82_FR_3313 82 FR 3306 - Mountain Regional Water Special Services District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

82 FR 3306 - Mountain Regional Water Special Services District; Notice of Preliminary Determination of a Qualifying Conduit Hydropower Facility and Soliciting Comments and Motions To Intervene

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 7 (January 11, 2017)

Page Range3306-3306
FR Document2017-00379

Federal Register, Volume 82 Issue 7 (Wednesday, January 11, 2017)
[Federal Register Volume 82, Number 7 (Wednesday, January 11, 2017)]
[Notices]
[Page 3306]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-00379]



[[Page 3306]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CD17-7-000]


Mountain Regional Water Special Services District; Notice of 
Preliminary Determination of a Qualifying Conduit Hydropower Facility 
and Soliciting Comments and Motions To Intervene

    On December 30, 2016, Mountain Regional Water Special Services 
District filed a notice of intent to construct a qualifying conduit 
hydropower facility, pursuant to section 30 of the Federal Power Act 
(FPA), as amended by section 4 of the Hydropower Regulatory Efficiency 
Act of 2013 (HREA). The proposed Silver Creek Hydro Energy Recovery 
Facility Project would have a maximum installed capacity of 200 
kilowatts (kW) and would be located on Signal Hill Water Treatment 
Plant's proposed 14-inch-diameter water transmission pipe, in an 
existing pump station. The project would be located in Park City, in 
Summit County, Utah.
    Applicant Contact: Doug Evans--Water and Energy Manager, Mountain 
Regional Water Special Services District, P.O. Box 982320, 6421 N 
Business Park Loop Road, Suite A, Park City, UT 84098, Phone No. (435) 
940-1916, Extension 313.
    FERC Contact: Robert Bell, Phone No. (202) 502-6062, email: 
[email protected].
    Qualifying Conduit Hydropower Facility Description: The proposed 
project would consist of: (1) Two proposed generating units with a 
maximum installed capacity of 200-kW on a proposed 14-inch-diameter, 
5,800 foot-long water distribution pipe, located in an existing pump 
station, discharging into a new 2 million gallon water storage tank; 
and (2) appurtenant facilities. The proposed project would have an 
initial estimated annual generating capacity of 250 megawatt-hours, and 
increase to approximately 1,000 megawatt-hours by 2022.
    A qualifying conduit hydropower facility is one that is determined 
or deemed to meet all of the criteria shown in the table below.

      Table 1--Criteria for Qualifying Conduit Hydropower Facility
------------------------------------------------------------------------
                                                            Satisfies (Y/
       Statutory provision               Description             N)
------------------------------------------------------------------------
FPA 30(a)(3)(A), as amended by    The conduit is a tunnel,            Y
 HREA.                             canal, pipeline,
                                   aqueduct, flume, ditch,
                                   or similar manmade
                                   water conveyance that
                                   is operated for the
                                   distribution of water
                                   for agricultural,
                                   municipal, or
                                   industrial consumption
                                   and not primarily for
                                   the generation of
                                   electricity.
FPA 30(a)(3)(C)(i), as amended    The facility is                     Y
 by HREA.                          constructed, operated,
                                   or maintained for the
                                   generation of electric
                                   power and uses for such
                                   generation only the
                                   hydroelectric potential
                                   of a non-federally
                                   owned conduit.
FPA 30(a)(3)(C)(ii), as amended   The facility has an                 Y
 by HREA.                          installed capacity that
                                   does not exceed 5
                                   megawatts.
FPA 30(a)(3)(C)(iii), as amended  On or before August 9,              Y
 by HREA.                          2013, the facility is
                                   not licensed, or
                                   exempted from the
                                   licensing requirements
                                   of Part I of the FPA.
------------------------------------------------------------------------

    Preliminary Determination: Based upon the above criteria, 
Commission staff has preliminarily determined that the proposal 
satisfies the requirements for a qualifying conduit hydropower facility 
under 16 U.S.C. 823a, and is exempted from the licensing requirements 
of the FPA.
    Comments and Motions to Intervene: The deadline for filing comments 
contesting whether the facility meets the qualifying criteria is 45 
days from the issuance date of this notice.
    The deadline for filing motions to intervene is 30 days from the 
issuance date of this notice.
    Anyone may submit comments or a motion to intervene in accordance 
with the requirements of Rules of Practice and Procedure, 18 CFR 
385.210 and 385.214. Any motions to intervene must be received on or 
before the specified deadline date for the particular proceeding.
    Filing and Service of Responsive Documents: All filings must (1) 
bear in all capital letters the ``COMMENTS CONTESTING QUALIFICATION FOR 
A CONDUIT HYDROPOWER FACILITY'' or ``MOTION TO INTERVENE,'' as 
applicable; (2) state in the heading the name of the applicant and the 
project number of the application to which the filing responds; (3) 
state the name, address, and telephone number of the person filing; and 
(4) otherwise comply with the requirements of sections 385.2001 through 
385.2005 of the Commission's regulations.\1\ All comments contesting 
Commission staff's preliminary determination that the facility meets 
the qualifying criteria must set forth their evidentiary basis.
---------------------------------------------------------------------------

    \1\ 18 CFR 385.2001-2005 (2015).
---------------------------------------------------------------------------

    The Commission strongly encourages electronic filing. Please file 
motions to intervene and comments using the Commission's eFiling system 
at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit 
brief comments up to 6,000 characters, without prior registration, 
using the eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You must include your name and contact information at the 
end of your comments. For assistance, please contact FERC Online 
Support at [email protected], (866) 208-3676 (toll free), or 
(202) 502-8659 (TTY). In lieu of electronic filing, please send a paper 
copy to: Secretary, Federal Energy Regulatory Commission, 888 First 
Street NE., Washington, DC 20426. A copy of all other filings in 
reference to this application must be accompanied by proof of service 
on all persons listed in the service list prepared by the Commission in 
this proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    Locations of Notice of Intent: Copies of the notice of intent can 
be obtained directly from the applicant or such copies can be viewed 
and reproduced at the Commission in its Public Reference Room, Room 2A, 
888 First Street NE., Washington, DC 20426. The filing may also be 
viewed on the web at http://www.ferc.gov/docs-filing/elibrary.asp using 
the ``eLibrary'' link. Enter the docket number (e.g., CD17-7-000) in 
the docket number field to access the document. For assistance, call 
toll-free 1-866-208-3676 or email [email protected]. For TTY, 
call (202) 502-8659.

    Dated: January 4, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00379 Filed 1-10-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                3306                        Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices

                                                DEPARTMENT OF ENERGY                                    proposed Silver Creek Hydro Energy                       Qualifying Conduit Hydropower
                                                                                                        Recovery Facility Project would have a                 Facility Description: The proposed
                                                Federal Energy Regulatory                               maximum installed capacity of 200                      project would consist of: (1) Two
                                                Commission                                              kilowatts (kW) and would be located on                 proposed generating units with a
                                                [Docket No. CD17–7–000]                                 Signal Hill Water Treatment Plant’s                    maximum installed capacity of 200-kW
                                                                                                        proposed 14-inch-diameter water                        on a proposed 14-inch-diameter, 5,800
                                                Mountain Regional Water Special                         transmission pipe, in an existing pump                 foot-long water distribution pipe,
                                                Services District; Notice of Preliminary                station. The project would be located in               located in an existing pump station,
                                                Determination of a Qualifying Conduit                   Park City, in Summit County, Utah.                     discharging into a new 2 million gallon
                                                Hydropower Facility and Soliciting                         Applicant Contact: Doug Evans—                      water storage tank; and (2) appurtenant
                                                Comments and Motions To Intervene                       Water and Energy Manager, Mountain                     facilities. The proposed project would
                                                   On December 30, 2016, Mountain                       Regional Water Special Services                        have an initial estimated annual
                                                Regional Water Special Services District                District, P.O. Box 982320, 6421 N                      generating capacity of 250 megawatt-
                                                filed a notice of intent to construct a                 Business Park Loop Road, Suite A, Park                 hours, and increase to approximately
                                                qualifying conduit hydropower facility,                 City, UT 84098, Phone No. (435) 940–                   1,000 megawatt-hours by 2022.
                                                pursuant to section 30 of the Federal                   1916, Extension 313.                                     A qualifying conduit hydropower
                                                Power Act (FPA), as amended by section                     FERC Contact: Robert Bell, Phone No.                facility is one that is determined or
                                                4 of the Hydropower Regulatory                          (202) 502–6062, email: robert.bell@                    deemed to meet all of the criteria shown
                                                Efficiency Act of 2013 (HREA). The                      ferc.gov.                                              in the table below.

