DEPARTMENT OF THE INTERIOR
Bureau of Reclamation

Federal Register Volume 82, Issue 159 (August 18, 2017)

Page Range39454-39455
FR Document2017-17487

The Bureau of Reclamation (Reclamation), as the National Environmental Policy Act (NEPA) Federal lead agency, and the Sites Project Authority, as the California Environmental Quality Act (CEQA) State lead agency, have made available for public review and comment the Sites Reservoir Project Draft Environmental Impact Report/ Environmental Impact Statement (Draft EIR/EIS) and Draft Feasibility Report (Draft FR). The Draft EIR/EIS and Draft FR describe the environmental effects and evaluate the feasibility of the No-Action Alternative and four action alternatives. Two public meetings will be held to receive comments from individuals and organizations on the Draft EIR/EIS and Draft FR.

Federal Register, Volume 82 Issue 159 (Friday, August 18, 2017)
[Federal Register Volume 82, Number 159 (Friday, August 18, 2017)]
[Notices]
[Pages 39454-39455]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-17487]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Reclamation

[RR02030000, 17XR0687NA, RX185279066000000]


Draft Environmental Impact Report/Environmental Impact Statement 
and Draft Feasibility Report for Sites Reservoir Project, Sites, 
California

AGENCY: Bureau of Reclamation, Interior.

ACTION: Notice of availability and notice of public meetings.

-----------------------------------------------------------------------

SUMMARY: The Bureau of Reclamation (Reclamation), as the National 
Environmental Policy Act (NEPA) Federal lead agency, and the Sites 
Project Authority, as the California Environmental Quality Act (CEQA) 
State lead agency, have made available for public review and comment 
the Sites Reservoir Project Draft Environmental Impact Report/
Environmental Impact Statement (Draft EIR/EIS) and Draft Feasibility 
Report (Draft FR). The Draft EIR/EIS and Draft FR describe the 
environmental effects and evaluate the feasibility of the No-Action 
Alternative and four action alternatives. Two public meetings will be 
held to receive comments from individuals and organizations on the 
Draft EIR/EIS and Draft FR.

DATES: Submit written comments on the Draft EIR/EIS on or before 
November 13, 2017.
    Two public meetings have been scheduled to receive oral or written 
comments regarding environmental effects:
     Tuesday, September 26, 2017, 6:00 p.m.-8:00 p.m., Maxwell, 
CA
     Thursday, September 28, 2017, 1:00 p.m.-3:00 p.m., 
Sacramento, CA
    A 1-hour open house to view project information and interact with 
the project team will precede each public meeting.

ADDRESSES: Send written comments on the Draft EIR/EIS or Draft FR to 
DEIR/EIS Comments, Sites Project Authority, P.O. Box 517, Maxwell, CA 
95955, or email to [email protected].
    The public meetings will be held at the following locations:

 Maxwell--Sites Project Authority, 122 Old Highway 99 West, 
Maxwell, CA 95955
 Sacramento--Convention Center, 1400 J Street, Room 306, 
Sacramento, CA 95814

    Electronic CD copies of the Draft EIR/EIS may be requested from 
Sites Project Authority, at (530) 410-8250, or [email protected]. The Draft EIR/EIS is also accessible from 
the following Web site: https://www.usbr.gov/mp/nepa/nepa_projdetails.cfm?project_ID=29024.
    Copies of the Draft EIR/EIS are available for public review at the 
following locations:

1. Bureau of Reclamation, Mid-Pacific Region, Regional Library, 2800 
Cottage Way, Sacramento, CA 95825
2. Sacramento Public Library, 828 I Street, Sacramento, CA 95814
3. Sites Authority, 122 Old Highway 99 West, Maxwell, CA 95955

FOR FURTHER INFORMATION CONTACT: Please contact Mr. Michael Dietl, 
Bureau of Reclamation, at (916) 978-

[[Page 39455]]

5070, or via email at [email protected]; or Mr. Rob Thomson, Sites 
Project Authority, at (530) 438-2309, or via email at [email protected].

SUPPLEMENTARY INFORMATION: This Draft EIR/EIS describes the Sites 
Reservoir Project, potential alternatives to the Sites Reservoir 
Project, environmental setting, potential direct, indirect, and 
cumulative impacts that could result from implementation of each of the 
alternatives, and mitigation measures for potentially significant 
impacts, as applicable. Four alternative methods of constructing and 
operating the Sites Reservoir Project are evaluated in the Draft FR to 
meet all or the majority of the purpose, and need, and goals, and 
objectives of the Sites Reservoir Project. Other alternatives evaluated 
over the past several decades (some of which were the subject of prior 
CEQA and National Environmental Policy Act (NEPA) analyses and decision 
making) are summarized and discussed in Chapter 2 Alternatives Analysis 
of the Draft EIR/EIS.
    The proposed Sites Reservoir Project facilities would primarily be 
located in Glenn and Colusa counties, approximately 10 miles west of 
the town of Maxwell, California. Proposed minor modifications to an 
existing diversion facility would also need to occur at the existing 
Red Bluff Pumping Plant in Tehama County, California. The Sites 
Reservoir Project would consist of a new offstream surface storage 
reservoir (Sites Reservoir) with two main dams, up to nine saddle dams, 
and up to three recreation areas. The Sites Reservoir would be filled 
via two existing Sacramento River diversions/canals (included in all 
alternatives) and a proposed new inlet/outlet structure and pipeline 
(included in the majority of alternatives). The pipeline would allow 
for diversion of excess Sacramento River flows for most alternatives, 
and discharge of water under all alternatives. Water conveyance between 
the reservoir and the canals and pipeline would be facilitated by two 
new regulating reservoirs. Pumping/generating plants would also be 
included as part of most alternatives. A new overhead power line would 
connect the pumping/generating plants and their associated electrical 
switchyards to an existing overhead power line in the Sites Reservoir 
Project area. New roads and a bridge across the proposed Sites 
Reservoir would be constructed to provide access to the proposed Sites 
Reservoir Project facilities and over the proposed reservoir, and some 
existing roads would be relocated or improved. The Sites Reservoir 
Project would require modifications to the T-C Canal and the Holthouse 
Reservoir. A more complete description of the Sites Reservoir Project 
can be found in Chapter 3 Description of the Sites Reservoir Project 
Alternatives in the Draft EIR/EIS.
    The Sites Reservoir Project is the subject of a Notice of 
Preparation (NOP) issued on November 5, 2001, to prepare an EIR under 
CEQA, and a Notice of Intent (NOI) published on November 9, 2001 (66 FR 
56708), to prepare an EIS under NEPA. The Sites Reservoir Project was 
formerly known as the North-of-Delta Offstream Storage project led by 
the California Department of Water Resources (DWR). The Sites Project 
Authority has assumed the role of the CEQA lead agency in lieu of DWR 
and will be responsible for constructing, operating, and maintaining 
the Sites Reservoir Project. Because of this change in lead agency, the 
Sites Project Authority issued a Supplemental NOP on February 2, 2017, 
for the Draft EIR for the Project.
    Reclamation's involvement in the Sites Reservoir Project includes 
the following actions: (1) The development of a Federal feasibility 
report, and related EIS under NEPA, to support potential funding by the 
Federal Government, pursuant to the Calfed Bay-Delta Authorization Act 
(Pub. L. 108-361); (2) the potential approval of the use of the Tehama-
Colusa Canal for water diversion and conveyance of water to Sites 
Reservoir; and (3) the coordinated operations of Central Valley Project 
(CVP) facilities and the Sites Reservoir Project. In addition, 
Reclamation's involvement in the Sites Reservoir Project also could 
include: (1) Potential Federal funding of the Project pursuant to the 
Water Infrastructure Improvements for the Nation Act (Pub. L. 114-322); 
(2) participation in the power lines to and from the Sites Reservoir; 
(3) involvement in and jurisdiction over the potential electrical power 
generation from the Sites Reservoir Project; and (4) potential new 
legislative authority to acquire shares of the water managed by the 
Sites Project Authority for federal conservation activities.
    If special assistance is required at the public meetings, please 
contact Mr. Michael Dietl at (916) 978-5070; or via email at 
[email protected]. Please notify Mr. Dietl as far in advance as possible 
to enable Reclamation to secure the needed services. If a request 
cannot be honored, the requestor will be notified. A telephone device 
for the hearing impaired (TTY) is available at (800) 877-8339.
    Before including your address, phone number, email address, or 
other personal identifying information in your comment, you should be 
aware that your entire comment--including your personal identifying 
information--may be made publicly available at any time. While you can 
ask us in your comment to withhold your personal identifying 
information from public review, we cannot guarantee that we will be 
able to do so.

    Dated: August 14, 2017.
Grayford F. Payne,
 Deputy Commissioner--Policy, Administration and Budget.
[FR Doc. 2017-17487 Filed 8-17-17; 8:45 am]
BILLING CODE 4332-90-P



                                                  39454                         Federal Register / Vol. 82, No. 159 / Friday, August 18, 2017 / Notices

                                                     3. Kaktovik, AK—Kaktovik                             written comments on this Draft EIS                    Project Authority, as the California
                                                  Community Center, 2051 Barter Avenue.                   through the Federal eRulemaking Portal:               Environmental Quality Act (CEQA)
                                                     4. Utqiagvik (Barrow), AK—Inupiat                    http://www.regulations.gov. In the field              State lead agency, have made available
                                                  Heritage Center, 5421 North Star Street.                entitled ‘‘Enter Keyword or ID,’’ enter               for public review and comment the Sites
                                                     5. Anchorage, AK—Dena’ina Civic &                    BOEM–2015–0068, and then click                        Reservoir Project Draft Environmental
                                                  Convention Center, 600 West 7th                         ‘‘search.’’ Commenters should follow                  Impact Report/Environmental Impact
                                                  Avenue.                                                 the instructions to submit their                      Statement (Draft EIR/EIS) and Draft
                                                     As described in SUPPLEMENTARY                        comments and view supporting and                      Feasibility Report (Draft FR). The Draft
                                                  INFORMATION, submit written comments                    related materials. Written comments                   EIR/EIS and Draft FR describe the
                                                  on this Draft EIS through the Federal                   may be submitted to: Bureau of Ocean                  environmental effects and evaluate the
                                                  eRulemaking Portal: http://                             Energy Management, Attn: Liberty Draft                feasibility of the No-Action Alternative
                                                  www.regulations.gov or by mail to:                      EIS Comments, BLM Public Information                  and four action alternatives. Two public
                                                  Bureau of Ocean Energy Management,                      Center, 222 W. 7th Avenue #13,                        meetings will be held to receive
                                                  Attn: Liberty Draft EIS Comments, BLM                   Anchorage, Alaska, 99513.                             comments from individuals and
                                                  Public Information Center, 222 W. 7th                      BOEM does not accept anonymous                     organizations on the Draft EIR/EIS and
                                                  Avenue #13, Anchorage, Alaska, 99513.                   comments and requires name and                        Draft FR.
                                                  FOR FURTHER INFORMATION CONTACT:                        contact information. Before including                 DATES: Submit written comments on the
                                                  Bureau of Ocean Energy Management,                      your address, phone number, email                     Draft EIR/EIS on or before November 13,
                                                  Alaska OCS Region, 3801 Centerpoint                     address or other personal identifying                 2017.
                                                  Drive, Suite 500, Anchorage, Alaska                     information within the body of your                      Two public meetings have been
                                                  99503–5823; or Lauren Boldrick, Project                 comment, you should be aware that                     scheduled to receive oral or written
                                                  Manager, (907) 334–5200, or Frances                     your entire comment, including your                   comments regarding environmental
                                                  Mann, Section Chief, (907) 334–5277.                    personal identifying information, may                 effects:
                                                  SUPPLEMENTARY INFORMATION: The
                                                                                                          be made publicly available at any time.                  • Tuesday, September 26, 2017, 6:00
                                                  proposed action would recover and                       While you can ask us in your comments                 p.m.–8:00 p.m., Maxwell, CA
                                                  process oil from the Liberty oil field and              to withhold your personal identifying                    • Thursday, September 28, 2017, 1:00
                                                  transport sales-quality oil to market. To               information from public review, we                    p.m.–3:00 p.m., Sacramento, CA
                                                  accomplish this, the applicant for the                  cannot guarantee that we will be able to                 A 1-hour open house to view project
                                                  DPP would construct a Liberty Drilling                  do so.                                                information and interact with the
                                                                                                             Public Hearings: BOEM will hold                    project team will precede each public
                                                  and Production Island (LDPI) to recover
                                                                                                          public hearings on the Draft EIS                      meeting.
                                                  reserves from three Federal leases
                                                                                                          according to the schedule above. The
                                                  (OCS–Y–1585, OCS–Y–1650, and OCS–                                                                             ADDRESSES:    Send written comments on
                                                                                                          purpose of these hearings is to receive
                                                  Y–1886) in Foggy Island Bay of the                                                                            the Draft EIR/EIS or Draft FR to DEIR/
                                                                                                          public testimony on the Draft EIS.
                                                  Beaufort Sea. The applicant would                                                                             EIS Comments, Sites Project Authority,
                                                                                                             Authority: This Notice of Availability
                                                  construct a new pipeline linking the                                                                          P.O. Box 517, Maxwell, CA 95955, or
                                                                                                          for a Draft Environmental Impact
                                                  LDPI to the Badami Sales Oil Pipeline                                                                         email to EIR-EIS-Comments@
                                                                                                          Statement is in compliance with the
                                                  (Badami pipeline). The applicant would                                                                        SitesProject.org.
                                                                                                          National Environmental Policy Act of
                                                  bury the subsea portion (approximately                                                                           The public meetings will be held at
                                                                                                          1969, as amended (42 U.S.C. 4231 et
                                                  5.6 miles) of the pipeline along a route                                                                      the following locations:
                                                                                                          seq.), and is published pursuant to 40
                                                  leading south from the LDPI to the                                                                            • Maxwell—Sites Project Authority, 122
                                                                                                          CFR 1506.6 and 43 CFR 46.435.
                                                  Alaska coastline west of the                                                                                     Old Highway 99 West, Maxwell, CA
                                                  Kadleroshilik River. The pipeline would                  Dated: August 14, 2017.
                                                                                                          Walter D. Cruickshank,
                                                                                                                                                                   95955
                                                  transition to an above-ground portion                                                                         • Sacramento—Convention Center,
                                                  (approximately 1.5 miles) of the                        Acting Director, Bureau of Ocean Energy
                                                                                                          Management.
                                                                                                                                                                   1400 J Street, Room 306, Sacramento,
                                                  pipeline that would continue south to                                                                            CA 95814
                                                  tie into the existing Badami pipeline.                  [FR Doc. 2017–17481 Filed 8–17–17; 8:45 am]
                                                  The applicant would produce oil from                    BILLING CODE 4310–MR–P
                                                                                                                                                                   Electronic CD copies of the Draft EIR/
                                                  the LDPI, transport it through the                                                                            EIS may be requested from Sites Project
                                                  Badami pipeline to the existing common                                                                        Authority, at (530) 410–8250, or EIR-
                                                  carrier pipeline system, and on to the                  DEPARTMENT OF THE INTERIOR                            EIS-Comments@SitesProject.org. The
                                                  Trans-Alaska Pipeline System.                                                                                 Draft EIR/EIS is also accessible from the
                                                     Availability of the Draft EIS: The Draft             Bureau of Reclamation                                 following Web site: https://
                                                  EIS, Liberty DPP, and associated                        [RR02030000, 17XR0687NA,
                                                                                                                                                                www.usbr.gov/mp/nepa/nepa_
                                                  information are available on the BOEM                   RX185279066000000]                                    projdetails.cfm?project_ID=29024.
                                                  Web site at https://www.boem.gov/                                                                                Copies of the Draft EIR/EIS are
                                                  Hilcorp-Liberty/. BOEM will distribute                  Draft Environmental Impact Report/                    available for public review at the
                                                  digital copies of the Draft EIS (primarily              Environmental Impact Statement and                    following locations:
                                                  on compact disc (CD)) to interested                     Draft Feasibility Report for Sites                    1. Bureau of Reclamation, Mid-Pacific
                                                  parties upon request. If you require a                  Reservoir Project, Sites, California                       Region, Regional Library, 2800
                                                  paper copy, BOEM will provide one                       AGENCY:   Bureau of Reclamation,                           Cottage Way, Sacramento, CA
                                                  upon request, as long as copies are                                                                                95825
mstockstill on DSK30JT082PROD with NOTICES




                                                                                                          Interior.
                                                  available. You may request a CD, paper                                                                        2. Sacramento Public Library, 828 I
                                                                                                          ACTION: Notice of availability and notice
                                                  copy, or the location of a library with a                                                                          Street, Sacramento, CA 95814
                                                                                                          of public meetings.                                   3. Sites Authority, 122 Old Highway 99
                                                  paper copy of the Draft EIS by calling
                                                  (907) 334–5200.                                         SUMMARY:  The Bureau of Reclamation                        West, Maxwell, CA 95955
                                                     Comment Submission: Federal, state,                  (Reclamation), as the National                        FOR FURTHER INFORMATION CONTACT:
                                                  tribal, and local governments and/or                    Environmental Policy Act (NEPA)                       Please contact Mr. Michael Dietl,
                                                  agencies and the public may submit                      Federal lead agency, and the Sites                    Bureau of Reclamation, at (916) 978–


                                             VerDate Sep<11>2014   17:47 Aug 17, 2017   Jkt 241001   PO 00000   Frm 00051   Fmt 4703   Sfmt 4703   E:\FR\FM\18AUN1.SGM   18AUN1


                                                                                Federal Register / Vol. 82, No. 159 / Friday, August 18, 2017 / Notices                                                  39455

                                                  5070, or via email at mdietl@usbr.gov; or               would be relocated or improved. The                     Before including your address, phone
                                                  Mr. Rob Thomson, Sites Project                          Sites Reservoir Project would require                 number, email address, or other
                                                  Authority, at (530) 438–2309, or via                    modifications to the T–C Canal and the                personal identifying information in your
                                                  email at EIR-EIS-Comments@                              Holthouse Reservoir. A more complete                  comment, you should be aware that
                                                  SitesProject.org.                                       description of the Sites Reservoir Project            your entire comment—including your
                                                  SUPPLEMENTARY INFORMATION: This Draft                   can be found in Chapter 3 Description                 personal identifying information—may
                                                  EIR/EIS describes the Sites Reservoir                   of the Sites Reservoir Project                        be made publicly available at any time.
                                                  Project, potential alternatives to the                  Alternatives in the Draft EIR/EIS.                    While you can ask us in your comment
                                                  Sites Reservoir Project, environmental                     The Sites Reservoir Project is the                 to withhold your personal identifying
                                                  setting, potential direct, indirect, and                subject of a Notice of Preparation (NOP)              information from public review, we
                                                                                                          issued on November 5, 2001, to prepare                cannot guarantee that we will be able to
                                                  cumulative impacts that could result
                                                                                                          an EIR under CEQA, and a Notice of                    do so.
                                                  from implementation of each of the
                                                                                                          Intent (NOI) published on November 9,
                                                  alternatives, and mitigation measures                                                                           Dated: August 14, 2017.
                                                                                                          2001 (66 FR 56708), to prepare an EIS
                                                  for potentially significant impacts, as                                                                       Grayford F. Payne,
                                                                                                          under NEPA. The Sites Reservoir Project
                                                  applicable. Four alternative methods of                                                                       Deputy Commissioner—Policy,
                                                                                                          was formerly known as the North-of-
                                                  constructing and operating the Sites                                                                          Administration and Budget.
                                                                                                          Delta Offstream Storage project led by
                                                  Reservoir Project are evaluated in the                                                                        [FR Doc. 2017–17487 Filed 8–17–17; 8:45 am]
                                                                                                          the California Department of Water
                                                  Draft FR to meet all or the majority of                                                                       BILLING CODE 4332–90–P
                                                                                                          Resources (DWR). The Sites Project
                                                  the purpose, and need, and goals, and
                                                                                                          Authority has assumed the role of the
                                                  objectives of the Sites Reservoir Project.              CEQA lead agency in lieu of DWR and
                                                  Other alternatives evaluated over the                   will be responsible for constructing,                 INTERNATIONAL TRADE
                                                  past several decades (some of which                     operating, and maintaining the Sites                  COMMISSION
                                                  were the subject of prior CEQA and                      Reservoir Project. Because of this
                                                  National Environmental Policy Act                                                                             [Investigation No. 731–TA–1380
                                                                                                          change in lead agency, the Sites Project              (Preliminary)]
                                                  (NEPA) analyses and decision making)                    Authority issued a Supplemental NOP
                                                  are summarized and discussed in                         on February 2, 2017, for the Draft EIR                Tapered Roller Bearings From Korea;
                                                  Chapter 2 Alternatives Analysis of the                  for the Project.                                      Determination
                                                  Draft EIR/EIS.                                             Reclamation’s involvement in the
                                                     The proposed Sites Reservoir Project                 Sites Reservoir Project includes the                     On the basis of the record 1 developed
                                                  facilities would primarily be located in                following actions: (1) The development                in the subject investigation, the United
                                                  Glenn and Colusa counties,                              of a Federal feasibility report, and                  States International Trade Commission
                                                  approximately 10 miles west of the                      related EIS under NEPA, to support                    (‘‘Commission’’) determines, pursuant
                                                  town of Maxwell, California. Proposed                   potential funding by the Federal                      to the Tariff Act of 1930 (‘‘the Act’’),
                                                  minor modifications to an existing                      Government, pursuant to the Calfed                    that there is a reasonable indication that
                                                  diversion facility would also need to                   Bay-Delta Authorization Act (Pub. L.                  an industry in the United States is
                                                  occur at the existing Red Bluff Pumping                 108–361); (2) the potential approval of               materially injured by reason of imports
                                                  Plant in Tehama County, California. The                 the use of the Tehama-Colusa Canal for                of tapered roller bearings from Korea,
                                                  Sites Reservoir Project would consist of                water diversion and conveyance of                     provided for in subheadings 8482.20,
                                                  a new offstream surface storage reservoir               water to Sites Reservoir; and (3) the                 8482.91, and 8482.99 of the Harmonized
                                                  (Sites Reservoir) with two main dams,                   coordinated operations of Central Valley              Tariff Schedule of the United States,
                                                  up to nine saddle dams, and up to three                 Project (CVP) facilities and the Sites                that are alleged to be sold in the United
                                                  recreation areas. The Sites Reservoir                   Reservoir Project. In addition,                       States at less than fair value (‘‘LTFV’’).2
                                                  would be filled via two existing                        Reclamation’s involvement in the Sites                Commencement of Final Phase
                                                  Sacramento River diversions/canals                      Reservoir Project also could include: (1)             Investigation
                                                  (included in all alternatives) and a                    Potential Federal funding of the Project
                                                  proposed new inlet/outlet structure and                 pursuant to the Water Infrastructure                     Pursuant to section 207.18 of the
                                                  pipeline (included in the majority of                   Improvements for the Nation Act (Pub.                 Commission’s rules, the Commission
                                                  alternatives). The pipeline would allow                 L. 114–322); (2) participation in the                 also gives notice of the commencement
                                                  for diversion of excess Sacramento River                power lines to and from the Sites                     of the final phase of its investigation.
                                                  flows for most alternatives, and                        Reservoir; (3) involvement in and                     The Commission will issue a final phase
                                                  discharge of water under all                            jurisdiction over the potential electrical            notice of scheduling, which will be
                                                  alternatives. Water conveyance between                  power generation from the Sites                       published in the Federal Register as
                                                  the reservoir and the canals and                        Reservoir Project; and (4) potential new              provided in section 207.21 of the
                                                  pipeline would be facilitated by two                    legislative authority to acquire shares of            Commission’s rules, upon notice from
                                                  new regulating reservoirs. Pumping/                     the water managed by the Sites Project                the Department of Commerce
                                                  generating plants would also be                         Authority for federal conservation                    (‘‘Commerce’’) of an affirmative
                                                  included as part of most alternatives. A                activities.                                           preliminary determination in the
                                                  new overhead power line would                              If special assistance is required at the           investigation under section 733(b) of the
                                                  connect the pumping/generating plants                   public meetings, please contact Mr.                   Act, or, if the preliminary determination
                                                  and their associated electrical                         Michael Dietl at (916) 978–5070; or via               is negative, upon notice of an
                                                  switchyards to an existing overhead                     email at mdietl@usbr.gov. Please notify               affirmative final determination in that
mstockstill on DSK30JT082PROD with NOTICES




                                                  power line in the Sites Reservoir Project               Mr. Dietl as far in advance as possible               investigation under section 735(a) of the
                                                  area. New roads and a bridge across the                 to enable Reclamation to secure the                   Act. Parties that filed entries of
                                                  proposed Sites Reservoir would be                       needed services. If a request cannot be
                                                                                                                                                                  1 The record is defined in sec. 207.2(f) of the
                                                  constructed to provide access to the                    honored, the requestor will be notified.
                                                                                                                                                                Commission’s Rules of Practice and Procedure (19
                                                  proposed Sites Reservoir Project                        A telephone device for the hearing                    CFR 207.2(f)).
                                                  facilities and over the proposed                        impaired (TTY) is available at (800)                    2 Commissioner Meredith M. Broadbent

                                                  reservoir, and some existing roads                      877–8339.                                             dissenting.



                                             VerDate Sep<11>2014   17:47 Aug 17, 2017   Jkt 241001   PO 00000   Frm 00052   Fmt 4703   Sfmt 4703   E:\FR\FM\18AUN1.SGM   18AUN1



Document Created: 2017-08-18 07:40:22
Document Modified: 2017-08-18 07:40:22
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability and notice of public meetings.
DatesSubmit written comments on the Draft EIR/EIS on or before November 13, 2017.
ContactPlease contact Mr. Michael Dietl, Bureau of Reclamation, at (916) 978- 5070, or via email at [email protected]; or Mr. Rob Thomson, Sites Project Authority, at (530) 438-2309, or via email at EIR-EIS- [email protected]
FR Citation82 FR 39454 