82_FR_37601 82 FR 37448 - Texas Eastern Transmission, L.P, Brazoria Interconnector Gas Pipeline, LLC; Notice of Schedule for Environmental Review of the Stratton Ridge Expansion Project

82 FR 37448 - Texas Eastern Transmission, L.P, Brazoria Interconnector Gas Pipeline, LLC; Notice of Schedule for Environmental Review of the Stratton Ridge Expansion Project

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 153 (August 10, 2017)

Page Range37448-37449
FR Document2017-16879

Federal Register, Volume 82 Issue 153 (Thursday, August 10, 2017)
[Federal Register Volume 82, Number 153 (Thursday, August 10, 2017)]
[Notices]
[Pages 37448-37449]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-16879]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-56-000; CP17-57-000]


Texas Eastern Transmission, L.P, Brazoria Interconnector Gas 
Pipeline, LLC; Notice of Schedule for Environmental Review of the 
Stratton Ridge Expansion Project

    On February 3, 2017, Texas Eastern Transmission, LP (Texas Eastern) 
and Brazoria Interconnector Gas Pipeline, LLC (BIG Pipeline) filed 
jointly an application in Docket Nos. CP17-56-000 and CP17-57-000 
requesting a Certificate of Public Convenience and Necessity pursuant 
to Section 7(c) of the Natural Gas Act to construct and operate certain 
natural gas pipeline facilities. The proposed project is known as the 
Stratton Ridge Expansion Project (Project), and is designed to provide 
the capacity necessary for Texas Eastern to transport up to 322,000 
dekatherms per day of natural gas on a firm basis from Texas Eastern's 
existing interconnections to a delivery point on the BIG Pipeline near 
Stratton Ridge, Texas.
    On February 16, 2017, the Federal Energy Regulatory Commission 
(Commission or FERC) issued its Notice of Application for the Project. 
Among other things, that notice alerted agencies issuing federal 
authorizations of the requirement to complete all necessary reviews and 
to reach a final decision on a request for a federal authorization 
within 90 days of the date of issuance of the Commission staff's 
Environmental Assessment (EA) for the Project. This instant notice 
identifies the FERC staff's planned schedule for the completion of the 
EA for the Project.

Schedule for Environmental Review

Issuance of EA--October 5, 2017
90-day Federal Authorization Decision Deadline--January 3, 2018

    If a schedule change becomes necessary, additional notice will be 
provided so that the relevant agencies are kept informed of the 
Project's progress.

Project Description

    The Stratton Ridge Project would consist of:
     A new Angleton Compressor Station, consisting of a 12,500 
horsepower electric motor-driven compressor in Brazoria County, Texas;
     a new 0.5 mile, 30-inch-diameter pipeline lateral in 
Brazoria County, Texas to interconnect with the BIG intrastate pipeline 
system;
     installation of Clean Burn Equipment at the Mont Belvieu 
Compressor Station in Chambers County, Texas; and
     installation of minor auxiliary and support facilities 
(e.g. launcher and receiver modification, valves, piping modification) 
at existing Texas Eastern facilities in San Jacinto, Lavaca, Waller, 
and Shelby Counties, Texas.

Background

    On March 24, 2017, the Commission issued a Notice of Intent to 
Prepare an Environmental Assessment for the Proposed Stratton Ridge 
Project and

[[Page 37449]]

Request for Comments on Environmental Issues (NOI). The NOI was sent to 
affected landowners; federal, state, and local government agencies; 
elected officials; environmental and public interest groups; Native 
American tribes; other interested parties; and local libraries and 
newspapers. In response to the NOI, the Commission received comments 
from the Texas Parks and Wildlife Department, United States 
Environmental Protection Agency, and one local resident. The primary 
issues raised by the commenters are impacts on: land use; water 
supplies; migratory birds; threatened and endangered species; cultural 
resources; air quality; and environmental justice.

Additional Information

    In order to receive notification of the issuance of the EA and to 
keep track of all formal issuances and submittals in specific dockets, 
the Commission offers a free service called eSubscription. This can 
reduce the amount of time you spend researching proceedings by 
automatically providing you with notification of these filings, 
document summaries, and direct links to the documents. Go to 
www.ferc.gov/docs-filing/esubscription.asp.
    Additional information about the Project is available from the 
Commission's Office of External Affairs at (866) 208-FERC or on the 
FERC Web site (www.ferc.gov). Using the eLibrary link, select General 
Search from the eLibrary menu, enter the selected date range and Docket 
Number excluding the last three digits (i.e., CP17-56 and CP17-57), and 
follow the instructions.
    For assistance with access to eLibrary, the helpline can be reached 
at (866) 208-3676, TTY (202) 502-8659, or at 
[email protected]. The eLibrary link on the FERC Web site also 
provides access to the texts of formal documents issued by the 
Commission, such as orders, notices, and rule makings.

    Dated: August 4, 2017.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2017-16879 Filed 8-9-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                  37448                        Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices

                                                  received during the scoping process, we                  intervene. Instructions for becoming an               application in Docket Nos. CP17–56–
                                                  may also publish and distribute the EA                   intervenor are in the Document-less                   000 and CP17–57–000 requesting a
                                                  to the public for an allotted comment                    Intervention Guide under the e-filing                 Certificate of Public Convenience and
                                                  period. We will consider all comments                    link on the Commission’s Web site.                    Necessity pursuant to Section 7(c) of the
                                                  on the EA before making our                              Motions to intervene are more fully                   Natural Gas Act to construct and operate
                                                  recommendations to the Commission.                       described at http://www.ferc.gov/                     certain natural gas pipeline facilities.
                                                  To ensure we have the opportunity to                     resources/guides/how-to/intervene.asp.                The proposed project is known as the
                                                  consider and address your comments,                                                                            Stratton Ridge Expansion Project
                                                  please carefully follow the instructions                 Additional Information
                                                                                                                                                                 (Project), and is designed to provide the
                                                  in the Public Participation section,                        Additional information about the                   capacity necessary for Texas Eastern to
                                                  beginning on page 2.                                     project is available from the                         transport up to 322,000 dekatherms per
                                                    With this notice, we are asking                        Commission’s Office of External Affairs,              day of natural gas on a firm basis from
                                                  agencies with jurisdiction by law and/                   at (866) 208–FERC, or on the FERC Web                 Texas Eastern’s existing
                                                  or special expertise with respect to the                 site at www.ferc.gov using the eLibrary               interconnections to a delivery point on
                                                  environmental issues of this project to                  link. Click on the eLibrary link, click on            the BIG Pipeline near Stratton Ridge,
                                                  formally cooperate with us in the                        General Search and enter the docket                   Texas.
                                                  preparation of the EA.4 Agencies that                    number, excluding the last three digits                  On February 16, 2017, the Federal
                                                  would like to request cooperating                        in the Docket Number field (i.e., CP17–               Energy Regulatory Commission
                                                  agency status should follow the                          464). Be sure you have selected an                    (Commission or FERC) issued its Notice
                                                  instructions for filing comments                         appropriate date range. For assistance,               of Application for the Project. Among
                                                  provided under the Public Participation                  please contact FERC Online Support at                 other things, that notice alerted agencies
                                                  section of this notice.                                  FercOnlineSupport@ferc.gov or toll free               issuing federal authorizations of the
                                                  Environmental Mailing List                               at (866) 208–3676, or for TTY, contact                requirement to complete all necessary
                                                                                                           (202) 502–8659. The eLibrary link also                reviews and to reach a final decision on
                                                     The environmental mailing list                        provides access to the texts of formal                a request for a federal authorization
                                                  includes federal, state, and local                       documents issued by the Commission,                   within 90 days of the date of issuance
                                                  government representatives and                           such as orders, notices, and                          of the Commission staff’s Environmental
                                                  agencies; environmental and public                       rulemakings.                                          Assessment (EA) for the Project. This
                                                  interest groups; and other interested                       In addition, the Commission offers a               instant notice identifies the FERC staff’s
                                                  parties. This list also includes all                     free service called eSubscription which               planned schedule for the completion of
                                                  affected landowners (as defined in the                   allows you to keep track of all formal                the EA for the Project.
                                                  Commission’s regulations) who are                        issuances and submittals in specific
                                                  within 0.5 mile of the Majorsville                                                                             Schedule for Environmental Review
                                                                                                           dockets. This can reduce the amount of
                                                  Compressor Station, and anyone who                                                                             Issuance of EA—October 5, 2017
                                                                                                           time you spend researching proceedings
                                                  submits comments on the project. We                                                                            90-day Federal Authorization Decision
                                                                                                           by automatically providing you with
                                                  will update the environmental mailing                                                                             Deadline—January 3, 2018
                                                                                                           notification of these filings, document
                                                  list as the analysis proceeds to ensure                                                                           If a schedule change becomes
                                                                                                           summaries, and direct links to the
                                                  that we send the information related to                                                                        necessary, additional notice will be
                                                                                                           documents. Go to www.ferc.gov/docs-
                                                  this environmental review to all                                                                               provided so that the relevant agencies
                                                                                                           filing/esubscription.asp.
                                                  individuals, organizations, and                                                                                are kept informed of the Project’s
                                                                                                              Finally, any public sessions or site
                                                  government entities interested in and/or
                                                                                                           visits will be posted on the                          progress.
                                                  potentially affected by the proposed
                                                  project.                                                 Commission’s calendar located at                      Project Description
                                                     If we publish and distribute the EA,                  www.ferc.gov/EventCalendar/
                                                                                                           EventsList.aspx along with other related                The Stratton Ridge Project would
                                                  copies will be sent to the environmental                                                                       consist of:
                                                  mailing list for public review and                       information.
                                                                                                                                                                   • A new Angleton Compressor
                                                  comment. If you would prefer to receive                    Dated: August 4, 2017.                              Station, consisting of a 12,500
                                                  a paper copy of the document instead of                  Nathaniel J. Davis, Sr.,                              horsepower electric motor-driven
                                                  the CD version or would like to remove                   Deputy Secretary.                                     compressor in Brazoria County, Texas;
                                                  your name from the mailing list, please                  [FR Doc. 2017–16878 Filed 8–9–17; 8:45 am]              • a new 0.5 mile, 30-inch-diameter
                                                  return the attached Information Request                  BILLING CODE 6717–01–P                                pipeline lateral in Brazoria County,
                                                  (appendix 2).                                                                                                  Texas to interconnect with the BIG
                                                  Becoming an Intervenor                                                                                         intrastate pipeline system;
                                                                                                           DEPARTMENT OF ENERGY                                    • installation of Clean Burn
                                                    In addition to involvement in the EA
                                                                                                                                                                 Equipment at the Mont Belvieu
                                                  scoping process, you may want to                         Federal Energy Regulatory                             Compressor Station in Chambers
                                                  become an intervenor which is an                         Commission                                            County, Texas; and
                                                  official party to the Commission’s                                                                               • installation of minor auxiliary and
                                                  proceeding. Intervenors play a more                      [Docket Nos. CP17–56–000; CP17–57–000]
                                                                                                                                                                 support facilities (e.g. launcher and
                                                  formal role in the process and are able                                                                        receiver modification, valves, piping
                                                  to file briefs, appear at hearings, and be               Texas Eastern Transmission, L.P,
                                                                                                           Brazoria Interconnector Gas Pipeline,                 modification) at existing Texas Eastern
                                                  heard by the courts if they choose to
                                                                                                                                                                 facilities in San Jacinto, Lavaca, Waller,
mstockstill on DSK30JT082PROD with NOTICES




                                                  appeal the Commission’s final ruling.                    LLC; Notice of Schedule for
                                                                                                           Environmental Review of the Stratton                  and Shelby Counties, Texas.
                                                  An intervenor formally participates in
                                                  the proceeding by filing a request to                    Ridge Expansion Project                               Background
                                                    4 The Council on Environmental Quality
                                                                                                             On February 3, 2017, Texas Eastern                     On March 24, 2017, the Commission
                                                  regulations addressing cooperating agency
                                                                                                           Transmission, LP (Texas Eastern) and                  issued a Notice of Intent to Prepare an
                                                  responsibilities are at Title 40, Code of Federal        Brazoria Interconnector Gas Pipeline,                 Environmental Assessment for the
                                                  Regulations, Part 1501.6.                                LLC (BIG Pipeline) filed jointly an                   Proposed Stratton Ridge Project and


                                             VerDate Sep<11>2014    17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1


                                                                              Federal Register / Vol. 82, No. 153 / Thursday, August 10, 2017 / Notices                                                 37449

                                                  Request for Comments on                                 ENVIRONMENTAL PROTECTION                              FEDERAL DEPOSIT INSURANCE
                                                  Environmental Issues (NOI). The NOI                     AGENCY                                                CORPORATION
                                                  was sent to affected landowners; federal,
                                                  state, and local government agencies;                   [CERCLA–04–2017–3757; FRL–9965–77–
                                                                                                                                                                Notice to All Interested Parties of the
                                                  elected officials; environmental and                    Region 4]                                             Termination of the Receivership of
                                                  public interest groups; Native American                                                                       10517—Hometown National Bank
                                                  tribes; other interested parties; and local             Coronet Industries, Inc. Plant City,                  Longview, Washington
                                                  libraries and newspapers. In response to                Hillsborough County, Florida; Notice of
                                                                                                                                                                   Notice is hereby given that the Federal
                                                  the NOI, the Commission received                        Amendment to Federal Register Notice
                                                                                                                                                                Deposit Insurance Corporation (FDIC) as
                                                  comments from the Texas Parks and                                                                             Receiver for Hometown National Bank,
                                                                                                          AGENCY: Environmental Protection
                                                  Wildlife Department, United States                                                                            Longview, Washington (‘‘the Receiver’’)
                                                                                                          Agency (EPA).
                                                  Environmental Protection Agency, and                                                                          intends to terminate its receivership for
                                                  one local resident. The primary issues                  ACTION:   Notice; amendment.                          said institution. The FDIC was
                                                  raised by the commenters are impacts                                                                          appointed Receiver of Hometown
                                                  on: land use; water supplies; migratory                 SUMMARY:   On July 26, 2017, the                      National Bank on October 2, 2015. The
                                                  birds; threatened and endangered                        Environmental Protection Agency (EPA)                 liquidation of the receivership assets
                                                  species; cultural resources; air quality;               published a Notice of Settlement under                has been completed. To the extent
                                                  and environmental justice.                              Section 122(h) of the Comprehensive                   permitted by available funds and in
                                                                                                          Environmental Response, Compensation                  accordance with law, the Receiver will
                                                  Additional Information                                  and Liability Act (CERCLA) addressing                 be making a final dividend payment to
                                                                                                          cost for work performed at the Coronet                proven creditors.
                                                     In order to receive notification of the              Industries, Inc. Site located in Plant                   Based upon the foregoing, the
                                                  issuance of the EA and to keep track of                 City, Hillsborough County, Florida,                   Receiver has determined that the
                                                  all formal issuances and submittals in                  FRL–9965–49–Region 4 (82 FR 34655).                   continued existence of the receivership
                                                  specific dockets, the Commission offers                 The published notice did not list                     will serve no useful purpose.
                                                  a free service called eSubscription. This               Coronet Industries Inc, as one of the                 Consequently, notice is given that the
                                                  can reduce the amount of time you                       settling parties to the settlement.                   receivership shall be terminated, to be
                                                  spend researching proceedings by                                                                              effective no sooner than thirty days after
                                                                                                          DATES:  The comment period for the
                                                  automatically providing you with                                                                              the date of this notice. If any person
                                                                                                          original notice is unchanged. The
                                                  notification of these filings, document                 Agency will consider public comments                  wishes to comment concerning the
                                                  summaries, and direct links to the                      on the settlement until August 25, 2017.              termination of the receivership, such
                                                  documents. Go to www.ferc.gov/docs-                     The Agency will consider all comments                 comment must be made in writing and
                                                  filing/esubscription.asp.                               received and may modify or withdraw                   sent within thirty days of the date of
                                                     Additional information about the                     its consent to the settlement if                      this notice to: Federal Deposit Insurance
                                                  Project is available from the                           comments received disclose facts or                   Corporation, Division of Resolutions
                                                  Commission’s Office of External Affairs                 considerations which indicate that the                and Receiverships, Attention:
                                                  at (866) 208–FERC or on the FERC Web                    proposed settlement is inappropriate,                 Receivership Oversight Department
                                                  site (www.ferc.gov). Using the eLibrary                 improper, or inadequate.                              34.6, 1601 Bryan Street, Dallas, TX
                                                                                                                                                                75201.
                                                  link, select General Search from the                    ADDRESSES:   Copies of the settlement are                No comments concerning the
                                                  eLibrary menu, enter the selected date                  available from the Agency by contacting               termination of this receivership will be
                                                  range and Docket Number excluding the                   Ms. Paula V. Painter, Program Analyst,                considered which are not sent within
                                                  last three digits (i.e., CP17–56 and                    using the contact information provided                this time frame.
                                                  CP17–57), and follow the instructions.                  in this notice. Comments may also be
                                                                                                          submitted by referencing the Site’s                     Dated: August 7, 2017.
                                                     For assistance with access to eLibrary,
                                                                                                          name through one of the following                     Federal Deposit Insurance Corporation.
                                                  the helpline can be reached at (866)
                                                                                                          methods:                                              Robert E. Feldman,
                                                  208–3676, TTY (202) 502–8659, or at
                                                                                                            • Internet: https://www.epa.gov/                    Executive Secretary.
                                                  FERCOnlineSupport@ferc.gov. The
                                                                                                          aboutepa/about-epa-region-4-                          [FR Doc. 2017–16883 Filed 8–9–17; 8:45 am]
                                                  eLibrary link on the FERC Web site also
                                                  provides access to the texts of formal                  southeast#r4-public-notices.                          BILLING CODE 6714–01–P

                                                  documents issued by the Commission,                       • U.S. Mail: U.S. Environmental
                                                  such as orders, notices, and rule                       Protection Agency, Superfund Division,
                                                  makings.                                                Attn: Paula V. Painter, 61 Forsyth Street             FEDERAL ELECTION COMMISSION
                                                    Dated: August 4, 2017.
                                                                                                          SW., Atlanta, Georgia 30303.
                                                  Nathaniel J. Davis, Sr.,                                  • Email: Painter.Paula@epa.gov.                     Sunshine Act Meeting
                                                  Deputy Secretary.                                       FOR FURTHER INFORMATION CONTACT:                      AGENCY:  Federal Election Commission.
                                                  [FR Doc. 2017–16879 Filed 8–9–17; 8:45 am]              Paula V. Painter at 404–562–8887. Attn:               DATE AND TIME: Tuesday, August 15,
                                                  BILLING CODE 6717–01–P
                                                                                                          Paula V. Painter, 61 Forsyth Street SW.,              2017 at 10:00 a.m. and its Continuation
                                                                                                          Atlanta, Georgia 30303.                               at the Conclusion of the Open Meeting
                                                                                                            • Email: Painter.Paula@epa.gov.
mstockstill on DSK30JT082PROD with NOTICES




                                                                                                                                                                on August 17, 2017.
                                                                                                            Dated: July 27, 2017.                               PLACE: 999 E Street NW., Washington,
                                                                                                          Anita L. Davis,                                       DC.
                                                                                                          Chief, Enforcement and Community                      STATUS: This Meeting Will Be Closed to
                                                                                                          Engagement Branch, Superfund Division.                the Public.
                                                                                                          [FR Doc. 2017–16899 Filed 8–9–17; 8:45 am]            ITEMS TO BE DISCUSSED: Compliance
                                                                                                          BILLING CODE 6560–50–P                                matters pursuant to 52 U.S.C. 30109.


                                             VerDate Sep<11>2014   17:03 Aug 09, 2017   Jkt 241001   PO 00000   Frm 00032   Fmt 4703   Sfmt 4703   E:\FR\FM\10AUN1.SGM   10AUN1



Document Created: 2017-08-10 01:01:02
Document Modified: 2017-08-10 01:01:02
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 37448 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR