82_FR_37598 82 FR 37445 - Bonneville Power Administration; Notice of Filing

82 FR 37445 - Bonneville Power Administration; Notice of Filing

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 153 (August 10, 2017)

Page Range37445-37446
FR Document2017-16880

Federal Register, Volume 82 Issue 153 (Thursday, August 10, 2017)
[Federal Register Volume 82, Number 153 (Thursday, August 10, 2017)]
[Notices]
[Pages 37445-37446]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-16880]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EF17-4-000]


Bonneville Power Administration; Notice of Filing

    Take notice that on July 31, 2017, Bonneville Power Administration 
submitted tariff filing per: BP-18 IS-18 Rate to be effective 10/1/
2017.
    Any person desiring to intervene or to protest this filing must 
file in accordance with Rules 211 and 214 of the Commission's Rules of 
Practice and Procedure (18 CFR 385.211, 385.214). Protests will be 
considered by the Commission in determining the appropriate action to 
be taken, but will not serve to make protestants parties to the 
proceeding. Any person wishing to become a party must file a notice of 
intervention or motion to intervene, as appropriate. Such notices, 
motions, or protests must be filed on or before the comment date. On or 
before the comment date, it is not necessary to serve motions to 
intervene or protests on persons other than the Applicant.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper using the eFiling link at http://www.ferc.gov. Persons unable to file electronically should submit an 
original and 5 copies of the protest or intervention to the Federal 
Energy Regulatory Commission, 888 First Street NE., Washington, DC 
20426.
    This filing is accessible on-line at http://www.ferc.gov, using the 
eLibrary link and is available for review in the Commission's Public 
Reference Room in Washington, DC. There is an eSubscription link on the 
Web site that enables subscribers to receive email notification when a 
document is added

[[Page 37446]]

to a subscribed docket(s). For assistance with any FERC Online service, 
please email [email protected], or call (866) 208-3676 (toll 
free). For TTY, call (202) 502-8659.
    Comment Date: 5:00 p.m. Eastern Time on August 30, 2017.

    Dated: August 2, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-16880 Filed 8-9-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices                                                 37445

                                                  changes to the proposed electrical                      changes proposed in this amendment to                    Copies of this application amendment
                                                  configuration, which has been designed                  the location of the new, approximately                will be made available for public
                                                  to make the proposed Project more cost-                 two-mile, overhead, 230-kV AC                         inspection and copying (upon request)
                                                  effective for the Applicant.                            transmission line extending south from                at the address provided above, and by
                                                     The reconfiguration would connect                    the proposed Gateway Substation to the                accessing the program Web site at:
                                                  the proposed Project to the UNSE                        proposed international border crossing.               http://energy.gov/oe/services/electricity-
                                                  transmission system at the proposed                     The proposed reconfiguration would not                policy-coordination-and-
                                                  Gateway Substation rather than at the                   affect the location of the proposed route             implementation/international-
                                                  existing Valencia Substation, as initially              or ROW requirements, but certain                      electricity-regulatio-2.
                                                  proposed. A new, approximately 3-mile,                  changes were proposed to be made to                     Issued in Washington, DC, on August 3,
                                                  overhead double-circuit 138-kV AC                       the conductors and towers. A                          2017.
                                                  transmission line would be constructed                  comparison of the initial configuration               Christopher A. Lawrence,
                                                  on new monopoles. The first circuit                     and the reconfiguration for each of the               Electricity Policy Analyst, Transmission
                                                  would originate at an existing pole                     alternative routes is provided in the                 Permitting and Technical Assistance
                                                  1,900 feet west of the existing Valencia                application amendment.                                Division, Office of Electricity Delivery and
                                                  Substation and terminate at the                            The draft Environmental Assessment                 Energy Reliability.
                                                  proposed Gateway Substation. At this                    contains relevant figures in Chapters 1               [FR Doc. 2017–16882 Filed 8–9–17; 8:45 am]
                                                  origination point, the existing UNSE                    and 2. It can be downloaded from the                  BILLING CODE 6450–01–P
                                                  ‘‘Vail to Valencia’’ transmission line                  Document Library page on the project
                                                  would be severed and connected to this                  Web site: http://
                                                  new line, thereby converting the                        nogalesinterconnectionea.com/.                        DEPARTMENT OF ENERGY
                                                  existing UNSE ‘‘Vail to Valencia’’                         The Proposed Project One-line
                                                  transmission line to the ‘‘Vail to                      Diagram (Figure 2.4–5) illustrates the                Federal Energy Regulatory
                                                  Gateway’’ transmission line. The second                 details of the configuration as proposed              Commission
                                                  circuit would originate at the proposed                 by the amendment. A side-by-side
                                                                                                                                                                [Docket No. EF17–4–000]
                                                  Gateway Substation and proceed in an                    comparison of the reconfiguration to the
                                                  easterly direction to the same pole                     original application is also in the
                                                                                                                                                                Bonneville Power Administration;
                                                  (1,900 feet west of the existing Valencia               appendix to the Applicant’s amendment
                                                                                                                                                                Notice of Filing
                                                  Substation), where it would connect                     (which can also be downloaded from
                                                  with the existing portion of the UNSE                   the project Web site).                                   Take notice that on July 31, 2017,
                                                  138-kV ‘‘Vail to Valencia’’ transmission                   Procedural Matters: Any person may                 Bonneville Power Administration
                                                  line that travels east to the existing                  comment on this application by filing                 submitted tariff filing per: BP–18 IS–18
                                                  Valencia Substation. This circuit would                 such comment at the address provided                  Rate to be effective 10/1/2017.
                                                  constitute the new ‘‘Gateway to                         above. Any person seeking to become a                    Any person desiring to intervene or to
                                                  Valencia’’ transmission line and serve as               party to this proceeding must file a                  protest this filing must file in
                                                  the source for Valencia. The existing                   motion to intervene at the address                    accordance with Rules 211 and 214 of
                                                  UNSE Vail to Valencia line currently                    provided above in accordance with Rule                the Commission’s Rules of Practice and
                                                  connects to the Valencia Substation; this               214 of the Federal Energy Regulatory                  Procedure (18 CFR 385.211, 385.214).
                                                  line is the current (and only) source of                Commission’s Rules of Practice and                    Protests will be considered by the
                                                  power for the City of Nogales. The                      Procedure (18 CFR 385.214). Two copies                Commission in determining the
                                                  Valencia Substation is the first existing               of each comment or motion to intervene                appropriate action to be taken, but will
                                                  substation within the U.S. The Nogales                  should be filed with DOE on or before                 not serve to make protestants parties to
                                                  Interconnection project would change                    the date listed above.                                the proceeding. Any person wishing to
                                                  the configuration such that the Vail to                    Additional copies of such motions to               become a party must file a notice of
                                                  Valencia line would become the Vail to                  intervene also should be filed directly               intervention or motion to intervene, as
                                                  Gateway line. Because the Valencia                      with: Enrique Marroquin, Nogales                      appropriate. Such notices, motions, or
                                                  Substation still needs a source of power,               Transmission, L.L.C., 1900 North Akard                protests must be filed on or before the
                                                  the Gateway to Valencia line would be                   Street, Dallas, Texas 75201.                          comment date. On or before the
                                                  built. Minor modifications to relaying                     Before a Presidential permit may be                comment date, it is not necessary to
                                                  equipment within the Valencia                           issued or amended, DOE must                           serve motions to intervene or protests
                                                  Substation would be made to                             determine that the proposed action is in              on persons other than the Applicant.
                                                  accommodate this Gateway to Valencia                    the public interest. In making that                      The Commission encourages
                                                  line.                                                   determination, DOE considers the                      electronic submission of protests and
                                                     In addition to the DC tie at the                     environmental impacts of the proposed                 interventions in lieu of paper using the
                                                  Gateway site as initially proposed (now                 project pursuant to the National                      eFiling link at http://www.ferc.gov.
                                                  referred to as the Nogales Gateway                      Environmental Policy Act of 1969, as                  Persons unable to file electronically
                                                  Substation), on the eastern portion of                  amended, determines the project’s                     should submit an original and 5 copies
                                                  the Gateway site, a 138-kV UNSE                         impact on electric reliability by                     of the protest or intervention to the
                                                  Gateway Substation would consist of a                   ascertaining whether the proposed                     Federal Energy Regulatory Commission,
                                                  three bay breaker and a half open air                   project would adversely affect the                    888 First Street NE., Washington, DC
                                                  configuration to accommodate the line                   operation of the U.S. electric power                  20426.
                                                  from Vail, the line to Valencia, and the                supply system under normal and                           This filing is accessible on-line at
mstockstill on DSK30JT082PROD with NOTICES




                                                  connection to the DC tie, as well as a                  contingency conditions, and any other                 http://www.ferc.gov, using the eLibrary
                                                  future UNSE distribution transformer.                   factors that DOE may also consider                    link and is available for review in the
                                                  The Nogales Gateway Substation and                      relevant to the public interest. DOE also             Commission’s Public Reference Room in
                                                  the UNSE Gateway Substation would be                    must obtain the concurrences of the                   Washington, DC. There is an
                                                  located on the Gateway site and                         Secretary of State and the Secretary of               eSubscription link on the Web site that
                                                  collectively referred to as the Gateway                 Defense before taking final action on a               enables subscribers to receive email
                                                  Substation. There were no additional                    Presidential permit application.                      notification when a document is added


                                             VerDate Sep<11>2014   17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00028   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1


                                                  37446                       Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices

                                                  to a subscribed docket(s). For assistance                  Comments Due: 5 p.m. ET 8/24/17.                      Comments Due: 5 p.m. ET 8/25/17.
                                                  with any FERC Online service, please                       Take notice that the Commission                       Docket Numbers: ER17–2243–000.
                                                  email FERCOnlineSupport@ferc.gov, or                    received the following electric rate                     Applicants: Public Service Company
                                                  call (866) 208–3676 (toll free). For TTY,               filings:                                              of Oklahoma.
                                                  call (202) 502–8659.                                       Docket Numbers: ER17–1789–001.                        Description: 205(d) Rate Filing: PSO
                                                    Comment Date: 5:00 p.m. Eastern                          Applicants: Interstate Power and                   CSW Operating Companies MBR
                                                  Time on August 30, 2017.                                Light Company.                                        Concurrence Cancellation to be effective
                                                    Dated: August 2, 2017.                                   Description: Tariff Amendment:                     6/30/2017.
                                                  Nathaniel J. Davis, Sr.,                                Amendment to IPL Wholesale Tariff                        Filed Date: 8/4/17.
                                                  Deputy Secretary.                                       Application to be effective 8/8/2017.                    Accession Number: 20170804–5141.
                                                                                                             Filed Date: 8/4/17.                                   Comments Due: 5 p.m. ET 8/25/17.
                                                  [FR Doc. 2017–16880 Filed 8–9–17; 8:45 am]
                                                  BILLING CODE 6717–01–P
                                                                                                             Accession Number: 20170804–5189.                      Docket Numbers: ER17–2244–000.
                                                                                                             Comments Due: 5 p.m. ET 8/25/17.                      Applicants: PJM Interconnection,
                                                                                                             Docket Numbers: ER17–2075–001.                     L.L.C.
                                                  DEPARTMENT OF ENERGY                                       Applicants: Idaho Power Company.                      Description: Tariff Cancellation:
                                                                                                             Description: Tariff Amendment:                     Notice of Cancellation of
                                                  Federal Energy Regulatory                               Amendment to EIM Tariff Filing to be                  Interconnection Construction Service
                                                  Commission                                              effective 1/25/2018.                                  Agreement No 3460 to be effective 7/12/
                                                                                                             Filed Date: 8/4/17.                                2017.
                                                  Combined Notice of Filings #1                              Accession Number: 20170804–5179.                      Filed Date: 8/4/17.
                                                     Take notice that the Commission                         Comments Due: 5 p.m. ET 8/25/17.                      Accession Number: 20170804–5146.
                                                  received the following electric corporate                  Docket Numbers: ER17–2238–000.                        Comments Due: 5 p.m. ET 8/25/17.
                                                  filings:                                                   Applicants: Nexus Energy Inc.                         Docket Numbers: ER17–2245–000.
                                                     Docket Numbers: EC17–134–000.                           Description: Baseline eTariff Filing:                 Applicants: Moffett Solar 1, LLC.
                                                     Applicants: Ameren Illinois                          Nexus Energy Market-based Rate Tariff                    Description: Baseline eTariff Filing:
                                                  Company.                                                v1 to be effective 11/1/2017.                         Baseline—Market-Based Rate Tariff to
                                                     Description: Supplement to June 28,                     Filed Date: 8/4/17.                                be effective 9/1/2017.
                                                  2017 Application of Ameren Illinois                        Accession Number: 20170804–5004.                      Filed Date: 8/4/17.
                                                  Company for Authorization under                            Comments Due: 5 p.m. ET 8/25/17.                      Accession Number: 20170804–5158.
                                                  Section 203 of the Federal Power Act                       Docket Numbers: ER17–2239–000.                        Comments Due: 5 p.m. ET 8/25/17.
                                                  (revised Attachment N).                                    Applicants: NorthWestern                              Docket Numbers: ER17–2246–000.
                                                     Filed Date: 8/4/17.                                  Corporation.                                             Applicants: Midcontinent
                                                     Accession Number: 20170804–5130.                        Description: Notice of Termination of              Independent System Operator.
                                                     Comments Due: 5 p.m. ET 8/14/17.                     Transmission Service Agreement No.                       Description: § 205(d) Rate Filing:
                                                     Docket Numbers: EC17–149–000.                        19–SD of NorthWestern Corporation.                    2017–08–04_Tariff revisions to
                                                     Applicants: Bayshore Solar A, LLC.                      Filed Date: 8/3/17.                                implement regional cost allocation for
                                                     Description: Application for                            Accession Number: 20170803–5181.                   TMEPs to be effective 10/4/2017.
                                                  Authorization under Section 203 of the                     Comments Due: 5 p.m. ET 8/24/17.                      Filed Date: 8/4/17.
                                                  Federal Power Act the Disposition of                       Docket Numbers: ER17–2240–000.                        Accession Number: 20170804–5159.
                                                  Jurisdictional Facilities, Request for                     Applicants: New York Independent                      Comments Due: 5 p.m. ET 8/25/17.
                                                  Expedited Consideration and                             System Operator, Inc.                                    Docket Numbers: ER17–2247–000.
                                                  Confidential Treatment of Bay Shore                        Description: 205(d) Rate Filing: 205                  Applicants: PJM Interconnection,
                                                  Solar A, LLC.                                           filing re: Removal of Bunce Creek PARs                L.L.C.
                                                     Filed Date: 8/3/17.                                  cost recovery mechanism to be effective                  Description: § 205(d) Rate Filing:
                                                     Accession Number: 20170803–5179.                     10/3/2017.                                            Original Service Agreement No. 4591,
                                                     Comments Due: 5 p.m. ET 8/24/17.                        Filed Date: 8/4/17.                                Non-Queue No. NQ143 to be effective 7/
                                                     Docket Numbers: EC17–150–000.                           Accession Number: 20170804–5075.                   7/2017.
                                                     Applicants: Apple Blossom Wind,                         Comments Due: 5 p.m. ET 8/25/17.                      Filed Date: 8/4/17.
                                                  LLC.                                                       Docket Numbers: ER17–2241–000.                        Accession Number: 20170804–5168.
                                                     Description: Application for                            Applicants: PJM Interconnection,                      Comments Due: 5 p.m. ET 8/25/17.
                                                  Authorization of Transaction Pursuant                   L.L.C.                                                   Take notice that the Commission
                                                  to Section 203 of the Federal Power Act                    Description: 205(d) Rate Filing: First             received the following electric securities
                                                  and Request of Apple Blossom Wind,                      Revised Service Agreement No. 3903,                   filings:
                                                  LLC.                                                    Queue No. T174/AB1–106 to be                             Docket Numbers: ES17–51–000.
                                                     Filed Date: 8/4/17.                                  effective 7/9/2017.                                      Applicants: NorthWestern
                                                     Accession Number: 20170804–5170.                        Filed Date: 8/4/17.                                Corporation.
                                                     Comments Due: 5 p.m. ET 8/25/17.                        Accession Number: 20170804–5078.                      Description: Application for
                                                     Take notice that the Commission                         Comments Due: 5 p.m. ET 8/25/17.                   Authorization Under Section 204 of the
                                                  received the following exempt                              Docket Numbers: ER17–2242–000.                     Federal Power Act to Issue Securities of
                                                  wholesale generator filings:                               Applicants: Southern California                    NorthWestern Corporation.
mstockstill on DSK30JT082PROD with NOTICES




                                                     Docket Numbers: EG17–137–000.                        Edison Company.                                          Filed Date: 8/4/17.
                                                     Applicants: Techren Solar I LLC.                        Description: 205(d) Rate Filing:                      Accession Number: 20170804–5133.
                                                     Description: Notice of Self-                         Amended and Restated Silver Peak 55                      Comments Due: 5 p.m. ET 8/25/17.
                                                  Certification of Exempt Wholesale                       kV Interconnection Agreement to be                       The filings are accessible in the
                                                  Generator Status of Techren Solar I LLC.                effective 8/6/2017.                                   Commission’s eLibrary system by
                                                     Filed Date: 8/3/17.                                     Filed Date: 8/4/17.                                clicking on the links or querying the
                                                     Accession Number: 20170803–5195.                        Accession Number: 20170804–5110.                   docket number.


                                             VerDate Sep<11>2014   17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00029   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1



Document Created: 2017-08-10 01:01:36
Document Modified: 2017-08-10 01:01:36
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on August 30, 2017.
FR Citation82 FR 37445 

2025 Federal Register | Disclaimer | Privacy Policy