The Coast Guard proposes to modify the operating regulation that governs the DELAIR Memorial Railroad Bridge across the Delaware River, mile 104.6, at Pennsauken Township, NJ. This proposed regulation will allow the bridge to be remotely operated from the Conrail South Jersey dispatch center in Mount Laurel, NJ, instead of being operated by an on-site bridge tender. This regulation will not change the operating schedule of the bridge.

Federal Register, Volume 82 Issue 125 (Friday, June 30, 2017)
[Federal Register Volume 82, Number 125 (Friday, June 30, 2017)]
[Proposed Rules]
[Pages 29800-29804]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-13857]


=======================================================================
-----------------------------------------------------------------------

DEPARTMENT OF HOMELAND SECURITY

Coast Guard

33 CFR Part 117

[Docket No. USCG-2016-0257]
RIN 1625-AA09


Drawbridge Operation Regulation; Delaware River, Pennsauken 
Township, NJ

AGENCY: Coast Guard, DHS.

ACTION: Notice of proposed rulemaking.

-----------------------------------------------------------------------

SUMMARY: The Coast Guard proposes to modify the operating regulation 
that governs the DELAIR Memorial Railroad Bridge across the Delaware 
River, mile 104.6, at Pennsauken Township, NJ. This proposed regulation 
will allow the bridge to be remotely operated from the Conrail South 
Jersey dispatch center in Mount Laurel, NJ, instead of being operated 
by an on-site bridge tender. This regulation will not change the 
operating schedule of the bridge.

DATES: Comments and related material must reach the Coast Guard on or 
before August 18, 2017.

ADDRESSES: You may submit comments identified by docket number USCG-
2016-0257 using Federal eRulemaking Portal at http://www.regulations.gov.
    See the ``Public Participation and Request for Comments'' portion 
of the SUPPLEMENTARY INFORMATION section below for instructions on 
submitting comments.

[[Page 29801]]


FOR FURTHER INFORMATION CONTACT: If you have questions on this proposed 
rule, call or email Mr. Hal R. Pitts, Fifth Coast Guard District (dpb); 
telephone (757) 398-6222, email [email protected].

SUPPLEMENTARY INFORMATION: 

I. Table of Abbreviations

CFR Code of Federal Regulations
DHS Department of Homeland Security
FR Federal Register
NPRM Notice of proposed rulemaking
Sec.  Section
U.S.C. United States Code

II. Background, Purpose and Legal Basis

    The DELAIR Memorial Railroad Bridge across the Delaware River, mile 
104.6, at Pennsauken Township, NJ, owned and operated by Conrail Shared 
Assets, has a vertical clearance of 49 feet above mean high water in 
the closed-to-navigation position. There is a daily average of 28 New 
Jersey Transit trains and eight Conrail freight trains that cross the 
bridge and a daily average of three bridge openings that allow one or 
more vessels to transit through the bridge during each opening. The 
bridge is normally maintained in the closed position due to the average 
daily number of trains crossing the bridge. The operating schedule is 
published in 33 CFR 117.716. This current operating schedule has been 
in effect since 1984 and will not change with the implementation of 
remote operation of the bridge. However, within this proposed operating 
schedule, Sec.  117.716 will be restructured from its current 
configuration to clearly distinguish the remote operation of the DELAIR 
Memorial Railroad Bridge. This proposed operating regulation allows the 
bridge to be operated remotely from the bridge owner's South Jersey 
dispatch center in Mount Laurel, NJ.
    The Delaware River is used by a variety of vessels, including deep 
draft commercial vessels, tug and barge traffic, recreational vessels, 
and public vessels, including military vessels of various sizes. The 
three-year average number of bridge openings and maximum number of 
bridge openings by month and overall for 2013 through 2015, as drawn 
from the data contained in the bridge tender logs, is presented below.

------------------------------------------------------------------------
                                              Average         Maximum
                  Month                      openings        openings
------------------------------------------------------------------------
January.................................              73              88
February................................              54              56
March...................................              80              94
April...................................              55              68
May.....................................              60              67
June....................................              60              71
July....................................             122             162
August..................................             112             138
September...............................             143             201
October.................................             109             117
November................................             100             116
December................................             100             122
Monthly.................................              89             201
Daily...................................               3               7
------------------------------------------------------------------------

    The bridge owner and the maritime community have been working 
together since 2013 in an effort to incorporate sensors and other 
technologies into the bridge and the Conrail South Jersey dispatch 
center to allow for the safe and effective remote operation of the 
bridge.
    On April 12, 2017, the Coast Guard published a temporary deviation 
entitled ``Drawbridge Operation Regulation; Delaware River, Pennsauken 
Township, NJ'' in the Federal Register (82 FR 17561). This test 
deviation allows the bridge to be operated remotely from the bridge 
owner's South Jersey dispatch center in Mount Laurel, NJ. This test 
deviation is effective from 8 a.m. on April 24, 2017, to 7:59 a.m. on 
October 21, 2017.

III. Discussion of Proposed Rule

    This proposed operating regulation will allow the bridge to be 
operated remotely from the bridge owner's South Jersey dispatch center 
in Mount Laurel, NJ. The remote operation system will include eight 
camera views (four marine and four rail), two forward-looking infrared 
equipped camera views (marine), marine radar, a dedicated telephone 
line for bridge operations, radio telephone on VHF-FM channels 13 and 
16, and an automated identification system (AIS) transmitter to provide 
bridge status. The AIS transmitter has been installed on the New Jersey 
side of the bridge at the bridge and land intersection in approximate 
position 39[deg]58'50.52'' N. (39.9807), 75[deg]03'58.75'' W. (-
75.06632). The AIS transmitter is assigned maritime mobile service 
identity (MMSI) number 993663001 and will provide the status of the 
bridge (open/closed/inoperative) via the name transmitted by the 
private aids to navigation as DELAIR BRG-OPEN (fully open and locked 
position, channel light green), DELAIR BRG-CLOSED (other than fully 
open, not inoperative), or DELAIR BRG-INOP (other than fully open, 
inoperative). The AIS transmitter will transmit the bridge status every 
two minutes and upon a change in the bridge status.
    The remote operation system is designed to provide equal or greater 
capabilities compared to the on-site bridge tender in visibility of the 
waterway and bridge and in signals (communications) via sound and 
visual signals and radio telephone (voice) via VHF-FM channels 13 and 
16. The remote operation system also incorporates real-time bridge 
status via AIS signal to aid mariners in voyage planning and 
navigational decision-making, a dedicated telephone line (856) 231-2301 
for bridge operations, and push-to-talk (PTT) capability on VHF-FM 
channel 13.
    The signals for the remote operation center or on-site bridge 
tender to respond to a sound signal for a bridge opening will include: 
(1) When the draw can be opened immediately--a sound signal of one 
prolonged blast followed by one short blast and illumination of a fixed 
white light not more than 30 seconds after the requesting signal, and 
(2) when the draw cannot be opened immediately--five short blasts 
sounded in rapid succession and illumination of a fixed red light not 
more 30 seconds after the vessel's opening signal. The signals for the 
remote operation center or on-site

