82_FR_46502 82 FR 46311 - STP Nuclear Operating Company; South Texas Project, Units 1 and 2

82 FR 46311 - STP Nuclear Operating Company; South Texas Project, Units 1 and 2

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 82, Issue 191 (October 4, 2017)

Page Range46311-46311
FR Document2017-21253

The U.S. Nuclear Regulatory Commission (NRC) has issued renewed Facility Operating License Nos. NPF-76 and NPF-80 to STP Nuclear Operating Company (licensee), the operator of the South Texas Project (STP), Units 1 and 2. Renewed Facility Operating License Nos. NPF-76 and NPF-80 authorize operation of STP by the licensee at reactor core power levels not in excess of 3,853 megawatts thermal for each unit, in accordance with the provisions of the STP renewed licenses and technical specifications. In addition, the NRC has prepared a record of decision (ROD) that supports the NRC's decision to renew Facility Operating License Nos. NPF-76 and NPF-80.

Federal Register, Volume 82 Issue 191 (Wednesday, October 4, 2017)
[Federal Register Volume 82, Number 191 (Wednesday, October 4, 2017)]
[Notices]
[Page 46311]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-21253]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[Docket Nos. 50-498 & 50-499; NRC-2010-0375]


STP Nuclear Operating Company; South Texas Project, Units 1 and 2

AGENCY: Nuclear Regulatory Commission.

ACTION: License renewal and record of decision; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) has issued 
renewed Facility Operating License Nos. NPF-76 and NPF-80 to STP 
Nuclear Operating Company (licensee), the operator of the South Texas 
Project (STP), Units 1 and 2. Renewed Facility Operating License Nos. 
NPF-76 and NPF-80 authorize operation of STP by the licensee at reactor 
core power levels not in excess of 3,853 megawatts thermal for each 
unit, in accordance with the provisions of the STP renewed licenses and 
technical specifications. In addition, the NRC has prepared a record of 
decision (ROD) that supports the NRC's decision to renew Facility 
Operating License Nos. NPF-76 and NPF-80.

DATES: The renewal of Facility Operating License Nos. NPF-76 and NPF-80 
was issued on September 28, 2017.

ADDRESSES: Please refer to Docket ID NRC-2010-0375 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Web site: Go to http://www.regulations.gov and search for Docket ID NRC-2010-0375. Address 
questions about NRC dockets to Carol Gallagher; telephone: 301-415-
3463; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in this 
document.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.

FOR FURTHER INFORMATION CONTACT: Lois M. James, Office of Nuclear 
Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 
20555; telephone: 301-415-3306; email: [email protected].

SUPPLEMENTARY INFORMATION: Notice is hereby given that the NRC has 
issued renewed Facility Operating License Nos. NPF-76 and NPF-80 to STP 
Nuclear Operating Company (licensee), the operator of STP, Units 1 and 
2. Renewed Facility Operating License Nos. NPF-76 and NPF-80 authorize 
operation of STP by the licensee at reactor core power levels not in 
excess of 3,853 megawatts thermal for each unit, in accordance with the 
provisions of the STP renewed license and technical specifications. The 
NRC's ROD that supports the NRC's decision to renew Facility Operating 
License Nos. NPF-76 and NPF-80 is available in ADAMS under Accession 
No. ML17138A276 and was published in the Federal Register (FR) on 
September 25, 2017 (82 FR 44666). As discussed in the ROD and the final 
supplemental environmental impact statement (FSEIS) for STP, Supplement 
48 to NUREG-1437, ``Generic Environmental Impact Statement for License 
Renewal of Nuclear Plants Regarding South Texas Project, Units 1 and 2, 
Final Report'' dated November 2013 (ADAMS Accession No. ML13322A890), 
the NRC has considered a range of reasonable alternatives that included 
natural gas combined-cycle (NGCC); supercritical pulverized coal; 
combination of wind, solar, and NGCC; and the no action alternative. 
The FSEIS documents the environmental review, including the 
determination that the adverse environmental impacts of license renewal 
for STP are not so great that preserving the option of license renewal 
for energy planning decisionmakers would be unreasonable.
    South Texas Project, Units 1 and 2, are pressurized water reactors 
located in Bay City, TX (90 miles SW of Houston, TX). The application 
for the renewed licenses, ``License Renewal Application, South Texas 
Project, Unit 1 and Unit 2, Facility Operating License Nos. NPF-76 and 
NPF-80,'' dated October 25, 2010 (ADAMS Package Accession No. 
ML103010256), as supplemented by letters dated through May 2, 2017, 
complies with the standards and requirements of the Atomic Energy Act 
of 1954, as amended (the Act), and the NRC's regulations. As required 
by the Act and the NRC's regulations in Chapter 1 of title10 of the 
Code of Federal Regulations (10 CFR), the NRC has made appropriate 
findings, which are set forth in the license. A public notice of the 
proposed issuance of the renewed license and an opportunity for a 
hearing was published in the Federal Register on January 13, 2011 (76 
FR 2426). No adjudicatory matters are pending before the Commission or 
the Atomic Safety and Licensing Board Panel regarding the STP license 
renewal application.
    For further details with respect to this action, see: (1) STP 
Nuclear Operating Company license renewal application for STP dated 
October 25, 2010 (ADAMS Package Accession No. ML103010256), as 
supplemented by letters through May 2, 2017; (2) the NRC's safety 
evaluation report published on June 8, 2017 (ADAMS Package Accession 
No. ML17142A263); (3) the NRC's final environmental impact statement 
(NUREG-1437, Supplement 48) for STP published on November 30, 2013 
(ADAMS Accession No. ML13322A890); and (4) the NRC's ROD (ADAMS 
Accession No. ML17138A276).

    Dated at Rockville, Maryland, this 28th day of September 2017.

    For the Nuclear Regulatory Commission.
Joseph E. Donoghue,
Deputy Director, Division of License Renewal, Office of Nuclear Reactor 
Regulation.
[FR Doc. 2017-21253 Filed 10-3-17; 8:45 am]
 BILLING CODE 7590-01-P



                                                                           Federal Register / Vol. 82, No. 191 / Wednesday, October 4, 2017 / Notices                                                 46311

                                                collections/forms/nrc3.pdf. A Spanish                   for Docket ID NRC–2010–0375. Address                  included natural gas combined-cycle
                                                language version of the form (NRC Form                  questions about NRC dockets to Carol                  (NGCC); supercritical pulverized coal;
                                                3A) can also be found at https://                       Gallagher; telephone: 301–415–3463;                   combination of wind, solar, and NGCC;
                                                www.nrc.gov/reading-rm/doc-                             email: Carol.Gallagher@nrc.gov. For                   and the no action alternative. The FSEIS
                                                collections/forms/nrc3a.pdf . Additional                technical questions, contact the                      documents the environmental review,
                                                copies of NRC Form 3 may be obtained                    individual listed in the FOR FURTHER                  including the determination that the
                                                by writing to the Regional Administrator                INFORMATION CONTACT section of this                   adverse environmental impacts of
                                                of the appropriate U.S. Nuclear                         document.                                             license renewal for STP are not so great
                                                Regulatory Commission Regional Office,                     • NRC’s Agencywide Documents                       that preserving the option of license
                                                or via email to FORMS.Resource@                         Access and Management System                          renewal for energy planning
                                                nrc.gov. A list of current NRC                          (ADAMS): You may obtain publicly-                     decisionmakers would be unreasonable.
                                                Headquarters and Regional offices is                    available documents online in the
                                                available on NRC’s public Web site,                     ADAMS Public Documents collection at                     South Texas Project, Units 1 and 2,
                                                http://www.nrc.gov/about-nrc/                           http://www.nrc.gov/reading-rm/                        are pressurized water reactors located in
                                                locations.html.                                         adams.html. To begin the search, select               Bay City, TX (90 miles SW of Houston,
                                                                                                        ‘‘ADAMS Public Documents’’ and then                   TX). The application for the renewed
                                                  Dated at Rockville, Maryland, this 28th day
                                                of September 2017.                                      select ‘‘Begin Web-based ADAMS                        licenses, ‘‘License Renewal Application,
                                                                                                        Search.’’ For problems with ADAMS,                    South Texas Project, Unit 1 and Unit 2,
                                                  For the Nuclear Regulatory Commission.
                                                                                                        please contact the NRC’s Public                       Facility Operating License Nos. NPF–76
                                                Patricia K. Holahan,
                                                                                                        Document Room (PDR) reference staff at                and NPF–80,’’ dated October 25, 2010
                                                Director, Office of Enforcement.
                                                                                                        1–800–397–4209, 301–415–4737, or by                   (ADAMS Package Accession No.
                                                [FR Doc. 2017–21349 Filed 10–3–17; 8:45 am]
                                                                                                        email to pdr.resource@nrc.gov. The                    ML103010256), as supplemented by
                                                BILLING CODE 7590–01–P                                                                                        letters dated through May 2, 2017,
                                                                                                        ADAMS accession number for each
                                                                                                        document referenced (if it is available in            complies with the standards and
                                                                                                        ADAMS) is provided the first time that                requirements of the Atomic Energy Act
                                                NUCLEAR REGULATORY
                                                                                                        it is mentioned in this document.                     of 1954, as amended (the Act), and the
                                                COMMISSION
                                                                                                           • NRC’s PDR: You may examine and                   NRC’s regulations. As required by the
                                                [Docket Nos. 50–498 & 50–499; NRC–2010–                 purchase copies of public documents at                Act and the NRC’s regulations in
                                                0375]                                                   the NRC’s PDR, Room O1–F21, One                       Chapter 1 of title10 of the Code of
                                                                                                        White Flint North, 11555 Rockville                    Federal Regulations (10 CFR), the NRC
                                                STP Nuclear Operating Company;                          Pike, Rockville, Maryland 20852.
                                                South Texas Project, Units 1 and 2                                                                            has made appropriate findings, which
                                                                                                        FOR FURTHER INFORMATION CONTACT: Lois                 are set forth in the license. A public
                                                AGENCY:  Nuclear Regulatory                             M. James, Office of Nuclear Reactor                   notice of the proposed issuance of the
                                                Commission.                                             Regulation, U.S. Nuclear Regulatory                   renewed license and an opportunity for
                                                ACTION: License renewal and record of                   Commission, Washington, DC 20555;                     a hearing was published in the Federal
                                                decision; issuance.                                     telephone: 301–415–3306; email:                       Register on January 13, 2011 (76 FR
                                                                                                        Lois.James@nrc.gov.                                   2426). No adjudicatory matters are
                                                SUMMARY:   The U.S. Nuclear Regulatory                  SUPPLEMENTARY INFORMATION: Notice is                  pending before the Commission or the
                                                Commission (NRC) has issued renewed                     hereby given that the NRC has issued
                                                Facility Operating License Nos. NPF–76                                                                        Atomic Safety and Licensing Board
                                                                                                        renewed Facility Operating License Nos.               Panel regarding the STP license renewal
                                                and NPF–80 to STP Nuclear Operating                     NPF–76 and NPF–80 to STP Nuclear
                                                Company (licensee), the operator of the                                                                       application.
                                                                                                        Operating Company (licensee), the
                                                South Texas Project (STP), Units 1 and                  operator of STP, Units 1 and 2. Renewed                  For further details with respect to this
                                                2. Renewed Facility Operating License                   Facility Operating License Nos. NPF–76                action, see: (1) STP Nuclear Operating
                                                Nos. NPF–76 and NPF–80 authorize                        and NPF–80 authorize operation of STP                 Company license renewal application
                                                operation of STP by the licensee at                     by the licensee at reactor core power                 for STP dated October 25, 2010
                                                reactor core power levels not in excess                 levels not in excess of 3,853 megawatts               (ADAMS Package Accession No.
                                                of 3,853 megawatts thermal for each                     thermal for each unit, in accordance                  ML103010256), as supplemented by
                                                unit, in accordance with the provisions                 with the provisions of the STP renewed                letters through May 2, 2017; (2) the
                                                of the STP renewed licenses and                         license and technical specifications. The             NRC’s safety evaluation report
                                                technical specifications. In addition, the              NRC’s ROD that supports the NRC’s                     published on June 8, 2017 (ADAMS
                                                NRC has prepared a record of decision                   decision to renew Facility Operating                  Package Accession No. ML17142A263);
                                                (ROD) that supports the NRC’s decision                  License Nos. NPF–76 and NPF–80 is                     (3) the NRC’s final environmental
                                                to renew Facility Operating License                     available in ADAMS under Accession                    impact statement (NUREG–1437,
                                                Nos. NPF–76 and NPF–80.                                 No. ML17138A276 and was published                     Supplement 48) for STP published on
                                                DATES: The renewal of Facility                          in the Federal Register (FR) on                       November 30, 2013 (ADAMS Accession
                                                Operating License Nos. NPF–76 and                       September 25, 2017 (82 FR 44666). As                  No. ML13322A890); and (4) the NRC’s
                                                NPF–80 was issued on September 28,                      discussed in the ROD and the final                    ROD (ADAMS Accession No.
                                                2017.                                                   supplemental environmental impact                     ML17138A276).
                                                ADDRESSES: Please refer to Docket ID                    statement (FSEIS) for STP, Supplement                   Dated at Rockville, Maryland, this 28th day
                                                                                                        48 to NUREG–1437, ‘‘Generic
sradovich on DSK3GMQ082PROD with NOTICES




                                                NRC–2010–0375 when contacting the                                                                             of September 2017.
                                                NRC about the availability of                           Environmental Impact Statement for                      For the Nuclear Regulatory Commission.
                                                information regarding this document.                    License Renewal of Nuclear Plants
                                                                                                        Regarding South Texas Project, Units 1                Joseph E. Donoghue,
                                                You may obtain publicly-available
                                                information related to this document                    and 2, Final Report’’ dated November                  Deputy Director, Division of License Renewal,
                                                using any of the following methods:                     2013 (ADAMS Accession No.                             Office of Nuclear Reactor Regulation.
                                                   • Federal Rulemaking Web site: Go to                 ML13322A890), the NRC has considered                  [FR Doc. 2017–21253 Filed 10–3–17; 8:45 am]
                                                http://www.regulations.gov and search                   a range of reasonable alternatives that               BILLING CODE 7590–01–P




                                           VerDate Sep<11>2014   20:18 Oct 03, 2017   Jkt 244001   PO 00000   Frm 00101   Fmt 4703   Sfmt 9990   E:\FR\FM\04OCN1.SGM   04OCN1



Document Created: 2018-10-25 09:52:36
Document Modified: 2018-10-25 09:52:36
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionLicense renewal and record of decision; issuance.
DatesThe renewal of Facility Operating License Nos. NPF-76 and NPF-80 was issued on September 28, 2017.
ContactLois M. James, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555; telephone: 301-415-3306; email: [email protected]
FR Citation82 FR 46311 