The U.S. Nuclear Regulatory Commission (NRC) is issuing final NUREG-2191, ``Generic Aging Lessons Learned for Subsequent License Renewal (GALL-SLR) Report,'' Vol. 1 and Vol. 2, and NUREG-2192, ``Standard Review Plan for Review of Subsequent License Renewal Applications for Nuclear Power Plants'' (SRP-SLR). These final documents describe methods acceptable to the NRC staff for granting a subsequent license renewal in accordance with the license renewal regulations, as well as techniques that will be used by the NRC staff in evaluating applications for subsequent license renewal.

Federal Register, Volume 82 Issue 134 (Friday, July 14, 2017)
[Federal Register Volume 82, Number 134 (Friday, July 14, 2017)]
[Notices]
[Page 32588]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-14747]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2015-0251]


Final Guidance Documents for Subsequent License Renewal

AGENCY: Nuclear Regulatory Commission.

ACTION: NUREG; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing final 
NUREG-2191, ``Generic Aging Lessons Learned for Subsequent License 
Renewal (GALL-SLR) Report,'' Vol. 1 and Vol. 2, and NUREG-2192, 
``Standard Review Plan for Review of Subsequent License Renewal 
Applications for Nuclear Power Plants'' (SRP-SLR). These final 
documents describe methods acceptable to the NRC staff for granting a 
subsequent license renewal in accordance with the license renewal 
regulations, as well as techniques that will be used by the NRC staff 
in evaluating applications for subsequent license renewal.

DATES: July 14, 2017.

ADDRESSES: Please refer to Docket ID NRC-2015-0251 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2015-0251. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individuals listed in the FOR FURTHER INFORMATION CONTACT section 
of this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
``Generic Aging Lessons Learned for Subsequent License Renewal (GALL-
SLR) Report,'' Vol. 1.; ``Generic Aging Lessons Learned for Subsequent 
License Renewal (GALL-SLR) Report,'' Vol. 2, and the ``Standard Review 
Plan for Review of Subsequent License Renewal Applications for Nuclear 
Power Plants'' (SRP-SLR) are available in ADAMS under Accession Nos. 
ML17187A031, ML17187A204 and ML17188A158, respectively.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Bennett Brady, telephone: 301-415-
2981, email: [email protected] or Sheldon Stuchell, telephone: 301-
415-1213, email: [email protected]; both are staff of the Office 
of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, 
Washington DC 20555-0001.

SUPPLEMENTARY INFORMATION: 

I. Discussion

    The Atomic Energy Act (AEA) of 1954, as amended, authorizes the NRC 
to issue 40-year initial licenses and upon application and approval, 
subsequently renew licenses for nuclear power reactors. The NRC's 
regulations permit these licenses to be renewed beyond the initial 40-
year term for an additional period of time, limited to 20-year 
increments per renewal, based on the outcome of an assessment to 
determine if the nuclear facility can continue to operate safely during 
the period of extended operation. There are no limitations in the AEA 
or the NRC's regulations restricting the number of times a license may 
be renewed.
    The nuclear power industry has sent letters of intent to apply for 
subsequent license renewals in fiscal years 2018 and 2019. Subsequent 
License Renewal is a term referring to all license renewals allowing a 
plant to operate beyond the 60-year period (40-year of an initial 
operating license and a 20-year period of the first license renewal). 
Based on a survey conducted by the nuclear power industry and provided 
to the NRC, the NRC staff believes that additional applications for 
subsequent license renewal will be submitted in future years.
    The NRC developed guidance for licensees that intend to apply for 
subsequent license renewal. The guidance documents for first license 
renewal (i.e., for operation from 40 to 60 years), the Generic Aging 
Lessons Learned Report, Revision 2 (GALL Report Rev. 2, ADAMS Accession 
No. ML103490041), and the Standard Review Plan for Review of License 
Renewal Applications, Revision 2 (SRP-LR Rev. 2, ADAMS Accession No. 
ML103490036) were revised to reflect aging differences for increased 
operating time from 60 to 80 years. The guidance was also revised to 
consider new operating experience and provide information identified as 
missing since the release of GALL Report Rev. 2. The GALL-SLR Report 
and SRP-SLR also include changes that have been previously issued for 
public comment as part of the staff's license renewal Interim Staff 
Guidance (ISG) process. These ISGs can be found at http://www.nrc.gov/reading-rm/doc-collections/isg/license-renewal.html. These ISGs 
(ML12286A275, ML11297A085, ML12138A296, ML12270A436, ML12044A215, 
ML12352A057, ML13227A361, ML15308A018, and ML16237A383) have been 
incorporated into the GALL-SLR Report and the associated sections of 
the SRP-SLR. The NRC has previously received public comments on these 
ISGs, and is not requesting additional comments.
    A notice of availability, requesting comment on the draft Guidance 
Documents was published in the Federal Register on December 23, 2015 
(80 FR 79956). The public comment period ended on February 29, 2016. 
The NRC received 508 comments on these draft guidance documents. The 
NRC also published a supplement to the draft guidance documents in the 
Federal Register on March 29, 2016 (81 FR 17500). The public comment 
period ended on May 31, 2016. The NRC reviewed and dispositioned all of 
the comments and is publishing the disposition of the comments and the 
technical bases for their disposition in companion NUREGs. The NRC's 
resolution of these comments are incorporated into the final subsequent 
license renewal guidance documents.

II. Congressional Review Act

    This NUREG is a rule as defined in the Congressional Review Act (5 
U.S.C. 801-808). However, the Office of Management and Budget has not 
found it to be a major rule as defined in the Congressional Review Act.

    Dated at Rockville, Maryland, this 7th day of July 2017.

    For the Nuclear Regulatory Commission.
George A. Wilson Jr.,
Director, Division of License Renewal, Office of Nuclear Reactor 
Regulation.
[FR Doc. 2017-14747 Filed 7-13-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                  32588                            Federal Register / Vol. 82, No. 134 / Friday, July 14, 2017 / Notices

                                                    Dated: July 12, 2017.                                  Subsequent License Renewal (GALL–                     ML103490041), and the Standard
                                                  Denise L. McGovern,                                      SLR) Report,’’ Vol. 1.; ‘‘Generic Aging               Review Plan for Review of License
                                                  Policy Coordinator, Office of the Secretary.             Lessons Learned for Subsequent License                Renewal Applications, Revision 2 (SRP–
                                                  [FR Doc. 2017–14933 Filed 7–12–17; 4:15 pm]              Renewal (GALL–SLR) Report,’’ Vol. 2,                  LR Rev. 2, ADAMS Accession No.
                                                  BILLING CODE 7590–01–P
                                                                                                           and the ‘‘Standard Review Plan for                    ML103490036) were revised to reflect
                                                                                                           Review of Subsequent License Renewal                  aging differences for increased operating
                                                                                                           Applications for Nuclear Power Plants’’               time from 60 to 80 years. The guidance
                                                  NUCLEAR REGULATORY                                       (SRP–SLR) are available in ADAMS                      was also revised to consider new
                                                  COMMISSION                                               under Accession Nos. ML17187A031,                     operating experience and provide
                                                                                                           ML17187A204 and ML17188A158,                          information identified as missing since
                                                  [NRC–2015–0251]
                                                                                                           respectively.                                         the release of GALL Report Rev. 2. The
                                                  Final Guidance Documents for                               • NRC’s PDR: You may examine and                    GALL–SLR Report and SRP–SLR also
                                                  Subsequent License Renewal                               purchase copies of public documents at                include changes that have been
                                                                                                           the NRC’s PDR, Room O1–F21, One                       previously issued for public comment as
                                                  AGENCY: Nuclear Regulatory                               White Flint North, 11555 Rockville                    part of the staff’s license renewal
                                                  Commission.                                              Pike, Rockville, Maryland 20852.                      Interim Staff Guidance (ISG) process.
                                                  ACTION: NUREG; issuance.                                 FOR FURTHER INFORMATION CONTACT:                      These ISGs can be found at http://
                                                                                                           Bennett Brady, telephone: 301–415–                    www.nrc.gov/reading-rm/doc-
                                                  SUMMARY:    The U.S. Nuclear Regulatory                  2981, email: Bennett.Brady@nrc.gov or                 collections/isg/license-renewal.html.
                                                  Commission (NRC) is issuing final                        Sheldon Stuchell, telephone: 301–415–                 These ISGs (ML12286A275,
                                                  NUREG–2191, ‘‘Generic Aging Lessons                      1213, email: Sheldon.Stuchell@nrc.gov;                ML11297A085, ML12138A296,
                                                  Learned for Subsequent License                           both are staff of the Office of Nuclear               ML12270A436, ML12044A215,
                                                  Renewal (GALL–SLR) Report,’’ Vol. 1                      Reactor Regulation, U.S. Nuclear                      ML12352A057, ML13227A361,
                                                  and Vol. 2, and NUREG–2192,                              Regulatory Commission, Washington DC                  ML15308A018, and ML16237A383)
                                                  ‘‘Standard Review Plan for Review of                     20555–0001.                                           have been incorporated into the GALL–
                                                  Subsequent License Renewal                                                                                     SLR Report and the associated sections
                                                                                                           SUPPLEMENTARY INFORMATION:
                                                  Applications for Nuclear Power Plants’’                                                                        of the SRP–SLR. The NRC has
                                                  (SRP–SLR). These final documents                         I. Discussion                                         previously received public comments
                                                  describe methods acceptable to the NRC                      The Atomic Energy Act (AEA) of                     on these ISGs, and is not requesting
                                                  staff for granting a subsequent license                  1954, as amended, authorizes the NRC                  additional comments.
                                                  renewal in accordance with the license                   to issue 40-year initial licenses and                    A notice of availability, requesting
                                                  renewal regulations, as well as                          upon application and approval,                        comment on the draft Guidance
                                                  techniques that will be used by the NRC                  subsequently renew licenses for nuclear               Documents was published in the
                                                  staff in evaluating applications for                     power reactors. The NRC’s regulations                 Federal Register on December 23, 2015
                                                  subsequent license renewal.                              permit these licenses to be renewed                   (80 FR 79956). The public comment
                                                  DATES: July 14, 2017.                                    beyond the initial 40-year term for an                period ended on February 29, 2016. The
                                                  ADDRESSES: Please refer to Docket ID                     additional period of time, limited to 20-             NRC received 508 comments on these
                                                  NRC–2015–0251 when contacting the                        year increments per renewal, based on                 draft guidance documents. The NRC
                                                  NRC about the availability of                            the outcome of an assessment to                       also published a supplement to the draft
                                                  information regarding this document.                     determine if the nuclear facility can                 guidance documents in the Federal
                                                  You may obtain publicly-available                        continue to operate safely during the                 Register on March 29, 2016 (81 FR
                                                  information related to this document                     period of extended operation. There are               17500). The public comment period
                                                  using any of the following methods:                      no limitations in the AEA or the NRC’s                ended on May 31, 2016. The NRC
                                                     • Federal Rulemaking Web site: Go to                  regulations restricting the number of                 reviewed and dispositioned all of the
                                                  http://www.regulations.gov and search                    times a license may be renewed.                       comments and is publishing the
                                                  for Docket ID NRC–2015–0251. Address                        The nuclear power industry has sent                disposition of the comments and the
                                                  questions about NRC dockets to Carol                     letters of intent to apply for subsequent             technical bases for their disposition in
                                                  Gallagher; telephone: 301–415–3463;                      license renewals in fiscal years 2018                 companion NUREGs. The NRC’s
                                                  email: Carol.Gallagher@nrc.gov. For                      and 2019. Subsequent License Renewal                  resolution of these comments are
                                                  technical questions, contact the                         is a term referring to all license renewals           incorporated into the final subsequent
                                                  individuals listed in the FOR FURTHER                    allowing a plant to operate beyond the                license renewal guidance documents.
                                                  INFORMATION CONTACT section of this                      60-year period (40-year of an initial
                                                  document.                                                operating license and a 20-year period                II. Congressional Review Act
                                                     • NRC’s Agencywide Documents                          of the first license renewal). Based on a                This NUREG is a rule as defined in
                                                  Access and Management System                             survey conducted by the nuclear power                 the Congressional Review Act (5 U.S.C.
                                                  (ADAMS): You may obtain publicly-                        industry and provided to the NRC, the                 801–808). However, the Office of
                                                  available documents online in the                        NRC staff believes that additional                    Management and Budget has not found
                                                  ADAMS Public Documents collection at                     applications for subsequent license                   it to be a major rule as defined in the
                                                  http://www.nrc.gov/reading-rm/                           renewal will be submitted in future                   Congressional Review Act.
                                                  adams.html. To begin the search, select                  years.
                                                  ‘‘ADAMS Public Documents’’ and then                         The NRC developed guidance for                        Dated at Rockville, Maryland, this 7th day
mstockstill on DSK30JT082PROD with NOTICES




                                                                                                                                                                 of July 2017.
                                                  select ‘‘Begin Web-based ADAMS                           licensees that intend to apply for
                                                  Search.’’ For problems with ADAMS,                       subsequent license renewal. The                          For the Nuclear Regulatory Commission.
                                                  please contact the NRC’s Public                          guidance documents for first license                  George A. Wilson Jr.,
                                                  Document Room (PDR) reference staff at                   renewal (i.e., for operation from 40 to 60            Director, Division of License Renewal, Office
                                                  1–800–397–4209, 301–415–4737, or by                      years), the Generic Aging Lessons                     of Nuclear Reactor Regulation.
                                                  email to pdr.resource@nrc.gov. The                       Learned Report, Revision 2 (GALL                      [FR Doc. 2017–14747 Filed 7–13–17; 8:45 am]
                                                  ‘‘Generic Aging Lessons Learned for                      Report Rev. 2, ADAMS Accession No.                    BILLING CODE 7590–01–P




                                             VerDate Sep<11>2014   17:44 Jul 13, 2017   Jkt 241001   PO 00000   Frm 00061   Fmt 4703   Sfmt 9990   E:\FR\FM\14JYN1.SGM   14JYN1



Document Created: 2018-10-24 11:16:05
Document Modified: 2018-10-24 11:16:05
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNUREG; issuance.
DatesJuly 14, 2017.
ContactBennett Brady, telephone: 301-415- 2981, email: [email protected] or Sheldon Stuchell, telephone: 301- 415-1213, email: [email protected]; both are staff of the Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington DC 20555-0001.
FR Citation82 FR 32588 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR