82_FR_29193 82 FR 29071 - Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

82 FR 29071 - Merchant Hydro Developers, LLC; Notice of Preliminary Permit Application Accepted for Filing and Soliciting Comments, Motions To Intervene, and Competing Applications

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 122 (June 27, 2017)

Page Range29071-29071
FR Document2017-13388

Federal Register, Volume 82 Issue 122 (Tuesday, June 27, 2017)
[Federal Register Volume 82, Number 122 (Tuesday, June 27, 2017)]
[Notices]
[Page 29071]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-13388]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14825-000]


Merchant Hydro Developers, LLC; Notice of Preliminary Permit 
Application Accepted for Filing and Soliciting Comments, Motions To 
Intervene, and Competing Applications

    On January 18, 2017, Merchant Hydro Developers, LLC, filed an 
application for a preliminary permit, pursuant to section 4(f) of the 
Federal Power Act (FPA), proposing to study the feasibility of the Four 
Mile Pumped Storage Hydro Project to be located near the City of 
Frostburg in Allegany County, Maryland. The sole purpose of a 
preliminary permit, if issued, is to grant the permit holder priority 
to file a license application during the permit term. A preliminary 
permit does not authorize the permit holder to perform any land-
disturbing activities or otherwise enter upon lands or waters owned by 
others without the owners' express permission.
    The proposed project would consist of the following: (1) A new 
upper reservoir with a surface area of 168 acres and a storage capacity 
of 2,520 acre-feet at a surface elevation of approximately 2,800 feet 
above mean sea level (msl) created through construction of a new 
roller-compacted concrete or rock-fill dam; (2) a new lower reservoir 
with a surface area of 55 acres and a storage capacity of 3,024 acre-
feet at a surface elevation of 2,250 feet msl; (3) a new 5,823-foot-
long, 48-inch-diameter penstock connecting the upper and lower 
reservoirs; (4) a new 150-foot-long, 50-foot-wide, 25-foot-high 
powerhouse containing two turbine-generator units with a total rated 
capacity of 114 megawatts; (5) a new 2,640-foot-long transmission line 
connecting the powerhouse to the Frostburg-Jennings 138-kilovolt 
circuit owned by Potomac Edison; and (6) appurtenant facilities. The 
proposed project would have an annual generation of 414,741 megawatt-
hours.
    Applicant Contact: Adam Rousselle, Merchant Hydro Developers, LLC, 
5710 Oak Crest Drive, Doylestown, PA 18902; phone: 267-254-6107.
    FERC Contact: Woohee Choi; phone: (202) 502-6336.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-14825-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the ``eLibrary'' link of the 
Commission's Web site at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14825) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: June 21, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-13388 Filed 6-26-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                                 Federal Register / Vol. 82, No. 122 / Tuesday, June 27, 2017 / Notices                                                  29071

                                                  of the Aroo Pioneer Peak Pumped                         (TTY). In lieu of electronic filing, please            containing two turbine-generator units
                                                  Storage Hydro Project to be located near                send a paper copy to: Secretary, Federal               with a total rated capacity of 114
                                                  Archbald Borough and Jefferson                          Energy Regulatory Commission, 888                      megawatts; (5) a new 2,640-foot-long
                                                  Township in Lackawanna County,                          First Street NE., Washington, DC 20426.                transmission line connecting the
                                                  Pennsylvania. The sole purpose of a                     The first page of any filing should                    powerhouse to the Frostburg-Jennings
                                                  preliminary permit, if issued, is to grant              include docket number P–14822–000.                     138-kilovolt circuit owned by Potomac
                                                  the permit holder priority to file a                       More information about this project,                Edison; and (6) appurtenant facilities.
                                                  license application during the permit                   including a copy of the application, can               The proposed project would have an
                                                  term. A preliminary permit does not                     be viewed or printed on the ‘‘eLibrary’’               annual generation of 414,741 megawatt-
                                                  authorize the permit holder to perform                  link of the Commission’s Web site at                   hours.
                                                  any land-disturbing activities or                       http://www.ferc.gov/docs-filing/
                                                  otherwise enter upon lands or waters                    elibrary.asp. Enter the docket number                     Applicant Contact: Adam Rousselle,
                                                  owned by others without the owners’                     (P–14822) in the docket number field to                Merchant Hydro Developers, LLC, 5710
                                                  express permission.                                     access the document. For assistance,                   Oak Crest Drive, Doylestown, PA 18902;
                                                     The proposed project would consist of                contact FERC Online Support.                           phone: 267–254–6107.
                                                  the following: (1) A new upper reservoir                                                                          FERC Contact: Woohee Choi; phone:
                                                                                                            Dated: June 21, 2017.
                                                  with a surface area of 116 acres and a                                                                         (202) 502–6336.
                                                  storage capacity of 1,740 acre-feet at a                Nathaniel J. Davis, Sr.,
                                                  surface elevation of approximately 2,265                Deputy Secretary.                                         Deadline for filing comments, motions
                                                  feet above mean sea level (msl) created                 [FR Doc. 2017–13387 Filed 6–26–17; 8:45 am]            to intervene, competing applications
                                                  through construction of a new roller-                   BILLING CODE 6717–01–P                                 (without notices of intent), or notices of
                                                  compacted concrete or rock-fill dam; (2)                                                                       intent to file competing applications: 60
                                                  a new lower reservoir with a surface                                                                           days from the issuance of this notice.
                                                  area of 184 acres and a storage capacity                DEPARTMENT OF ENERGY                                   Competing applications and notices of
                                                  of 2,088 acre-feet at a surface elevation                                                                      intent must meet the requirements of 18
                                                  of 1,400 feet msl; (3) a new 10,000-foot-               Federal Energy Regulatory                              CFR 4.36.
                                                  long, 48-inch-diameter penstock                         Commission
                                                                                                                                                                    The Commission strongly encourages
                                                  connecting the upper and lower                          [Project No. 14825–000]                                electronic filing. Please file comments,
                                                  reservoirs; (4) a new 150-foot-long, 50-
                                                                                                          Merchant Hydro Developers, LLC;                        motions to intervene, notices of intent,
                                                  foot-wide, 25-foot-high powerhouse
                                                  containing two turbine-generator units                  Notice of Preliminary Permit                           and competing applications using the
                                                  with a total rated capacity of 123                      Application Accepted for Filing and                    Commission’s eFiling system at http://
                                                  megawatts; (5) a new 2,640-foot-long                    Soliciting Comments, Motions To                        www.ferc.gov/docs-filing/efiling.asp.
                                                  transmission line connecting the                        Intervene, and Competing Applications                  Commenters can submit brief comments
                                                  powerhouse to the PPL Electric Utilities’                                                                      up to 6,000 characters, without prior
                                                  Peckville 230-kilovolt circuit; and (6)                    On January 18, 2017, Merchant Hydro                 registration, using the eComment system
                                                  appurtenant facilities. The proposed                    Developers, LLC, filed an application for              at http://www.ferc.gov/docs-filing/
                                                  project would have an annual                            a preliminary permit, pursuant to                      ecomment.asp. You must include your
                                                  generation of 450,380 megawatt-hours.                   section 4(f) of the Federal Power Act                  name and contact information at the end
                                                     Applicant Contact: Adam Rousselle,                   (FPA), proposing to study the feasibility              of your comments. For assistance,
                                                  Merchant Hydro Developers, LLC, 5710                    of the Four Mile Pumped Storage Hydro                  please contact FERC Online Support at
                                                  Oak Crest Drive, Doylestown, PA 18902;                  Project to be located near the City of
                                                                                                                                                                 FERCOnlineSupport@ferc.gov, (866)
                                                  phone: 267–254–6107.                                    Frostburg in Allegany County,
                                                                                                                                                                 208–3676 (toll free), or (202) 502–8659
                                                     FERC Contact: Woohee Choi; phone:                    Maryland. The sole purpose of a
                                                                                                                                                                 (TTY). In lieu of electronic filing, please
                                                  (202) 502–6336.                                         preliminary permit, if issued, is to grant
                                                                                                          the permit holder priority to file a                   send a paper copy to: Secretary, Federal
                                                     Deadline for filing comments, motions
                                                                                                          license application during the permit                  Energy Regulatory Commission, 888
                                                  to intervene, competing applications
                                                  (without notices of intent), or notices of              term. A preliminary permit does not                    First Street NE., Washington, DC 20426.
                                                  intent to file competing applications: 60               authorize the permit holder to perform                 The first page of any filing should
                                                  days from the issuance of this notice.                  any land-disturbing activities or                      include docket number P–14825–000.
                                                  Competing applications and notices of                   otherwise enter upon lands or waters                      More information about this project,
                                                  intent must meet the requirements of 18                 owned by others without the owners’                    including a copy of the application, can
                                                  CFR 4.36.                                               express permission.                                    be viewed or printed on the ‘‘eLibrary’’
                                                     The Commission strongly encourages                      The proposed project would consist of               link of the Commission’s Web site at
                                                  electronic filing. Please file comments,                the following: (1) A new upper reservoir               http://www.ferc.gov/docs-filing/
                                                  motions to intervene, notices of intent,                with a surface area of 168 acres and a                 elibrary.asp. Enter the docket number
                                                  and competing applications using the                    storage capacity of 2,520 acre-feet at a               (P–14825) in the docket number field to
                                                  Commission’s eFiling system at http://                  surface elevation of approximately 2,800               access the document. For assistance,
                                                  www.ferc.gov/docs-filing/efiling.asp.                   feet above mean sea level (msl) created                contact FERC Online Support.
                                                  Commenters can submit brief comments                    through construction of a new roller-
                                                  up to 6,000 characters, without prior                   compacted concrete or rock-fill dam; (2)                 Dated: June 21, 2017.
                                                  registration, using the eComment system                 a new lower reservoir with a surface                   Nathaniel J. Davis, Sr.,
mstockstill on DSK30JT082PROD with NOTICES




                                                  at http://www.ferc.gov/docs-filing/                     area of 55 acres and a storage capacity                Deputy Secretary.
                                                  ecomment.asp. You must include your                     of 3,024 acre-feet at a surface elevation              [FR Doc. 2017–13388 Filed 6–26–17; 8:45 am]
                                                  name and contact information at the end                 of 2,250 feet msl; (3) a new 5,823-foot-               BILLING CODE 6717–01–P
                                                  of your comments. For assistance,                       long, 48-inch-diameter penstock
                                                  please contact FERC Online Support at                   connecting the upper and lower
                                                  FERCOnlineSupport@ferc.gov, (866)                       reservoirs; (4) a new 150-foot-long, 50-
                                                  208–3676 (toll free), or (202) 502–8659                 foot-wide, 25-foot-high powerhouse


                                             VerDate Sep<11>2014   18:33 Jun 26, 2017   Jkt 241001   PO 00000   Frm 00050   Fmt 4703   Sfmt 9990   E:\FR\FM\27JNN1.SGM   27JNN1



Document Created: 2018-11-14 10:15:01
Document Modified: 2018-11-14 10:15:01
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 29071 

2025 Federal Register | Disclaimer | Privacy Policy