82 FR 34992 - Southern Nuclear Operating Company, Inc., Vogtle Electric Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and Acceptance Criteria

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 82, Issue 143 (July 27, 2017)

Page Range34992-34993
FR Document2017-15754

The U.S. Nuclear Regulatory Commission (NRC) has determined that the inspections, tests, and analyses have been successfully completed, and that the specified acceptance criteria are met for the Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

Federal Register, Volume 82 Issue 143 (Thursday, July 27, 2017)
[Federal Register Volume 82, Number 143 (Thursday, July 27, 2017)]
[Notices]
[Pages 34992-34993]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-15754]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 52-025 and 52-026; NRC-2008-0252]


Southern Nuclear Operating Company, Inc., Vogtle Electric 
Generating Plant, Units 3 and 4; Inspections, Tests, Analyses, and 
Acceptance Criteria

AGENCY: Nuclear Regulatory Commission.

ACTION: Determination of the successful completion of inspections, 
tests, and analyses.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has determined 
that the inspections, tests, and analyses have been successfully 
completed, and that the specified acceptance criteria are met for the 
Vogtle Electric Generating Plant (VEGP), Units 3 and 4.

DATES: The determination of the successful completion of inspections, 
tests, and analyses for VEGP, Units 3 and 4 is effective July 27, 2017.

ADDRESSES: Please refer to Docket ID NRC-2008-0252 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2008-0252. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Chandu Patel, Office of New Reactors, 
U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; 
telephone: 301-415-3025; email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Licensee Notification of Completion of ITAAC

    Southern Nuclear Operating Company, Inc. (SNC), Georgia Power 
Company, Oglethorpe Power Corporation, MEAG Power SPVM, LLC., MEAG 
Power SPVJ, LLC., MEAG Power SPVP, LLC., and the City of Dalton, 
Georgia, (hereafter called the licensee) has submitted inspections, 
tests, analyses, and acceptance criteria (ITAAC) closure notifications 
(ICNs) under Sec.  52.99(c)(1) of title 10 of the Code of Federal 
Regulations (10 CFR), informing the NRC that the licensee has 
successfully performed the required inspections, tests, and analyses, 
and that the acceptance criteria are met for:

VEGP, Unit 3 ITAAC
    2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.2.01.06d.i (105), 2.2.03.09b 
(204), 2.3.05.02.ii (341), 2.5.02.07b (535), and 3.2.00.01c.i (741)
VEGP, Unit 4 ITAAC
    2.1.01.06.ii (7), 2.1.03.09a.i (81), 2.2.01.06d.i (105), 2.2.03.09b 
(204), 2.3.05.02.ii (341), 2.5.02.07b (535), and 3.2.00.01c.i (741)

    The ITAAC for VEGP, Unit 3 are in Appendix C of the VEGP, Unit 3 
combined license (ADAMS Accession No. ML14100A106). The ITAAC for VEGP, 
Unit 4 are in Appendix C of VEGP, Unit 4 combined license (ADAMS 
Accession No. ML14100A135).

II. NRC Staff Determination of Completion of ITAAC

    The NRC staff has determined that the specified inspections, tests, 
and analyses have been successfully completed, and that the specified 
acceptance criteria are met. The documentation of the NRC staff's 
determination is in the ITAAC Closure Verification Evaluation Form 
(VEF) for each ITAAC. The VEF is a form that represents the NRC staff's 
structured process for reviewing ICNs. Each ICN presents a narrative 
description of how the ITAAC was completed. The NRC's ICN review 
process involves a determination on whether, among other things: (1) 
each ICN provides sufficient information, including a summary of the 
methodology used to perform the ITAAC, to demonstrate that the 
inspections, tests, and analyses have been successfully completed; (2) 
each ICN provides sufficient information to demonstrate that the 
acceptance criteria of the ITAAC are met; and (3) any NRC inspections 
for the ITAAC have been completed and any ITAAC findings associated 
with that ITAAC have been closed.
    The NRC staff's determination of the successful completion of these 
ITAAC is based on information available at this time and is subject to 
the licensee's ability to maintain the condition that the acceptance 
criteria are met. If the NRC staff receives new information that 
suggests the NRC staff's determination on any of these ITAAC is 
incorrect, then the NRC staff will determine whether to reopen that 
ITAAC (including

[[Page 34993]]

withdrawing the NRC staff's determination on that ITAAC). The NRC 
staff's determination will be used to support a subsequent finding, 
pursuant to 10 CFR 52.103(g), at the end of construction that all 
acceptance criteria in the combined license are met. The ITAAC closure 
process is not finalized for these ITAAC until the NRC makes an 
affirmative finding under 10 CFR 52.103(g). Any future updates to the 
status of these ITAAC will be reflected on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/oversight/itaac.html.
    This notice fulfills the NRC staff's obligations under 10 CFR 
52.99(e)(1) to publish a notice in the Federal Register of the NRC 
staff's determination of the successful completion of inspections, 
tests and analyses.

Vogtle Electric Generating Plant Unit 3, Docket No. 5200025

    A complete list of the review status for VEGP, Unit 3 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the ADAMS Accession Number for each VEF, and the ADAMS 
Accession Numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog3-icnsr.pdf.

Vogtle Electric Generating Plant Unit 4, Docket No. 5200026

    A complete list of the review status for VEGP Unit 4 ITAAC, 
including the submission date and ADAMS Accession Number for each ICN 
received, the ADAMS Accession Number for each VEF, and the ADAMS 
Accession Numbers for the inspection reports associated with these 
specific ITAAC, can be found on the NRC's Web site at http://www.nrc.gov/reactors/new-reactors/new-licensing-files/vog4-icnsr.pdf.

    Dated at Rockville, Maryland, this 18th day of July 2017.

    For the Nuclear Regulatory Commission.
Jennifer Dixon-Herrity,
Chief, Licensing Branch 4, Division of New Reactor Licensing, Office of 
New Reactors.
[FR Doc. 2017-15754 Filed 7-26-17; 8:45 am]
BILLING CODE 7590-01-P


Current View
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionDetermination of the successful completion of inspections, tests, and analyses.
DatesThe determination of the successful completion of inspections, tests, and analyses for VEGP, Units 3 and 4 is effective July 27, 2017.
ContactChandu Patel, Office of New Reactors, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-3025; email: [email protected]
FR Citation82 FR 34992 