[[Page 29802]]

bridge tender to respond to a visual signal for a bridge opening will 
include: (1) When the draw can be opened immediately--illumination of a 
fixed white light not more than 30 seconds after the requesting signal, 
and (2) when the draw cannot be opened immediately--illumination of a 
fixed red light not more than 30 seconds after the vessel's opening 
signal. The fixed white light will remain illuminated until the bridge 
reaches the fully open position. The fixed white and red lights will be 
positioned on the east (New Jersey) bridge abutment adjacent to the 
navigation span.
    Vessels that require an opening shall continue to request an 
opening via the methods defined in 33 CFR 117.15(b) through (d) (sound 
or visual signals or radio telephone (VHF-FM) voice communications), 
via telephone at (856) 231-2301, or via push-to-talk (PTT) on VHF-FM 
channel 13. Vessels may push the PTT button five times while on VHF-FM 
channel 13 to request an opening.
    The remote operation system will be considered in a failed 
condition and qualified personnel will return and operate the bridge 
within 60 minutes if any of the following conditions are found: (1) The 
remote operation system becomes incapable of safely and effectively 
operating the bridge from the remote operation center, (2) visibility 
of the waterway or bridge is degraded to less than equal that of an on-
site bridge tender (all eight camera views are required), (3) signals 
(communications) via sound or visual signals or radio telephone (voice) 
via VHF-FM channels 13 or 16 become inoperative, or (4) AIS becomes 
inoperative.

IV. Regulatory Analyses

    We developed this proposed rule after considering numerous statutes 
and Executive Orders related to rulemaking. Below we summarize our 
analyses based on these statutes and Executive Orders, and we discuss 
First Amendment rights of protestors.

A. Regulatory Planning and Review

    Executive Orders 12866 and 13563 direct agencies to assess the 
costs and benefits of available regulatory alternatives and, if 
regulation is necessary, to select regulatory approaches that maximize 
net benefits. Executive Order 13771 directs agencies to control 
regulatory costs through a budgeting process. This NPRM has not been 
designated a ``significant regulatory action'' under Executive Order 
12866. Accordingly, the NPRM has not been reviewed by the Office of 
Management and Budget (OMB), and pursuant to OMB guidance it is exempt 
from the requirements of Executive Order 13771.
    The determination that this NPRM is not a significant regulatory 
action is based on the findings that: (1) Vessels will continue to 
transit the bridge in accordance with 33 CFR 117.716, (2) the remote 
operation system is designed to provide equal or greater capabilities 
compared to the on-site bridge tender, and (3) the bridge owner will be 
capable of restoring on-site operation of the bridge within 60 minutes 
if the remote operation system fails.

B. Impact on Small Entities

    The Regulatory Flexibility Act of 1980 (RFA), 5 U.S.C. 601-612, as 
amended, requires federal agencies to consider the potential impact of 
regulations on small entities during rulemaking. The term ``small 
entities'' comprises small businesses, not-for-profit organizations 
that are independently owned and operated and are not dominant in their 
fields, and governmental jurisdictions with populations of less than 
50,000. The Coast Guard certifies under 5 U.S.C. 605(b) that this 
proposed rule would not have a significant economic impact on a 
substantial number of small entities. There are no known adverse 
impacts to any entities related to this proposed rule, given no aspects 
of the remote operating system for the bridge will create any burdens 
on any entity as described in section IV.A above. The incorporation of 
the automated identification system (AIS) capability into the remote 
operation system is expected to aid mariners who have AIS capability or 
access to computer-based AIS data in safely navigating through the 
bridge by providing real-time bridge status.
    If you think that your business, organization, or governmental 
jurisdiction qualifies as a small entity and that this rule would have 
a significant economic impact on it, please submit a comment (see 
ADDRESSES) explaining why you think it qualifies, and how, and to what 
degree this rule would economically affect it.
    Under section 213(a) of the Small Business Regulatory Enforcement 
Fairness Act of 1996 (Pub. L. 104-121), we want to assist small 
entities in understanding this proposed rule. If the rule would affect 
your small business, organization, or governmental jurisdiction and you 
have questions concerning its provisions or options for compliance, 
please contact the person listed in the FOR FURTHER INFORMATION CONTACT 
section above. The Coast Guard will not retaliate against small 
entities that question or complain about this proposed rule or any 
policy or action of the Coast Guard.

C. Collection of Information

    This proposed rule would call for no new collection of information 
under the Paperwork Reduction Act of 1995 (44 U.S.C. 3501-3520.).

D. Federalism and Indian Tribal Government

    A rule has implications for federalism under Executive Order 13132, 
Federalism, if it has a substantial direct effect on the states, on the 
relationship between the national government and the states, or on the 
distribution of power and responsibilities among the various levels of 
government. We have analyzed this proposed rule under that Order and 
have determined that it is consistent with the fundamental federalism 
principles and preemption requirements described in Executive Order 
13132.
    Also, this proposed rule does not have tribal implications under 
Executive Order 13175, Consultation and Coordination with Indian Tribal 
Governments, because it would not have a substantial direct effect on 
one or more Indian tribes, on the relationship between the federal 
government and Indian tribes, or on the distribution of power and 
responsibilities between the federal government and Indian tribes. If 
you believe this proposed rule has implications for federalism or 
Indian tribes, please contact the person listed in the FOR FURTHER 
INFORMATION CONTACT section above.

E. Unfunded Mandates Reform Act

    The Unfunded Mandates Reform Act of 1995 (Act) (2 U.S.C. 1531-1538) 
requires federal agencies to assess the effects of their discretionary 
regulatory actions. In particular, the Act addresses actions that may 
result in the expenditure by a state, local, or tribal government, in 
the aggregate, or by the private sector of $100,000,000 (adjusted for 
inflation) or more in any one year. Though this proposed rule will not 
result in such an expenditure, we do discuss the effects of this 
proposed rule elsewhere in this preamble.

F. Environment

    We have analyzed this proposed rule under Department of Homeland 
Security Management Directive 023-01 and Commandant Instruction 
M16475.lD, which guides the Coast Guard in complying with the National 
Environmental Policy Act of 1969 (NEPA)(42 U.S.C. 4321-4370f), and have 
made a preliminary determination that this action is one of a category 
of

[[Page 29803]]

actions which do not individually or cumulatively have a significant 
effect on the human environment. This proposed rule simply promulgates 
the operating regulations or procedures for drawbridges. Normally, such 
actions are categorically excluded from further review under figure 2-
1, paragraph (32)(e), of the Instruction.
    A preliminary Record of Environmental Consideration and a 
Memorandum for the Record are not required for this rule. We seek any 
comments or information that may lead to the discovery of a significant 
environmental impact from this proposed rule.

G. Protest Activities

    The Coast Guard respects the First Amendment rights of protesters. 
Protesters are asked to contact the person listed in the FOR FURTHER 
INFORMATION CONTACT section to coordinate protest activities so that 
their message can be received without jeopardizing the safety or 
security of people, places, or vessels.

V. Public Participation and Request for Comments

    We view public participation as essential to effective rulemaking 
and will consider all comments and material received during the comment 
period. Your comment can help shape the outcome of this rulemaking. If 
you submit a comment, please include the docket number for this 
rulemaking, indicate the specific section of this document to which 
each comment applies, and provide a reason for each suggestion or 
recommendation.
    We encourage you to submit comments through the Federal eRulemaking 
Portal at http://www.regulations.gov. If your material cannot be 
submitted using http://www.regulations.gov, contact the person in the 
FOR FURTHER INFORMATION CONTACT section of this document for alternate 
instructions.
    We accept anonymous comments. All comments received will be posted 
without change to http://www.regulations.gov and will include any 
personal information you have provided. For more about privacy and the 
docket, you may review a Privacy Act notice regarding the Federal 
Docket Management System in the March 24, 2005, issue of the Federal 
Register (70 FR 15086).
    Documents mentioned in this notice of proposed rulemaking and all 
public comments are in our online docket at http://www.regulations.gov 
and can be viewed by following that Web site's instructions. 
Additionally, if you go to the online docket and sign up for email 
alerts, you will be notified when comments are posted or a final rule 
is published.

