82_FR_27924 82 FR 27808 - Kinder Morgan Louisiana Pipeline, LLC; Notice of Schedule for Environmental Review of the Sabine Pass Expansion Project

82 FR 27808 - Kinder Morgan Louisiana Pipeline, LLC; Notice of Schedule for Environmental Review of the Sabine Pass Expansion Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 116 (June 19, 2017)

Page Range27808-27809
FR Document2017-12677

Federal Register, Volume 82 Issue 116 (Monday, June 19, 2017)
[Federal Register Volume 82, Number 116 (Monday, June 19, 2017)]
[Notices]
[Pages 27808-27809]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-12677]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-22-000]


Kinder Morgan Louisiana Pipeline, LLC; Notice of Schedule for 
Environmental Review of the Sabine Pass Expansion Project

    On December 13, 2016, Kinder Morgan Louisiana Pipeline, LLC (Kinder 
Morgan) filed an application in Docket No. CP17-22-000 requesting a 
Certificate of Public Convenience and Necessity pursuant to Section 
7(b) and 7(c) of the Natural Gas Act to construct and operate certain 
natural gas pipeline facilities. The proposed project is known as the 
Sabine Pass Expansion Project (Project), and would allow Kinder Morgan 
to provide firm incremental transportation service of up to 600 million 
cubic feet per day of natural gas to the existing Sabine Pass 
Liquefaction Facility, that is currently under expansion in Cameron 
Parish, Louisiana.
    On December 21, 2016 the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

    Issuance of EA: July 28, 2017.
    90-day Federal Authorization Decision Deadline: October 26, 2017.
    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    Kinder Morgan proposes to construct and operate the Sabine Pass 
Expansion Project in Louisiana which consists of the following: (1) 
Modifications to four existing meter stations (Columbia Gulf 
Transmission, LLC; Texas Gas Transmission, LLC; ANR Pipeline Company; 
and Pine Prairie Energy Center) in Evangeline and Acadia Parishes; (2) 
construction of one new 36-inch-diameter delivery interconnect 
consisting of a 36-inch-diameter tap and appurtenances and 1,200 feet 
of 36-inch-diameter lateral at the Sabine Pass Liquefaction Facility in 
Cameron Parish; (3) installation of three additional 15,900 horsepower 
compressor units at Kinder Morgan's previously approved Compressor 
Station 760 in Acadia Parish; \1\ (4) construction of 6,400 feet of 36-
inch-diameter and 700 feet of 24-inch-diameter header pipelines in 
Acadia Parish; and (5) replacement of a meter and increase in capacity 
from 200 to 650 million cubic feet per day at the existing Pine Prairie 
Meter Station in Acadia Parish. The proposed facilities would provide 
north-to-south transportation on Kinder Morgan's system.
---------------------------------------------------------------------------

    \1\ The compressor station has not yet been constructed, but was 
approved by Commission Order dated April 15, 2016 as part of the 
Lake Charles Expansion Project in Docket No. CP14-511-000.
---------------------------------------------------------------------------

    Kinder Morgan proposes to begin construction of the Project by 
April 2018 and to place the facilities in service by April 1, 2019.

[[Page 27809]]

Background

    On January 24, 2017, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Sabine Pass 
Expansion Project and Request for Comments on Environmental Issues 
(NOI). The NOI was sent to affected landowners; federal, state, and 
local government agencies; elected officials; Native American tribes; 
other interested parties; and local libraries and newspapers. In 
response to the NOI, the Commission received a comment from a 
stakeholder stating the U.S. Army Corps of Engineers permits and 
authorizations that would be necessary for the various Project 
components. The Commission also received a comment letter from the 
Louisiana Department of Wildlife and Fisheries stating the Project 
would have minimal or no long-term adverse impacts on wetland functions 
and a comment from the Choctaw Nation of Oklahoma requesting to receive 
a copy of the EA and the cultural resources survey.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-22), and follow the 
instructions. For assistance with access to eLibrary, the helpline can 
be reached at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC Web site also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: June 8, 2017.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2017-12677 Filed 6-16-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                    27808                          Federal Register / Vol. 82, No. 116 / Monday, June 19, 2017 / Notices

                                                       Comments Due: 5 p.m. ET 6/29/17.                        Filed Date: 6/12/17.                                under expansion in Cameron Parish,
                                                       The filings are accessible in the                       Accession Number: 20170612–5117.                    Louisiana.
                                                    Commission’s eLibrary system by                            Comments Due: 5 p.m. ET 7/3/17.                        On December 21, 2016 the Federal
                                                    clicking on the links or querying the                      Docket Numbers: ER17–1799–000.                      Energy Regulatory Commission
                                                    docket number.                                             Applicants: Mehoopany Wind Energy                   (Commission or FERC) issued its Notice
                                                       Any person desiring to intervene or                  LLC.                                                   of Application for the Project. Among
                                                    protest in any of the above proceedings                    Description: § 205(d) Rate Filing:                  other things, that notice alerted agencies
                                                    must file in accordance with Rules 211                  Revised Market-Based Rate Tariff to be                 issuing federal authorizations of the
                                                    and 214 of the Commission’s                             effective 8/12/2017.                                   requirement to complete all necessary
                                                    Regulations (18 CFR 385.211 and                            Filed Date: 6/12/17.                                reviews and to reach a final decision on
                                                    385.214) on or before 5:00 p.m. Eastern                    Accession Number: 20170612–5124.                    a request for a federal authorization
                                                    time on the specified comment date.                        Comments Due: 5 p.m. ET 7/3/17.                     within 90 days of the date of issuance
                                                    Protests may be considered, but                            The filings are accessible in the                   of the Commission staff’s Environmental
                                                    intervention is necessary to become a                   Commission’s eLibrary system by                        Assessment (EA) for the Project. This
                                                    party to the proceeding.                                clicking on the links or querying the                  instant notice identifies the FERC staff’s
                                                       eFiling is encouraged. More detailed                 docket number.                                         planned schedule for the completion of
                                                    information relating to filing                             Any person desiring to intervene or                 the EA for the Project.
                                                    requirements, interventions, protests,                  protest in any of the above proceedings                Schedule for Environmental Review
                                                    service, and qualifying facilities filings              must file in accordance with Rules 211
                                                    can be found at: http://www.ferc.gov/                   and 214 of the Commission’s                              Issuance of EA: July 28, 2017.
                                                    docs-filing/efiling/filing-req.pdf. For                 Regulations (18 CFR 385.211 and                          90-day Federal Authorization
                                                    other information, call (866) 208–3676                  385.214) on or before 5:00 p.m. Eastern                Decision Deadline: October 26, 2017.
                                                    (toll free). For TTY, call (202) 502–8659.              time on the specified comment date.                      If a schedule change becomes
                                                                                                            Protests may be considered, but                        necessary, additional notice will be
                                                      Dated: June 8, 2017.
                                                                                                            intervention is necessary to become a                  provided so that the relevant agencies
                                                    Kimberly D. Bose,
                                                                                                            party to the proceeding.                               are kept informed of the Project’s
                                                    Secretary.                                                                                                     progress.
                                                                                                               eFiling is encouraged. More detailed
                                                    [FR Doc. 2017–12680 Filed 6–16–17; 8:45 am]             information relating to filing                         Project Description
                                                    BILLING CODE 6717–01–P                                  requirements, interventions, protests,
                                                                                                            service, and qualifying facilities filings                Kinder Morgan proposes to construct
                                                                                                            can be found at: http://www.ferc.gov/                  and operate the Sabine Pass Expansion
                                                    DEPARTMENT OF ENERGY                                    docs-filing/efiling/filing-req.pdf. For                Project in Louisiana which consists of
                                                                                                            other information, call (866) 208–3676                 the following: (1) Modifications to four
                                                    Federal Energy Regulatory                                                                                      existing meter stations (Columbia Gulf
                                                    Commission                                              (toll free). For TTY, call (202) 502–8659.
                                                                                                                                                                   Transmission, LLC; Texas Gas
                                                                                                              Dated: June 12, 2017.
                                                    Combined Notice of Filings #2                                                                                  Transmission, LLC; ANR Pipeline
                                                                                                            Kimberly D. Bose,
                                                                                                                                                                   Company; and Pine Prairie Energy
                                                       Take notice that the Commission                      Secretary.                                             Center) in Evangeline and Acadia
                                                    received the following electric rate                    [FR Doc. 2017–12673 Filed 6–16–17; 8:45 am]            Parishes; (2) construction of one new
                                                    filings:                                                BILLING CODE 6717–01–P                                 36-inch-diameter delivery interconnect
                                                       Docket Numbers: ER10–1790–015;                                                                              consisting of a 36-inch-diameter tap and
                                                    ER10–2596–006; ER10–2597–004;                                                                                  appurtenances and 1,200 feet of 36-
                                                    ER12–2200–003.                                          DEPARTMENT OF ENERGY                                   inch-diameter lateral at the Sabine Pass
                                                       Applicants: BP Energy Company,                                                                              Liquefaction Facility in Cameron Parish;
                                                                                                            Federal Energy Regulatory
                                                    Fowler Ridge II Wind Farm LLC, Fowler                                                                          (3) installation of three additional
                                                                                                            Commission
                                                    Ridge III Wind Farm LLC, Mehoopany                                                                             15,900 horsepower compressor units at
                                                    Wind Energy LLC.                                        [Docket No. CP17–22–000]                               Kinder Morgan’s previously approved
                                                       Description: Updated Market Analysis                                                                        Compressor Station 760 in Acadia
                                                    for Northeast Region of BP Energy                       Kinder Morgan Louisiana Pipeline,                      Parish; 1 (4) construction of 6,400 feet of
                                                    Company, et al.                                         LLC; Notice of Schedule for                            36-inch-diameter and 700 feet of 24-
                                                       Filed Date: 6/12/17.                                 Environmental Review of the Sabine                     inch-diameter header pipelines in
                                                       Accession Number: 20170612–5089.                     Pass Expansion Project                                 Acadia Parish; and (5) replacement of a
                                                       Comments Due: 5 p.m. ET 8/11/17.                       On December 13, 2016, Kinder                         meter and increase in capacity from 200
                                                       Docket Numbers: ER17–1532–001.                       Morgan Louisiana Pipeline, LLC (Kinder                 to 650 million cubic feet per day at the
                                                       Applicants: Golden Spread Electric                   Morgan) filed an application in Docket                 existing Pine Prairie Meter Station in
                                                    Cooperative, Inc.                                       No. CP17–22–000 requesting a                           Acadia Parish. The proposed facilities
                                                       Description: Tariff Amendment:                       Certificate of Public Convenience and                  would provide north-to-south
                                                    Clarification to Amended and Restated                   Necessity pursuant to Section 7(b) and                 transportation on Kinder Morgan’s
                                                    WPC to be effective 5/3/2017.                           7(c) of the Natural Gas Act to construct               system.
                                                       Filed Date: 6/12/17.                                                                                           Kinder Morgan proposes to begin
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                            and operate certain natural gas pipeline
                                                       Accession Number: 20170612–5064.                     facilities. The proposed project is                    construction of the Project by April
                                                       Comments Due: 5 p.m. ET 7/3/17.                      known as the Sabine Pass Expansion                     2018 and to place the facilities in
                                                       Docket Numbers: ER17–1798–000.                       Project (Project), and would allow                     service by April 1, 2019.
                                                       Applicants: Fowler Ridge III Wind                    Kinder Morgan to provide firm
                                                                                                                                                                     1 The compressor station has not yet been
                                                    Farm LLC.                                               incremental transportation service of up
                                                                                                                                                                   constructed, but was approved by Commission
                                                       Description: § 205(d) Rate Filing:                   to 600 million cubic feet per day of                   Order dated April 15, 2016 as part of the Lake
                                                    Revised Market-Based Rate Tariff to be                  natural gas to the existing Sabine Pass                Charles Expansion Project in Docket No. CP14–511–
                                                    effective 8/12/2017.                                    Liquefaction Facility, that is currently               000.



                                               VerDate Sep<11>2014   17:09 Jun 16, 2017   Jkt 241001   PO 00000   Frm 00027   Fmt 4703   Sfmt 4703   E:\FR\FM\19JNN1.SGM   19JNN1


                                                                                   Federal Register / Vol. 82, No. 116 / Monday, June 19, 2017 / Notices                                                       27809

                                                    Background                                              DEPARTMENT OF ENERGY                                   546–3669; or Steve Padula, McMillen
                                                                                                                                                                   Jacobs and Associates, 500 Broadway
                                                       On January 24, 2017, the Commission                  Federal Energy Regulatory                              Street, Suite 606, Vancouver, WA
                                                    issued a Notice of Intent to Prepare an                 Commission                                             98660, phone: (360) 576–3579.
                                                    Environmental Assessment for the                                                                                  FERC Contact: Kim Nguyen, (202)
                                                                                                            [Project No. 14568–002]
                                                    Proposed Sabine Pass Expansion Project                                                                         502–6105.
                                                    and Request for Comments on                             CB Energy Park, LLC; Notice of                            Deadline for filing comments, motions
                                                    Environmental Issues (NOI). The NOI                     Preliminary Permit Application                         to intervene, competing applications
                                                    was sent to affected landowners; federal,               Accepted For Filing And Soliciting                     (without notices of intent), or notices of
                                                    state, and local government agencies;                   Comments, Motions To Intervene, And                    intent to file competing applications: 60
                                                    elected officials; Native American tribes;              Competing Applications                                 days from the issuance of this notice.
                                                    other interested parties; and local                                                                            Competing applications and notices of
                                                    libraries and newspapers. In response to                   On June 1, 2017, CB Energy Park, LLC                intent must meet the requirements of 18
                                                                                                            filed an application for a preliminary                 CFR 4.36.
                                                    the NOI, the Commission received a
                                                                                                            permit, pursuant to section 4(f) of the
                                                    comment from a stakeholder stating the                                                                            The Commission strongly encourages
                                                                                                            Federal Power Act, proposing to study
                                                    U.S. Army Corps of Engineers permits                                                                           electronic filing. Please file comments,
                                                                                                            the feasibility of the Coffin Butte
                                                    and authorizations that would be                                                                               motions to intervene, notices of intent,
                                                                                                            Pumped Storage Project (project) to be
                                                    necessary for the various Project                                                                              and competing applications using the
                                                                                                            located near Two Dot in Wheatland and
                                                    components. The Commission also                                                                                Commission’s eFiling system at http://
                                                                                                            Meagher Counties, Montana. The sole
                                                    received a comment letter from the                                                                             www.ferc.gov/docs-filing/efiling.asp.
                                                                                                            purpose of a preliminary permit, if
                                                    Louisiana Department of Wildlife and                                                                           Commenters can submit brief comments
                                                                                                            issued, is to grant the permit holder
                                                    Fisheries stating the Project would have                                                                       up to 6,000 characters, without prior
                                                                                                            priority to file a license application
                                                    minimal or no long-term adverse                                                                                registration, using the eComment system
                                                                                                            during the permit term. A preliminary
                                                    impacts on wetland functions and a                                                                             at http://www.ferc.gov/docs-filing/
                                                                                                            permit does not authorize the permit
                                                    comment from the Choctaw Nation of                                                                             ecomment.asp. You must include your
                                                                                                            holder to perform any land-disturbing
                                                                                                                                                                   name and contact information at the end
                                                    Oklahoma requesting to receive a copy                   activities or otherwise enter upon lands
                                                                                                                                                                   of your comments. For assistance,
                                                    of the EA and the cultural resources                    or waters owned by others without the
                                                                                                                                                                   please contact FERC Online Support at
                                                    survey.                                                 owners’ express permission.
                                                                                                               The proposed project would consist of               FERCOnlineSupport@ferc.gov, (866)
                                                    Additional Information                                  the following:                                         208–3676 (toll free), or (202) 502–8659
                                                                                                                                                                   (TTY). In lieu of electronic filing, please
                                                       In order to receive notification of the              Lower Reservoir                                        send a paper copy to: Secretary, Federal
                                                    issuance of the EA and to keep track of                   (1) A 5,000-foot-long, 50-foot-high                  Energy Regulatory Commission, 888
                                                    all formal issuances and submittals in                  earth and roller compacted concrete                    First Street NE., Washington, DC 20426.
                                                    specific dockets, the Commission offers                 embankment; (2) a 50-acre lower                        The first page of any filing should
                                                    a free service called eSubscription. This               reservoir with a storage capacity of                   include docket number P–14568–002.
                                                    can reduce the amount of time you                       2,500-acre-foot at an elevation of 5,200                  More information about this project,
                                                    spend researching proceedings by                        feet; (3) a temporary pump and pipeline                including a copy of the application, can
                                                    automatically providing you with                        to bring initial fill water to the lower               be viewed or printed on the ‘‘eLibrary’’
                                                    notification of these filings, document                 reservoir from Martinsdale Reservoir; (4)              link of Commission’s Web site at http://
                                                    summaries, and direct links to the                      a new well; (5) a powerhouse containing                www.ferc.gov/docs-filing/elibary.asp.
                                                    documents. Go to www.ferc.gov/docs-                     two Ternary 125-megawatt (MW)                          Enter the docket number (P–14568) in
                                                    filing/esubscription.asp.                               turbine/generator units, for a total                   the docket number field to access the
                                                       Additional information about the                     installed capacity of 250 MW; and (6) an               document. For assistance, contact FERC
                                                                                                            approximately 10-mile-long, 230-                       Online Support.
                                                    Project is available from the
                                                    Commission’s Office of External Affairs                 kilovolt transmission line connecting to                 Dated: June 13, 2017.
                                                    at (866) 208–FERC or on the FERC Web                    the proposed Gordon Butte substation.                  Kimberly D. Bose,
                                                    site (www.ferc.gov). Using the eLibrary                 Upper Reservoir                                        Secretary.
                                                    link, select General Search from the                                                                           [FR Doc. 2017–12669 Filed 6–16–17; 8:45 am]
                                                                                                              (1) A 4,600-foot-long, 50-foot-high
                                                    eLibrary menu, enter the selected date                  earth and roller compacted concrete                    BILLING CODE 6717–01–P
                                                    range and Docket Number excluding the                   embankment; (2) a 50-acre upper
                                                    last three digits (i.e., CP17–22), and                  reservoir with a storage capacity of
                                                    follow the instructions. For assistance                                                                        DEPARTMENT OF ENERGY
                                                                                                            2,500-acre-foot at an elevation of 6,240
                                                    with access to eLibrary, the helpline can               feet; (3) a 12-foot-diameter, 4,000-foot-
                                                    be reached at (866) 208–3676, TTY (202)                                                                        Federal Energy Regulatory
                                                                                                            long steel-lined tunnel connecting the                 Commission
                                                    502–8659, or at FERCOnlineSupport@                      two reservoirs; and (4) appurtenant
                                                    ferc.gov. The eLibrary link on the FERC                 facilities.                                            Supplemental Notice of Technical
                                                    Web site also provides access to the                      The estimated annual generation of                   Conference
                                                    texts of formal documents issued by the
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                            the project would be 880,000 megawatt-
                                                    Commission, such as orders, notices,                    hours.                                                                                       Docket Nos.
                                                    and rule makings.                                         Applicant Contact: Carl Borgquist, CB                Developments in Natural Gas        AD17–12–000
                                                      Dated: June 8, 2017.                                  Energy Park, LLC, 209 South Wilson                       Index Liquidity and Trans-
                                                                                                            Avenue, P.O. Box 309, Bozeman, MT                        parency.
                                                    Kimberly D. Bose,                                                                                              Price Discovery in Natural         PL03–3–000
                                                                                                            59771, phone: (406) 585–3006; Martin J.
                                                    Secretary.                                                                                                       Gas and Electric Markets.
                                                                                                            Weber, P.E., Stanley Consultants, Inc.,                Natural Gas Price Formation        AD03–7–000
                                                    [FR Doc. 2017–12677 Filed 6–16–17; 8:45 am]             5775 Wayzata Blvd., No. 300,                           ISO New England Inc ............   ER17–795–000
                                                    BILLING CODE 6717–01–P                                  Minneapolis, MN 55416, phone: (952)                                                       ER17–795–001



                                               VerDate Sep<11>2014   17:09 Jun 16, 2017   Jkt 241001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\19JNN1.SGM   19JNN1



Document Created: 2017-06-17 01:48:35
Document Modified: 2017-06-17 01:48:35
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 27808 

2025 Federal Register | Disclaimer | Privacy Policy