                                                                                  TABLE 1—CRITERIA FOR QUALIFYING CONDUIT HYDROPOWER FACILITY
                                                                                                                                                                                                    Satisfies
                                                             Statutory provision                                                             Description                                             (Y/N)

                                                FPA 30(a)(3)(A), as amended by HREA ...             The conduit is a tunnel, canal, pipeline, aqueduct, flume, ditch, or similar manmade                Y
                                                                                                      water conveyance that is operated for the distribution of water for agricultural, mu-
                                                                                                      nicipal, or industrial consumption and not primarily for the generation of electricity.
                                                FPA 30(a)(3)(C)(i), as amended by HREA              The facility is constructed, operated, or maintained for the generation of electric                 Y
                                                                                                      power and uses for such generation only the hydroelectric potential of a non-feder-
                                                                                                      ally owned conduit.
                                                FPA 30(a)(3)(C)(ii), as amended by HREA             The facility has an installed capacity that does not exceed 5 megawatts .....................       Y
                                                FPA 30(a)(3)(C)(iii), as amended by                 On or before August 9, 2013, the facility is not licensed, or exempted from the licens-             Y
                                                  HREA.                                               ing requirements of Part I of the FPA.



                                                   Preliminary Determination: Based                     filing responds; (3) state the name,                   by proof of service on all persons listed
                                                upon the above criteria, Commission                     address, and telephone number of the                   in the service list prepared by the
                                                staff has preliminarily determined that                 person filing; and (4) otherwise comply                Commission in this proceeding, in
                                                the proposal satisfies the requirements                 with the requirements of sections                      accordance with 18 CFR 4.34(b) and
                                                for a qualifying conduit hydropower                     385.2001 through 385.2005 of the                       385.2010.
                                                facility under 16 U.S.C. 823a, and is                   Commission’s regulations.1 All
                                                                                                                                                                 Locations of Notice of Intent: Copies
                                                exempted from the licensing                             comments contesting Commission staff’s
                                                                                                                                                               of the notice of intent can be obtained
                                                requirements of the FPA.                                preliminary determination that the
                                                   Comments and Motions to Intervene:                   facility meets the qualifying criteria                 directly from the applicant or such
                                                The deadline for filing comments                        must set forth their evidentiary basis.                copies can be viewed and reproduced at
                                                contesting whether the facility meets the                  The Commission strongly encourages                  the Commission in its Public Reference
                                                qualifying criteria is 45 days from the                 electronic filing. Please file motions to              Room, Room 2A, 888 First Street NE.,
                                                issuance date of this notice.                           intervene and comments using the                       Washington, DC 20426. The filing may
                                                   The deadline for filing motions to                   Commission’s eFiling system at http://                 also be viewed on the web at http://
                                                intervene is 30 days from the issuance                  www.ferc.gov/docs-filing/efiling.asp.                  www.ferc.gov/docs-filing/elibrary.asp
                                                date of this notice.                                    Commenters can submit brief comments                   using the ‘‘eLibrary’’ link. Enter the
                                                   Anyone may submit comments or a                      up to 6,000 characters, without prior                  docket number (e.g., CD17–7–000) in
                                                motion to intervene in accordance with                  registration, using the eComment system                the docket number field to access the
                                                the requirements of Rules of Practice                   at http://www.ferc.gov/docs-filing/                    document. For assistance, call toll-free
                                                and Procedure, 18 CFR 385.210 and                       ecomment.asp. You must include your                    1–866–208–3676 or email
                                                385.214. Any motions to intervene must                  name and contact information at the end                FERCOnlineSupport@ferc.gov. For TTY,
                                                be received on or before the specified                  of your comments. For assistance,                      call (202) 502–8659.
                                                deadline date for the particular                        please contact FERC Online Support at
                                                                                                                                                                 Dated: January 4, 2017.
                                                proceeding.                                             FERCOnlineSupport@ferc.gov, (866)
                                                   Filing and Service of Responsive                     208–3676 (toll free), or (202) 502–8659                Kimberly D. Bose,
                                                Documents: All filings must (1) bear in                                                                        Secretary.
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        (TTY). In lieu of electronic filing, please
                                                all capital letters the ‘‘COMMENTS                      send a paper copy to: Secretary, Federal               [FR Doc. 2017–00379 Filed 1–10–17; 8:45 am]
                                                CONTESTING QUALIFICATION FOR A                          Energy Regulatory Commission, 888                      BILLING CODE 6717–01–P
                                                CONDUIT HYDROPOWER FACILITY’’                           First Street NE., Washington, DC 20426.
                                                or ‘‘MOTION TO INTERVENE,’’ as                          A copy of all other filings in reference
                                                applicable; (2) state in the heading the                to this application must be accompanied
                                                name of the applicant and the project
                                                number of the application to which the                    1 18   CFR 385.2001–2005 (2015).



                                           VerDate Sep<11>2014   19:05 Jan 10, 2017   Jkt 241001   PO 00000   Frm 00027   Fmt 4703   Sfmt 9990   E:\FR\FM\11JAN1.SGM   11JAN1



Document Created: 2018-02-01 14:59:39
Document Modified: 2018-02-01 14:59:39
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 3306 

2025 Federal Register | Disclaimer | Privacy Policy