82_FR_37600 82 FR 37447 - Rover Pipeline LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Majorsville Compressor Station Amendment and Request for Comments on Environmental Issues

82 FR 37447 - Rover Pipeline LLC; Notice of Intent To Prepare an Environmental Assessment for the Proposed Majorsville Compressor Station Amendment and Request for Comments on Environmental Issues

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 153 (August 10, 2017)

Page Range37447-37448
FR Document2017-16878

Federal Register, Volume 82 Issue 153 (Thursday, August 10, 2017)
[Federal Register Volume 82, Number 153 (Thursday, August 10, 2017)]
[Notices]
[Pages 37447-37448]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-16878]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP17-464-000]


Rover Pipeline LLC; Notice of Intent To Prepare an Environmental 
Assessment for the Proposed Majorsville Compressor Station Amendment 
and Request for Comments on Environmental Issues

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) will prepare an environmental assessment (EA) that will 
discuss the environmental impacts of the Amendment to the Rover 
Pipeline Project involving construction and operation of facilities by 
Rover Pipeline, LLC (Rover) in Marshall County, West Virginia. The 
Commission will use this EA in its decision-making process to determine 
whether the project is in the public convenience and necessity.
    This notice announces the opening of the scoping process the 
Commission will use to gather input from the public and interested 
agencies on the project. You can make a difference by providing us with 
your specific comments or concerns about the project. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
Your input will help the Commission staff determine what issues they 
need to evaluate in the EA. To ensure that your comments are timely and 
properly recorded, please send your comments so that the Commission 
receives them in Washington, DC on or before September 4, 2017.
    If you sent comments on this amendment to the Commission before the 
opening of this docket on May 17, 2017, you will need to file those 
comments in Docket No. CP17-464-000 to ensure they are considered as 
part of this proceeding.
    This notice is being sent to the Commission's current environmental 
mailing list for this project. State and local government 
representatives should notify their constituents of this proposed 
project and encourage them to comment on their areas of concern.

Public Participation

    For your convenience, there are three methods you can use to submit 
your comments to the Commission. The Commission encourages electronic 
filing of comments and has expert staff available to assist you at 
(202) 502-8258 or [email protected]. Please carefully follow 
these instructions so that your comments are properly recorded.
    (1) You can file your comments electronically using the eComment 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can file your comments electronically by using the eFiling 
feature on the Commission's Web site (www.ferc.gov) under the link to 
Documents and Filings. With eFiling, you can provide comments in a 
variety of formats by attaching them as a file with your submission. 
New eFiling users must first create an account by clicking on 
eRegister. If you are filing a comment on a particular project, please 
select ``Comment on a Filing'' as the filing type; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address. Be sure to reference the project docket number 
(CP17-464-000 with your submission: Kimberly D. Bose, Secretary, 
Federal Energy Regulatory Commission, 888 First Street NE., Room 1A, 
Washington, DC 20426.

Summary of the Proposed Project

    Rover proposes to install a third 3,550 horsepower natural gas 
compressor unit at the Majorsville Compressor Station \1\ and a new 
equipment run at the Majorsville Meter Station in Marshall County, West 
Virginia. The new unit would bring the Majorsville Compressor Station 
to a total of 10,650 horsepower. The proposal would increase the point 
capacity of the Majorsville Compressor Station and the Majorsville 
Meter Station from 300 million cubic feet per day (MMcf/d) to 400 MMcf/
d. Rover would house the new unit (and the previously approved units) 
in a larger compressor building. Rover has not proposed to expand the 
station boundary beyond the previously approved limits. The general 
location of the project facilities is shown in appendix 1.\2\
---------------------------------------------------------------------------

    \1\ The Majorsville Compressor Station was approved by the 
Commission on February 2, 2017 in docket no. CP15-93-000 as a 
component of the Rover Pipeline Project and is currently under 
construction.
    \2\ The appendices referenced in this notice will not appear in 
the Federal Register. Copies of appendices were sent to all those 
receiving this notice in the mail and are available at www.ferc.gov 
using the link called eLibrary or from the Commission's Public 
Reference Room, 888 First Street NE., Washington, DC 20426, or call 
(202) 502-8371. For instructions on connecting to eLibrary, refer to 
the last page of this notice.
---------------------------------------------------------------------------

Land Requirements for Construction

    Construction of the proposed facilities would occur at Rover's 
previously approved and under construction Majorsville Compressor 
Station. Following construction, Rover would maintain about the 
project's facilities as part of operations associated with the Rover 
Pipeline Project.

The EA Process

    The National Environmental Policy Act (NEPA) requires the 
Commission to take into account the environmental impacts that could 
result from an action whenever it considers the issuance of a 
Certificate of Public Convenience and Necessity. NEPA also requires us 
\3\ to discover and address concerns the public may have about 
proposals. This process is referred to as scoping. The main goal of the 
scoping process is to focus the analysis in the EA on the important 
environmental issues. By this notice, the Commission requests public 
comments on the scope of the issues to address in the EA. We will 
consider all filed comments during the preparation of the EA.
---------------------------------------------------------------------------

    \3\ We, us, and our refer to the environmental staff of the 
Commission's Office of Energy Projects.
---------------------------------------------------------------------------

    In the EA we will discuss the environmental impacts that could 
occur as a result of the construction and operation of the proposed 
project. We will also evaluate reasonable alternatives to the proposed 
project or portions of the project, and make recommendations on how to 
lessen or avoid impacts on the various resource areas.
    The EA will present our independent analysis of the issues. The EA 
will be available in the public record through eLibrary. Depending on 
the comments

[[Page 37448]]

received during the scoping process, we may also publish and distribute 
the EA to the public for an allotted comment period. We will consider 
all comments on the EA before making our recommendations to the 
Commission. To ensure we have the opportunity to consider and address 
your comments, please carefully follow the instructions in the Public 
Participation section, beginning on page 2.
    With this notice, we are asking agencies with jurisdiction by law 
and/or special expertise with respect to the environmental issues of 
this project to formally cooperate with us in the preparation of the 
EA.\4\ Agencies that would like to request cooperating agency status 
should follow the instructions for filing comments provided under the 
Public Participation section of this notice.
---------------------------------------------------------------------------

    \4\ The Council on Environmental Quality regulations addressing 
cooperating agency responsibilities are at Title 40, Code of Federal 
Regulations, Part 1501.6.
---------------------------------------------------------------------------

Environmental Mailing List

    The environmental mailing list includes federal, state, and local 
government representatives and agencies; environmental and public 
interest groups; and other interested parties. This list also includes 
all affected landowners (as defined in the Commission's regulations) 
who are within 0.5 mile of the Majorsville Compressor Station, and 
anyone who submits comments on the project. We will update the 
environmental mailing list as the analysis proceeds to ensure that we 
send the information related to this environmental review to all 
individuals, organizations, and government entities interested in and/
or potentially affected by the proposed project.
    If we publish and distribute the EA, copies will be sent to the 
environmental mailing list for public review and comment. If you would 
prefer to receive a paper copy of the document instead of the CD 
version or would like to remove your name from the mailing list, please 
return the attached Information Request (appendix 2).

Becoming an Intervenor

    In addition to involvement in the EA scoping process, you may want 
to become an intervenor which is an official party to the Commission's 
proceeding. Intervenors play a more formal role in the process and are 
able to file briefs, appear at hearings, and be heard by the courts if 
they choose to appeal the Commission's final ruling. An intervenor 
formally participates in the proceeding by filing a request to 
intervene. Instructions for becoming an intervenor are in the Document-
less Intervention Guide under the e-filing link on the Commission's Web 
site. Motions to intervene are more fully described at http://www.ferc.gov/resources/guides/how-to/intervene.asp.

Additional Information

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC Web site at www.ferc.gov using the eLibrary link. Click on the 
eLibrary link, click on General Search and enter the docket number, 
excluding the last three digits in the Docket Number field (i.e., CP17-
464). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.
    Finally, any public sessions or site visits will be posted on the 
Commission's calendar located at www.ferc.gov/EventCalendar/EventsList.aspx along with other related information.

    Dated: August 4, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-16878 Filed 8-9-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                              Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices                                                    37447

                                                     Any person desiring to intervene or                  Washington, DC on or before September                 would bring the Majorsville Compressor
                                                  protest in any of the above proceedings                 4, 2017.                                              Station to a total of 10,650 horsepower.
                                                  must file in accordance with Rules 211                     If you sent comments on this                       The proposal would increase the point
                                                  and 214 of the Commission’s                             amendment to the Commission before                    capacity of the Majorsville Compressor
                                                  Regulations (18 CFR 385.211 and                         the opening of this docket on May 17,                 Station and the Majorsville Meter
                                                  385.214) on or before 5:00 p.m. Eastern                 2017, you will need to file those                     Station from 300 million cubic feet per
                                                  time on the specified comment date.                     comments in Docket No. CP17–464–000                   day (MMcf/d) to 400 MMcf/d. Rover
                                                  Protests may be considered, but                         to ensure they are considered as part of              would house the new unit (and the
                                                  intervention is necessary to become a                   this proceeding.                                      previously approved units) in a larger
                                                  party to the proceeding.                                   This notice is being sent to the                   compressor building. Rover has not
                                                     eFiling is encouraged. More detailed                 Commission’s current environmental                    proposed to expand the station
                                                  information relating to filing                          mailing list for this project. State and              boundary beyond the previously
                                                  requirements, interventions, protests,                  local government representatives should               approved limits. The general location of
                                                  service, and qualifying facilities filings              notify their constituents of this                     the project facilities is shown in
                                                  can be found at: http://www.ferc.gov/                   proposed project and encourage them to                appendix 1.2
                                                  docs-filing/efiling/filing-req.pdf. For                 comment on their areas of concern.
                                                                                                                                                                Land Requirements for Construction
                                                  other information, call (866) 208–3676                  Public Participation
                                                  (toll free). For TTY, call (202) 502–8659.                                                                      Construction of the proposed facilities
                                                                                                             For your convenience, there are three              would occur at Rover’s previously
                                                    Dated: August 4, 2017.                                methods you can use to submit your                    approved and under construction
                                                  Nathaniel J. Davis, Sr.,                                comments to the Commission. The                       Majorsville Compressor Station.
                                                  Deputy Secretary.                                       Commission encourages electronic filing               Following construction, Rover would
                                                  [FR Doc. 2017–16877 Filed 8–9–17; 8:45 am]              of comments and has expert staff                      maintain about the project’s facilities as
                                                  BILLING CODE 6717–01–P                                  available to assist you at (202) 502–8258             part of operations associated with the
                                                                                                          or FercOnlineSupport@ferc.gov. Please                 Rover Pipeline Project.
                                                                                                          carefully follow these instructions so
                                                                                                          that your comments are properly                       The EA Process
                                                  DEPARTMENT OF ENERGY
                                                                                                          recorded.                                                The National Environmental Policy
                                                  Federal Energy Regulatory                                  (1) You can file your comments                     Act (NEPA) requires the Commission to
                                                  Commission                                              electronically using the eComment                     take into account the environmental
                                                  [Docket No. CP17–464–000]                               feature on the Commission’s Web site                  impacts that could result from an action
                                                                                                          (www.ferc.gov) under the link to                      whenever it considers the issuance of a
                                                  Rover Pipeline LLC; Notice of Intent To                 Documents and Filings. This is an easy                Certificate of Public Convenience and
                                                  Prepare an Environmental Assessment                     method for submitting brief, text-only                Necessity. NEPA also requires us 3 to
                                                  for the Proposed Majorsville                            comments on a project;                                discover and address concerns the
                                                  Compressor Station Amendment and                           (2) You can file your comments                     public may have about proposals. This
                                                  Request for Comments on                                 electronically by using the eFiling                   process is referred to as scoping. The
                                                  Environmental Issues                                    feature on the Commission’s Web site                  main goal of the scoping process is to
                                                                                                          (www.ferc.gov) under the link to                      focus the analysis in the EA on the
                                                     The staff of the Federal Energy                      Documents and Filings. With eFiling,                  important environmental issues. By this
                                                  Regulatory Commission (FERC or                          you can provide comments in a variety                 notice, the Commission requests public
                                                  Commission) will prepare an                             of formats by attaching them as a file                comments on the scope of the issues to
                                                  environmental assessment (EA) that will                 with your submission. New eFiling                     address in the EA. We will consider all
                                                  discuss the environmental impacts of                    users must first create an account by                 filed comments during the preparation
                                                  the Amendment to the Rover Pipeline                     clicking on eRegister. If you are filing a            of the EA.
                                                  Project involving construction and                      comment on a particular project, please                  In the EA we will discuss the
                                                  operation of facilities by Rover Pipeline,              select ‘‘Comment on a Filing’’ as the                 environmental impacts that could occur
                                                  LLC (Rover) in Marshall County, West                    filing type; or                                       as a result of the construction and
                                                  Virginia. The Commission will use this                     (3) You can file a paper copy of your              operation of the proposed project. We
                                                  EA in its decision-making process to                    comments by mailing them to the                       will also evaluate reasonable
                                                  determine whether the project is in the                 following address. Be sure to reference               alternatives to the proposed project or
                                                  public convenience and necessity.                       the project docket number (CP17–464–                  portions of the project, and make
                                                     This notice announces the opening of                 000 with your submission: Kimberly D.                 recommendations on how to lessen or
                                                  the scoping process the Commission                      Bose, Secretary, Federal Energy                       avoid impacts on the various resource
                                                  will use to gather input from the public                Regulatory Commission, 888 First Street               areas.
                                                  and interested agencies on the project.                 NE., Room 1A, Washington, DC 20426.                      The EA will present our independent
                                                  You can make a difference by providing                                                                        analysis of the issues. The EA will be
                                                                                                          Summary of the Proposed Project                       available in the public record through
                                                  us with your specific comments or
                                                  concerns about the project. Your                           Rover proposes to install a third 3,550            eLibrary. Depending on the comments
                                                  comments should focus on the potential                  horsepower natural gas compressor unit
                                                  environmental effects, reasonable                       at the Majorsville Compressor Station 1                 2 The appendices referenced in this notice will

                                                  alternatives, and measures to avoid or                  and a new equipment run at the                        not appear in the Federal Register. Copies of
mstockstill on DSK30JT082PROD with NOTICES




                                                                                                                                                                appendices were sent to all those receiving this
                                                  lessen environmental impacts. Your                      Majorsville Meter Station in Marshall                 notice in the mail and are available at www.ferc.gov
                                                  input will help the Commission staff                    County, West Virginia. The new unit                   using the link called eLibrary or from the
                                                  determine what issues they need to                                                                            Commission’s Public Reference Room, 888 First
                                                  evaluate in the EA. To ensure that your                   1 The Majorsville Compressor Station was            Street NE., Washington, DC 20426, or call (202)
                                                                                                          approved by the Commission on February 2, 2017        502–8371. For instructions on connecting to
                                                  comments are timely and properly                        in docket no. CP15–93–000 as a component of the       eLibrary, refer to the last page of this notice.
                                                  recorded, please send your comments so                  Rover Pipeline Project and is currently under           3 We, us, and our refer to the environmental staff

                                                  that the Commission receives them in                    construction.                                         of the Commission’s Office of Energy Projects.



                                             VerDate Sep<11>2014   17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00030   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1


                                                  37448                        Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices

                                                  received during the scoping process, we                  intervene. Instructions for becoming an               application in Docket Nos. CP17–56–
                                                  may also publish and distribute the EA                   intervenor are in the Document-less                   000 and CP17–57–000 requesting a
                                                  to the public for an allotted comment                    Intervention Guide under the e-filing                 Certificate of Public Convenience and
                                                  period. We will consider all comments                    link on the Commission’s Web site.                    Necessity pursuant to Section 7(c) of the
                                                  on the EA before making our                              Motions to intervene are more fully                   Natural Gas Act to construct and operate
                                                  recommendations to the Commission.                       described at http://www.ferc.gov/                     certain natural gas pipeline facilities.
                                                  To ensure we have the opportunity to                     resources/guides/how-to/intervene.asp.                The proposed project is known as the
                                                  consider and address your comments,                                                                            Stratton Ridge Expansion Project
                                                  please carefully follow the instructions                 Additional Information
                                                                                                                                                                 (Project), and is designed to provide the
                                                  in the Public Participation section,                        Additional information about the                   capacity necessary for Texas Eastern to
                                                  beginning on page 2.                                     project is available from the                         transport up to 322,000 dekatherms per
                                                    With this notice, we are asking                        Commission’s Office of External Affairs,              day of natural gas on a firm basis from
                                                  agencies with jurisdiction by law and/                   at (866) 208–FERC, or on the FERC Web                 Texas Eastern’s existing
                                                  or special expertise with respect to the                 site at www.ferc.gov using the eLibrary               interconnections to a delivery point on
                                                  environmental issues of this project to                  link. Click on the eLibrary link, click on            the BIG Pipeline near Stratton Ridge,
                                                  formally cooperate with us in the                        General Search and enter the docket                   Texas.
                                                  preparation of the EA.4 Agencies that                    number, excluding the last three digits                  On February 16, 2017, the Federal
                                                  would like to request cooperating                        in the Docket Number field (i.e., CP17–               Energy Regulatory Commission
                                                  agency status should follow the                          464). Be sure you have selected an                    (Commission or FERC) issued its Notice
                                                  instructions for filing comments                         appropriate date range. For assistance,               of Application for the Project. Among
                                                  provided under the Public Participation                  please contact FERC Online Support at                 other things, that notice alerted agencies
                                                  section of this notice.                                  FercOnlineSupport@ferc.gov or toll free               issuing federal authorizations of the
                                                  Environmental Mailing List                               at (866) 208–3676, or for TTY, contact                requirement to complete all necessary
                                                                                                           (202) 502–8659. The eLibrary link also                reviews and to reach a final decision on
                                                     The environmental mailing list                        provides access to the texts of formal                a request for a federal authorization
                                                  includes federal, state, and local                       documents issued by the Commission,                   within 90 days of the date of issuance
                                                  government representatives and                           such as orders, notices, and                          of the Commission staff’s Environmental
                                                  agencies; environmental and public                       rulemakings.                                          Assessment (EA) for the Project. This
                                                  interest groups; and other interested                       In addition, the Commission offers a               instant notice identifies the FERC staff’s
                                                  parties. This list also includes all                     free service called eSubscription which               planned schedule for the completion of
                                                  affected landowners (as defined in the                   allows you to keep track of all formal                the EA for the Project.
                                                  Commission’s regulations) who are                        issuances and submittals in specific
                                                  within 0.5 mile of the Majorsville                                                                             Schedule for Environmental Review
                                                                                                           dockets. This can reduce the amount of
                                                  Compressor Station, and anyone who                                                                             Issuance of EA—October 5, 2017
                                                                                                           time you spend researching proceedings
                                                  submits comments on the project. We                                                                            90-day Federal Authorization Decision
                                                                                                           by automatically providing you with
                                                  will update the environmental mailing                                                                             Deadline—January 3, 2018
                                                                                                           notification of these filings, document
                                                  list as the analysis proceeds to ensure                                                                           If a schedule change becomes
                                                                                                           summaries, and direct links to the
                                                  that we send the information related to                                                                        necessary, additional notice will be
                                                                                                           documents. Go to www.ferc.gov/docs-
                                                  this environmental review to all                                                                               provided so that the relevant agencies
                                                                                                           filing/esubscription.asp.
                                                  individuals, organizations, and                                                                                are kept informed of the Project’s
                                                                                                              Finally, any public sessions or site
                                                  government entities interested in and/or
                                                                                                           visits will be posted on the                          progress.
                                                  potentially affected by the proposed
                                                  project.                                                 Commission’s calendar located at                      Project Description
                                                     If we publish and distribute the EA,                  www.ferc.gov/EventCalendar/
                                                                                                           EventsList.aspx along with other related                The Stratton Ridge Project would
                                                  copies will be sent to the environmental                                                                       consist of:
                                                  mailing list for public review and                       information.
                                                                                                                                                                   • A new Angleton Compressor
                                                  comment. If you would prefer to receive                    Dated: August 4, 2017.                              Station, consisting of a 12,500
                                                  a paper copy of the document instead of                  Nathaniel J. Davis, Sr.,                              horsepower electric motor-driven
                                                  the CD version or would like to remove                   Deputy Secretary.                                     compressor in Brazoria County, Texas;
                                                  your name from the mailing list, please                  [FR Doc. 2017–16878 Filed 8–9–17; 8:45 am]              • a new 0.5 mile, 30-inch-diameter
                                                  return the attached Information Request                  BILLING CODE 6717–01–P                                pipeline lateral in Brazoria County,
                                                  (appendix 2).                                                                                                  Texas to interconnect with the BIG
                                                  Becoming an Intervenor                                                                                         intrastate pipeline system;
                                                                                                           DEPARTMENT OF ENERGY                                    • installation of Clean Burn
                                                    In addition to involvement in the EA
                                                                                                                                                                 Equipment at the Mont Belvieu
                                                  scoping process, you may want to                         Federal Energy Regulatory                             Compressor Station in Chambers
                                                  become an intervenor which is an                         Commission                                            County, Texas; and
                                                  official party to the Commission’s                                                                               • installation of minor auxiliary and
                                                  proceeding. Intervenors play a more                      [Docket Nos. CP17–56–000; CP17–57–000]
                                                                                                                                                                 support facilities (e.g. launcher and
                                                  formal role in the process and are able                                                                        receiver modification, valves, piping
                                                  to file briefs, appear at hearings, and be               Texas Eastern Transmission, L.P,
                                                                                                           Brazoria Interconnector Gas Pipeline,                 modification) at existing Texas Eastern
                                                  heard by the courts if they choose to
                                                                                                                                                                 facilities in San Jacinto, Lavaca, Waller,
mstockstill on DSK30JT082PROD with NOTICES




                                                  appeal the Commission’s final ruling.                    LLC; Notice of Schedule for
                                                                                                           Environmental Review of the Stratton                  and Shelby Counties, Texas.
                                                  An intervenor formally participates in
                                                  the proceeding by filing a request to                    Ridge Expansion Project                               Background
                                                    4 The Council on Environmental Quality
                                                                                                             On February 3, 2017, Texas Eastern                     On March 24, 2017, the Commission
                                                  regulations addressing cooperating agency
                                                                                                           Transmission, LP (Texas Eastern) and                  issued a Notice of Intent to Prepare an
                                                  responsibilities are at Title 40, Code of Federal        Brazoria Interconnector Gas Pipeline,                 Environmental Assessment for the
                                                  Regulations, Part 1501.6.                                LLC (BIG Pipeline) filed jointly an                   Proposed Stratton Ridge Project and


                                             VerDate Sep<11>2014    17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1



Document Created: 2017-08-10 01:01:30
Document Modified: 2017-08-10 01:01:30
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 37447 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR