DEPARTMENT OF THE INTERIOR
Bureau of Land Management

Federal Register Volume 82, Issue 207 (October 27, 2017)

Page Range49846-49847
FR Document2017-23417

In accordance with the National Environmental Policy Act of 1969, as amended (NEPA), and the Federal Land Policy and Management Act of 1976, as amended (FLPMA), the Bureau of Land Management (BLM) has prepared a Draft Amendment to the California Desert Conservation Area (CDCA) Plan and a Draft Supplemental Environmental Impact Statement (EIS) for the Palen Solar Photovoltaic (PSP) Project and by this Notice is announcing the opening of the comment period. This document is also an Environmental Impact Report (EIR) prepared by Riverside County under the California Environmental Quality Act (CEQA).

Federal Register, Volume 82 Issue 207 (Friday, October 27, 2017)
[Federal Register Volume 82, Number 207 (Friday, October 27, 2017)]
[Notices]
[Pages 49846-49847]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-23417]


-----------------------------------------------------------------------

DEPARTMENT OF THE INTERIOR

Bureau of Land Management

[LLCAD06000.51010000.ER0000.LVRWB17B5480 17X5017AP; CACA41880]


Notice of Availability of the Draft Supplemental Environmental 
Impact Statement and Environmental Impact Report and Draft Land Use 
Plan Amendment for the Palen Solar Photovoltaic Project, California

AGENCY: Bureau of Land Management, Interior.

ACTION: Notice of availability.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act of 
1969, as amended (NEPA), and the Federal Land Policy and Management Act 
of 1976, as amended (FLPMA), the Bureau of Land Management (BLM) has 
prepared a Draft Amendment to the California Desert Conservation Area 
(CDCA) Plan and a Draft Supplemental Environmental Impact Statement 
(EIS) for the Palen Solar Photovoltaic (PSP) Project and by this Notice 
is announcing the opening of the comment period. This document is also 
an Environmental Impact Report (EIR) prepared by Riverside County under 
the California Environmental Quality Act (CEQA).

DATES: To ensure that all comments will be considered, the BLM must 
receive written comments on the Draft Supplemental EIS/EIR within 45 
days following the date the Environmental Protection Agency publishes 
its Notice of Availability in the Federal Register. The BLM will 
announce future meetings or hearings and any other public involvement 
activities at least 15 days in advance through public notices, media 
releases, on the project Web site, and/or mailings.

ADDRESSES: You may submit comments related to the PSP Project by any of 
the following methods:
    Web site: https://eplanning.blm.gov/epl-front-office/eplanning/planAndProjectSite.do?methodName=renderDefaultPlanOrProjectSite&projectId=68122.
    Email: [email protected].
    Mail: Palen Solar PV Project, c/o Aspen Environmental Group, 235 
Montgomery Street, Suite 935, San Francisco, CA 94104
    Copies of the Draft Supplemental EIS/EIR are available in the BLM-
Palm Springs South Coast Field Office, 1201 Bird Center Drive, Palm 
Springs, CA 92262, and at the BLM California Desert District Office, 
22835 Calle San Juan De Los Lagos, Moreno Valley, CA 92553, and 
electronically on the project Web site. Compact Disc copies of the 
document are available through request on this project Web site 
address.

FOR FURTHER INFORMATION CONTACT: Mark DeMaio, BLM Project Manager, 
telephone: (760) 833-7124; address: BLM, Palm Springs-South Coast Field 
Office, 1201 Bird Center Drive, Palm Springs, CA 92262; email: 
[email protected].
    Persons who use telecommunication devices for the deaf may call the 
Federal Relay Service at 1-800-877-8339 to contact the above individual 
during normal business hours. The Service is available 24 hours a day, 
7 days a week, to leave a message or questions with the above 
individual regarding the project. You will receive a reply during 
normal business hours.

SUPPLEMENTARY INFORMATION: EDF Renewable Energy has applied for a 
Right-of-Way (ROW) from the BLM to construct, operate, maintain, and 
decommission a 500 megawatt (MW) solar photovoltaic facility near 
Desert Center, Riverside County, California. The ROW application area 
comprises about 4,200 acres, with a proposed project footprint of about 
3,400 acres. The proposed project also includes construction of a 6.7-
mile single circuit 230 kilovolt generation interconnection (gen-tie) 
transmission line connecting the project to the Southern California 
Edison (SCE) Red Bluff Substation.
    The BLM is also considering an amendment to the CDCA Plan that 
would be necessary to authorize the project. This is a joint EIS/EIR 
for compliance with NEPA and CEQA. Riverside County is the lead agency 
under CEQA.
    This Project application was originally submitted in 2007 as the 
Palen Solar Power Project (PSPP) by Palen Solar I, LLC (PSI), a wholly 
owned subsidiary of Solar Millennium. The PSPP was proposed as a solar 
trough project, and was the subject of an EIS under NEPA. The BLM, 
pursuant to its obligations under FLPMA and NEPA, published a Draft 
EIS, followed by a Proposed Resource Management Plan Amendment (RMP) 
and Final EIS on May 13, 2011 (76 FR 28064).
    Before the BLM issued a Record of Decision (ROD), PSI informed the 
BLM that it would not construct the Project due to bankruptcy. As a 
result, the BLM did not issue a ROD, did not amend the RMP, and did not 
issue a ROW grant for the PSPP.
    On June 21, 2012, the bankruptcy court approved the transfer of the 
application from PSI to Palen Solar III, LLC (PSIII). BrightSource 
Energy Inc., (BSE) then acquired all rights to PSIII at auction. PSIII 
submitted a revised ROW application to the BLM for the Palen Solar 
Electricity Generating System Project (PSEGS), a 500 MW concentrating 
solar power tower technology facility and single-circuit 230 kV gen-tie 
line. On July 27, 2013, the BLM issued a Draft Supplemental EIS and 
Plan Amendment to evaluate the potential additional environmental 
impacts caused by PSEGS. As part of the State permitting process, the 
California Energy Commission evaluated the PSEGS under CEQA, and issued 
Preliminary and Final Staff Assessments for the amended project in June 
and November of 2013, respectively.
    The BLM did not issue a Final Supplemental EIS for the PSEGS 
Project because BSE and its partner, Abengoa Solar Inc., abandoned the 
State authorization proceedings at the California Energy Commission. In 
December 2015, EDF Renewable Energy acquired the PSEGS project. EDF 
Renewable Energy has submitted a revised ROW application for the 
Proposed Project, which is analyzed in

[[Page 49847]]

this Draft Supplemental EIS/EIR and Draft Plan Amendment.
    For the PSP Project, the BLM held public meetings on the revised 
ROW application in June and August 2016 in Palm Springs, California. 
The Draft Supplemental EIS/EIR includes analysis of the revised ROW 
application as it relates to the following issues:
    (1) Updated description of the Proposed Project, based on the 
revised ROW application;
    (2) Impacts to cultural resources and tribal concerns;
    (3) Impacts to the Sand Transport Corridor and Mojave fringe-toed 
lizard habitat and washes;
    (4) Impacts to Joshua Tree National Park;
    (5) Impacts to avian species;
    (6) Impacts to visual resources; and
    (7) Relationship between the project and the regional renewable 
energy planning in the Desert Renewable Energy Conservation Plan.
    In addition to the Proposed Action, the Draft Supplemental EIS/EIR 
considers a No-Action Alternative and two additional action 
alternatives. Alternative 1, Reduced Footprint, would be a 500 MW 
Photovoltaic (PV) array on about 3,100 acres. It avoids the central and 
largest desert wash and incorporates a more efficient use of the land 
for the solar array. Alternative 2, Avoidance Alternative, would be an 
up to 230 MW solar PV array on about 1,620 acres. Like the Proposed 
Action, under each of these alternatives, the BLM would amend the CDCA 
Plan to allow the project. Under the No-Action Alternative, the BLM 
would deny the ROW application, and would not amend the CDCA Plan to 
allow the project.
    The BLM has selected Alternative 1--Reduced Footprint Alternative--
as the Agency-Preferred Alternative for the Draft Supplemental EIS. The 
BLM and other cooperating agencies involved are inviting Draft 
Supplemental EIS reviewers to offer comments on the comparison of 
alternatives, as presented in the document.
    Your input is important and will be considered in the environmental 
and land-use planning analysis. Please note that public comments and 
information submitted, including names, street addresses, and email 
addresses of persons who submit comments will be available for public 
review and disclosure at the above address during regular business 
hours (8 a.m. to 4 p.m.), Monday through Friday, except holidays.
    Before including your address, phone number, email address, or 
other personal identifying information in your comment, you should be 
aware that your entire comment--including your personal identifying 
information--may be made publicly available at any time. While you can 
ask us in your comment to withhold your personal identifying 
information from public review, we cannot guarantee that we will be 
able to do so.

    Authority:  40 CFR 1506.6, 40 CFR 1506.10, 43 CFR 1610.2.

Danielle Chi,
Deputy State Director, California.
[FR Doc. 2017-23417 Filed 10-26-17; 8:45 am]
 BILLING CODE 4310-40-P



                                                    49846                            Federal Register / Vol. 82, No. 207 / Friday, October 27, 2017 / Notices

                                                         Permit                Applicant                    Species/numbers                      Location            Activity            Type of take          Permit action
                                                     application No.

                                                    TE 034476–4 .....     Florida Forest         Red-cockaded woodpecker (Picoides          Blackwater River    Population man-     Install artificial nest   Renewal and
                                                                            Service,               borealis).                                 State Forest,       agement and         cavities and              Amendment.
                                                                            Blackwater For-                                                   Florida.            monitoring.         restrictors, mon-
                                                                            estry Center, Mil-                                                                                        itor nest cavities,
                                                                            ton, FL.                                                                                                  capture, band,
                                                                                                                                                                                      and translocate.



                                                      Authority: We provide this notice under                  ADDRESSES:    You may submit comments                   would be necessary to authorize the
                                                    section 10(c) of the Act.                                  related to the PSP Project by any of the                project. This is a joint EIS/EIR for
                                                      Dated: September 7, 2017.                                following methods:                                      compliance with NEPA and CEQA.
                                                    Aaron L. Valenta,                                             Web site: https://eplanning.blm.gov/                 Riverside County is the lead agency
                                                    Acting Assistant Regional Director, Ecological
                                                                                                               epl-front-office/eplanning/                             under CEQA.
                                                    Services, Southeast Region.                                planAndProjectSite.do?method                               This Project application was
                                                    [FR Doc. 2017–23390 Filed 10–26–17; 8:45 am]
                                                                                                               Name=renderDefaultPlanOrProject                         originally submitted in 2007 as the
                                                                                                               Site&projectId=68122.                                   Palen Solar Power Project (PSPP) by
                                                    BILLING CODE 4333–15–P
                                                                                                                  Email: palensolar@blm.gov.                           Palen Solar I, LLC (PSI), a wholly
                                                                                                                  Mail: Palen Solar PV Project, c/o
                                                                                                                                                                       owned subsidiary of Solar Millennium.
                                                                                                               Aspen Environmental Group, 235
                                                    DEPARTMENT OF THE INTERIOR                                                                                         The PSPP was proposed as a solar
                                                                                                               Montgomery Street, Suite 935, San
                                                                                                                                                                       trough project, and was the subject of an
                                                    Bureau of Land Management                                  Francisco, CA 94104
                                                                                                                  Copies of the Draft Supplemental EIS/                EIS under NEPA. The BLM, pursuant to
                                                                                                               EIR are available in the BLM-Palm                       its obligations under FLPMA and NEPA,
                                                    [LLCAD06000.51010000.                                      Springs South Coast Field Office, 1201                  published a Draft EIS, followed by a
                                                    ER0000.LVRWB17B5480 17X5017AP;
                                                                                                               Bird Center Drive, Palm Springs, CA                     Proposed Resource Management Plan
                                                    CACA41880]                                                                                                         Amendment (RMP) and Final EIS on
                                                                                                               92262, and at the BLM California Desert
                                                                                                               District Office, 22835 Calle San Juan De                May 13, 2011 (76 FR 28064).
                                                    Notice of Availability of the Draft
                                                                                                               Los Lagos, Moreno Valley, CA 92553,                        Before the BLM issued a Record of
                                                    Supplemental Environmental Impact
                                                                                                               and electronically on the project Web                   Decision (ROD), PSI informed the BLM
                                                    Statement and Environmental Impact
                                                                                                               site. Compact Disc copies of the                        that it would not construct the Project
                                                    Report and Draft Land Use Plan
                                                                                                               document are available through request                  due to bankruptcy. As a result, the BLM
                                                    Amendment for the Palen Solar
                                                                                                               on this project Web site address.                       did not issue a ROD, did not amend the
                                                    Photovoltaic Project, California
                                                                                                               FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                       RMP, and did not issue a ROW grant for
                                                    AGENCY:   Bureau of Land Management,                       Mark DeMaio, BLM Project Manager,                       the PSPP.
                                                    Interior.                                                  telephone: (760) 833–7124; address:                        On June 21, 2012, the bankruptcy
                                                    ACTION: Notice of availability.                            BLM, Palm Springs-South Coast Field                     court approved the transfer of the
                                                                                                               Office, 1201 Bird Center Drive, Palm                    application from PSI to Palen Solar III,
                                                    SUMMARY:   In accordance with the                          Springs, CA 92262; email: mdemaio@                      LLC (PSIII). BrightSource Energy Inc.,
                                                    National Environmental Policy Act of                       blm.gov.                                                (BSE) then acquired all rights to PSIII at
                                                    1969, as amended (NEPA), and the                              Persons who use telecommunication                    auction. PSIII submitted a revised ROW
                                                    Federal Land Policy and Management                         devices for the deaf may call the Federal               application to the BLM for the Palen
                                                    Act of 1976, as amended (FLPMA), the                       Relay Service at 1–800–877–8339 to                      Solar Electricity Generating System
                                                    Bureau of Land Management (BLM) has                        contact the above individual during                     Project (PSEGS), a 500 MW
                                                    prepared a Draft Amendment to the                          normal business hours. The Service is                   concentrating solar power tower
                                                    California Desert Conservation Area                        available 24 hours a day, 7 days a week,                technology facility and single-circuit
                                                    (CDCA) Plan and a Draft Supplemental                       to leave a message or questions with the                230 kV gen-tie line. On July 27, 2013,
                                                    Environmental Impact Statement (EIS)                       above individual regarding the project.                 the BLM issued a Draft Supplemental
                                                    for the Palen Solar Photovoltaic (PSP)                     You will receive a reply during normal                  EIS and Plan Amendment to evaluate
                                                    Project and by this Notice is announcing                   business hours.                                         the potential additional environmental
                                                    the opening of the comment period.                         SUPPLEMENTARY INFORMATION: EDF                          impacts caused by PSEGS. As part of the
                                                    This document is also an Environmental                     Renewable Energy has applied for a                      State permitting process, the California
                                                    Impact Report (EIR) prepared by                            Right-of-Way (ROW) from the BLM to                      Energy Commission evaluated the
                                                    Riverside County under the California                      construct, operate, maintain, and                       PSEGS under CEQA, and issued
                                                    Environmental Quality Act (CEQA).                          decommission a 500 megawatt (MW)                        Preliminary and Final Staff Assessments
                                                    DATES: To ensure that all comments will                    solar photovoltaic facility near Desert                 for the amended project in June and
                                                    be considered, the BLM must receive                        Center, Riverside County, California.                   November of 2013, respectively.
                                                    written comments on the Draft                              The ROW application area comprises                         The BLM did not issue a Final
                                                    Supplemental EIS/EIR within 45 days                        about 4,200 acres, with a proposed                      Supplemental EIS for the PSEGS Project
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    following the date the Environmental                       project footprint of about 3,400 acres.                 because BSE and its partner, Abengoa
                                                    Protection Agency publishes its Notice                     The proposed project also includes                      Solar Inc., abandoned the State
                                                    of Availability in the Federal Register.                   construction of a 6.7-mile single circuit               authorization proceedings at the
                                                    The BLM will announce future meetings                      230 kilovolt generation interconnection                 California Energy Commission. In
                                                    or hearings and any other public                           (gen-tie) transmission line connecting                  December 2015, EDF Renewable Energy
                                                    involvement activities at least 15 days                    the project to the Southern California                  acquired the PSEGS project. EDF
                                                    in advance through public notices,                         Edison (SCE) Red Bluff Substation.                      Renewable Energy has submitted a
                                                    media releases, on the project Web site,                      The BLM is also considering an                       revised ROW application for the
                                                    and/or mailings.                                           amendment to the CDCA Plan that                         Proposed Project, which is analyzed in


                                               VerDate Sep<11>2014      17:54 Oct 26, 2017   Jkt 244001   PO 00000   Frm 00066   Fmt 4703    Sfmt 4703   E:\FR\FM\27OCN1.SGM    27OCN1


                                                                                  Federal Register / Vol. 82, No. 207 / Friday, October 27, 2017 / Notices                                           49847

                                                    this Draft Supplemental EIS/EIR and                     your entire comment—including your                    1205–06 (Jan. 11, 2016). The complaint,
                                                    Draft Plan Amendment.                                   personal identifying information—may                  as supplemented, alleges violations of
                                                       For the PSP Project, the BLM held                    be made publicly available at any time.               section 337 in the importation into the
                                                    public meetings on the revised ROW                      While you can ask us in your comment                  United States, the sale for importation,
                                                    application in June and August 2016 in                  to withhold your personal identifying                 and the sale within the United States
                                                    Palm Springs, California. The Draft                     information from public review, we                    after importation of certain radio
                                                    Supplemental EIS/EIR includes analysis                  cannot guarantee that we will be able to              frequency identification (‘‘RFID’’)
                                                    of the revised ROW application as it                    do so.                                                products and components thereof by
                                                    relates to the following issues:                          Authority: 40 CFR 1506.6, 40 CFR                    reason of infringement of certain claims
                                                       (1) Updated description of the                       1506.10, 43 CFR 1610.2.                               of U.S. Patent Nos. 8,325,044 (‘‘the ’044
                                                    Proposed Project, based on the revised                                                                        patent’’); 7,119,664 (‘‘the ’664 patent’’);
                                                    ROW application;                                        Danielle Chi,                                         and 8,587,436 (‘‘the ’436 patent’’). The
                                                       (2) Impacts to cultural resources and                Deputy State Director, California.                    complaint further alleges that an
                                                    tribal concerns;                                        [FR Doc. 2017–23417 Filed 10–26–17; 8:45 am]          industry in the United States exists as
                                                       (3) Impacts to the Sand Transport                    BILLING CODE 4310–40–P                                required by 19 U.S.C. 1337(a)(2). The
                                                    Corridor and Mojave fringe-toed lizard                                                                        notice of investigation named numerous
                                                    habitat and washes;                                                                                           respondents. Respondents Kapsch
                                                       (4) Impacts to Joshua Tree National                  INTERNATIONAL TRADE                                   TrafficCom IVHS, Inc. of McLean,
                                                    Park;                                                   COMMISSION                                            Virginia; Kapsch TrafficCom Holding
                                                       (5) Impacts to avian species;                                                                              Corp. of McLean, Virginia; Kapsch
                                                       (6) Impacts to visual resources; and                 [Investigation No. 337–TA–979]                        TrafficCom Canada, Inc. of Mississauga,
                                                       (7) Relationship between the project                                                                       Ontario, Canada; Star Systems
                                                    and the regional renewable energy                       Certain Radio Frequency Identification                International, Ltd. of Kwai Chung, Hong
                                                    planning in the Desert Renewable                        (‘‘RFID’’) Products and Components                    Kong; and STAR RFID Co., Ltd. of
                                                    Energy Conservation Plan.                               Thereof Commission Determination                      Bangkok, Thailand (collectively,
                                                       In addition to the Proposed Action,                  Finding No Violation of Section 337;                  ‘‘Respondents’’) remain in the
                                                    the Draft Supplemental EIS/EIR                          Termination of the Investigation                      investigation. The Office of Unfair
                                                    considers a No-Action Alternative and                                                                         Import Investigations is also a party in
                                                                                                            AGENCY: U.S. International Trade
                                                    two additional action alternatives.                                                                           this investigation.
                                                                                                            Commission.
                                                    Alternative 1, Reduced Footprint, would                                                                          All asserted claims of the ’664 patent
                                                    be a 500 MW Photovoltaic (PV) array on                  ACTION: Notice.
                                                                                                                                                                  and certain asserted claims of the ’044
                                                    about 3,100 acres. It avoids the central                SUMMARY:   Notice is hereby given that                patent and the ’436 patent have been
                                                    and largest desert wash and                             the U.S. International Trade                          terminated from the investigation. See
                                                    incorporates a more efficient use of the                Commission has determined to find no                  Comm’n Notice (Sept. 27, 2016). Only
                                                    land for the solar array. Alternative 2,                violation of section 337 of the Tariff Act            claims 13, 14, and 25 of the ’044 patent
                                                    Avoidance Alternative, would be an up                   of 1930, in the above-identified                      and claims 1, 2, and 4 of the ’436 patent
                                                    to 230 MW solar PV array on about                       investigation. The investigation is                   remain in the investigation (collectively,
                                                    1,620 acres. Like the Proposed Action,                  terminated in its entirety.                           ‘‘the Asserted Claims’’).
                                                    under each of these alternatives, the                                                                            On June 22, 2017, the ALJ issued her
                                                    BLM would amend the CDCA Plan to                        FOR FURTHER INFORMATION CONTACT:
                                                                                                                                                                  final ID finding no violation of section
                                                    allow the project. Under the No-Action                  Cathy Chen, Esq., Office of the General               337 by the Respondents in connection
                                                    Alternative, the BLM would deny the                     Counsel, U.S. International Trade                     with the Asserted Claims. The final ID
                                                    ROW application, and would not amend                    Commission, 500 E Street SW.,                         found that all of the Asserted Claims are
                                                    the CDCA Plan to allow the project.                     Washington, DC 20436, telephone (202)                 invalid on multiple grounds. Had the
                                                       The BLM has selected Alternative 1—                  205–2392. Copies of non-confidential                  Asserted Claims not been found invalid,
                                                    Reduced Footprint Alternative—as the                    documents filed in connection with this               the final ID also found that the accused
                                                    Agency-Preferred Alternative for the                    investigation are or will be available for            products infringe the Asserted Claims;
                                                    Draft Supplemental EIS. The BLM and                     inspection during official business                   that Neology’s domestic industry
                                                    other cooperating agencies involved are                 hours (8:45 a.m. to 5:15 p.m.) in the                 products practice claim 25 of the ’044
                                                    inviting Draft Supplemental EIS                         Office of the Secretary, U.S.                         patent and claims 1, 2, and 4 of the ’436
                                                    reviewers to offer comments on the                      International Trade Commission, 500 E                 patent; and that Neology has satisfied
                                                    comparison of alternatives, as presented                Street SW., Washington, DC 20436,                     the economic prong of the domestic
                                                    in the document.                                        telephone (202) 205–2000. General                     industry requirement as to the ’044 and
                                                       Your input is important and will be                  information concerning the Commission                 the ’436 patents.
                                                    considered in the environmental and                     may also be obtained by accessing its                    Neology filed a timely petition for
                                                    land-use planning analysis. Please note                 Internet server at https://www.usitc.gov.             review of the final ID, challenging the
                                                    that public comments and information                    The public record for this investigation              final ID’s finding that the Asserted
                                                    submitted, including names, street                      may be viewed on the Commission’s                     Claims are invalid. That same day, the
                                                    addresses, and email addresses of                       electronic docket (EDIS) at https://                  Commission’s Investigative Attorney
                                                    persons who submit comments will be                     edis.usitc.gov. Hearing-impaired                      (‘‘IA’’) filed a contingent petition for
                                                                                                            persons are advised that information on
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    available for public review and                                                                               review of the final ID and Respondents
                                                    disclosure at the above address during                  this matter can be obtained by                        filed a joint contingent petition for
                                                    regular business hours (8 a.m. to 4 p.m.),              contacting the Commission’s TDD                       review of the final ID. Neology and the
                                                    Monday through Friday, except                           terminal on (202) 205–1810.                           IA both challenge certain of the final
                                                    holidays.                                               SUPPLEMENTARY INFORMATION: The                        ID’s findings with respect to the
                                                       Before including your address, phone                 Commission instituted this investigation              economic prong of the domestic
                                                    number, email address, or other                         on January 11, 2016, based on a                       industry requirement as to the ’436
                                                    personal identifying information in your                complaint filed by Neology, Inc. of                   patent. Respondents also challenge the
                                                    comment, you should be aware that                       Poway, California (‘‘Neology’’). 81 FR                final ID’s finding that the Asserted


                                               VerDate Sep<11>2014   17:54 Oct 26, 2017   Jkt 244001   PO 00000   Frm 00067   Fmt 4703   Sfmt 4703   E:\FR\FM\27OCN1.SGM   27OCN1



Document Created: 2017-10-27 02:05:54
Document Modified: 2017-10-27 02:05:54
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of availability.
DatesTo ensure that all comments will be considered, the BLM must receive written comments on the Draft Supplemental EIS/EIR within 45 days following the date the Environmental Protection Agency publishes its Notice of Availability in the Federal Register. The BLM will announce future meetings or hearings and any other public involvement activities at least 15 days in advance through public notices, media releases, on the project Web site, and/or mailings.
ContactMark DeMaio, BLM Project Manager,
FR Citation82 FR 49846 