82 FR 55594 - Notice of Intent To Prepare an Environmental Impact Statement for the Byram River Basin Flood Risk Management Study

DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers

Federal Register Volume 82, Issue 224 (November 22, 2017)

Page Range55594-55595
FR Document2017-25273

Pursuant to the requirements of the National Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers, New York District (Corps) in partnership with the Town of Greenwich as the non-federal sponsor, is preparing an integrated Feasibility Report/Environmental Impact Statement (FR/EIS) for the proposed Byram River Basin Flood Risk Management Feasibility Study. The study is assessing the feasibility of flood risk management alternatives to be implemented within the congressionally authorized study area with a specific emphasis on the Town of Greenwich, Fairfield County, Connecticut and Port Chester, Westchester County, New York.

Federal Register, Volume 82 Issue 224 (Wednesday, November 22, 2017)
[Federal Register Volume 82, Number 224 (Wednesday, November 22, 2017)]
[Notices]
[Pages 55594-55595]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-25273]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army, Corps of Engineers


Notice of Intent To Prepare an Environmental Impact Statement for 
the Byram River Basin Flood Risk Management Study

AGENCY: U.S. Army Corps of Engineers, DoD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: Pursuant to the requirements of the National Environmental 
Policy Act (NEPA), the U.S. Army Corps of Engineers, New York District 
(Corps) in partnership with the Town of Greenwich as the non-federal 
sponsor, is preparing an integrated Feasibility Report/Environmental 
Impact Statement (FR/EIS) for the proposed Byram River Basin Flood Risk 
Management Feasibility Study. The study is assessing the feasibility of 
flood risk management alternatives to be implemented within the 
congressionally authorized study area with a specific emphasis on the 
Town of Greenwich, Fairfield County, Connecticut and Port Chester, 
Westchester County, New York.

ADDRESSES: U.S. Army Corps of Engineers, New York District, Programs 
and Project Management Division, Civil Works Programs Branch, 26 
Federal Plaza, Room 2127, New York, NY 10279-0090. Pertinent 
information about the study can be found at: www.nan.usace.army.mil/Byram. Send written comments and suggestions concerning the scope of 
issues to be evaluated within the EIS to: [email protected].

FOR FURTHER INFORMATION CONTACT: Questions about the overall Byram 
River Basin Flood Risk Management Feasibility Study should be directed 
to Rifat Salim, Project Manager, U.S. Army Corps of Engineers, New York 
District, Programs and Project Management Division, Civil Works 
Programs Branch, 26 Federal Plaza, Room 2127, New York, NY 10279-0090; 
Phone: (917) 790-8215; email: [email protected].

SUPPLEMENTARY INFORMATION: 

1. Background

    The U.S. Army Corps of Engineers (Corps), in partnership with the 
Town of Greenwich as the non-Federal sponsor, is undertaking this 
study. The Town of Greenwich and Village of Port Chester have been 
subjected to repeated, severe flooding caused by overflow of the Byram 
River due to precipitation of high intensity, large amounts, or 
prolonged duration. The Byram River Basin study was authorized by a 
resolution of the Committee on Transportation and Infrastructure, 
Docket 2779, dated May 2nd, 2007.
    A Feasibility Cost Sharing Agreement (FCSA) was executed on August 
29, 2012 with the Town of Greenwich. The preliminary alternative 
analyses was completed early 2015 and identified Alternative #2a--
Nonstructural Within the 10-yr Floodplain, and Alternative #5--
Replacement of the Route 1 Highway Bridges, as each having a Benefit 
Cost Ratio over one and are being moved forward for further evaluation 
for eventual identification of the Tentatively Selected Plan.

2. Project Area

    The project area encompasses the portion of the Byram River located 
from southern section of the Pemberwick neighborhood to the Rt. 1 
bridges in the Town of Greenwich, Fairfield County, Connecticut and 
Village of Port Chester, Westchester County, New York.

Public Participation

    The Corps and the Town of Greenwich are currently anticipating 
hosting a NEPA Scoping Meeting in November 2017. Public notices 
announcing the meeting date, time, location and agenda will be 
published in the appropriate local newspapers, the Town of Greenwich 
Web page and on the Corps' New York District Web page (see the 
ADDRESSES section) and will be distributed to the local stakeholders 
and known interested parties.
    A scoping comment period of 30 days will be established from the 
scheduled date of the meeting to allow agencies, organizations and 
individuals to submit comments, questions and/or concerns regarding the 
Feasibility Study. Comments, concerns and information submitted to the 
Corps will be evaluated and considered during the development of the 
Draft EIS.

Lead and Cooperating Agencies

    The Corps is the lead federal agency for the preparation of the FR/
EIS and meeting the requirements of the National Environmental Policy 
Act and the NEPA Implementing Regulations of the President's Council on 
Environmental Quality (40 CFR 1500-1508). Federal agencies interested 
in participating as a Cooperating Agency are requested to submit a 
letter of intent to Colonel Thomas D. Asbery, District Engineer (see 
ADDRESSES). The preparation of the FR/EIS will be coordinated with the 
States of New York and Connecticut, Town of Greenwich and local 
municipalities with discretionary authority relative to the

[[Page 55595]]

proposed actions. The Draft FR/EIS is currently scheduled for 
distribution to the public in June 2018.

    Dated: November 14, 2017.
Peter M. Weppler,
Chief, Environmental Analysis Branch, Planning Division.
[FR Doc. 2017-25273 Filed 11-21-17; 8:45 am]
 BILLING CODE 3720-58-P



                                                    55594                    Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices

                                                    osd.pentagon.odam.mbx.defense-                          DEPARTMENT OF DEFENSE                                 was authorized by a resolution of the
                                                    business-board@mail.mil. A copy of the                                                                        Committee on Transportation and
                                                    public agenda and the terms of reference                Department of the Army, Corps of                      Infrastructure, Docket 2779, dated May
                                                    for the Task Group study may be                         Engineers                                             2nd, 2007.
                                                    obtained from the Board’s Web site at                                                                           A Feasibility Cost Sharing Agreement
                                                                                                            Notice of Intent To Prepare an                        (FCSA) was executed on August 29,
                                                    http://dbb.defense.gov/meetings.                        Environmental Impact Statement for                    2012 with the Town of Greenwich. The
                                                       Purpose of the Meeting: The mission                  the Byram River Basin Flood Risk                      preliminary alternative analyses was
                                                    of the Board is to examine and advise                   Management Study                                      completed early 2015 and identified
                                                    the Secretary of Defense on overall DoD                                                                       Alternative #2a—Nonstructural Within
                                                                                                            AGENCY:    U.S. Army Corps of Engineers,
                                                    management and governance. The Board                                                                          the 10-yr Floodplain, and Alternative
                                                                                                            DoD.
                                                    provides independent advice which                                                                             #5—Replacement of the Route 1
                                                                                                            ACTION:   Notice of intent.
                                                    reflects an outside private sector                                                                            Highway Bridges, as each having a
                                                    perspective on proven and effective best                SUMMARY:   Pursuant to the requirements               Benefit Cost Ratio over one and are
                                                    business practices that can be applied to               of the National Environmental Policy                  being moved forward for further
                                                    DoD. The Board will receive an out                      Act (NEPA), the U.S. Army Corps of                    evaluation for eventual identification of
                                                    brief, findings, and recommendations                    Engineers, New York District (Corps) in               the Tentatively Selected Plan.
                                                    from its Task Group on the study ‘‘Fully                partnership with the Town of
                                                                                                                                                                  2. Project Area
                                                    Burdened and Life Cycle Cost of the                     Greenwich as the non-federal sponsor,
                                                    Workforce.’’                                            is preparing an integrated Feasibility                   The project area encompasses the
                                                                                                            Report/Environmental Impact Statement                 portion of the Byram River located from
                                                       Agenda: 11:00 a.m.–11:05 a.m. DFO                                                                          southern section of the Pemberwick
                                                                                                            (FR/EIS) for the proposed Byram River
                                                    Comments to Public Attendees; 11:05                                                                           neighborhood to the Rt. 1 bridges in the
                                                                                                            Basin Flood Risk Management
                                                    a.m.–11:45 a.m. DBB Study Out brief on                  Feasibility Study. The study is assessing             Town of Greenwich, Fairfield County,
                                                    ‘‘Fully Burdened and Life Cycle Cost of                 the feasibility of flood risk management              Connecticut and Village of Port Chester,
                                                    the Workforce’’; 11:45 a.m.–11:50 a.m.                  alternatives to be implemented within                 Westchester County, New York.
                                                    Public Comments (if time permits);                      the congressionally authorized study
                                                    11:50 a.m.–12:00 p.m. Board                                                                                   Public Participation
                                                                                                            area with a specific emphasis on the
                                                    Deliberations and Vote.                                 Town of Greenwich, Fairfield County,                    The Corps and the Town of
                                                       Meeting Accessibility: Pursuant to 5                 Connecticut and Port Chester,                         Greenwich are currently anticipating
                                                                                                            Westchester County, New York.                         hosting a NEPA Scoping Meeting in
                                                    U.S.C. 552b, as amended, and 41 CFR
                                                                                                                                                                  November 2017. Public notices
                                                    102–3.140 through 102–3.165, this                       ADDRESSES: U.S. Army Corps of
                                                                                                                                                                  announcing the meeting date, time,
                                                    meeting is open to the public, subject to               Engineers, New York District, Programs
                                                                                                                                                                  location and agenda will be published
                                                    the availability of space. Seating is                   and Project Management Division, Civil
                                                                                                                                                                  in the appropriate local newspapers, the
                                                    limited and is on a first-come basis.                   Works Programs Branch, 26 Federal
                                                                                                                                                                  Town of Greenwich Web page and on
                                                                                                            Plaza, Room 2127, New York, NY
                                                       Written Statements: Written                                                                                the Corps’ New York District Web page
                                                                                                            10279–0090. Pertinent information
                                                    comments should be received by the                                                                            (see the ADDRESSES section) and will be
                                                                                                            about the study can be found at:
                                                    Designated Federal Officer (DFO) at                                                                           distributed to the local stakeholders and
                                                                                                            www.nan.usace.army.mil/Byram. Send
                                                    least five (5) business days prior to the                                                                     known interested parties.
                                                                                                            written comments and suggestions                        A scoping comment period of 30 days
                                                    meeting date so that the comments may                   concerning the scope of issues to be
                                                    be made available to the Board for their                                                                      will be established from the scheduled
                                                                                                            evaluated within the EIS to:                          date of the meeting to allow agencies,
                                                    consideration prior to the meeting.                     byram.river@usace.army.mil.
                                                    Written comments should be submitted                                                                          organizations and individuals to submit
                                                                                                            FOR FURTHER INFORMATION CONTACT:                      comments, questions and/or concerns
                                                    via email to the email address for public               Questions about the overall Byram River
                                                    comments given in the SUPPLEMENTARY                                                                           regarding the Feasibility Study.
                                                                                                            Basin Flood Risk Management                           Comments, concerns and information
                                                    INFORMATION section in either Adobe                     Feasibility Study should be directed to               submitted to the Corps will be evaluated
                                                    Acrobat or Microsoft Word format.                       Rifat Salim, Project Manager, U.S. Army               and considered during the development
                                                    Please note that since the Board                        Corps of Engineers, New York District,                of the Draft EIS.
                                                    operates under the provisions of the                    Programs and Project Management
                                                    FACA, as amended, all submitted                         Division, Civil Works Programs Branch,                Lead and Cooperating Agencies
                                                    comments and public presentations will                  26 Federal Plaza, Room 2127, New                        The Corps is the lead federal agency
                                                    be treated as public documents and will                 York, NY 10279–0090; Phone: (917)                     for the preparation of the FR/EIS and
                                                    be made available for public inspection,                790–8215; email: Rifat.Salim@                         meeting the requirements of the
                                                    including, but not limited to, being                    usace.army.mil.                                       National Environmental Policy Act and
                                                    posted on the Board’s Web site.                         SUPPLEMENTARY INFORMATION:                            the NEPA Implementing Regulations of
                                                      Dated November 17, 2017.                                                                                    the President’s Council on
                                                                                                            1. Background                                         Environmental Quality (40 CFR 1500–
                                                    Aaron Siegel,
                                                                                                               The U.S. Army Corps of Engineers                   1508). Federal agencies interested in
                                                    Alternate OSD Federal Register Liaison
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                            (Corps), in partnership with the Town of              participating as a Cooperating Agency
                                                    Officer, Department of Defense.                         Greenwich as the non-Federal sponsor,                 are requested to submit a letter of intent
                                                    [FR Doc. 2017–25259 Filed 11–21–17; 8:45 am]            is undertaking this study. The Town of                to Colonel Thomas D. Asbery, District
                                                    BILLING CODE 5001–06–P                                  Greenwich and Village of Port Chester                 Engineer (see ADDRESSES). The
                                                                                                            have been subjected to repeated, severe               preparation of the FR/EIS will be
                                                                                                            flooding caused by overflow of the                    coordinated with the States of New York
                                                                                                            Byram River due to precipitation of high              and Connecticut, Town of Greenwich
                                                                                                            intensity, large amounts, or prolonged                and local municipalities with
                                                                                                            duration. The Byram River Basin study                 discretionary authority relative to the


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00042   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1


                                                                             Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices                                           55595

                                                    proposed actions. The Draft FR/EIS is                   security code 1111, Web Conference                    192 miles to an existing substation
                                                    currently scheduled for distribution to                 URL: https://www.webmeeting.att.com,                  located in Deerfield, NH.
                                                    the public in June 2018.                                Meeting number 877–848–7030, Access                   ADDRESSES: The final Environmental
                                                      Dated: November 14, 2017.                             Code 9079541.                                         Impact Statement (EIS) and this Record
                                                    Peter M. Weppler,
                                                                                                              Written comments are accepted until                 of Decision (ROD) are available on the
                                                                                                            December 8, 2017. Written comments                    DOE National Environmental Policy Act
                                                    Chief, Environmental Analysis Branch,
                                                    Planning Division.
                                                                                                            may be submitted in the following ways:               (NEPA) Web site at https://energy.gov/
                                                                                                              Mail and Hand Delivery: to U.S. Army                nepa/and the Northern Pass
                                                    [FR Doc. 2017–25273 Filed 11–21–17; 8:45 am]
                                                                                                            Corps of Engineers, Chicago District,                 Transmission Line Project EIS Web site
                                                    BILLING CODE 3720–58–P
                                                                                                            ATTN: GLMRIS-Brandon Road                             at http://www.northernpasseis.us/. The
                                                                                                            Comments, 231 S. LaSalle St., Suite                   EIS Web site also includes a list of
                                                                                                            1500, Chicago, IL 60604. Comments                     libraries where the final EIS is available
                                                    DEPARTMENT OF DEFENSE
                                                                                                            must be postmarked by December 8,                     for review. Copies of the final EIS and
                                                    Department of the Army, Corps of                        2017 GLMRIS Project Web site: Use the                 this ROD may be requested by
                                                    Engineers                                               web comment function found at http://                 contacting Mr. Brian Mills, Office of
                                                                                                            glmris.anl.gov.                                       Electricity Delivery and Energy
                                                    Notice of a Public Meeting for The                        A Facebook Live participants can use                Reliability (OE–20), U.S. Department of
                                                    Great Lakes and Mississippi River                       the ‘‘Live Chat’’ feature. However, these             Energy, 1000 Independence Avenue
                                                    Interbasin Study—Brandon Road Draft                     comments will not be recorded in the                  SW., Washington, DC 20585; phone
                                                    Integrated Feasibility Study and                        official record.                                      202–586–8267; email Brian.Mills@
                                                    Environmental Impact Statement—Will                       The draft report/EIS and additional                 hq.doe.gov.
                                                    County, Illinois and Extension of                       information regarding this meeting can                FOR FURTHER INFORMATION CONTACT: For
                                                    Public Comment Period                                   be found at http://glmris.anl.gov/                    further information on the Northern
                                                                                                            brandon-rd/.                                          Pass Transmission Line Project EIS,
                                                    AGENCY:  Department of the Army, U.S.
                                                    Army Corps of Engineers, DoD.                             Authority: This action is being undertaken          contact Mr. Brian Mills as indicated in
                                                                                                            pursuant to the Water Resources and                   the ADDRESSES section above.
                                                    ACTION: Public meeting and extension of                 Development Act of 2007, Section 3061(d),
                                                    public comment period.                                                                                        SUPPLEMENTARY INFORMATION:
                                                                                                            Public Law 110–114 and the National
                                                                                                            Environmental Policy Act of 1969 (NEPA), 42           Background
                                                    SUMMARY:   The Rock Island and Chicago                  U.S.C. 4321, et seq., as amended.
                                                    Districts, U.S. Army Corps of Engineers                                                                          Executive Order (EO) 10485 (Sept. 3,
                                                    (USACE), will host a public meeting in                    Dated: November 15, 2017.                           1953), as amended by EO 12038 (Feb. 3,
                                                    New Orleans, Louisiana to discuss the                   Andrew Barnes,                                        1978), delegates to DOE the authority to
                                                    draft report titled The Great Lakes and                 Assistant Chief, Programs and Project                 issue Presidential permits for the
                                                    Mississippi River Interbasin Study—                     Management Division.                                  construction, operation, maintenance, or
                                                    Brandon Road Draft Integrated                           [FR Doc. 2017–25272 Filed 11–21–17; 8:45 am]          connection of electricity transmission
                                                    Feasibility Study and Environmental                     BILLING CODE 3720–58–P                                facilities at the U.S. international
                                                    Impact Statement—Will County, Illinois                                                                        borders. DOE may issue a permit if it
                                                    and receive input regarding this study.                                                                       determines that the permit is in the
                                                    DATES: The meeting will be held on                      DEPARTMENT OF ENERGY                                  public interest and after obtaining
                                                    December 5, 2017, from 1:00 to 4:00                                                                           favorable recommendations from the
                                                                                                            [OE Docket No 371]                                    U.S. Departments of State and Defense.
                                                    p.m. in New Orleans, Louisiana. USACE
                                                    is also extending the public comment                    Record of Decision for Issuing a                      In determining whether issuance of a
                                                    period for the original notice that                     Presidential Permit to Northern Pass                  permit would be in the public interest,
                                                    published in the Federal Register on                    Transmission LLC for the Northern                     DOE assesses the potential
                                                    September 27, 2017 (82 FR 45008) until                  Pass Transmission Line Project                        environmental impacts of the proposed
                                                    December 8, 2017.                                                                                             project, the potential impact of the
                                                    ADDRESSES: The meeting will be held at
                                                                                                            AGENCY:  Office of Electricity Delivery               proposed project on electric reliability,
                                                    USACE, New Orleans District, 7400                       and Energy Reliability, U.S. Department               and any other factors that DOE
                                                    Leake Ave, New Orleans, Louisiana,                      of Energy.                                            considers relevant to the public interest.
                                                    70118.                                                  ACTION: Record of decision.                           Issuance of a Presidential permit is a
                                                                                                                                                                  Presidential action, carried out by DOE
                                                    FOR FURTHER INFORMATION CONTACT:                        SUMMARY:   The U.S. Department of                     pursuant to delegated Presidential
                                                    Andrew Leichty, Program Manager, by                     Energy (DOE) announces its decision to                authority. Accordingly, DOE has no
                                                    mail: U.S. Army Corps of Engineers,                     issue a Presidential permit to Northern               legal obligation to prepare an EIS when
                                                    Rock Island District, Clock Tower                       Pass Transmission LLC (Northern Pass                  it considers a Presidential permit
                                                    Building (ATTN: Leichty), P.O. Box                      or Applicant) to construct, operate,                  application, since NEPA does not apply
                                                    2004, Rock Island, IL 61204–2004, by                    maintain, and connect an electric                     to acts of the President. Nonetheless,
                                                    phone: 309–794–5399; or by email:                       transmission line across the U.S./                    DOE opts to comply with NEPA and
                                                    Andrew.L.Leichty@usace.army.mil.                        Canada international border in northern               other Federal statutes as part of its
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    SUPPLEMENTARY INFORMATION: Web                          New Hampshire. The potential                          ‘‘public interest’’ review of Presidential
                                                    Participation: A Facebook Live format                   environmental impacts associated with                 permit applications, pursuant to DOE’s
                                                    web audio/video broadcast will be                       the transmission line are analyzed in the             long-standing Presidential permit
                                                    available for the meeting. Visit http://                Final Northern Pass Transmission Line                 regulations.
                                                    glmris.anl.gov/brandon-rd/ for details                  Project Environmental Impact                             On October 14, 2010, Northern Pass
                                                    on how to participate in these virtual                  Statement (DOE/EIS–0463). The                         applied to the DOE for a Presidential
                                                    meetings. Phone and web conference                      transmission line would cross the U.S./               permit to construct, operate, maintain,
                                                    access is as follows: Phone: Toll-Free:                 Canada international border into                      and connect a high voltage direct
                                                    877–848–7030, access code 9079541,                      Pittsburg, NH and extend approximately                current (HVDC) electric transmission


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00043   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1



Document Created: 2017-11-22 00:49:06
Document Modified: 2017-11-22 00:49:06
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of intent.
ContactQuestions about the overall Byram River Basin Flood Risk Management Feasibility Study should be directed to Rifat Salim, Project Manager, U.S. Army Corps of Engineers, New York District, Programs and Project Management Division, Civil Works Programs Branch, 26 Federal Plaza, Room 2127, New York, NY 10279-0090; Phone: (917) 790-8215; email: [email protected]
FR Citation82 FR 55594 