List of Subjects in 33 CFR Part 117

    Bridges.

    For the reasons discussed in the preamble, the Coast Guard proposes 
to amend 33 CFR part 117 as follows:

PART 117--DRAWBRIDGE OPERATION REGULATIONS

0
1. The authority citation for part 117 continues to read as follows:

    Authority:  33 U.S.C. 499; 33 CFR 1.05-1; and Department of 
Homeland Security Delegation No. 0170.1.

0
2. Revise Sec.  117.716 to read as follows:


Sec. 117.716  Delaware River.

    (a) The following apply to all drawbridges across the Delaware 
River:
    (1) The draws of railroad bridges need not be opened when there is 
a train in the bridge block approaching the bridge with the intention 
of crossing or within five minutes of the known time of the passage of 
a scheduled passenger train.
    (2) The opening of a bridge may not be delayed more than five 
minutes for a highway bridge or 10 minutes for a railroad bridge after 
the signal to open is given.
    (3) The owners of drawbridges shall provide and keep in good 
legible condition two board gages painted white with black figures not 
less than six inches high to indicate the vertical clearance under the 
closed draw at all stages of the tide. The gages shall be so placed on 
the bridge that they are plainly visible to operators of vessels 
approaching the bridge either up or downstream.
    (b) The draw of the Conrail Memorial Railroad Bridge, mile 104.6, 
at Pennsauken Township, NJ shall be operated as follows:
    (1) The bridge will be remotely operated from the Conrail South 
Jersey dispatch center in Mount Laurel, NJ unless the remote operation 
system is in a failed condition.
    (2) An AIS transmitter has been installed on the New Jersey side of 
the bridge at the bridge and land intersection in approximate position 
39[deg]58'50.52'' N. (39.9807), 75[deg]03'58.75'' (-75.06632). The AIS 
transmitter is assigned maritime mobile service identity (MMSI) number 
993663001. The status of the bridge (open/closed/inoperative) will be 
provided via the name transmitted by the AIS private aids to navigation 
as DELAIR BRG-OPEN (fully open and locked position, channel light 
green), DELAIR BRG-CLOSED (other than fully open, not inoperative), or 
DELAIR BRG-INOP (other than fully open, inoperative). The AIS 
transmitter will transmit the bridge status every two minutes and upon 
a change in the bridge status.
    (3) The remote operation system will be considered in a failed 
condition and qualified personnel will return and operate the bridge 
within 60 minutes if any of the following conditions are found:
    (i) The remote operation system becomes incapable of safely and 
effectively operating the bridge from the remote operation center; or
    (ii) Visibility of the waterway or bridge is degraded to less than 
equal that of an on-site bridge tender; or
    (iii) Signals (communications) via sound or visual signals or radio 
telephone (voice) via VHF-FM channels 13 or 16 become inoperative; or
    (iv) AIS becomes inoperative.
    (4) Vessels that require an opening shall continue to request an 
opening via the methods defined in Sec.  117.15(b) through (d) (sound 
or visual signals or radio telephone (VHF-FM) voice communications), 
via telephone at (856) 231-2301, or via push-to-talk (PTT) on VHF-FM 
channel 13. Vessels may push the PTT button five times while on VHF-FM 
channel 13 to request an opening.
    (5) The signals for the remote operation center or on-site bridge 
tender to respond to a sound signal for a bridge opening include:
    (i) When the draw can be opened immediately--a sound signal of one 
prolonged blast followed by one short blast and illumination of a fixed 
white light not more than 30 seconds after the requesting signal; or
    (ii) When the draw cannot be opened immediately--five short blasts 
sounded in rapid succession and illumination of a fixed red light not 
more 30 seconds after the vessel's opening signal.
    (6) The signals for the remote operation center or on-site bridge 
tender to respond to a visual signal for a bridge opening include:
    (i) When the draw can be opened immediately--illumination of a 
fixed white light not more than 30 seconds after the requesting signal; 
or
    (ii) When the draw cannot be opened immediately--illumination of a 
fixed red light not more 30 seconds after the vessel's opening signal.
    (7) The fixed white light will remain illuminated until the bridge 
reaches the fully open position. The fixed white and red lights will be 
positioned on the east (New Jersey) bridge abutment adjacent to the 
navigation span.


[[Page 29804]]


    Dated: June 19, 2017.
M.L. Austin,
Rear Admiral, U.S. Coast Guard, Commander, Fifth Coast Guard District.
[FR Doc. 2017-13857 Filed 6-29-17; 8:45 am]
 BILLING CODE 9110-04-P



                                                    29800                     Federal Register / Vol. 82, No. 125 / Friday, June 30, 2017 / Proposed Rules

                                                    A applied the same heritage process                     ii. National Security and Foreign Policy               is designed and manufactured by NASA
                                                    profile to the new equipment, retained                  Implications                                           KSC and is part of the independent
                                                    heritage printed circuit board samples                    The FAA has identified no national                   safety system which will be installed on
                                                    for periodic process control                            security or foreign policy implications                the launch vehicles. This safety system
                                                    comparisons, and implemented periodic                   associated with granting this waiver.                  will be capable of determining if the
                                                    visual/x-ray inspections for consistency                                                                       flight of the launch vehicle will pose an
                                                    validation. Heritage and new equipment                  iii. Public Interest                                   unacceptable increased risk to the
                                                    specifications were also assessed to                       The waiver is consistent with the                   public based on mission rules designed
                                                    compare their performance                               public interest goals of Chapter 509 and               for its unique vehicle and flight
                                                    characteristics. White Sand Missile                     the National Space Transportation                      characteristics and programmed into the
                                                    Range has reviewed and accepted this                    Policy. Three of the public policy goals               safety system and terminate the flight of
                                                    process change, for U.S. Government                     of Chapter 509 are: (1) To promote                     such launch vehicle. This type of
                                                                                                            economic growth and entrepreneurial                    capability is in public interest because
                                                    launch vehicle programs conducting
                                                                                                            activity through use of the space                      this safety system will allow for
                                                    launches from its launch range, based
                                                                                                            environment; (2) to encourage the                      improved protection of the public from
                                                    on improved reliability and quality of
                                                                                                            United States private sector to provide                mishaps resulting from flight of errant
                                                    the process.                                                                                                   launch vehicles.
                                                                                                            launch and reentry vehicles and
                                                       The FAA waives the requirements of                   associated services; and (3) to facilitate               Issued in Washington, DC, on May 15,
                                                    E417.7(f)(2) and (5) because the Electron               the strengthening and expansion of the                 2017.
                                                    has implemented a failsafe flight safety                United States space transportation                     Kenneth Wong,
                                                    system design that would terminate                      infrastructure to support the full range               Commercial Space Transportation, Licensing
                                                    thrust to the vehicle should both flight                of United States space-related activities.             and Evaluation Division Manager.
                                                    termination receivers fail or                           See 51 U.S.C. 50901(b)(1), (2), (4).                   [FR Doc. 2017–13567 Filed 6–29–17; 8:45 am]
                                                    communication was lost with the                            RL seeks to lower the cost and                      BILLING CODE 4910–13–P
                                                    ground station, and RL’s operating area                 increase the frequency of access to space
                                                    is remote enough that were it to                        for small payloads, potentially
                                                    experience a catastrophic failure, it                   expanding the opportunity for space
                                                    would not jeopardize public health and                  services and research. These activities                DEPARTMENT OF HOMELAND
                                                    safety and safety of property. The                      will help to make the U.S. launch                      SECURITY
                                                    Electron test flight missions would                     industry more competitive
                                                                                                                                                                   Coast Guard
                                                    occur from the isolated Mahia Peninsula                 internationally. The National Space
                                                    in New Zealand. The area within 20 NM                   Transportation Policy states that
                                                                                                                                                                   33 CFR Part 117
                                                    of Mahia Peninsula has a very low                       strengthening U.S. competitiveness in
                                                    population density. The Electron flight                 the international launch market and                    [Docket No. USCG–2016–0257]
                                                    corridor is over the broad ocean area                   improving the cost effectiveness of U.S.
                                                    with minimal impact on air and marine                   space transportation services are in the               RIN 1625–AA09
                                                    traffic. Consequence analysis showed                    public interest:
                                                                                                               Maintaining an assured capability to                Drawbridge Operation Regulation;
                                                    that less than 1 in 100,000 casualties
                                                                                                            meet United States Government needs,                   Delaware River, Pennsauken
                                                    would be expected if the worst
                                                                                                            while also taking the necessary steps to               Township, NJ
                                                    foreseeable vehicle response mode (i.e.,                strengthen U.S. competitiveness in the
                                                    where the vehicle guidance is assumed                   international commercial launch                        AGENCY:   Coast Guard, DHS.
                                                    to fail in a manner that leads to an                    market, is important to ensuring that                  ACTION:   Notice of proposed rulemaking.
                                                    attempt to guide to erroneous, randomly                 U.S. space transportation capabilities
                                                    located points) occurred at the worst                   will be reliable, robust, safe, and                    SUMMARY:   The Coast Guard proposes to
                                                    flight time (relatively early in flight                 affordable in the future. Among other                  modify the operating regulation that
                                                    before the vehicle proceeds downrange)                  steps, improving the cost effectiveness                governs the DELAIR Memorial Railroad
                                                    and the flight termination receiver failed              of U.S. space transportation services                  Bridge across the Delaware River, mile
                                                    to activate. Thus, the casualty                         could help achieve this goal by allowing               104.6, at Pennsauken Township, NJ.
                                                    expectation given the assumption of the                 the United States Government to invest                 This proposed regulation will allow the
                                                    worst possible failure would on average                 a greater share of its resources in other              bridge to be remotely operated from the
                                                                                                            needs such as facilities modernization,                Conrail South Jersey dispatch center in
                                                    still produce significantly less casualties
                                                                                                            technology advancement, scientific                     Mount Laurel, NJ, instead of being
                                                    than the FAA’s limit of 1 in 10,000,
                                                                                                            discovery, and national security.                      operated by an on-site bridge tender.
                                                    which does not assume failure but
                                                                                                            Further, a healthier, more competitive                 This regulation will not change the
                                                    rather assigns realistic failure                                                                               operating schedule of the bridge.
                                                    probabilities. Also, the flight                         U.S. space transportation industry
                                                                                                            would facilitate new markets, encourage                DATES: Comments and related material
                                                    termination receiver’s failsafe feature
                                                                                                            new industries, create high technology                 must reach the Coast Guard on or before
                                                    will terminate thrust if there is a loss of
                                                                                                            jobs, lead to greater economic growth                  August 18, 2017.
                                                    power or Radio Frequency carrier or
                                                                                                            and security, and would further the                    ADDRESSES: You may submit comments
mstockstill on DSK30JT082PROD with PROPOSALS




                                                    pilot tone signal, providing an
                                                    additional safety margin. For these                     Nation’s leadership role in space.                     identified by docket number USCG–
                                                                                                               More specifically, Rocket Lab will be               2016–0257 using Federal eRulemaking
                                                    reasons, the FAA has determined that
                                                                                                            carrying onboard the Electron launch                   Portal at http://www.regulations.gov.
                                                    waiving sections E417.7(f)(2) and (5) for
                                                                                                            vehicle on its inaugural launch a flight                 See the ‘‘Public Participation and
                                                    the Electron test flight missions from
                                                                                                            test experiment for NASA Kennedy                       Request for Comments’’ portion of the
                                                    Mahia, New Zealand will not jeopardize                  Space Center which will improve public                 SUPPLEMENTARY INFORMATION section
                                                    public health and safety or safety of                   risk mitigation capabilities from an                   below for instructions on submitting
                                                    property.                                               errant launch vehicle. This component                  comments.


                                               VerDate Sep<11>2014   15:56 Jun 29, 2017   Jkt 241001   PO 00000   Frm 00021   Fmt 4702   Sfmt 4702   E:\FR\FM\30JNP1.SGM   30JNP1


                                                                                         Federal Register / Vol. 82, No. 125 / Friday, June 30, 2017 / Proposed Rules                                                                                  29801

                                                    FOR FURTHER INFORMATION CONTACT:       If                                     owned and operated by Conrail Shared                                          will be restructured from its current
                                                    you have questions on this proposed                                           Assets, has a vertical clearance of 49 feet                                   configuration to clearly distinguish the
                                                    rule, call or email Mr. Hal R. Pitts, Fifth                                   above mean high water in the closed-to-                                       remote operation of the DELAIR
                                                    Coast Guard District (dpb); telephone                                         navigation position. There is a daily                                         Memorial Railroad Bridge. This
                                                    (757) 398–6222, email Hal.R.Pitts@                                            average of 28 New Jersey Transit trains                                       proposed operating regulation allows
                                                    uscg.mil.                                                                     and eight Conrail freight trains that                                         the bridge to be operated remotely from
                                                    SUPPLEMENTARY INFORMATION:                                                    cross the bridge and a daily average of                                       the bridge owner’s South Jersey
                                                                                                                                  three bridge openings that allow one or                                       dispatch center in Mount Laurel, NJ.
                                                    I. Table of Abbreviations
                                                                                                                                  more vessels to transit through the                                              The Delaware River is used by a
                                                    CFR Code of Federal Regulations                                               bridge during each opening. The bridge                                        variety of vessels, including deep draft
                                                    DHS Department of Homeland Security                                           is normally maintained in the closed                                          commercial vessels, tug and barge
                                                    FR Federal Register                                                           position due to the average daily                                             traffic, recreational vessels, and public
                                                    NPRM Notice of proposed rulemaking                                            number of trains crossing the bridge.                                         vessels, including military vessels of
                                                    § Section
                                                    U.S.C. United States Code
                                                                                                                                  The operating schedule is published in                                        various sizes. The three-year average
                                                                                                                                  33 CFR 117.716. This current operating                                        number of bridge openings and
                                                    II. Background, Purpose and Legal                                             schedule has been in effect since 1984                                        maximum number of bridge openings by
                                                    Basis                                                                         and will not change with the                                                  month and overall for 2013 through
                                                       The DELAIR Memorial Railroad                                               implementation of remote operation of                                         2015, as drawn from the data contained
                                                    Bridge across the Delaware River, mile                                        the bridge. However, within this                                              in the bridge tender logs, is presented
                                                    104.6, at Pennsauken Township, NJ,                                            proposed operating schedule, § 117.716                                        below.

                                                                                                                                                                                                                                       Average      Maximum
                                                                                                                                       Month                                                                                           openings     openings

                                                    January ....................................................................................................................................................................               73           88
                                                    February ...................................................................................................................................................................               54           56
                                                    March .......................................................................................................................................................................              80           94
                                                    April ..........................................................................................................................................................................           55           68
                                                    May ..........................................................................................................................................................................             60           67
                                                    June .........................................................................................................................................................................             60           71
                                                    July ...........................................................................................................................................................................          122          162
                                                    August ......................................................................................................................................................................             112          138
                                                    September ...............................................................................................................................................................                 143          201
                                                    October ....................................................................................................................................................................              109          117
                                                    November ................................................................................................................................................................                 100          116
                                                    December ................................................................................................................................................................                 100          122
                                                    Monthly ....................................................................................................................................................................               89          201
                                                    Daily .........................................................................................................................................................................             3            7



                                                       The bridge owner and the maritime                                          (marine), marine radar, a dedicated                                           bridge tender in visibility of the
                                                    community have been working together                                          telephone line for bridge operations,                                         waterway and bridge and in signals
                                                    since 2013 in an effort to incorporate                                        radio telephone on VHF–FM channels                                            (communications) via sound and visual
                                                    sensors and other technologies into the                                       13 and 16, and an automated                                                   signals and radio telephone (voice) via
                                                    bridge and the Conrail South Jersey                                           identification system (AIS) transmitter                                       VHF–FM channels 13 and 16. The
                                                    dispatch center to allow for the safe and                                     to provide bridge status. The AIS                                             remote operation system also
                                                    effective remote operation of the bridge.                                     transmitter has been installed on the                                         incorporates real-time bridge status via
                                                       On April 12, 2017, the Coast Guard                                         New Jersey side of the bridge at the                                          AIS signal to aid mariners in voyage
                                                    published a temporary deviation                                               bridge and land intersection in                                               planning and navigational decision-
                                                    entitled ‘‘Drawbridge Operation                                               approximate position 39°58′50.52″ N.                                          making, a dedicated telephone line
                                                    Regulation; Delaware River, Pennsauken                                        (39.9807), 75°03′58.75″ W. (¥75.06632).                                       (856) 231–2301 for bridge operations,
                                                    Township, NJ’’ in the Federal Register                                        The AIS transmitter is assigned                                               and push-to-talk (PTT) capability on
                                                    (82 FR 17561). This test deviation                                            maritime mobile service identity                                              VHF–FM channel 13.
                                                    allows the bridge to be operated                                              (MMSI) number 993663001 and will                                                 The signals for the remote operation
                                                    remotely from the bridge owner’s South                                        provide the status of the bridge (open/                                       center or on-site bridge tender to
                                                    Jersey dispatch center in Mount Laurel,                                       closed/inoperative) via the name                                              respond to a sound signal for a bridge
                                                    NJ. This test deviation is effective from                                     transmitted by the private aids to                                            opening will include: (1) When the
                                                    8 a.m. on April 24, 2017, to 7:59 a.m.                                        navigation as DELAIR BRG–OPEN (fully                                          draw can be opened immediately—a
                                                    on October 21, 2017.                                                          open and locked position, channel light                                       sound signal of one prolonged blast
                                                                                                                                  green), DELAIR BRG–CLOSED (other                                              followed by one short blast and
                                                    III. Discussion of Proposed Rule                                              than fully open, not inoperative), or                                         illumination of a fixed white light not
mstockstill on DSK30JT082PROD with PROPOSALS




                                                      This proposed operating regulation                                          DELAIR BRG–INOP (other than fully                                             more than 30 seconds after the
                                                    will allow the bridge to be operated                                          open, inoperative). The AIS transmitter                                       requesting signal, and (2) when the
                                                    remotely from the bridge owner’s South                                        will transmit the bridge status every two                                     draw cannot be opened immediately—
                                                    Jersey dispatch center in Mount Laurel,                                       minutes and upon a change in the                                              five short blasts sounded in rapid
                                                    NJ. The remote operation system will                                          bridge status.                                                                succession and illumination of a fixed
                                                    include eight camera views (four marine                                          The remote operation system is                                             red light not more 30 seconds after the
                                                    and four rail), two forward-looking                                           designed to provide equal or greater                                          vessel’s opening signal. The signals for
                                                    infrared equipped camera views                                                capabilities compared to the on-site                                          the remote operation center or on-site


                                               VerDate Sep<11>2014          15:56 Jun 29, 2017          Jkt 241001       PO 00000        Frm 00022        Fmt 4702       Sfmt 4702       E:\FR\FM\30JNP1.SGM               30JNP1


                                                    29802                     Federal Register / Vol. 82, No. 125 / Friday, June 30, 2017 / Proposed Rules

                                                    bridge tender to respond to a visual                    pursuant to OMB guidance it is exempt                  proposed rule or any policy or action of
                                                    signal for a bridge opening will include:               from the requirements of Executive                     the Coast Guard.
                                                    (1) When the draw can be opened                         Order 13771.
                                                                                                              The determination that this NPRM is                  C. Collection of Information
                                                    immediately—illumination of a fixed
                                                    white light not more than 30 seconds                    not a significant regulatory action is                   This proposed rule would call for no
                                                    after the requesting signal, and (2) when               based on the findings that: (1) Vessels                new collection of information under the
                                                    the draw cannot be opened                               will continue to transit the bridge in                 Paperwork Reduction Act of 1995 (44
                                                    immediately—illumination of a fixed                     accordance with 33 CFR 117.716, (2) the                U.S.C. 3501–3520.).
                                                    red light not more than 30 seconds after                remote operation system is designed to
                                                                                                                                                                   D. Federalism and Indian Tribal
                                                    the vessel’s opening signal. The fixed                  provide equal or greater capabilities
                                                                                                                                                                   Government
                                                    white light will remain illuminated                     compared to the on-site bridge tender,
                                                    until the bridge reaches the fully open                 and (3) the bridge owner will be capable                  A rule has implications for federalism
                                                    position. The fixed white and red lights                of restoring on-site operation of the                  under Executive Order 13132,
                                                    will be positioned on the east (New                     bridge within 60 minutes if the remote                 Federalism, if it has a substantial direct
                                                    Jersey) bridge abutment adjacent to the                 operation system fails.                                effect on the states, on the relationship
                                                    navigation span.                                                                                               between the national government and
                                                                                                            B. Impact on Small Entities                            the states, or on the distribution of
                                                       Vessels that require an opening shall
                                                    continue to request an opening via the                     The Regulatory Flexibility Act of 1980              power and responsibilities among the
                                                    methods defined in 33 CFR 117.15(b)                     (RFA), 5 U.S.C. 601–612, as amended,                   various levels of government. We have
                                                    through (d) (sound or visual signals or                 requires federal agencies to consider the              analyzed this proposed rule under that
                                                    radio telephone (VHF–FM) voice                          potential impact of regulations on small               Order and have determined that it is
                                                    communications), via telephone at (856)                 entities during rulemaking. The term                   consistent with the fundamental
                                                    231–2301, or via push-to-talk (PTT) on                  ‘‘small entities’’ comprises small                     federalism principles and preemption
                                                    VHF–FM channel 13. Vessels may push                     businesses, not-for-profit organizations               requirements described in Executive
                                                    the PTT button five times while on                      that are independently owned and                       Order 13132.
                                                    VHF–FM channel 13 to request an                         operated and are not dominant in their                    Also, this proposed rule does not have
                                                    opening.                                                fields, and governmental jurisdictions                 tribal implications under Executive
                                                       The remote operation system will be                  with populations of less than 50,000.                  Order 13175, Consultation and
                                                    considered in a failed condition and                    The Coast Guard certifies under 5 U.S.C.               Coordination with Indian Tribal
                                                    qualified personnel will return and                     605(b) that this proposed rule would not               Governments, because it would not have
                                                    operate the bridge within 60 minutes if                 have a significant economic impact on                  a substantial direct effect on one or
                                                    any of the following conditions are                     a substantial number of small entities.                more Indian tribes, on the relationship
                                                    found: (1) The remote operation system                  There are no known adverse impacts to                  between the federal government and
                                                    becomes incapable of safely and                         any entities related to this proposed                  Indian tribes, or on the distribution of
                                                    effectively operating the bridge from the               rule, given no aspects of the remote                   power and responsibilities between the
                                                    remote operation center, (2) visibility of              operating system for the bridge will                   federal government and Indian tribes. If
                                                    the waterway or bridge is degraded to                   create any burdens on any entity as                    you believe this proposed rule has
                                                    less than equal that of an on-site bridge               described in section IV.A above. The                   implications for federalism or Indian
                                                    tender (all eight camera views are                      incorporation of the automated                         tribes, please contact the person listed
                                                    required), (3) signals (communications)                 identification system (AIS) capability                 in the FOR FURTHER INFORMATION
                                                    via sound or visual signals or radio                    into the remote operation system is                    CONTACT section above.
                                                    telephone (voice) via VHF–FM channels                   expected to aid mariners who have AIS
                                                                                                            capability or access to computer-based                 E. Unfunded Mandates Reform Act
                                                    13 or 16 become inoperative, or (4) AIS
                                                    becomes inoperative.                                    AIS data in safely navigating through                     The Unfunded Mandates Reform Act
                                                                                                            the bridge by providing real-time bridge               of 1995 (Act) (2 U.S.C. 1531–1538)
                                                    IV. Regulatory Analyses                                 status.                                                requires federal agencies to assess the
                                                      We developed this proposed rule after                    If you think that your business,                    effects of their discretionary regulatory
                                                    considering numerous statutes and                       organization, or governmental                          actions. In particular, the Act addresses
                                                    Executive Orders related to rulemaking.                 jurisdiction qualifies as a small entity               actions that may result in the
                                                    Below we summarize our analyses                         and that this rule would have a                        expenditure by a state, local, or tribal
                                                    based on these statutes and Executive                   significant economic impact on it,                     government, in the aggregate, or by the
                                                    Orders, and we discuss First                            please submit a comment (see                           private sector of $100,000,000 (adjusted
                                                    Amendment rights of protestors.                         ADDRESSES) explaining why you think it                 for inflation) or more in any one year.
                                                                                                            qualifies, and how, and to what degree                 Though this proposed rule will not
                                                    A. Regulatory Planning and Review                       this rule would economically affect it.                result in such an expenditure, we do
                                                       Executive Orders 12866 and 13563                        Under section 213(a) of the Small                   discuss the effects of this proposed rule
                                                    direct agencies to assess the costs and                 Business Regulatory Enforcement                        elsewhere in this preamble.
                                                    benefits of available regulatory                        Fairness Act of 1996 (Pub. L. 104–121),
                                                    alternatives and, if regulation is                      we want to assist small entities in                    F. Environment
                                                    necessary, to select regulatory                         understanding this proposed rule. If the                 We have analyzed this proposed rule
                                                    approaches that maximize net benefits.                  rule would affect your small business,                 under Department of Homeland
mstockstill on DSK30JT082PROD with PROPOSALS




                                                    Executive Order 13771 directs agencies                  organization, or governmental                          Security Management Directive 023–01
                                                    to control regulatory costs through a                   jurisdiction and you have questions                    and Commandant Instruction
                                                    budgeting process. This NPRM has not                    concerning its provisions or options for               M16475.lD, which guides the Coast
                                                    been designated a ‘‘significant                         compliance, please contact the person                  Guard in complying with the National
                                                    regulatory action’’ under Executive                     listed in the FOR FURTHER INFORMATION                  Environmental Policy Act of 1969
                                                    Order 12866. Accordingly, the NPRM                      CONTACT section above. The Coast Guard                 (NEPA)(42 U.S.C. 4321–4370f), and
                                                    has not been reviewed by the Office of                  will not retaliate against small entities              have made a preliminary determination
                                                    Management and Budget (OMB), and                        that question or complain about this                   that this action is one of a category of


                                               VerDate Sep<11>2014   15:56 Jun 29, 2017   Jkt 241001   PO 00000   Frm 00023   Fmt 4702   Sfmt 4702   E:\FR\FM\30JNP1.SGM   30JNP1


                                                                              Federal Register / Vol. 82, No. 125 / Friday, June 30, 2017 / Proposed Rules                                           29803

                                                    actions which do not individually or                    the online docket and sign up for email                CLOSED (other than fully open, not
                                                    cumulatively have a significant effect on               alerts, you will be notified when                      inoperative), or DELAIR BRG–INOP
                                                    the human environment. This proposed                    comments are posted or a final rule is                 (other than fully open, inoperative). The
                                                    rule simply promulgates the operating                   published.                                             AIS transmitter will transmit the bridge
                                                    regulations or procedures for                                                                                  status every two minutes and upon a
                                                                                                            List of Subjects in 33 CFR Part 117
                                                    drawbridges. Normally, such actions are                                                                        change in the bridge status.
                                                    categorically excluded from further                       Bridges.                                                (3) The remote operation system will
                                                    review under figure 2–1, paragraph                        For the reasons discussed in the                     be considered in a failed condition and
                                                    (32)(e), of the Instruction.                            preamble, the Coast Guard proposes to                  qualified personnel will return and
                                                      A preliminary Record of                               amend 33 CFR part 117 as follows:                      operate the bridge within 60 minutes if
                                                    Environmental Consideration and a                                                                              any of the following conditions are
                                                    Memorandum for the Record are not                       PART 117—DRAWBRIDGE                                    found:
                                                    required for this rule. We seek any                     OPERATION REGULATIONS                                     (i) The remote operation system
                                                    comments or information that may lead                                                                          becomes incapable of safely and
                                                    to the discovery of a significant                       ■ 1. The authority citation for part 117
                                                                                                            continues to read as follows:                          effectively operating the bridge from the
                                                    environmental impact from this                                                                                 remote operation center; or
                                                    proposed rule.                                            Authority: 33 U.S.C. 499; 33 CFR 1.05–1;                (ii) Visibility of the waterway or
                                                                                                            and Department of Homeland Security                    bridge is degraded to less than equal
                                                    G. Protest Activities                                   Delegation No. 0170.1.
                                                                                                                                                                   that of an on-site bridge tender; or
                                                      The Coast Guard respects the First                    ■   2. Revise § 117.716 to read as follows:               (iii) Signals (communications) via
                                                    Amendment rights of protesters.                                                                                sound or visual signals or radio
                                                    Protesters are asked to contact the                     §117.716     Delaware River.
                                                                                                                                                                   telephone (voice) via VHF–FM channels
                                                    person listed in the FOR FURTHER                           (a) The following apply to all
                                                                                                                                                                   13 or 16 become inoperative; or
                                                    INFORMATION CONTACT section to                          drawbridges across the Delaware River:
                                                                                                                                                                      (iv) AIS becomes inoperative.
                                                    coordinate protest activities so that their                (1) The draws of railroad bridges need
                                                                                                            not be opened when there is a train in                    (4) Vessels that require an opening
                                                    message can be received without
                                                                                                            the bridge block approaching the bridge                shall continue to request an opening via
                                                    jeopardizing the safety or security of
                                                                                                            with the intention of crossing or within               the methods defined in § 117.15(b)
                                                    people, places, or vessels.
                                                                                                            five minutes of the known time of the                  through (d) (sound or visual signals or
                                                    V. Public Participation and Request for                 passage of a scheduled passenger train.                radio telephone (VHF–FM) voice
                                                    Comments                                                   (2) The opening of a bridge may not                 communications), via telephone at (856)
                                                       We view public participation as                      be delayed more than five minutes for                  231–2301, or via push-to-talk (PTT) on
                                                    essential to effective rulemaking and                   a highway bridge or 10 minutes for a                   VHF–FM channel 13. Vessels may push
                                                    will consider all comments and material                 railroad bridge after the signal to open               the PTT button five times while on
                                                    received during the comment period.                     is given.                                              VHF–FM channel 13 to request an
                                                    Your comment can help shape the                            (3) The owners of drawbridges shall                 opening.
                                                    outcome of this rulemaking. If you                      provide and keep in good legible                          (5) The signals for the remote
                                                    submit a comment, please include the                    condition two board gages painted                      operation center or on-site bridge tender
                                                    docket number for this rulemaking,                      white with black figures not less than                 to respond to a sound signal for a bridge
                                                    indicate the specific section of this                   six inches high to indicate the vertical               opening include:
                                                    document to which each comment                          clearance under the closed draw at all                    (i) When the draw can be opened
                                                    applies, and provide a reason for each                  stages of the tide. The gages shall be so              immediately—a sound signal of one
                                                    suggestion or recommendation.                           placed on the bridge that they are                     prolonged blast followed by one short
                                                       We encourage you to submit                           plainly visible to operators of vessels                blast and illumination of a fixed white
                                                    comments through the Federal                            approaching the bridge either up or                    light not more than 30 seconds after the
                                                    eRulemaking Portal at http://                           downstream.                                            requesting signal; or
                                                    www.regulations.gov. If your material                      (b) The draw of the Conrail Memorial                   (ii) When the draw cannot be opened
                                                    cannot be submitted using http://                       Railroad Bridge, mile 104.6, at                        immediately—five short blasts sounded
                                                    www.regulations.gov, contact the person                 Pennsauken Township, NJ shall be                       in rapid succession and illumination of
                                                    in the FOR FURTHER INFORMATION                          operated as follows:                                   a fixed red light not more 30 seconds
                                                    CONTACT section of this document for                       (1) The bridge will be remotely                     after the vessel’s opening signal.
                                                    alternate instructions.                                 operated from the Conrail South Jersey                    (6) The signals for the remote
                                                       We accept anonymous comments. All                    dispatch center in Mount Laurel, NJ                    operation center or on-site bridge tender
                                                    comments received will be posted                        unless the remote operation system is in               to respond to a visual signal for a bridge
                                                    without change to http://                               a failed condition.                                    opening include:
                                                    www.regulations.gov and will include                       (2) An AIS transmitter has been                        (i) When the draw can be opened
                                                    any personal information you have                       installed on the New Jersey side of the                immediately—illumination of a fixed
                                                    provided. For more about privacy and                    bridge at the bridge and land                          white light not more than 30 seconds
                                                    the docket, you may review a Privacy                    intersection in approximate position                   after the requesting signal; or
                                                    Act notice regarding the Federal Docket                 39°58′50.52″ N. (39.9807), 75°03′58.75″                   (ii) When the draw cannot be opened
                                                    Management System in the March 24,                      (-75.06632). The AIS transmitter is                    immediately—illumination of a fixed
mstockstill on DSK30JT082PROD with PROPOSALS




                                                    2005, issue of the Federal Register (70                 assigned maritime mobile service                       red light not more 30 seconds after the
                                                    FR 15086).                                              identity (MMSI) number 993663001.                      vessel’s opening signal.
                                                       Documents mentioned in this notice                   The status of the bridge (open/closed/                    (7) The fixed white light will remain
                                                    of proposed rulemaking and all public                   inoperative) will be provided via the                  illuminated until the bridge reaches the
                                                    comments are in our online docket at                    name transmitted by the AIS private                    fully open position. The fixed white and
                                                    http://www.regulations.gov and can be                   aids to navigation as DELAIR BRG–                      red lights will be positioned on the east
                                                    viewed by following that Web site’s                     OPEN (fully open and locked position,                  (New Jersey) bridge abutment adjacent
                                                    instructions. Additionally, if you go to                channel light green), DELAIR BRG–                      to the navigation span.


                                               VerDate Sep<11>2014   15:56 Jun 29, 2017   Jkt 241001   PO 00000   Frm 00024   Fmt 4702   Sfmt 4702   E:\FR\FM\30JNP1.SGM   30JNP1


                                                    29804                     Federal Register / Vol. 82, No. 125 / Friday, June 30, 2017 / Proposed Rules

                                                      Dated: June 19, 2017.                                 ADDRESSES:   Written petitions for                      uses of those materials by
                                                    M.L. Austin,                                            renewal of current exemptions must be                   individuals.’’ 4
                                                    Rear Admiral, U.S. Coast Guard, Commander,              completed using the form provided on                       These protections, codified in section
                                                    Fifth Coast Guard District.                             the Office’s Web site at https://                       1201 of title 17, United States Code, as
                                                    [FR Doc. 2017–13857 Filed 6–29–17; 8:45 am]             www.copyright.gov/1201/2018/renewal-                    envisioned by Congress, seek to balance
                                                    BILLING CODE 9110–04–P                                  petition.pdf. Written petitions proposing               the interests of copyright owners and
                                                                                                            new exemptions must be completed                        users, including the personal interests of
                                                                                                            using the form provided on the Office’s                 consumers, in the digital environment.5
                                                    LIBRARY OF CONGRESS                                     Web site at https://www.copyright.gov/                  Section 1201 does this by protecting the
                                                                                                            1201/2018/new-petition.pdf. The                         use of technological measures (also
                                                    Copyright Office                                        Copyright Office is using the                           called technological protection
                                                                                                            regulations.gov system for the                          measures or TPMs) used by copyright
                                                    37 CFR Part 201                                         submission and posting of public                        owners to prevent unauthorized access
                                                                                                            petitions and comments in this                          to or use of their works.6 Section 1201
                                                    [Docket No. 2017–10]                                                                                            contains three separate protections for
                                                                                                            proceeding. All petitions and comments
                                                    Exemptions To Permit Circumvention                      are therefore to be submitted                           TPMs. First, it prohibits circumvention
                                                    of Access Controls on Copyrighted                                                                               of technological measures employed by
                                                                                                            electronically through regulations.gov.
                                                    Works                                                                                                           or on behalf of copyright owners to
                                                                                                            Specific instructions for submitting
                                                                                                                                                                    protect access to their works (also
                                                    AGENCY:  U.S. Copyright Office, Library                 petitions and comments are available on
                                                                                                                                                                    known as access controls). Access
                                                    of Congress.                                            the Copyright Office Web site at https://
                                                                                                                                                                    controls include, for example, a
                                                                                                            www.copyright.gov/1201/2018. If
                                                    ACTION: Notice of inquiry and request for                                                                       password requirement limiting access to
                                                                                                            electronic submission is not feasible,                  a Web site to paying customers, or
                                                    petitions.
                                                                                                            please contact the Office using the                     authentication codes in video game
                                                    SUMMARY:   The United States Copyright                  contact information below for special                   consoles to prevent the playing of
                                                    Office is initiating the seventh triennial              instructions.                                           pirated copies. Second, the statute
                                                    rulemaking proceeding under the Digital                                                                         prohibits trafficking in devices or
                                                    Millennium Copyright Act (‘‘DMCA’’),                    FOR FURTHER INFORMATION CONTACT:
                                                                                                            Regan A. Smith, Deputy General                          services primarily designed to
                                                    concerning possible temporary                                                                                   circumvent access controls. Finally, it
                                                    exemptions to the DMCA’s prohibition                    Counsel, by email at resm@loc.gov,
                                                                                                            Anna Chauvet, Assistant General                         prohibits trafficking in devices or
                                                    against circumvention of technological                                                                          services primarily designed to
                                                    measures that control access to                         Counsel, by email at achau@loc.gov, or
                                                                                                                                                                    circumvent TPMs used to protect the
                                                    copyrighted works. In this proceeding,                  Jason E. Sloan, Attorney-Advisor, by
                                                                                                                                                                    copyright rights of the owner of a work
                                                    the Copyright Office is establishing a                  email at jslo@loc.gov. Each can be
                                                                                                                                                                    (also known as copy controls). Copy
                                                    new, streamlined procedure for the                      contacted by telephone by calling (202)
                                                                                                                                                                    controls protect against unauthorized
                                                    renewal of exemptions that were                         707–8350.
                                                                                                                                                                    uses of a copyrighted work once access
                                                    granted during the sixth triennial                      SUPPLEMENTARY INFORMATION:                              has been lawfully obtained. They
                                                    rulemaking. If renewed, those current                                                                           include, for example, technology
                                                    exemptions would remain in force for                    I. The Digital Millennium Copyright Act                 preventing the copying of an e-book
                                                    an additional three-year period (October                and Section 1201                                        after it has been downloaded to a user’s
                                                    2018—October 2021). Members of the                                                                              device. Because title 17 already forbids
                                                    public seeking the renewal of current                      The Digital Millennium Copyright Act
                                                                                                            (‘‘DMCA’’) 1 has played a pivotal role in               copyright infringement, there is no
                                                    exemptions should submit petitions as                                                                           corresponding ban on the act of
                                                    described below; parties opposing such                  the development of the modern digital
                                                                                                                                                                    circumventing a copy control.7 These
                                                    renewal will then have the opportunity                  economy. Enacted by Congress in 1998
                                                                                                                                                                    prohibitions supplement the preexisting
                                                    to file comments in response. The Office                to implement the United States’
                                                                                                                                                                    rights of copyright owners under the
                                                    is also accepting petitions for new                     obligations under two international
                                                                                                                                                                    Copyright Act of 1976 by establishing
                                                    exemptions to engage in activities not                  treaties,2 the DMCA was intended to
                                                                                                                                                                    separate and distinct causes of action
                                                    currently permitted by existing                         foster the growth and development of a                  independent of any infringement of
                                                    exemptions, which may include                           thriving, innovative, and flexible digital              copyright.8
                                                    proposals that expand upon a current                    marketplace by making digital networks                     At the same time, section 1201
                                                    exemption. Those petitions, and any                     safe places to disseminate and use                      contains a number of discrete, statutory
                                                    renewal petitions that are meaningfully                 copyrighted materials.3 It did this by,                 exemptions to these prohibitions, to
                                                    opposed, will be considered pursuant to                 among other things, ensuring adequate                   avoid curtailing legitimate activities
                                                    a more comprehensive rulemaking                         legal protections for copyrighted content               such as security testing, law
                                                    process similar to that used for the sixth              to ‘‘support new ways of disseminating                  enforcement activities, or the protection
                                                    rulemaking (i.e., three rounds of written               copyrighted materials to users, and to                  of personally identifying information.9
                                                    comment, followed by public hearings).                  safeguard the availability of legitimate                In addition, to accommodate changing
                                                    DATES: Written petitions for renewal of                                                                         marketplace realities and ensure that
                                                    current exemptions must be received no                    1 Public  Law 105–304, 112 Stat. 2860 (1998).         access to copyrighted works for lawful
                                                    later than 11:59 p.m. Eastern Time on                     2 WIPO   Copyright Treaty, Dec. 20, 1996, 36 I.L.M.
mstockstill on DSK30JT082PROD with PROPOSALS




                                                    July 31, 2017. Written comments in                      65 (1997); WIPO Performances and Phonograms               4 House    Manager’s Report at 6.
                                                                                                            Treaty, Dec. 20, 1996, 36 I.L.M. 76 (1997).
                                                    response to any petitions for renewal                      3 See Staff of H. Comm. on the Judiciary, 105th
                                                                                                                                                                      5 See    H.R. Rep. No. 105–551, pt. 2, at 26.
                                                    must be received no later than 11:59                    Cong., Section-by-Section Analysis of H.R. 2281 as
                                                                                                                                                                       6 17 U.S.C. 1201(a)–(b).
                                                                                                                                                                       7 S. Rep. No. 105–190, at 12.
                                                    p.m. Eastern Time on September 13,                      Passed by the United States House of
                                                                                                                                                                       8 U.S. Copyright Office, Section 1201 of Title 17,
                                                    2017. Written petitions for new                         Representatives on August 4th, 1998, at 2, 6 (Comm.
                                                                                                            Print 1998) (‘‘House Manager’s Report’’); H.R. Rep.     at i, iii, 43–45 (June 2017), https://
                                                    exemptions must be received no later                    No. 105–551, pt. 2, at 21, 23 (1998); H.R. Rep. No.     www.copyright.gov/policy/1201/section-1201-full-
                                                    than 11:59 p.m. Eastern Time on                         105–551, pt. 1, at 10 (1998); S. Rep. No. 105–190,      report.pdf (‘‘Section 1201 Study’’).
                                                    September 13, 2017.                                     at 1–2, 8–9 (1998).                                        9 17 U.S.C. 1201(d)–(j).




                                               VerDate Sep<11>2014   15:56 Jun 29, 2017   Jkt 241001   PO 00000   Frm 00025   Fmt 4702   Sfmt 4702   E:\FR\FM\30JNP1.SGM      30JNP1



Document Created: 2017-06-30 06:01:41
Document Modified: 2017-06-30 06:01:41
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionProposed Rules
ActionNotice of proposed rulemaking.
DatesComments and related material must reach the Coast Guard on or before August 18, 2017.
ContactIf you have questions on this proposed rule, call or email Mr. Hal R. Pitts, Fifth Coast Guard District (dpb); telephone (757) 398-6222, email [email protected]
FR Citation82 FR 29800 
RIN Number1625-AA09

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR