82_FR_55824 82 FR 55600 - Pelzer Hydro Company, LLC; Consolidated Hydro Southeast, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

82 FR 55600 - Pelzer Hydro Company, LLC; Consolidated Hydro Southeast, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 224 (November 22, 2017)

Page Range55600-55601
FR Document2017-25319

Federal Register, Volume 82 Issue 224 (Wednesday, November 22, 2017)
[Federal Register Volume 82, Number 224 (Wednesday, November 22, 2017)]
[Notices]
[Pages 55600-55601]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-25319]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 10253-032]


Pelzer Hydro Company, LLC; Consolidated Hydro Southeast, LLC; 
Notice of Application Ready for Environmental Analysis and Soliciting 
Comments, Recommendations, Terms and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: New License.
    b. Project No.: 10253-032.
    c. Date filed: November 30, 2015.
    d. Applicant: Pelzer Hydro Company, LLC (Pelzer Hydro), 
Consolidated Hydro Southeast, LLC (Consolidated Hydro).
    e. Name of Project: Lower Pelzer Hydroelectric Project.
    f. Location: The existing project is located on the Saluda River 
near the Towns of Pelzer and Williamston, in Anderson and Greenville 
Counties, South Carolina. The project does not affect federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791(a)-825(r).
    h. Applicant Contact: Beth E. Harris, P.E., Regional Operations 
Manager, Enel Green Power North America, Inc., 11 Anderson Street, 
Piedmont, SC 29673; Telephone--(864) 846-0042; Email_
[email protected], OR Kevin Webb, Hydro Licensing Manager, Enel 
Green Power North America, Inc., One Tech Drive, Suite 220, Andover, MA 
01810; Telephone--(978) 681-1900; [email protected]
    i. FERC Contact: Navreet Deo, (202) 502-6304, or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-10253-032.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. The Lower Pelzer Project consists of: (1) A 696-foot-long by 40-
foot-high granite masonry dam, consisting of (i) a 310-foot-long 
spillway section topped with 4-foot-high wooden flashboards, (ii) a 40-
foot-long non-overflow section with two 10-foot-wide by 6-foot-high 
gates, and (iii) a 236-foot-long non-overflow section; (2) an 80-acre 
impoundment at a normal pool elevation of 693 feet mean sea level; (3) 
a 110-foot-long by 14-foot-wide intake, protected by a trashrack 
structure with 2-inch clear bar spacing, controlling flow to the 
powerhouse through five, 10.5-foot-wide square gates; (4) a 110-foot-
long by 68-foot-wide brick powerhouse integral with the dam, containing 
5 horizontal Francis turbine generating units that total 3,300 
kilowatts (kW); (5) a 600-foot-long by 110-foot-wide tailrace; (6) a 3-
mile-long, 3,300-volt transmission line connecting the powerhouse to 
the grid via a 7.2/12.47 kilovolt transformer; and (7) appurtenant 
facilities.
    Pelzer Hydro and Consolidated Hydro (co-licensees) operate the 
project in a run-of-river mode using automatic pond level control, with 
no storage or flood control capacity. A continuous minimum flow of 140 
cubic feet per second (cfs) or inflow, whichever is less, is released 
into the bypassed reach. The minimum flow is achieved via a sluice gate 
in the non-overflow section of the dam. The project operates under an 
estimated average head of 40 feet, including the 4-foot-high spillway 
flashboards. The impoundment water surface elevation is maintained at 
693 feet. River flows between 159 and 1,408 cfs are used for power 
generation, while flows in excess of 1,408 cfs are passed over the 
flashboards and spillway. Flow to the generating units is controlled by 
five manually operated square slide gates. The total installed capacity 
of the project is 3,300 kW between the five generating units. The 
project generates approximately 8,784 megawatt-hours annually, which 
are sold to a local utility.
    The co-licensees propose to continue to operate and maintain the 
Lower Pelzer Project as is required in the existing license, and to 
develop canoe portage facilities. The co-licensees also propose to 
remove the previous three-mile-long, 3,300-volt overhead transmission 
line, which is no longer in use, from the project boundary under a new 
license. Instead, the project uses a 165-foot-long, 3,300-volt 
transmission line that interconnects with the grid at an applicant-
owned transformer.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room, or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must: (1) Bear in all capital letters the title 
COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or 
PRESCRIPTIONS; (2) set forth in the heading the name of the applicant 
and the project number of the application to which the filing responds; 
(3) furnish the name, address, and telephone number of the person 
submitting the filing; and (4) otherwise comply with the requirements 
of 18 CFR 385.2001 through 385.2005. All comments, recommendations, 
terms and conditions or prescriptions must set forth their evidentiary 
basis and otherwise comply with the requirements of 18 CFR 4.34(b).

[[Page 55601]]

Agencies may obtain copies of the application directly from the 
applicant. Each filing must be accompanied by proof of service on all 
persons listed on the service list prepared by the Commission in this 
proceeding, in accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

Kimberly D. Bose,
Secretary.
[FR Doc. 2017-25319 Filed 11-21-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                    55600                    Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices

                                                       The filings in the above-referenced                     j. Deadline for filing comments,                      Pelzer Hydro and Consolidated Hydro
                                                    proceeding are accessible in the                        recommendations, terms and                            (co-licensees) operate the project in a
                                                    Commission’s eLibrary system by                         conditions, and prescriptions: 60 days                run-of-river mode using automatic pond
                                                    clicking on the appropriate link in the                 from the issuance date of this notice;                level control, with no storage or flood
                                                    above list. They are also available for                 reply comments are due 105 days from                  control capacity. A continuous
                                                    electronic review in the Commission’s                   the issuance date of this notice.                     minimum flow of 140 cubic feet per
                                                    Public Reference Room in Washington,                       The Commission strongly encourages                 second (cfs) or inflow, whichever is less,
                                                    DC. There is an eSubscription link on                   electronic filing. Please file comments,              is released into the bypassed reach. The
                                                    the Web site that enables subscribers to                recommendations, terms and                            minimum flow is achieved via a sluice
                                                    receive email notification when a                       conditions, and prescriptions using the               gate in the non-overflow section of the
                                                    document is added to a subscribed                       Commission’s eFiling system at http://                dam. The project operates under an
                                                    docket(s). For assistance with any FERC                 www.ferc.gov/docs-filing/efiling.asp.                 estimated average head of 40 feet,
                                                    Online service, please email                            Commenters can submit brief comments                  including the 4-foot-high spillway
                                                    FERCOnlineSupport@ferc.gov. or call                     up to 6,000 characters, without prior                 flashboards. The impoundment water
                                                    (866) 208–3676 (toll free). For TTY, call               registration, using the eComment system               surface elevation is maintained at 693
                                                    (202) 502–8659.                                         at http://www.ferc.gov/docs-filing/                   feet. River flows between 159 and 1,408
                                                                                                            ecomment.asp. You must include your                   cfs are used for power generation, while
                                                      Dated: November 16, 2017.
                                                                                                            name and contact information at the end               flows in excess of 1,408 cfs are passed
                                                    Kimberly D. Bose,
                                                                                                            of your comments. For assistance,                     over the flashboards and spillway. Flow
                                                    Secretary.                                              please contact FERC Online Support at                 to the generating units is controlled by
                                                    [FR Doc. 2017–25328 Filed 11–21–17; 8:45 am]            FERCOnlineSupport@ferc.gov, (866)                     five manually operated square slide
                                                    BILLING CODE 6717–01–P                                  208–3676 (toll free), or (202) 502–8659               gates. The total installed capacity of the
                                                                                                            (TTY). In lieu of electronic filing, please           project is 3,300 kW between the five
                                                                                                            send a paper copy to: Secretary, Federal              generating units. The project generates
                                                    DEPARTMENT OF ENERGY                                    Energy Regulatory Commission, 888                     approximately 8,784 megawatt-hours
                                                                                                            First Street NE., Washington, DC 20426.               annually, which are sold to a local
                                                    Federal Energy Regulatory
                                                                                                            The first page of any filing should                   utility.
                                                    Commission
                                                                                                            include docket number P–10253–032.                       The co-licensees propose to continue
                                                    [Project No. 10253–032]                                    The Commission’s Rules of Practice                 to operate and maintain the Lower
                                                                                                            require all intervenors filing documents              Pelzer Project as is required in the
                                                    Pelzer Hydro Company, LLC;                              with the Commission to serve a copy of                existing license, and to develop canoe
                                                    Consolidated Hydro Southeast, LLC;                      that document on each person on the                   portage facilities. The co-licensees also
                                                    Notice of Application Ready for                         official service list for the project.                propose to remove the previous three-
                                                    Environmental Analysis and Soliciting                   Further, if an intervenor files comments              mile-long, 3,300-volt overhead
                                                    Comments, Recommendations, Terms                        or documents with the Commission                      transmission line, which is no longer in
                                                    and Conditions, and Prescriptions                       relating to the merits of an issue that               use, from the project boundary under a
                                                      Take notice that the following                        may affect the responsibilities of a                  new license. Instead, the project uses a
                                                    hydroelectric application has been filed                particular resource agency, they must                 165-foot-long, 3,300-volt transmission
                                                    with the Commission and is available                    also serve a copy of the document on                  line that interconnects with the grid at
                                                                                                            that resource agency.                                 an applicant-owned transformer.
                                                    for public inspection.
                                                                                                               k. This application has been accepted                 m. A copy of the application is
                                                      a. Type of Application: New License.
                                                      b. Project No.: 10253–032.                            and is now ready for environmental                    available for review at the Commission
                                                      c. Date filed: November 30, 2015.                     analysis.                                             in the Public Reference Room, or may be
                                                      d. Applicant: Pelzer Hydro Company,                      l. The Lower Pelzer Project consists               viewed on the Commission’s Web site at
                                                    LLC (Pelzer Hydro), Consolidated Hydro                  of: (1) A 696-foot-long by 40-foot-high               http://www.ferc.gov using the
                                                    Southeast, LLC (Consolidated Hydro).                    granite masonry dam, consisting of (i) a              ‘‘eLibrary’’ link. Enter the docket
                                                      e. Name of Project: Lower Pelzer                      310-foot-long spillway section topped                 number excluding the last three digits in
                                                    Hydroelectric Project.                                  with 4-foot-high wooden flashboards,                  the docket number field to access the
                                                      f. Location: The existing project is                  (ii) a 40-foot-long non-overflow section              document. For assistance, contact FERC
                                                    located on the Saluda River near the                    with two 10-foot-wide by 6-foot-high                  Online Support. A copy is also available
                                                    Towns of Pelzer and Williamston, in                     gates, and (iii) a 236-foot-long non-                 for inspection and reproduction at the
                                                    Anderson and Greenville Counties,                       overflow section; (2) an 80-acre                      address in item h above.
                                                    South Carolina. The project does not                    impoundment at a normal pool                             All filings must: (1) Bear in all capital
                                                    affect federal land.                                    elevation of 693 feet mean sea level; (3)             letters the title COMMENTS, REPLY
                                                       g. Filed Pursuant to: Federal Power                  a 110-foot-long by 14-foot-wide intake,               COMMENTS, RECOMMENDATIONS,
                                                    Act 16 U.S.C. 791(a)–825(r).                            protected by a trashrack structure with               TERMS AND CONDITIONS, or
                                                       h. Applicant Contact: Beth E. Harris,                2-inch clear bar spacing, controlling                 PRESCRIPTIONS; (2) set forth in the
                                                    P.E., Regional Operations Manager, Enel                 flow to the powerhouse through five,                  heading the name of the applicant and
                                                    Green Power North America, Inc., 11                     10.5-foot-wide square gates; (4) a 110-               the project number of the application to
                                                    Anderson Street, Piedmont, SC 29673;                    foot-long by 68-foot-wide brick                       which the filing responds; (3) furnish
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                    Telephone—(864) 846–0042; Email—                        powerhouse integral with the dam,                     the name, address, and telephone
                                                    beth.harris@enel.com, OR Kevin Webb,                    containing 5 horizontal Francis turbine               number of the person submitting the
                                                    Hydro Licensing Manager, Enel Green                     generating units that total 3,300                     filing; and (4) otherwise comply with
                                                    Power North America, Inc., One Tech                     kilowatts (kW); (5) a 600-foot-long by                the requirements of 18 CFR 385.2001
                                                    Drive, Suite 220, Andover, MA 01810;                    110-foot-wide tailrace; (6) a 3-mile-long,            through 385.2005. All comments,
                                                    Telephone—(978) 681–1900; Email—                        3,300-volt transmission line connecting               recommendations, terms and conditions
                                                    kevin.webb@enel.com.                                    the powerhouse to the grid via a 7.2/                 or prescriptions must set forth their
                                                       i. FERC Contact: Navreet Deo, (202)                  12.47 kilovolt transformer; and (7)                   evidentiary basis and otherwise comply
                                                    502–6304, or navreet.deo@ferc.gov.                      appurtenant facilities.                               with the requirements of 18 CFR 4.34(b).


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00048   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1


                                                                             Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices                                             55601

                                                    Agencies may obtain copies of the                       Power North America, Inc., One Tech                   unit that totals 1,000 kilowatt (kW); (5)
                                                    application directly from the applicant.                Drive, Suite 220, Andover, MA 01810;                  a 180-foot-long by 38-foot-wide tailrace;
                                                    Each filing must be accompanied by                      Telephone—(978) 681–1900; Email—                      (6) a 263-foot-long, 600-volt
                                                    proof of service on all persons listed on               kevin.webb@enel.com.                                  transmission line connecting the
                                                    the service list prepared by the                           i. FERC Contact: Navreet Deo, (202)                powerhouse to the non-project
                                                    Commission in this proceeding, in                       502–6304, or navreet.deo@ferc.gov.                    substation; and (7) appurtenant
                                                    accordance with 18 CFR 4.34(b) and                         j. Deadline for filing comments,                   facilities.
                                                    385.2010.                                               recommendations, terms and                               Aquenergy operates the project in a
                                                       You may also register online at http://              conditions, and prescriptions: 60 days                run-of-river mode using automatic pond
                                                    www.ferc.gov/docs-filing/                               from the issuance date of this notice;                level control, with no useable storage or
                                                    esubscription.asp to be notified via                    reply comments are due 105 days from                  flood control capacity. A continuous
                                                    email of new filings and issuances                      the issuance date of this notice.                     minimum flow of 15 cubic feet per
                                                    related to this or other pending projects.                 The Commission strongly encourages                 second (cfs) or inflow, whichever is less,
                                                    For assistance, contact FERC Online                     electronic filing. Please file comments,              is released into the bypassed area. The
                                                    Support.                                                recommendations, terms and                            minimum flow is achieved via an 8-foot-
                                                       n. A license applicant must file no                  conditions, and prescriptions using the               wide by 1-foot-deep weir on the
                                                    later than 60 days following the date of                Commission’s eFiling system at http://                spillway crest. The project operates
                                                    issuance of this notice: (1) A copy of the              www.ferc.gov/docs-filing/efiling.asp.                 under an estimated average head of 26
                                                    water quality certification; (2) a copy of              Commenters can submit brief comments                  feet, including the 16-inch-high
                                                    the request for certification, including                up to 6,000 characters, without prior                 spillway flashboards. The impoundment
                                                    proof of the date on which the certifying               registration, using the eComment system               water surface elevation is maintained at
                                                    agency received the request; or (3)                     at http://www.ferc.gov/docs-filing/                   774 feet. River flows between 159 cfs
                                                    evidence of waiver of water quality                     ecomment.asp. You must include your                   and 535 cfs are used for power
                                                    certification.                                          name and contact information at the end               generation, while flows in excess of 535
                                                                                                            of your comments. For assistance,                     cfs are passed over the flashboards and
                                                    Kimberly D. Bose,                                       please contact FERC Online Support at                 spillway. The total installed capacity of
                                                    Secretary.                                              FERCOnlineSupport@ferc.gov, (866)                     the project is 1,000 kW from the single
                                                    [FR Doc. 2017–25319 Filed 11–21–17; 8:45 am]            208–3676 (toll free), or (202) 502–8659               generating unit. The project generates
                                                    BILLING CODE 6717–01–P                                  (TTY). In lieu of electronic filing, please           approximately 5,369 megawatt-hours
                                                                                                            send a paper copy to: Secretary, Federal              annually, which are sold to a local
                                                                                                            Energy Regulatory Commission, 888                     utility.
                                                    DEPARTMENT OF ENERGY                                    First Street NE., Washington, DC 20426.                  Aquenergy proposes to continue to
                                                                                                            The first page of any filing should                   operate and maintain the Piedmont
                                                    Federal Energy Regulatory                               include docket number P–2428–007.                     Project as is required in the existing
                                                    Commission                                                 The Commission’s Rules of Practice                 license, and to develop canoe portage
                                                                                                            require all intervenors filing documents              facilities.
                                                    [Project No. 2428–007]
                                                                                                            with the Commission to serve a copy of                   m. A copy of the application is
                                                    Aquenergy Systems, LLC; Notice of                       that document on each person on the                   available for review at the Commission
                                                    Application Ready for Environmental                     official service list for the project.                in the Public Reference Room, or may be
                                                    Analysis and Soliciting Comments,                       Further, if an intervenor files comments              viewed on the Commission’s Web site at
                                                    Recommendations, Terms and                              or documents with the Commission                      http://www.ferc.gov using the
                                                    Conditions, and Prescriptions                           relating to the merits of an issue that               ‘‘eLibrary’’ link. Enter the docket
                                                                                                            may affect the responsibilities of a                  number excluding the last three digits in
                                                      Take notice that the following                        particular resource agency, they must                 the docket number field to access the
                                                    hydroelectric application has been filed                also serve a copy of the document on                  document. For assistance, contact FERC
                                                    with the Commission and is available                    that resource agency.                                 Online Support. A copy is also available
                                                    for public inspection.                                     k. This application has been accepted              for inspection and reproduction at the
                                                      a. Type of Application: Subsequent                    and is now ready for environmental                    address in item h above.
                                                    License.                                                analysis.                                                All filings must: (1) Bear in all capital
                                                      b. Project No.: 2428–007.                                l. The Piedmont Project consists of:               letters the title COMMENTS, REPLY
                                                      c. Date filed: December 30, 2015.                     (1) A 600-foot-long by 25-foot-high stone             COMMENTS, RECOMMENDATIONS,
                                                      d. Applicant: Aquenergy Systems,                      masonry dam, consisting of (i) a 200-                 TERMS AND CONDITIONS, or
                                                    LLC (Aquenergy).                                        foot-long non-overflow section, (ii) a                ‘‘PRESCRIPTIONS;’’ (2) set forth in the
                                                      e. Name of Project: Piedmont                          200-foot-long central overflow spillway               heading the name of the applicant and
                                                    Hydroelectric Project.                                  topped with 16-inch-high wooden                       the project number of the application to
                                                      f. Location: The existing project is                  flashboards, and (iii) a 200-foot-long                which the filing responds; (3) furnish
                                                    located on the Saluda River in the Town                 non-overflow spillway housing the                     the name, address, and telephone
                                                    of Piedmont, in Anderson and                            inoperable J.P. Stevens Canal intake; (2)             number of the person submitting the
                                                    Greenville Counties, South Carolina.                    a 22-acre impoundment at a normal                     filing; and (4) otherwise comply with
                                                    The project does not affect federal land.               pool elevation of 774 feet mean sea                   the requirements of 18 CFR 385.2001
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                      g. Filed Pursuant to: Federal Power                   level; (3) a 140-foot-long by 81-foot-wide            through 385.2005. All comments,
                                                    Act 16 U.S.C. 791 (a)—825(r).                           intake canal consisting of eight gates at             recommendations, terms and conditions
                                                      h. Applicant Contact: Beth E. Harris,                 the head of the canal controlling flow to             or prescriptions must set forth their
                                                    P.E., Regional Operations Manager, Enel                 the powerhouse; (4) a 52-foot-long by                 evidentiary basis and otherwise comply
                                                    Green Power North America, Inc., 11                     52-foot-wide brick masonry powerhouse                 with the requirements of 18 CFR 4.34(b).
                                                    Anderson Street, Piedmont, SC 29673;                    protected by a trashrack structure with               Agencies may obtain copies of the
                                                    Telephone—(864) 846–0042; Email—                        2-inch clear bar spacing, located 120                 application directly from the applicant.
                                                    beth.harris@enel.com, OR Kevin Webb,                    feet downstream of the dam, containing                Each filing must be accompanied by
                                                    Hydro Licensing Manager, Enel Green                     one vertical Francis turbine generating               proof of service on all persons listed on


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1



Document Created: 2017-11-22 00:49:10
Document Modified: 2017-11-22 00:49:10
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 55600 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR