82_FR_2353 82 FR 2348 - Notice of Availability of the Draft Environmental Impact Statement for the Proposed Atlantic Coast Pipeline, Supply Header Project, and Capacity Lease Proposal

82 FR 2348 - Notice of Availability of the Draft Environmental Impact Statement for the Proposed Atlantic Coast Pipeline, Supply Header Project, and Capacity Lease Proposal

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 5 (January 9, 2017)

Page Range2348-2350
FR Document2017-00068

Federal Register, Volume 82 Issue 5 (Monday, January 9, 2017)
[Federal Register Volume 82, Number 5 (Monday, January 9, 2017)]
[Notices]
[Pages 2348-2350]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-00068]



[[Page 2348]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission


Notice of Availability of the Draft Environmental Impact 
Statement for the Proposed Atlantic Coast Pipeline, Supply Header 
Project, and Capacity Lease Proposal

------------------------------------------------------------------------
                                                   Docket Nos.
------------------------------------------------------------------------
Atlantic Coast Pipeline, LLC...........  CP15-554-000, CP15-554-001
Dominion Transmission, Inc.............  CP15-555-000
Piedmont Natural Gas Company, Inc......  CP15-556-000
------------------------------------------------------------------------

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared a draft environmental impact statement (EIS) 
for the Atlantic Coast Pipeline (ACP) and Supply Header Project (SHP) 
as proposed by Atlantic Coast Pipeline, LLC (Atlantic) and Dominion 
Transmission, Inc. (DTI), respectively, in the above-referenced 
dockets. Atlantic and DTI request authorization to construct and 
operate a total of 641.3 miles of natural gas transmission pipeline and 
associated facilities, and three new natural gas-fired compressor 
stations, and to modify four existing compressor stations. The projects 
would provide about 1.44 billion cubic feet per day of natural gas to 
electric generation, distribution, and end use markets in Virginia and 
North Carolina. In addition, Atlantic and Piedmont Natural Gas Co., 
Inc. (Piedmont) request authorization to allow Atlantic to lease 
capacity on Piedmont's existing pipeline distribution system in North 
Carolina for use by Atlantic (Capacity Lease Proposal). No construction 
or facility modifications are proposed with the Capacity Lease 
Proposal.
    The draft EIS assesses the potential environmental effects of the 
construction and operation of the projects in accordance with the 
requirements of the National Environmental Policy Act (NEPA). The FERC 
staff concludes that approval of the projects would have some adverse 
and significant environmental impacts; however, the majority of impacts 
would be reduced to less-than-significant levels with the 
implementation of the Atlantic's and DTI's proposed mitigation and the 
additional measures recommended in the draft EIS.
    The U.S. Department of Agriculture--Forest Service (FS); U.S. Army 
Corps of Engineers; U.S. Environmental Protection Agency; U.S. Fish and 
Wildlife Service--Great Dismal Swamp National Wildlife Refuge; West 
Virginia Department of Environmental Protection; and West Virginia 
Division of Natural Resources participated as cooperating agencies in 
the preparation of the draft EIS. Cooperating agencies have 
jurisdiction by law or special expertise with respect to resources 
potentially affected by the proposals and participate in the NEPA 
analysis. Further, the FS may use the EIS when it considers amendments 
to Land and Resource Management Plans (LRMPs) for the proposed 
crossings of the Monongahela National Forest (MNF) and George 
Washington National Forest (GWNF). Although the cooperating agencies 
provide input to the conclusions and recommendations presented in the 
draft EIS, each agency will present its own conclusions and 
recommendations in its respective record of decision or determination 
for the projects.
    The draft EIS addresses the potential environmental effects of the 
construction and operation of the following proposed project 
facilities:
    The ACP includes:
     519.1 miles of new 42- and 36-inch-diameter natural gas 
pipeline in West Virginia, Virginia, and North Carolina;
     84.6 miles of 20- and 16-inch-diameter natural gas 
pipeline in Virginia and North Carolina;
     three new compressor station in Lewis County, West 
Virginia; Buckingham County, Virginia; and Northampton County, North 
Carolina; and
     nine meter stations, along with pig launchers/receivers 
and mainline valves.
    The SHP includes:
     37.5 miles of new 36-inch-diameter natural gas pipeline in 
Pennsylvania and West Virginia;
     modifications at four existing compressor stations in 
Westmoreland and Green Counties Pennsylvania and Marshall and Wetzel 
Counties West Virginia;
     abandonment of existing compressor units and associated 
facilities in Wetzel County, West Virginia; and
     one meter station, along with pig launchers/receivers and 
mainline valves.

Actions of the Forest Service

    The FS's purpose and need for the proposed action is to respond to 
a special use application submitted by Atlantic on November 12, 2015, 
to allow the construction and operation of the ACP on national forest 
system (NFS) lands managed by the MNF and the GWNF. If the FS decides 
to authorize the pipeline crossing of NFS lands and issue a special use 
permit, the FS has determined that amendments to each national forest 
LRMP would be needed.
    Project-specific plan amendments would be needed to deviate from 
the precise wording of forest plan standards for the construction and 
operation of the ACP. These amendments are considered ``project-
specific'' amendments because they would not change FS requirements for 
other projects or authorize any other actions. Additionally, if the 
proposed route is authorized and a special use permit issued, the GWNF 
LRMP would need to be amended to change the current management 
prescriptions in the pipeline's operational corridor to Management 
Prescription Area (Rx) 5C-Designated Utility Corridors. The MNF does 
not have LRMP direction that would require a similar plan amendment to 
reallocate management prescriptions. Therefore, this amendment is 
considered a ``plan-level'' amendment and would change future 
management direction for the lands reallocated to the new management 
prescription. The FS has also identified other potential amendments 
that may be required, pending survey information and analyses that are 
not currently available.
    Pursuant to Title 40 of the Code of Federal Regulations, Part 
1506.3(c) (40 CFR 1506.3(c)), the FS may adopt and use the EIS 
developed by FERC to consider authorization for the construction and 
operation of the ACP crossing NFS lands. Further, the FS may use this 
EIS when it considers amendments to the LRMPs that would be required 
for the proposed crossings of the MNF and GWNF. The FS will prepare 
separate Records of Decision for the authorization decision and for the 
plan amendments decisions, after issuance of the FERC final EIS.
    The following amendments have been proposed by the FS as part of 
the proposed action in the FERC draft EIS:

Monongahela National Forest

    The type of amendment applicable to the MNF would be a project-
specific amendment. This amendment would not change FS requirements for 
other projects or authorize any other actions.
    Potential Amendment 1: The MNF LRMP may need to be amended to allow 
construction of the ACP to temporarily exceed standards identified 
under management direction for soils and water, specifically forest-
wide standards SW06 and SW07, provided that design criteria, mitigation 
measures, project requirements, and/or monitoring activities agreed 
upon by the FS are

[[Page 2349]]

implemented as needed to achieve adequate slope and soil stability.
    Other potential amendments may be needed pending the outcome of 
ongoing analyses and development of project design and mitigation.

George Washington National Forest

    The first type of LRMP amendment applicable to the GWNF would be a 
plan-level amendment that would change land allocations. This would 
change future management direction for the lands reallocated to the new 
Rx and is required by LRMP Standards FW-243 and FW-244.
    Proposed Amendment 1: The LRMP would be amended to reallocate 102.3 
acres to the Rx 5C-Designated Utility Corridors from these Rxs: 7E1-
Dispersed Recreation Areas (7 acres), and 13-Mosaics of Habitat (95 
acres). Rx 11-Riparian Corridors would remain embedded within the new 
Rx 5C area.
    Rx 5C-Designated Utility Corridors contains special uses which 
serve a public benefit by providing a reliable supply of electricity, 
natural gas, or water essential to local, regional, and national 
economies. The new Rx 5C land allocation would be 53.5 feet wide, the 
width of the final operational right-of-way of the ACP. The area would 
not cross into the Rx 4A-Appalachian National Scenic Area but would 
stop and start at the existing Rx 4A boundary. The Rx4A would continue 
to be managed for the Appalachian National Scenic Trail.
    The second type of amendment applicable to the GWNF would be a 
project-specific amendment that would apply only to the construction 
and operation of the ACP. The following standards would require a 
temporary waiver to allow the project to proceed. These amendments 
would not change LRMP requirements for other projects or authorize any 
other actions.
    Proposed Amendment 2: The LRMP would be amended to allow 
construction of the ACP to exceed restrictions on soil conditions and 
riparian corridor conditions as described in LRMP Standards FW-5, FW-
15, FW-16, FW-17, and 11-019, provided that mitigation measures or 
project requirements agreed upon by the FS are implemented as needed.
    Proposed Amendment 3: The LRMP would be amended to allow the ACP to 
cross the Appalachian National Scenic Trail in Augusta County, Virginia 
(reference LRMP Standard 4A-025).
    Potential Amendment 4: The LRMP may need to be amended to allow the 
removal of old growth trees within the construction corridor of ACP 
(reference LRMP Standard FW-85).
    Potential Amendment 5: The LRMP may need to be amended to allow 
major reconstruction of a NFS road within the Rx 2C3 area to provide 
access for pipeline construction. This is contingent on the final 
location of access roads (reference LRMP Standard 2C3-015).
    Potential Amendment 6: The LRMP may need to be amended to allow the 
ACP to not immediately meet Scenic Integrity Objectives; however, 
mitigation measures, including vegetation management and restoration 
actions, are expected to improve visual quality over an extended 
timeframe (reference LRMP Standard FW-182).
    The FS is requesting public comments on the authorization of the 
ACP on NFS lands and the draft proposed and potential amendments of the 
LRMPs that would allow the ACP to cross the MNF and GWNF. All comments 
must be submitted to the FERC as directed in this notice. The FS 
decision to authorize the ACP will be subject to FS predecisional 
administrative review procedures established in 36 CFR 218. The MNF 
Potential Amendment 1, GWNF Proposed Amendments 2 and 3, and Potential 
Amendments 4, 5, and 6 were developed in accordance with 36 CFR 219 
(2012 version) regulations but will be subject to the administrative 
review procedures under 36 CFR 218 regulations Subparts A and B, per 36 
CFR 219.59(b). GWNF Proposed Amendment 1 was developed in accordance to 
36 CFR 219 (2012) regulations and will be subject to the administrative 
review procedures under 36 CFR 219 Subpart B. Refer to the applicable 
administrative review regulations for eligibility requirements.
    All comments must be submitted to the FERC, the lead federal 
agency, within the timeframe stated in this Notice of Availability. 
Refer to Docket No. CP15-554-000 (ACP) in all correspondence to ensure 
that your comments are correctly filed in the record. You may submit 
your comments to the FERC using one of the four methods listed below.

Distribution and Comments on the Draft Environmental Impact Statement

    The FERC staff mailed copies of the draft EIS to federal, state, 
and local government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; newspapers and libraries in the project areas; and parties to 
this proceeding. Paper copy versions of this draft EIS were mailed to 
those specifically requesting them; all others received a CD version. 
In addition, the draft EIS is available for public viewing on the 
FERC's Web site (www.ferc.gov) using the eLibrary link. A limited 
number of copies of the draft EIS are available for distribution and 
public inspection at:

Federal Energy Regulatory Commission, Public Reference Room, 888 First 
Street NE., Room 2A, Washington, DC 20426, (202) 502-8371.

    Any person wishing to comment on the draft EIS may do so. To ensure 
consideration of your comments on the proposals in the final EIS, it is 
important that the Commission receive your comments by April 6, 2017.
    For your convenience, there are four methods you can use to submit 
your comments to the Commission. In all instances, please reference the 
appropriate docket numbers (CP15-554-000 and CP15-554-001 for ACP; 
CP15-555-000 for SHP; or CP15-556-000 for Capacity Lease) with your 
submission. The Commission encourages electronic filing of comments and 
has expert staff available to assist you at (202) 502-8258 or 
[email protected]. Please carefully follow these instructions so that 
your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project.
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
``eRegister.'' If you are filing a comment on a particular project, 
please select ``Comment on a Filing'' as the filing type.
    (3) You can file a paper copy of your comments by mailing them to 
the following address:

Nathaniel J. Davis, Sr., Deputy Secretary, Federal Energy Regulatory 
Commission, 888 First Street NE., Room 1A, Washington, DC 20426.

    (4) In lieu of sending written or electronic comments, the 
Commission invites you to attend one of the public comment sessions its 
staff will conduct in the project area to receive comments on the draft 
EIS. We encourage interested groups and individuals to attend and 
present oral comments on

[[Page 2350]]

the draft EIS. The sessions are scheduled as follows:

------------------------------------------------------------------------
        Date and time                           Location
------------------------------------------------------------------------
Monday, February 13, 2017,     Doubletree Hotel, 1965 Cedar Creek Road,
 5:00-9:00 p.m.                 Fayetteville, NC 28312.
Tuesday, February 14, 2017,    Forest Hills Middle School, 1210 Forest
 5:00-9:00 p.m.                 Hills Road, Wilson, NC 27893.
Wednesday, February 15, 2017,  Hilton Garden Inn Roanoke Rapids, 111
 5:00-9:00 p.m.                 Carolina Crossroads Parkway, Roanoke
                                Rapids, NC 27870.
Thursday, February 16, 2017,   Hilton Garden Inn Conference Center, 100
 5:30-9:30 p.m.                 East Constance Road, Suffolk, VA 23434.
Tuesday, February 21, 2017,    Moton Museum, 900 Griffin Boulevard,
 5:00-9:00 p.m.                 Farmville, VA 23901.
Wednesday, February 22, 2017,  Nelson County High School, 6919 Thomas
 5:00-9:00 p.m.                 Nelson Highway, Route 29, Lovingston, VA
                                22949.
Thursday, February 23, 2017,   Holiday Inn Hotel and Conference, 152
 5:00-9:00 p.m.                 Fairway Lane, Staunton, VA 24401.
Tuesday, February 28, 2017,    Highland Center, 61 Highland Center
 5:00-9:00 p.m.                 Drive, Monterey, VA 24465.
Wednesday, March 1, 2017,      Gandy Dance Theater, 359 Beverly Pike,
 5:00-9:00 p.m.                 Elkins, WV 26241.
Thursday, March 2, 2017, 5:00- Marlinton Community Wellness Center, 320
 9:00 p.m.                      9th Street, Marlinton, WV 24954.
------------------------------------------------------------------------

    There will not be a formal presentation by Commission staff at any 
of the ten public comment sessions, although a format outline handout 
will be made available. All sessions will begin at 5:00 p.m., with the 
exception of the session on Thursday, February 16, 2017, which will 
begin at 5:30 p.m. If you wish to provide verbal comments, the 
Commission staff will hand out numbers in the order of your arrival. 
Number distribution will be discontinued at 8:00 p.m. in order to 
ensure all comments are received by the session closing time. Comments 
will be taken until 9:00 p.m. (or 9:30 p.m. at the February 16 
session). However, if no additional numbers have been handed out and 
all individuals who wish to provide comments have had an opportunity to 
do so, staff may conclude the session at 8:00 p.m., or after the last 
comment is taken.
    The primary goal of the public sessions is to allow individuals to 
provide verbal comments on the draft EIS. Individual verbal comments 
will be taken on a one-on-one basis with a Court Reporter (with FERC 
staff or representative present), called up in the order of the numbers 
received. Because we anticipate considerable interest from concerned 
citizens, this format is designed to receive the maximum amount of 
verbal comments, in a convenient way during the timeframe allotted. If 
many people are interested in providing verbal comments in the one-on-
one setting at any particular session, a time limit of 3 minutes may be 
implemented for each commenter.
    Your verbal comments will be recorded by the Court Reporter. 
Transcripts of all comments from the sessions will be placed into the 
dockets for the projects, which are accessible for public viewing on 
the FERC's Web site (at www.ferc.gov) through our eLibrary system.
    Commission staff will be available at each venue of the public 
sessions to answer questions about our environmental review process. It 
is important to note that written comments mailed to the Commission and 
those submitted electronically are reviewed by staff with the same 
scrutiny and consideration as the verbal comments given at the public 
sessions.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR part 385.214).\1\ Only intervenors have 
the right to seek rehearing of the Commission's decision. The 
Commission grants affected landowners and others with environmental 
concerns intervenor status upon showing good cause by stating that they 
have a clear and direct interest in this proceeding which no other 
party can adequately represent. Simply filing environmental comments 
will not give you intervenor status, but you do not need intervenor 
status to have your comments considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

Questions?

    Additional information about the projects is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on ``General Search,'' and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP15-
554, CP15-555, or CP15-556). Be sure you have selected an appropriate 
date range. For assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676; for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription that allows you to keep track of all formal issuances and 
submittals in specific dockets. This can reduce the amount of time you 
spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp to 
subscribe.

    Dated: December 30, 2016.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00068 Filed 1-6-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                2348                           Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices

                                                DEPARTMENT OF ENERGY                                    Wildlife Service—Great Dismal Swamp                    GWNF. If the FS decides to authorize
                                                                                                        National Wildlife Refuge; West Virginia                the pipeline crossing of NFS lands and
                                                Federal Energy Regulatory                               Department of Environmental                            issue a special use permit, the FS has
                                                Commission                                              Protection; and West Virginia Division                 determined that amendments to each
                                                                                                        of Natural Resources participated as                   national forest LRMP would be needed.
                                                Notice of Availability of the Draft                     cooperating agencies in the preparation                   Project-specific plan amendments
                                                Environmental Impact Statement for                      of the draft EIS. Cooperating agencies                 would be needed to deviate from the
                                                the Proposed Atlantic Coast Pipeline,                   have jurisdiction by law or special                    precise wording of forest plan standards
                                                Supply Header Project, and Capacity                     expertise with respect to resources                    for the construction and operation of the
                                                Lease Proposal                                          potentially affected by the proposals                  ACP. These amendments are considered
                                                                                                        and participate in the NEPA analysis.                  ‘‘project-specific’’ amendments because
                                                                                      Docket Nos.                                                              they would not change FS requirements
                                                                                                        Further, the FS may use the EIS when
                                                Atlantic Coast Pipeline,         CP15–554–000,          it considers amendments to Land and                    for other projects or authorize any other
                                                  LLC.                            CP15–554–             Resource Management Plans (LRMPs)                      actions. Additionally, if the proposed
                                                                                  001                   for the proposed crossings of the                      route is authorized and a special use
                                                Dominion Transmission,           CP15–555–000           Monongahela National Forest (MNF)                      permit issued, the GWNF LRMP would
                                                  Inc.                                                  and George Washington National Forest                  need to be amended to change the
                                                Piedmont Natural Gas             CP15–556–000           (GWNF). Although the cooperating                       current management prescriptions in
                                                  Company, Inc.                                                                                                the pipeline’s operational corridor to
                                                                                                        agencies provide input to the
                                                                                                        conclusions and recommendations                        Management Prescription Area (Rx) 5C-
                                                  The staff of the Federal Energy                                                                              Designated Utility Corridors. The MNF
                                                Regulatory Commission (FERC or                          presented in the draft EIS, each agency
                                                                                                        will present its own conclusions and                   does not have LRMP direction that
                                                Commission) has prepared a draft                                                                               would require a similar plan
                                                environmental impact statement (EIS)                    recommendations in its respective
                                                                                                        record of decision or determination for                amendment to reallocate management
                                                for the Atlantic Coast Pipeline (ACP)                                                                          prescriptions. Therefore, this
                                                and Supply Header Project (SHP) as                      the projects.
                                                                                                           The draft EIS addresses the potential               amendment is considered a ‘‘plan-level’’
                                                proposed by Atlantic Coast Pipeline,                                                                           amendment and would change future
                                                LLC (Atlantic) and Dominion                             environmental effects of the
                                                                                                        construction and operation of the                      management direction for the lands
                                                Transmission, Inc. (DTI), respectively,                                                                        reallocated to the new management
                                                in the above-referenced dockets.                        following proposed project facilities:
                                                                                                           The ACP includes:                                   prescription. The FS has also identified
                                                Atlantic and DTI request authorization
                                                                                                           • 519.1 miles of new 42- and 36-inch-               other potential amendments that may be
                                                to construct and operate a total of 641.3                                                                      required, pending survey information
                                                                                                        diameter natural gas pipeline in West
                                                miles of natural gas transmission                                                                              and analyses that are not currently
                                                                                                        Virginia, Virginia, and North Carolina;
                                                pipeline and associated facilities, and                    • 84.6 miles of 20- and 16-inch-                    available.
                                                three new natural gas-fired compressor                  diameter natural gas pipeline in Virginia                 Pursuant to Title 40 of the Code of
                                                stations, and to modify four existing                   and North Carolina;                                    Federal Regulations, Part 1506.3(c) (40
                                                compressor stations. The projects would                    • three new compressor station in                   CFR 1506.3(c)), the FS may adopt and
                                                provide about 1.44 billion cubic feet per               Lewis County, West Virginia;                           use the EIS developed by FERC to
                                                day of natural gas to electric generation,              Buckingham County, Virginia; and                       consider authorization for the
                                                distribution, and end use markets in                    Northampton County, North Carolina;                    construction and operation of the ACP
                                                Virginia and North Carolina. In                         and                                                    crossing NFS lands. Further, the FS may
                                                addition, Atlantic and Piedmont Natural                    • nine meter stations, along with pig               use this EIS when it considers
                                                Gas Co., Inc. (Piedmont) request                        launchers/receivers and mainline                       amendments to the LRMPs that would
                                                authorization to allow Atlantic to lease                valves.                                                be required for the proposed crossings
                                                capacity on Piedmont’s existing                            The SHP includes:                                   of the MNF and GWNF. The FS will
                                                pipeline distribution system in North                      • 37.5 miles of new 36-inch-diameter                prepare separate Records of Decision for
                                                Carolina for use by Atlantic (Capacity                  natural gas pipeline in Pennsylvania                   the authorization decision and for the
                                                Lease Proposal). No construction or                     and West Virginia;                                     plan amendments decisions, after
                                                facility modifications are proposed with                   • modifications at four existing                    issuance of the FERC final EIS.
                                                the Capacity Lease Proposal.                            compressor stations in Westmoreland                       The following amendments have been
                                                  The draft EIS assesses the potential                  and Green Counties Pennsylvania and                    proposed by the FS as part of the
                                                environmental effects of the                            Marshall and Wetzel Counties West                      proposed action in the FERC draft EIS:
                                                construction and operation of the                       Virginia;
                                                projects in accordance with the                            • abandonment of existing                           Monongahela National Forest
                                                requirements of the National                            compressor units and associated                          The type of amendment applicable to
                                                Environmental Policy Act (NEPA). The                    facilities in Wetzel County, West                      the MNF would be a project-specific
                                                FERC staff concludes that approval of                   Virginia; and                                          amendment. This amendment would
                                                the projects would have some adverse                       • one meter station, along with pig                 not change FS requirements for other
                                                and significant environmental impacts;                  launchers/receivers and mainline                       projects or authorize any other actions.
                                                however, the majority of impacts would                  valves.                                                  Potential Amendment 1: The MNF
                                                be reduced to less-than-significant                                                                            LRMP may need to be amended to allow
                                                                                                        Actions of the Forest Service                          construction of the ACP to temporarily
sradovich on DSK3GMQ082PROD with NOTICES




                                                levels with the implementation of the
                                                Atlantic’s and DTI’s proposed                             The FS’s purpose and need for the                    exceed standards identified under
                                                mitigation and the additional measures                  proposed action is to respond to a                     management direction for soils and
                                                recommended in the draft EIS.                           special use application submitted by                   water, specifically forest-wide standards
                                                  The U.S. Department of Agriculture—                   Atlantic on November 12, 2015, to allow                SW06 and SW07, provided that design
                                                Forest Service (FS); U.S. Army Corps of                 the construction and operation of the                  criteria, mitigation measures, project
                                                Engineers; U.S. Environmental                           ACP on national forest system (NFS)                    requirements, and/or monitoring
                                                Protection Agency; U.S. Fish and                        lands managed by the MNF and the                       activities agreed upon by the FS are


                                           VerDate Sep<11>2014   21:14 Jan 06, 2017   Jkt 241001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\09JAN1.SGM   09JAN1


                                                                               Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices                                                 2349

                                                implemented as needed to achieve                           Potential Amendment 5: The LRMP                     requesting them; all others received a
                                                adequate slope and soil stability.                      may need to be amended to allow major                  CD version. In addition, the draft EIS is
                                                  Other potential amendments may be                     reconstruction of a NFS road within the                available for public viewing on the
                                                needed pending the outcome of ongoing                   Rx 2C3 area to provide access for                      FERC’s Web site (www.ferc.gov) using
                                                analyses and development of project                     pipeline construction. This is                         the eLibrary link. A limited number of
                                                design and mitigation.                                  contingent on the final location of                    copies of the draft EIS are available for
                                                George Washington National Forest                       access roads (reference LRMP Standard                  distribution and public inspection at:
                                                                                                        2C3–015).                                              Federal Energy Regulatory Commission,
                                                   The first type of LRMP amendment                        Potential Amendment 6: The LRMP
                                                applicable to the GWNF would be a                                                                                 Public Reference Room, 888 First
                                                                                                        may need to be amended to allow the                       Street NE., Room 2A, Washington, DC
                                                plan-level amendment that would                         ACP to not immediately meet Scenic
                                                change land allocations. This would                                                                               20426, (202) 502–8371.
                                                                                                        Integrity Objectives; however,
                                                change future management direction for                  mitigation measures, including                            Any person wishing to comment on
                                                the lands reallocated to the new Rx and                 vegetation management and restoration                  the draft EIS may do so. To ensure
                                                is required by LRMP Standards FW–243                    actions, are expected to improve visual                consideration of your comments on the
                                                and FW–244.                                             quality over an extended timeframe                     proposals in the final EIS, it is
                                                   Proposed Amendment 1: The LRMP                       (reference LRMP Standard FW–182).                      important that the Commission receive
                                                would be amended to reallocate 102.3                       The FS is requesting public comments                your comments by April 6, 2017.
                                                acres to the Rx 5C-Designated Utility                   on the authorization of the ACP on NFS                    For your convenience, there are four
                                                Corridors from these Rxs: 7E1-Dispersed                 lands and the draft proposed and                       methods you can use to submit your
                                                Recreation Areas (7 acres), and 13-                     potential amendments of the LRMPs                      comments to the Commission. In all
                                                Mosaics of Habitat (95 acres). Rx 11-                   that would allow the ACP to cross the                  instances, please reference the
                                                Riparian Corridors would remain                         MNF and GWNF. All comments must be                     appropriate docket numbers (CP15–
                                                embedded within the new Rx 5C area.                     submitted to the FERC as directed in                   554–000 and CP15–554–001 for ACP;
                                                   Rx 5C-Designated Utility Corridors                   this notice. The FS decision to authorize              CP15–555–000 for SHP; or CP15–556–
                                                contains special uses which serve a                     the ACP will be subject to FS                          000 for Capacity Lease) with your
                                                public benefit by providing a reliable                  predecisional administrative review                    submission. The Commission
                                                supply of electricity, natural gas, or                  procedures established in 36 CFR 218.                  encourages electronic filing of
                                                water essential to local, regional, and                 The MNF Potential Amendment 1,                         comments and has expert staff available
                                                national economies. The new Rx 5C                       GWNF Proposed Amendments 2 and 3,                      to assist you at (202) 502–8258 or
                                                land allocation would be 53.5 feet wide,                and Potential Amendments 4, 5, and 6                   efiling@ferc.gov. Please carefully follow
                                                the width of the final operational right-               were developed in accordance with 36                   these instructions so that your
                                                of-way of the ACP. The area would not                   CFR 219 (2012 version) regulations but                 comments are properly recorded.
                                                cross into the Rx 4A-Appalachian                        will be subject to the administrative                     (1) You can file your comments
                                                National Scenic Area but would stop                     review procedures under 36 CFR 218                     electronically using the eComment
                                                and start at the existing Rx 4A                         regulations Subparts A and B, per 36                   feature on the Commission’s Web site
                                                boundary. The Rx4A would continue to                    CFR 219.59(b). GWNF Proposed                           (www.ferc.gov) under the link to
                                                be managed for the Appalachian                          Amendment 1 was developed in                           Documents and Filings. This is an easy
                                                National Scenic Trail.                                  accordance to 36 CFR 219 (2012)                        method for submitting brief, text-only
                                                   The second type of amendment                         regulations and will be subject to the                 comments on a project.
                                                applicable to the GWNF would be a                       administrative review procedures under                    (2) You can file your comments
                                                project-specific amendment that would                   36 CFR 219 Subpart B. Refer to the                     electronically by using the eFiling
                                                apply only to the construction and                      applicable administrative review                       feature on the Commission’s Web site
                                                operation of the ACP. The following                     regulations for eligibility requirements.              (www.ferc.gov) under the link to
                                                standards would require a temporary                        All comments must be submitted to                   Documents and Filings. With eFiling,
                                                waiver to allow the project to proceed.                 the FERC, the lead federal agency,                     you can provide comments in a variety
                                                These amendments would not change                       within the timeframe stated in this                    of formats by attaching them as a file
                                                LRMP requirements for other projects or                 Notice of Availability. Refer to Docket                with your submission. New eFiling
                                                authorize any other actions.                            No. CP15–554–000 (ACP) in all                          users must first create an account by
                                                   Proposed Amendment 2: The LRMP                       correspondence to ensure that your                     clicking on ‘‘eRegister.’’ If you are filing
                                                would be amended to allow                               comments are correctly filed in the                    a comment on a particular project,
                                                construction of the ACP to exceed                       record. You may submit your comments                   please select ‘‘Comment on a Filing’’ as
                                                restrictions on soil conditions and                     to the FERC using one of the four                      the filing type.
                                                riparian corridor conditions as                         methods listed below.                                     (3) You can file a paper copy of your
                                                described in LRMP Standards FW–5,                                                                              comments by mailing them to the
                                                                                                        Distribution and Comments on the Draft
                                                FW–15, FW–16, FW–17, and 11–019,                                                                               following address:
                                                                                                        Environmental Impact Statement
                                                provided that mitigation measures or
                                                project requirements agreed upon by the                   The FERC staff mailed copies of the                  Nathaniel J. Davis, Sr., Deputy
                                                FS are implemented as needed.                           draft EIS to federal, state, and local                    Secretary, Federal Energy Regulatory
                                                   Proposed Amendment 3: The LRMP                       government representatives and                            Commission, 888 First Street NE.,
                                                would be amended to allow the ACP to                    agencies; elected officials;                              Room 1A, Washington, DC 20426.
                                                                                                        environmental and public interest                         (4) In lieu of sending written or
sradovich on DSK3GMQ082PROD with NOTICES




                                                cross the Appalachian National Scenic
                                                Trail in Augusta County, Virginia                       groups; Native American tribes;                        electronic comments, the Commission
                                                (reference LRMP Standard 4A–025).                       potentially affected landowners and                    invites you to attend one of the public
                                                   Potential Amendment 4: The LRMP                      other interested individuals and groups;               comment sessions its staff will conduct
                                                may need to be amended to allow the                     newspapers and libraries in the project                in the project area to receive comments
                                                removal of old growth trees within the                  areas; and parties to this proceeding.                 on the draft EIS. We encourage
                                                construction corridor of ACP (reference                 Paper copy versions of this draft EIS                  interested groups and individuals to
                                                LRMP Standard FW–85).                                   were mailed to those specifically                      attend and present oral comments on


                                           VerDate Sep<11>2014   21:14 Jan 06, 2017   Jkt 241001   PO 00000   Frm 00041   Fmt 4703   Sfmt 4703   E:\FR\FM\09JAN1.SGM   09JAN1


                                                2350                           Federal Register / Vol. 82, No. 5 / Monday, January 9, 2017 / Notices

                                                the draft EIS. The sessions are
                                                scheduled as follows:

                                                                  Date and time                                                                           Location

                                                Monday, February 13, 2017, 5:00–9:00 p.m ......          Doubletree Hotel, 1965 Cedar Creek Road, Fayetteville, NC 28312.
                                                Tuesday, February 14, 2017, 5:00–9:00 p.m .....          Forest Hills Middle School, 1210 Forest Hills Road, Wilson, NC 27893.
                                                Wednesday, February 15, 2017, 5:00–9:00 p.m              Hilton Garden Inn Roanoke Rapids, 111 Carolina Crossroads Parkway, Roanoke Rapids, NC
                                                                                                           27870.
                                                Thursday, February 16, 2017, 5:30–9:30 p.m ....          Hilton Garden Inn Conference Center, 100 East Constance Road, Suffolk, VA 23434.
                                                Tuesday, February 21, 2017, 5:00–9:00 p.m .....          Moton Museum, 900 Griffin Boulevard, Farmville, VA 23901.
                                                Wednesday, February 22, 2017, 5:00–9:00 p.m              Nelson County High School, 6919 Thomas Nelson Highway, Route 29, Lovingston, VA 22949.
                                                Thursday, February 23, 2017, 5:00–9:00 p.m ....          Holiday Inn Hotel and Conference, 152 Fairway Lane, Staunton, VA 24401.
                                                Tuesday, February 28, 2017, 5:00–9:00 p.m .....          Highland Center, 61 Highland Center Drive, Monterey, VA 24465.
                                                Wednesday, March 1, 2017, 5:00–9:00 p.m ......           Gandy Dance Theater, 359 Beverly Pike, Elkins, WV 26241.
                                                Thursday, March 2, 2017, 5:00–9:00 p.m ..........        Marlinton Community Wellness Center, 320 9th Street, Marlinton, WV 24954.



                                                   There will not be a formal                           environmental review process. It is                    allows you to keep track of all formal
                                                presentation by Commission staff at any                 important to note that written comments                issuances and submittals in specific
                                                of the ten public comment sessions,                     mailed to the Commission and those                     dockets. This can reduce the amount of
                                                although a format outline handout will                  submitted electronically are reviewed                  time you spend researching proceedings
                                                be made available. All sessions will                    by staff with the same scrutiny and                    by automatically providing you with
                                                begin at 5:00 p.m., with the exception of               consideration as the verbal comments                   notification of these filings, document
                                                the session on Thursday, February 16,                   given at the public sessions.                          summaries, and direct links to the
                                                2017, which will begin at 5:30 p.m. If                    Any person seeking to become a party                 documents. Go to www.ferc.gov/docs-
                                                you wish to provide verbal comments,                    to the proceeding must file a motion to                filing/esubscription.asp to subscribe.
                                                the Commission staff will hand out                      intervene pursuant to Rule 214 of the
                                                                                                                                                                 Dated: December 30, 2016.
                                                numbers in the order of your arrival.                   Commission’s Rules of Practice and
                                                                                                                                                               Kimberly D. Bose,
                                                Number distribution will be                             Procedures (18 CFR part 385.214).1 Only
                                                discontinued at 8:00 p.m. in order to                   intervenors have the right to seek                     Secretary.
                                                ensure all comments are received by the                 rehearing of the Commission’s decision.                [FR Doc. 2017–00068 Filed 1–6–17; 8:45 am]
                                                session closing time. Comments will be                  The Commission grants affected                         BILLING CODE 6717–01–P
                                                taken until 9:00 p.m. (or 9:30 p.m. at the              landowners and others with
                                                February 16 session). However, if no                    environmental concerns intervenor
                                                additional numbers have been handed                     status upon showing good cause by                      DEPARTMENT OF ENERGY
                                                out and all individuals who wish to                     stating that they have a clear and direct
                                                                                                                                                               Federal Energy Regulatory
                                                provide comments have had an                            interest in this proceeding which no
                                                                                                                                                               Commission
                                                opportunity to do so, staff may conclude                other party can adequately represent.
                                                the session at 8:00 p.m., or after the last             Simply filing environmental comments                   [Docket No. ER17–737–000]
                                                comment is taken.                                       will not give you intervenor status, but
                                                   The primary goal of the public                       you do not need intervenor status to                   Viridity Energy Solutions Inc.;
                                                sessions is to allow individuals to                     have your comments considered.                         Supplemental Notice That Initial
                                                provide verbal comments on the draft                                                                           Market-Based Rate Filing Includes
                                                EIS. Individual verbal comments will be                 Questions?                                             Request For Blanket Section 204
                                                taken on a one-on-one basis with a                         Additional information about the                    Authorization
                                                Court Reporter (with FERC staff or                      projects is available from the
                                                representative present), called up in the               Commission’s Office of External Affairs,                 This is a supplemental notice in the
                                                order of the numbers received. Because                  at (866) 208–FERC, or on the FERC Web                  above-referenced proceeding of Viridity
                                                we anticipate considerable interest from                site (www.ferc.gov) using the eLibrary                 Energy Solutions Inc.’s application for
                                                concerned citizens, this format is                      link. Click on the eLibrary link, click on             market-based rate authority, with an
                                                designed to receive the maximum                         ‘‘General Search,’’ and enter the docket               accompanying rate tariff, noting that
                                                amount of verbal comments, in a                         number excluding the last three digits in              such application includes a request for
                                                convenient way during the timeframe                     the Docket Number field (i.e., CP15–                   blanket authorization, under 18 CFR
                                                allotted. If many people are interested in              554, CP15–555, or CP15–556). Be sure                   part 34, of future issuances of securities
                                                providing verbal comments in the one-                   you have selected an appropriate date                  and assumptions of liability.
                                                on-one setting at any particular session,               range. For assistance, please contact                    Any person desiring to intervene or to
                                                a time limit of 3 minutes may be                        FERC Online Support at                                 protest should file with the Federal
                                                implemented for each commenter.                         FERCOnlineSupport@ferc.gov or toll                     Energy Regulatory Commission, 888
                                                   Your verbal comments will be                         free at (866) 208–3676; for TTY, contact               First Street NE., Washington, DC 20426,
                                                recorded by the Court Reporter.                         (202) 502–8659. The eLibrary link also                 in accordance with Rules 211 and 214
                                                Transcripts of all comments from the                    provides access to the texts of formal                 of the Commission’s Rules of Practice
                                                                                                                                                               and Procedure (18 CFR 385.211 and
sradovich on DSK3GMQ082PROD with NOTICES




                                                sessions will be placed into the dockets                documents issued by the Commission,
                                                for the projects, which are accessible for              such as orders, notices, and                           385.214). Anyone filing a motion to
                                                public viewing on the FERC’s Web site                   rulemakings.                                           intervene or protest must serve a copy
                                                (at www.ferc.gov) through our eLibrary                     In addition, the Commission offers a                of that document on the Applicant.
                                                system.                                                 free service called eSubscription that                   Notice is hereby given that the
                                                   Commission staff will be available at                                                                       deadline for filing protests with regard
                                                each venue of the public sessions to                       1 See the previous discussion on the methods for    to the applicant’s request for blanket
                                                answer questions about our                              filing comments.                                       authorization, under 18 CFR part 34, of


                                           VerDate Sep<11>2014   21:14 Jan 06, 2017   Jkt 241001   PO 00000   Frm 00042   Fmt 4703   Sfmt 4703   E:\FR\FM\09JAN1.SGM   09JAN1



Document Created: 2018-10-24 11:09:36
Document Modified: 2018-10-24 11:09:36
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 2348 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR