82_FR_3316 82 FR 3309 - Pomelo Connector, LLC; Notice of Application

82 FR 3309 - Pomelo Connector, LLC; Notice of Application

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 7 (January 11, 2017)

Page Range3309-3310
FR Document2017-00380

Federal Register, Volume 82 Issue 7 (Wednesday, January 11, 2017)
[Federal Register Volume 82, Number 7 (Wednesday, January 11, 2017)]
[Notices]
[Pages 3309-3310]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-00380]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-26-000]


Pomelo Connector, LLC; Notice of Application

    Take notice that on December 22, 2016, Pomelo Connector, LLC 
(Pomelo), 1331 Lamar Street, Suite 1675, Houston, Texas 77010, filed in 
Docket No. CP17-26-000 an application pursuant to sections 7(b) and 
7(c) of the Natural Gas Act (NGA), as amended, for authorization to: 
(i) Construct, own, operate, and maintain an approximately 14-mile 30-
inch-diameter pipeline in Nueces County, Texas; (ii) construct a 9,000 
horsepower compressor station; and (iii) abandon by lease the entire 
400,000 dekatherms per day of capacity to Texas Eastern Transmission, 
LP. Pomelo further requests a Part 157, Subpart F blanket certificate, 
all as more fully set forth in the application which is on file with 
the Commission and open to public inspection. The filing is available 
for review at the Commission in the Public Reference Room or may be 
viewed on the Commission's Web site web at http://www.ferc.gov using 
the ``eLibrary'' link. Enter the docket number excluding the last three 
digits in the docket number field to access the document. For 
assistance, contact FERC at [email protected] or call toll-
free, (886) 208-3676 or TYY, (202) 502-8659.
    Any questions concerning this application may be directed to Mark 
Fuqua, Senior Vice President, Pomelo Connector, LLC, 1331 Lamar Street, 
Suite 1675, Houston, Texas 77010, by telephone at (713) 308-8117.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit seven copies of filings made in the proceeding with the 
Commission and must mail a copy to the applicant and to every other 
party. Only parties to the proceeding can ask for court review of 
Commission orders in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party to the proceeding. The Commission's 
rules require that persons filing comments in opposition to the project 
provide copies of their protests only to the party or parties directly 
involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.

[[Page 3310]]

    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit an original and 7 copies of the protest or intervention to the 
Federal Energy regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: January 25, 2017.

    Dated: January 4, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00380 Filed 1-10-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                             Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices                                             3309

                                                PAD and any request to use alternative                   DEPARTMENT OF ENERGY                                  the date of issuance of the Commission
                                                licensing procedures.5                                                                                         staff’s EA.
                                                   Pursuant to 18 CFR 16.23(a), an                       Federal Energy Regulatory                                There are two ways to become
                                                existing licensee subject to section 15 of               Commission                                            involved in the Commission’s review of
                                                the FPA that fails to file a an NOI at                                                                         this project. First, any person wishing to
                                                least 5 years before the existing license                [Docket No. CP17–26–000]                              obtain legal status by becoming a party
                                                expires shall be deemed to have filed a                                                                        to the proceedings for this project
                                                notice indicating that it does not intend                Pomelo Connector, LLC; Notice of                      should, on or before the comment date
                                                to file an application for new license.                  Application                                           stated below file with the Federal
                                                Additionally, pursuant to 18 CFR                            Take notice that on December 22,                   Energy Regulatory Commission, 888
                                                16.24(a), an existing licensee that                      2016, Pomelo Connector, LLC (Pomelo),                 First Street NE., Washington, DC 20426,
                                                informs the Commission that it does not                  1331 Lamar Street, Suite 1675, Houston,               a motion to intervene in accordance
                                                intend to file an application, may not                   Texas 77010, filed in Docket No. CP17–                with the requirements of the
                                                file an application for a new license for                26–000 an application pursuant to                     Commission’s Rules of Practice and
                                                the project, either individually or in                   sections 7(b) and 7(c) of the Natural Gas             Procedure (18 CFR 385.214 or 385.211)
                                                conjunction with an entity or entities                   Act (NGA), as amended, for                            and the Regulations under the NGA (18
                                                that are not currently licensees of the                  authorization to: (i) Construct, own,                 CFR 157.10). A person obtaining party
                                                project.                                                 operate, and maintain an approximately                status will be placed on the service list
                                                   The Commission is not taking action                                                                         maintained by the Secretary of the
                                                                                                         14-mile 30-inch-diameter pipeline in
                                                on Algonquin’s late-filed NOI at this                                                                          Commission and will receive copies of
                                                                                                         Nueces County, Texas; (ii) construct a
                                                time; 6 however, Algonquin’s request to                                                                        all documents filed by the applicant and
                                                                                                         9,000 horsepower compressor station;
                                                delay filing the PAD or any request to                                                                         by all other parties. A party must submit
                                                                                                         and (iii) abandon by lease the entire
                                                use an alternative licensing process                                                                           seven copies of filings made in the
                                                                                                         400,000 dekatherms per day of capacity
                                                until August, 2017 is denied because the                                                                       proceeding with the Commission and
                                                                                                         to Texas Eastern Transmission, LP.
                                                requested delay would unreasonably                                                                             must mail a copy to the applicant and
                                                                                                         Pomelo further requests a Part 157,
                                                shorten the time available for                                                                                 to every other party. Only parties to the
                                                                                                         Subpart F blanket certificate, all as more
                                                preparation of a license application and/                                                                      proceeding can ask for court review of
                                                                                                         fully set forth in the application which
                                                or conducting necessary studies.                                                                               Commission orders in the proceeding.
                                                                                                         is on file with the Commission and open                  However, a person does not have to
                                                Instead, this notice sets a deadline of                  to public inspection. The filing is                   intervene in order to have comments
                                                120 days from the date of this notice for                available for review at the Commission                considered. The second way to
                                                Algonquin and competing applicants to                    in the Public Reference Room or may be                participate is by filing with the
                                                file NOIs, PADs, and requests to use an                  viewed on the Commission’s Web site                   Secretary of the Commission, as soon as
                                                alternative licensing process.                           web at http://www.ferc.gov using the                  possible, an original and two copies of
                                                   To the extent that Algonquin or any                   ‘‘eLibrary’’ link. Enter the docket                   comments in support of or in opposition
                                                competing applicant elects or is                         number excluding the last three digits in             to this project. The Commission will
                                                required to use the Commission’s ILP, a                  the docket number field to access the                 consider these comments in
                                                process plan will be issued within 180                   document. For assistance, contact FERC                determining the appropriate action to be
                                                days of this notice that accelerates the                 at FERCOnlineSupport@ferc.gov or call                 taken, but the filing of a comment alone
                                                steps of the ILP to allow for filing a new               toll-free, (886) 208–3676 or TYY, (202)               will not serve to make the filer a party
                                                license application by the December 3,                   502–8659.                                             to the proceeding. The Commission’s
                                                2019, deadline.                                             Any questions concerning this                      rules require that persons filing
                                                   Questions concerning this notice                      application may be directed to Mark                   comments in opposition to the project
                                                should be directed to John Baummer at                    Fuqua, Senior Vice President, Pomelo                  provide copies of their protests only to
                                                (202) 502–6837 or John.Baummer@                          Connector, LLC, 1331 Lamar Street,                    the party or parties directly involved in
                                                ferc.gov.                                                Suite 1675, Houston, Texas 77010, by                  the protest.
                                                  Dated: January 5, 2017.                                telephone at (713) 308–8117.                             Persons who wish to comment only
                                                Kimberly D. Bose,                                           Pursuant to section 157.9 of the                   on the environmental review of this
                                                Secretary.
                                                                                                         Commission’s rules, 18 CFR 157.9,                     project should submit an original and
                                                                                                         within 90 days of this Notice the                     two copies of their comments to the
                                                [FR Doc. 2017–00385 Filed 1–10–17; 8:45 am]
                                                                                                         Commission staff will either: Complete                Secretary of the Commission.
                                                BILLING CODE 6717–01–P
                                                                                                         its environmental assessment (EA) and                 Environmental commentors will be
                                                                                                         place it into the Commission’s public                 placed on the Commission’s
                                                   5 Algonquin’s December 8, 2016, filing indicates
                                                                                                         record (eLibrary) for this proceeding; or             environmental mailing list, will receive
                                                it is working to finalize the sale of the project to
                                                another entity by the end of the first quarter of 2017   issue a Notice of Schedule for                        copies of the environmental documents,
                                                and the additional time would ‘‘allow’’ the              Environmental Review. If a Notice of                  and will be notified of meetings
                                                potential purchaser time to prepare a PAD and            Schedule for Environmental Review is                  associated with the Commission’s
                                                select a licensing process. We note however that         issued, it will indicate, among other                 environmental review process.
                                                any transfer of ownership would require
                                                Commission approval. See FPA Section 8, 16 U.S.C.        milestones, the anticipated date for the              Environmental commentors will not be
                                                801 (2012) and 18 CFR part 9 (2016).                     Commission staff’s issuance of the EA                 required to serve copies of filed
                                                   6 Algonquin indicates that its NOI was late due       for this proposal. The filing of the EA               documents on all other parties.
                                                to ‘‘administrative oversight.’’ However,                in the Commission’s public record for                 However, the non-party commentors
sradovich on DSK3GMQ082PROD with NOTICES




                                                Commission staff sent letters reminding Algonquin
                                                of the NOI deadline on April 1, 2015, and February
                                                                                                         this proceeding or the issuance of a                  will not receive copies of all documents
                                                10, 2016. In addition, Commission staff contacted        Notice of Schedule for Environmental                  filed by other parties or issued by the
                                                Algonquin via email on August 16, 2016 and               Review will serve to notify federal and               Commission (except for the mailing of
                                                September 27, 2016 and via phone on March 15,            state agencies of the timing for the                  environmental documents issued by the
                                                2016 and December 5, 2016, to remind it of the NOI
                                                deadline. Algonquin suggests that due to a
                                                                                                         completion of all necessary reviews, and              Commission) and will not have the right
                                                ‘‘telecommunications failure,’’ it did not receive       the subsequent need to complete all                   to seek court review of the
                                                these messages.                                          federal authorizations within 90 days of              Commission’s final order.


                                           VerDate Sep<11>2014   19:05 Jan 10, 2017   Jkt 241001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\11JAN1.SGM   11JAN1


                                                3310                        Federal Register / Vol. 82, No. 7 / Wednesday, January 11, 2017 / Notices

                                                  The Commission strongly encourages                    Protests may be considered, but                        ‘‘eLibrary’’ link and is available for
                                                electronic filings of comments, protests                intervention is necessary to become a                  review in the Commission’s Public
                                                and interventions in lieu of paper using                party to the proceeding.                               Reference Room in Washington, DC.
                                                the ‘‘eFiling’’ link at http://                            eFiling is encouraged. More detailed                There is an ‘‘eSubscription’’ link on the
                                                www.ferc.gov. Persons unable to file                    information relating to filing                         Web site that enables subscribers to
                                                electronically should submit an original                requirements, interventions, protests,                 receive email notification when a
                                                and 7 copies of the protest or                          service, and qualifying facilities filings             document is added to a subscribed
                                                intervention to the Federal Energy                      can be found at: http://www.ferc.gov/                  docket(s). For assistance with any FERC
                                                regulatory Commission, 888 First Street                 docs-filing/efiling/filing-req.pdf. For                Online service, please email
                                                NE., Washington, DC 20426.                              other information, call (866) 208–3676                 FERCOnlineSupport@ferc.gov, or call
                                                  Comment Date: January 25, 2017.                       (toll free). For TTY, call (202) 502–8659.             (866) 208–3676 (toll free). For TTY, call
                                                  Dated: January 4, 2017.                                 Dated: January 5, 2017.                              (202) 502–8659.
                                                Kimberly D. Bose,                                       Nathaniel J. Davis, Sr.,                                  Comment Date: 5:00 p.m. Eastern time
                                                Secretary.                                              Deputy Secretary.                                      on January 13, 2017.
                                                [FR Doc. 2017–00380 Filed 1–10–17; 8:45 am]             [FR Doc. 2017–00390 Filed 1–10–17; 8:45 am]
                                                                                                                                                                 Dated: January 5, 2017.
                                                BILLING CODE 6717–01–P                                  BILLING CODE 6717–01–P
                                                                                                                                                               Kimberly D. Bose,
                                                                                                                                                               Secretary.
                                                DEPARTMENT OF ENERGY                                    DEPARTMENT OF ENERGY                                   [FR Doc. 2017–00384 Filed 1–10–17; 8:45 am]
                                                                                                                                                               BILLING CODE 6717–01–P
                                                Federal Energy Regulatory                               Federal Energy Regulatory
                                                Commission                                              Commission
                                                Combined Notice of Filings #2                           [Docket No. OR17–3–000]                                DEPARTMENT OF ENERGY

                                                   Take notice that the Commission                      Enbridge Energy, Limited Partnership;                  Federal Energy Regulatory
                                                received the following electric rate                    Notice of Filing of Supplement to                      Commission
                                                filings:                                                Facilities Surcharge Settlement
                                                   Docket Numbers: ER15–2114–002.                                                                              Notice of Effectiveness of Exempt
                                                                                                           Take notice that on December 14,                    Wholesale Generator Status
                                                   Applicants: Transource West Virginia,                2016, Enbridge Energy, Limited
                                                LLC, PJM Interconnection, L.L.C.                        Partnership (Petitioner), with the                                                                  Docket Nos.
                                                   Description: Compliance filing:                      support of the Canadian Association of
                                                Transource submits revisions to                         Petroleum Producers (CAPP), submitted                  ESS Lewes Project, LLC .............        EG17–1–000
                                                Attachment H–26 re: settlement 12/5/16                  a Supplement to the Facilities Surcharge               Comanche Peak Power Com-                    EG17–2–000
                                                to be effective 9/5/2015.                                                                                        pany LLC.
                                                                                                        Settlement approved by the Commission                  Clinton Battery Utility, LLC ..........     EG17–3–000
                                                   Filed Date: 1/4/17.                                  on June 30, 2004, in Docket No. OR04–                  CXA Sundevil Power I, Inc ..........        EG17–4–000
                                                   Accession Number: 20170104–5132.                     2–000 at 107 FERC ¶ 61,336 (2004).                     CXA Sundevil Power II, Inc .........        EG17–5–000
                                                   Comments Due: 5 p.m. ET 1/25/17.                        Any person desiring to intervene or to              Broadview Energy JN, LLC .........          EG17–6–000
                                                   Docket Numbers: ER17–748–000.                        protest this filing must file in                       Broadview Energy KW, LLC ........           EG17–7–000
                                                   Applicants: NorthWestern                             accordance with Rules 211 and 214 of                   Moapa Southern Paiute Solar,                EG17–8–000
                                                Corporation.                                                                                                     LLC.
                                                                                                        the Commission’s Rules of Practice and                 Ocean State Power LLC .............         EG17–9–000
                                                   Description: § 205(d) Rate Filing: SA                Procedure (18 CFR 385.211 and 385.214                  Applied Energy LLC ....................     EG17–10–000
                                                798—Agreement with Upper Missouri                       (2016)) on or before 5:00 p.m. Eastern                 Applied Energy LLC ....................     EG17–11–000
                                                Power Cooperative to be effective 1/6/                  time on the specified comment date.                    Javelina Wind Energy II, LLC ......         EG17–12–000
                                                2017.                                                   Protests will be considered by the                     ESS Snook Project, LLC .............        EG17–13–000
                                                   Filed Date: 1/5/17.                                  Commission in determining the                          ESS Rabbit Hill Project, LLC .......        EG17–14–000
                                                   Accession Number: 20170105–5085.                     appropriate action to be taken, but will               Bluestem Wind Energy, LLC .......           EG17–15–000
                                                   Comments Due: 5 p.m. ET 1/26/17.                     not serve to make protestants parties to
                                                                                                                                                               96WI 8me LLC ............................   EG17–16–000
                                                                                                                                                               TransCanada Maine Wind Devel-               EG17–17–000
                                                   Docket Numbers: ER17–749–000.                        the proceeding. Any person wishing to                    opment Inc.
                                                   Applicants: Southwest Power Pool,                    become a party must file a notice of                   Innovative Solar 47, LLC .............      EG17–18–000
                                                Inc.                                                    intervention or motion to intervene, as
                                                   Description: § 205(d) Rate Filing:                   appropriate. Such notices, motions, or                   Take notice that during the month of
                                                Violation Relaxation Limit Annual                       protests must be filed on or before the                December 2016, the status of the above-
                                                Update to be effective 3/6/2017.                        comment date. Anyone filing a motion                   captioned entities as Exempt Wholesale
                                                   Filed Date: 1/5/17.                                  to intervene or protest must serve a copy
                                                   Accession Number: 20170105–5116.                                                                            Generators became effective by
                                                                                                        of that document on Petitioner.
                                                   Comments Due: 5 p.m. ET 1/26/17.                                                                            operation of the Commission’s
                                                                                                           The Commission encourages
                                                                                                                                                               regulations. 18 CFR 366.7(a) (2017)
                                                   The filings are accessible in the                    electronic submission of protests and
                                                Commission’s eLibrary system by                         interventions in lieu of paper using the                 Dated: January 5, 2017.
                                                clicking on the links or querying the                   ‘‘eFiling’’ link at http://www.ferc.gov.               Nathaniel J. Davis, Sr.,
                                                docket number.                                          Persons unable to file electronically
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                                                                               Deputy Secretary.
                                                   Any person desiring to intervene or                  should submit an original and 5 copies                 [FR Doc. 2017–00391 Filed 1–10–17; 8:45 am]
                                                protest in any of the above proceedings                 of the protest or intervention to the
                                                                                                                                                               BILLING CODE 6717–01–P
                                                must file in accordance with Rules 211                  Federal Energy Regulatory Commission,
                                                and 214 of the Commission’s                             888 First Street NE., Washington, DC
                                                Regulations (18 CFR 385.211 and                         20426.
                                                385.214) on or before 5:00 p.m. Eastern                    This filing is accessible on-line at
                                                time on the specified comment date.                     http://www.ferc.gov, using the


                                           VerDate Sep<11>2014   19:05 Jan 10, 2017   Jkt 241001   PO 00000   Frm 00031   Fmt 4703   Sfmt 9990   E:\FR\FM\11JAN1.SGM    11JAN1



Document Created: 2018-02-01 14:59:13
Document Modified: 2018-02-01 14:59:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
DatesJanuary 25, 2017.
FR Citation82 FR 3309 

2025 Federal Register | Disclaimer | Privacy Policy