of the U.S.                    the applicant and to every other party in
                                                Department of Transportation’s Pipeline                 the proceeding. Only parties to the                   [Project No. 14792–000]
                                                and Hazardous Materials Safety                          proceeding can ask for court review of
                                                Administration. DTE Midstream                           Commission orders in the proceeding.                  Maysville Pumped Storage, LLC;
                                                requests Commission issue the                              However, a person does not have to                 Notice of Preliminary Permit
                                                requested authorizations by December                    intervene in order to have comments                   Application Accepted for Filing and
                                                15, 2017, in order to meet the June 30,                 considered. The second way to                         Soliciting Comments, Motions To
                                                2018, proposed in-service date. The                     participate is by filing with the                     Intervene, and Competing Applications
                                                total cost of the Project is estimated to               Secretary of the Commission, as soon as
                                                be approximately $47,276,982.                                                                                    On July 1, 2016, Maysville Pumped
                                                                                                        possible, an original and two copies of
                                                   On October 28, 2016, the Commission                                                                        Storage, LLC filed an application for a
                                                                                                        comments in support of or in opposition
                                                granted DTE Midstream’s request to                                                                            preliminary permit, pursuant to section
                                                                                                        to this project. The Commission will
                                                utilize the Commission’s Pre-Filing                                                                           4(f) of the Federal Power Act (FPA),
                                                                                                        consider these comments in
                                                Process and assigned Docket Number                                                                            proposing to study the feasibility of a
                                                                                                        determining the appropriate action to be
                                                PF17–1–000 to staff activities involved                                                                       hydropower project located on the Ohio
                                                                                                        taken, but the filing of a comment alone
                                                in the above referenced project. Now, as                                                                      River in Mason County, Kentucky. The
                                                                                                        will not serve to make the filer a party
                                                of the filing of the May 1, 2017                        to the proceeding. The Commission’s                   sole purpose of a preliminary permit, if
                                                application, the Pre-Filing Process for                 rules require that persons filing                     issued, is to grant the permit holder
                                                this project has ended. From this time                  comments in opposition to the project                 priority to file a license application
                                                forward, this proceeding will be                        provide copies of their protests only to              during the permit term. A preliminary
                                                conducted in Docket No. CP17–409–                       the party or parties directly involved in             permit does not authorize the permit
                                                000, as noted in the caption of this                    the protest.                                          holder to perform any land-disturbing
                                                Notice.                                                    Persons who wish to comment only                   activities or otherwise enter upon lands
                                                   Pursuant to section 157.9 of the                     on the environmental review of this                   or waters owned by others without the
                                                Commission’s rules, 18 CFR 157.9,                       project should submit an original and                 owners’ express permission.
                                                within 90 days of this Notice the                       two copies of their comments to the                      The proposed project would be
                                                Commission staff will either: Complete                  Secretary of the Commission.                          developed in three phases. In the final
                                                its environmental assessment (EA) and                   Environmental commentors will be                      phase the following project would
                                                place it into the Commission’s public                   placed on the Commission’s                            consist of: (1) A 15-foot-high, 40-foot-
                                                record (eLibrary) for this proceeding; or               environmental mailing list, will receive              long concrete intake structure on the
                                                issue a Notice of Schedule for                          copies of the environmental documents,                Ohio River; (2) two 10-foot-diameter,
                                                Environmental Review. If a Notice of                    and will be notified of meetings                      1,050-foot-long steel pipes to supply
                                                Schedule for Environmental Review is                    associated with the Commission’s                      water to the project; (3) a 135-foot-high,
                                                issued, it will indicate, among other                   environmental review process.                         500-foot-long earth fill or roller-
                                                milestones, the anticipated date for the                Environmental commentors will not be                  compacted, concrete embankment dam
                                                Commission staff’s issuance of the EA                   required to serve copies of filed                     surrounding; (4) an upper reservoir with
                                                for this proposal. The filing of the EA                 documents on all other parties.                       a surface area of 20 acres and a storage
                                                in the Commission’s public record for                   However, the non-party commentors                     capacity of 875 acre-feet; (5) five 12.5-
                                                this proceeding or the issuance of a                    will not receive copies of all documents              foot to 18 foot-diameter, 2,800-foot-long
                                                Notice of Schedule for Environmental                    filed by other parties or issued by the               penstocks; (6) a powerhouse 100-feet-
                                                Review will serve to notify federal and                 Commission (except for the mailing of                 below the lower reservoir containing
                                                state agencies of the timing for the                    environmental documents issued by the                 five pump/generating units with a total
                                                                                                                                                              capacity of 500 megawatts; (7) a lower
sradovich on DSK3GMQ082PROD with NOTICES




                                                completion of all necessary reviews, and                Commission) and will not have the right
                                                the subsequent need to complete all                     to seek court review of the                           reservoir established within an existing
                                                federal authorizations within 90 days of                Commission’s final order.                             underground mine space with a surface
                                                the date of issuance of the Commission                     The Commission strongly encourages                 area of 212 acres and a storage capacity
                                                staff’s EA.                                             electronic filings of comments, protests              of 9,540 acre-feet; and (8) a 10,500-foot-
                                                   There are two ways to become                         and interventions in lieu of paper using              long, 230 kilo-volt transmission line to
                                                involved in the Commission’s review of                  the eFiling link at http://www.ferc.gov.              a point of interconnection with the PJM
                                                this project. First, any person wishing to              Persons unable to file electronically                 system. The project would have an


                                           VerDate Sep<11>2014   16:42 May 15, 2017   Jkt 241001   PO 00000   Frm 00062   Fmt 4703   Sfmt 4703   E:\FR\FM\16MYN1.SGM   16MYN1



Document Created: 2017-05-16 13:52:14
Document Modified: 2017-05-16 13:52:14
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on May 30, 2017.
FR Citation82 FR 22537 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR