DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 224 (November 22, 2017)

Page Range55599-55600
FR Document2017-25328

Federal Register, Volume 82 Issue 224 (Wednesday, November 22, 2017)
[Federal Register Volume 82, Number 224 (Wednesday, November 22, 2017)]
[Notices]
[Pages 55599-55600]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-25328]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. ER18-301-000]


Ormesa LLC; Supplemental Notice That Initial Market-Based Rate 
Filing Includes Request for Blanket Section 204 Authorization

    This is a supplemental notice in the above-referenced proceeding 
Ormesa LLC's application for market-based rate authority, with an 
accompanying rate tariff, noting that such application includes a 
request for blanket authorization, under 18 CFR part 34, of future 
issuances of securities and assumptions of liability.
    Any person desiring to intervene or to protest should file with the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426, in accordance with Rules 211 and 214 of the Commission's 
Rules of Practice and Procedure (18 CFR 385.211 and 385.214). Anyone 
filing a motion to intervene or protest must serve a copy of that 
document on the Applicant.
    Notice is hereby given that the deadline for filing protests with 
regard to the applicant's request for blanket authorization, under 18 
CFR part 34, of future issuances of securities and assumptions of 
liability, is December 6, 2017.
    The Commission encourages electronic submission of protests and 
interventions in lieu of paper, using the FERC Online links at http://www.ferc.gov. To facilitate electronic service, persons with Internet 
access who will eFile a document and/or be listed as a contact for an 
intervenor must create and validate an eRegistration account using the 
eRegistration link. Select the eFiling link to log on and submit the 
intervention or protests.
    Persons unable to file electronically should submit an original and 
5 copies of the intervention or protest to the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426.

[[Page 55600]]

    The filings in the above-referenced proceeding are accessible in 
the Commission's eLibrary system by clicking on the appropriate link in 
the above list. They are also available for electronic review in the 
Commission's Public Reference Room in Washington, DC. There is an 
eSubscription link on the Web site that enables subscribers to receive 
email notification when a document is added to a subscribed docket(s). 
For assistance with any FERC Online service, please email 
[email protected]. or call (866) 208-3676 (toll free). For 
TTY, call (202) 502-8659.

    Dated: November 16, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-25328 Filed 11-21-17; 8:45 am]
BILLING CODE 6717-01-P



                                                                            Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices                                                 55599

                                                    measures (APMs) that apply directly to                  and permitting process for the project.’’             analysis assumes that the Applicant will
                                                    groundwater or any that apply                           DOE thanks EPA for its commitment to                  adhere to all stipulations defined in all
                                                    specifically to drinking water or                       work with the applicant and the Corps                 permits issued by the State of New
                                                    drinking water protection areas. We                     regarding project routing and impact                  Hampshire, including those defined by
                                                    recommend the DOE condition the                         minimization.                                         the New Hampshire Department of
                                                    Record of Decision (Presidential permit)                Pessamit Innu First Nation and Hydro-                 Environmental Services in their March
                                                    to require the Applicant to avoid or                    Quebec                                                2017 approval recommendation to the
                                                    minimize impacts to these resources,                                                                          SEC (NHDES 2017a).’’
                                                    including specific steps for contacting                   In an August 30, 2017 letter, the
                                                                                                                                                                  [FR Doc. 2017–25254 Filed 11–21–17; 8:45 am]
                                                    well owners (both private and public),                  Pessamit Innu First Nation provided
                                                                                                                                                                  BILLING CODE 6450–01–P
                                                    conducting water quality testing, and                   information about its past experiences
                                                    monitoring for impacts to well yield in                 with Hydro-Quebec and ongoing
                                                    areas near blasting and HDD. These                      concerns related to Hydro-Quebec’s                    DEPARTMENT OF ENERGY
                                                    steps would represent practicable means                 operations including planned
                                                    to avoid or minimize environmental                      modifications, operational changes,                   Federal Energy Regulatory
                                                    harm from the project.’’ The Water                      Canadian environmental review and                     Commission
                                                    Resources Technical Report (Section 3)                  potential effects on the Pessamit Innu
                                                    of the final EIS acknowledges the                       First Nation and its territory. Hydro-                [Docket No. ER18–301–000]
                                                    potential impacts of blasting on                        Quebec submitted a letter to DOE on
                                                    groundwater, including on wells. The                    October 11, 2017 in which it responded                Ormesa LLC; Supplemental Notice
                                                    report states that blasting ‘‘could                     to points raised in the letter from the               That Initial Market-Based Rate Filing
                                                    temporarily increase turbidity in                       Pessamit Innu First Nation. DOE                       Includes Request for Blanket Section
                                                    groundwater wells and infiltration of                   acknowledges the differing viewpoints                 204 Authorization
                                                    material spills or leaks near the blast                 of the commenters. However, the issues
                                                                                                            raised relate to impacts and processes in                This is a supplemental notice in the
                                                    zone.’’ DOE believes that the issues                                                                          above-referenced proceeding Ormesa
                                                    raised by EPA have been addressed in                    Canada. As DOE explained in its
                                                                                                            response to similar comments in                       LLC’s application for market-based rate
                                                    the mitigation measures incorporated in                                                                       authority, with an accompanying rate
                                                    the final EIS. The Water Resources                      Appendix L of the final EIS, potential
                                                                                                            impacts in Canada are beyond the scope                tariff, noting that such application
                                                    Technical Report (Section 3) goes on to                                                                       includes a request for blanket
                                                                                                            of the NEPA analysis, and ‘‘NEPA does
                                                    state that ‘‘BMPs would be implemented                                                                        authorization, under 18 CFR part 34, of
                                                                                                            not require an analysis of potential
                                                    to prevent the contamination of                                                                               future issuances of securities and
                                                                                                            environmental impacts that occur
                                                    groundwater and to identify private and                                                                       assumptions of liability.
                                                                                                            within another sovereign nation that
                                                    public water supply wells in advance.’’                                                                          Any person desiring to intervene or to
                                                                                                            result from actions approved by that
                                                    In addition, the APMs listed in Table H–                                                                      protest should file with the Federal
                                                                                                            sovereign nation.’’ As the final EIS
                                                    1 of Appendix H (noise), include the                                                                          Energy Regulatory Commission, 888
                                                                                                            noted, DOE does not analyze the
                                                    following measures, ‘‘[f]or any required                                                                      First Street NE., Washington, DC 20426,
                                                                                                            impacts in Canada of Hydro-Québec
                                                    project blasting activities, a blasting                                                                       in accordance with Rules 211 and 214
                                                                                                            power generation and transmission line
                                                    plan will be developed that addresses,                  projects because these impacts are                    of the Commission’s Rules of Practice
                                                    among other things, . . . pre-blast                     analyzed in accordance with the                       and Procedure (18 CFR 385.211 and
                                                    surveys, notification protocols, and                    sovereign laws of Canada and because                  385.214). Anyone filing a motion to
                                                    safety analysis. Blasting in any sensitive              DOE (nor any other U.S. federal agency)               intervene or protest must serve a copy
                                                    areas will be coordinated with the                      has no authority over development of                  of that document on the Applicant.
                                                    community and addressed in the                          the Hydro-Québec system.’’                              Notice is hereby given that the
                                                    construction planning phase.’’ Should                                                                         deadline for filing protests with regard
                                                    the project be approved, specific                       New Hampshire Department of                           to the applicant’s request for blanket
                                                    standards and methods required by the                   Environmental Services                                authorization, under 18 CFR part 34, of
                                                    New Hampshire Department of                                In its September 22, 2017 letter to                future issuances of securities and
                                                    Environmental Services would be                         DOE, the New Hampshire Department of                  assumptions of liability, is December 6,
                                                    established during the subsequent state                 Environmental Services (NHDES)                        2017.
                                                    permitting process.                                     provided recommended conditions that                     The Commission encourages
                                                       Regarding wetland issues, EPA                        ‘‘represent NHDES’ detailed technical                 electronic submission of protests and
                                                    commented that ‘‘the FEIS does not                      comments relative to the potential                    interventions in lieu of paper, using the
                                                    analyze the viability of the hybrid                     environmental impacts (and proposed                   FERC Online links at http://
                                                    alternative and additional narrative                    mitigation measures) related to this                  www.ferc.gov. To facilitate electronic
                                                    comparing the hybrid with the other                     project.’’ NHDES attached a March 1,                  service, persons with Internet access
                                                    alternatives would have made the EIS                    2017 letter and set of conditions it sent             who will eFile a document and/or be
                                                    more valuable for future state and                      to the NHSEC and characterized them as                listed as a contact for an intervenor
                                                    federal permitting. Regardless, the                     ‘‘conditions . . . that are to be                     must create and validate an
                                                    information provided will help focus                    incorporated into the decison-making                  eRegistration account using the
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    the upcoming analysis of project design                 process by the NHSEC during it                        eRegistration link. Select the eFiling
                                                    alternatives and determination of the                   upcoming deliberations.’’ DOE has                     link to log on and submit the
                                                    least environmentally damaging                          reviewed the recommended conditions                   intervention or protests.
                                                    practicable alternative by the Corps of                 provided by NHDES. DOE notes that                        Persons unable to file electronically
                                                    Engineers. EPA intends to continue to                   Appendix H (Applicant-Proposed                        should submit an original and 5 copies
                                                    work closely with the applicant and the                 Impact Avoidance and Minimization                     of the intervention or protest to the
                                                    Corps of Engineers regarding project                    Measures) of the final EIS references the             Federal Energy Regulatory Commission,
                                                    routing, impact minimization                            March 2017 NHDES conditions.                          888 First Street NE., Washington, DC
                                                    throughout the balance of the design                    Specifically, Appendix H states ‘‘this                20426.


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00047   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1


                                                    55600                    Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices

                                                       The filings in the above-referenced                     j. Deadline for filing comments,                      Pelzer Hydro and Consolidated Hydro
                                                    proceeding are accessible in the                        recommendations, terms and                            (co-licensees) operate the project in a
                                                    Commission’s eLibrary system by                         conditions, and prescriptions: 60 days                run-of-river mode using automatic pond
                                                    clicking on the appropriate link in the                 from the issuance date of this notice;                level control, with no storage or flood
                                                    above list. They are also available for                 reply comments are due 105 days from                  control capacity. A continuous
                                                    electronic review in the Commission’s                   the issuance date of this notice.                     minimum flow of 140 cubic feet per
                                                    Public Reference Room in Washington,                       The Commission strongly encourages                 second (cfs) or inflow, whichever is less,
                                                    DC. There is an eSubscription link on                   electronic filing. Please file comments,              is released into the bypassed reach. The
                                                    the Web site that enables subscribers to                recommendations, terms and                            minimum flow is achieved via a sluice
                                                    receive email notification when a                       conditions, and prescriptions using the               gate in the non-overflow section of the
                                                    document is added to a subscribed                       Commission’s eFiling system at http://                dam. The project operates under an
                                                    docket(s). For assistance with any FERC                 www.ferc.gov/docs-filing/efiling.asp.                 estimated average head of 40 feet,
                                                    Online service, please email                            Commenters can submit brief comments                  including the 4-foot-high spillway
                                                    FERCOnlineSupport@ferc.gov. or call                     up to 6,000 characters, without prior                 flashboards. The impoundment water
                                                    (866) 208–3676 (toll free). For TTY, call               registration, using the eComment system               surface elevation is maintained at 693
                                                    (202) 502–8659.                                         at http://www.ferc.gov/docs-filing/                   feet. River flows between 159 and 1,408
                                                                                                            ecomment.asp. You must include your                   cfs are used for power generation, while
                                                      Dated: November 16, 2017.
                                                                                                            name and contact information at the end               flows in excess of 1,408 cfs are passed
                                                    Kimberly D. Bose,
                                                                                                            of your comments. For assistance,                     over the flashboards and spillway. Flow
                                                    Secretary.                                              please contact FERC Online Support at                 to the generating units is controlled by
                                                    [FR Doc. 2017–25328 Filed 11–21–17; 8:45 am]            FERCOnlineSupport@ferc.gov, (866)                     five manually operated square slide
                                                    BILLING CODE 6717–01–P                                  208–3676 (toll free), or (202) 502–8659               gates. The total installed capacity of the
                                                                                                            (TTY). In lieu of electronic filing, please           project is 3,300 kW between the five
                                                                                                            send a paper copy to: Secretary, Federal              generating units. The project generates
                                                    DEPARTMENT OF ENERGY                                    Energy Regulatory Commission, 888                     approximately 8,784 megawatt-hours
                                                                                                            First Street NE., Washington, DC 20426.               annually, which are sold to a local
                                                    Federal Energy Regulatory
                                                                                                            The first page of any filing should                   utility.
                                                    Commission
                                                                                                            include docket number P–10253–032.                       The co-licensees propose to continue
                                                    [Project No. 10253–032]                                    The Commission’s Rules of Practice                 to operate and maintain the Lower
                                                                                                            require all intervenors filing documents              Pelzer Project as is required in the
                                                    Pelzer Hydro Company, LLC;                              with the Commission to serve a copy of                existing license, and to develop canoe
                                                    Consolidated Hydro Southeast, LLC;                      that document on each person on the                   portage facilities. The co-licensees also
                                                    Notice of Application Ready for                         official service list for the project.                propose to remove the previous three-
                                                    Environmental Analysis and Soliciting                   Further, if an intervenor files comments              mile-long, 3,300-volt overhead
                                                    Comments, Recommendations, Terms                        or documents with the Commission                      transmission line, which is no longer in
                                                    and Conditions, and Prescriptions                       relating to the merits of an issue that               use, from the project boundary under a
                                                      Take notice that the following                        may affect the responsibilities of a                  new license. Instead, the project uses a
                                                    hydroelectric application has been filed                particular resource agency, they must                 165-foot-long, 3,300-volt transmission
                                                    with the Commission and is available                    also serve a copy of the document on                  line that interconnects with the grid at
                                                                                                            that resource agency.                                 an applicant-owned transformer.
                                                    for public inspection.
                                                                                                               k. This application has been accepted                 m. A copy of the application is
                                                      a. Type of Application: New License.
                                                      b. Project No.: 10253–032.                            and is now ready for environmental                    available for review at the Commission
                                                      c. Date filed: November 30, 2015.                     analysis.                                             in the Public Reference Room, or may be
                                                      d. Applicant: Pelzer Hydro Company,                      l. The Lower Pelzer Project consists               viewed on the Commission’s Web site at
                                                    LLC (Pelzer Hydro), Consolidated Hydro                  of: (1) A 696-foot-long by 40-foot-high               http://www.ferc.gov using the
                                                    Southeast, LLC (Consolidated Hydro).                    granite masonry dam, consisting of (i) a              ‘‘eLibrary’’ link. Enter the docket
                                                      e. Name of Project: Lower Pelzer                      310-foot-long spillway section topped                 number excluding the last three digits in
                                                    Hydroelectric Project.                                  with 4-foot-high wooden flashboards,                  the docket number field to access the
                                                      f. Location: The existing project is                  (ii) a 40-foot-long non-overflow section              document. For assistance, contact FERC
                                                    located on the Saluda River near the                    with two 10-foot-wide by 6-foot-high                  Online Support. A copy is also available
                                                    Towns of Pelzer and Williamston, in                     gates, and (iii) a 236-foot-long non-                 for inspection and reproduction at the
                                                    Anderson and Greenville Counties,                       overflow section; (2) an 80-acre                      address in item h above.
                                                    South Carolina. The project does not                    impoundment at a normal pool                             All filings must: (1) Bear in all capital
                                                    affect federal land.                                    elevation of 693 feet mean sea level; (3)             letters the title COMMENTS, REPLY
                                                       g. Filed Pursuant to: Federal Power                  a 110-foot-long by 14-foot-wide intake,               COMMENTS, RECOMMENDATIONS,
                                                    Act 16 U.S.C. 791(a)–825(r).                            protected by a trashrack structure with               TERMS AND CONDITIONS, or
                                                       h. Applicant Contact: Beth E. Harris,                2-inch clear bar spacing, controlling                 PRESCRIPTIONS; (2) set forth in the
                                                    P.E., Regional Operations Manager, Enel                 flow to the powerhouse through five,                  heading the name of the applicant and
                                                    Green Power North America, Inc., 11                     10.5-foot-wide square gates; (4) a 110-               the project number of the application to
                                                    Anderson Street, Piedmont, SC 29673;                    foot-long by 68-foot-wide brick                       which the filing responds; (3) furnish
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    Telephone—(864) 846–0042; Email—                        powerhouse integral with the dam,                     the name, address, and telephone
                                                    beth.harris@enel.com, OR Kevin Webb,                    containing 5 horizontal Francis turbine               number of the person submitting the
                                                    Hydro Licensing Manager, Enel Green                     generating units that total 3,300                     filing; and (4) otherwise comply with
                                                    Power North America, Inc., One Tech                     kilowatts (kW); (5) a 600-foot-long by                the requirements of 18 CFR 385.2001
                                                    Drive, Suite 220, Andover, MA 01810;                    110-foot-wide tailrace; (6) a 3-mile-long,            through 385.2005. All comments,
                                                    Telephone—(978) 681–1900; Email—                        3,300-volt transmission line connecting               recommendations, terms and conditions
                                                    kevin.webb@enel.com.                                    the powerhouse to the grid via a 7.2/                 or prescriptions must set forth their
                                                       i. FERC Contact: Navreet Deo, (202)                  12.47 kilovolt transformer; and (7)                   evidentiary basis and otherwise comply
                                                    502–6304, or navreet.deo@ferc.gov.                      appurtenant facilities.                               with the requirements of 18 CFR 4.34(b).


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00048   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1



Document Created: 2017-11-22 00:49:14
Document Modified: 2017-11-22 00:49:14
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 55599 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR