82_FR_55825 82 FR 55601 - Aquenergy Systems, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

82 FR 55601 - Aquenergy Systems, LLC; Notice of Application Ready for Environmental Analysis and Soliciting Comments, Recommendations, Terms and Conditions, and Prescriptions

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 224 (November 22, 2017)

Page Range55601-55602
FR Document2017-25318

Federal Register, Volume 82 Issue 224 (Wednesday, November 22, 2017)
[Federal Register Volume 82, Number 224 (Wednesday, November 22, 2017)]
[Notices]
[Pages 55601-55602]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-25318]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2428-007]


Aquenergy Systems, LLC; Notice of Application Ready for 
Environmental Analysis and Soliciting Comments, Recommendations, Terms 
and Conditions, and Prescriptions

    Take notice that the following hydroelectric application has been 
filed with the Commission and is available for public inspection.
    a. Type of Application: Subsequent License.
    b. Project No.: 2428-007.
    c. Date filed: December 30, 2015.
    d. Applicant: Aquenergy Systems, LLC (Aquenergy).
    e. Name of Project: Piedmont Hydroelectric Project.
    f. Location: The existing project is located on the Saluda River in 
the Town of Piedmont, in Anderson and Greenville Counties, South 
Carolina. The project does not affect federal land.
    g. Filed Pursuant to: Federal Power Act 16 U.S.C. 791 (a)--825(r).
    h. Applicant Contact: Beth E. Harris, P.E., Regional Operations 
Manager, Enel Green Power North America, Inc., 11 Anderson Street, 
Piedmont, SC 29673; Telephone--(864) 846-0042; Email_
[email protected], OR Kevin Webb, Hydro Licensing Manager, Enel 
Green Power North America, Inc., One Tech Drive, Suite 220, Andover, MA 
01810; Telephone--(978) 681-1900; [email protected]
    i. FERC Contact: Navreet Deo, (202) 502-6304, or 
[email protected].
    j. Deadline for filing comments, recommendations, terms and 
conditions, and prescriptions: 60 days from the issuance date of this 
notice; reply comments are due 105 days from the issuance date of this 
notice.
    The Commission strongly encourages electronic filing. Please file 
comments, recommendations, terms and conditions, and prescriptions 
using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief comments up to 6,000 
characters, without prior registration, using the eComment system at 
http://www.ferc.gov/docs-filing/ecomment.asp. You must include your 
name and contact information at the end of your comments. For 
assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE., 
Washington, DC 20426. The first page of any filing should include 
docket number P-2428-007.
    The Commission's Rules of Practice require all intervenors filing 
documents with the Commission to serve a copy of that document on each 
person on the official service list for the project. Further, if an 
intervenor files comments or documents with the Commission relating to 
the merits of an issue that may affect the responsibilities of a 
particular resource agency, they must also serve a copy of the document 
on that resource agency.
    k. This application has been accepted and is now ready for 
environmental analysis.
    l. The Piedmont Project consists of: (1) A 600-foot-long by 25-
foot-high stone masonry dam, consisting of (i) a 200-foot-long non-
overflow section, (ii) a 200-foot-long central overflow spillway topped 
with 16-inch-high wooden flashboards, and (iii) a 200-foot-long non-
overflow spillway housing the inoperable J.P. Stevens Canal intake; (2) 
a 22-acre impoundment at a normal pool elevation of 774 feet mean sea 
level; (3) a 140-foot-long by 81-foot-wide intake canal consisting of 
eight gates at the head of the canal controlling flow to the 
powerhouse; (4) a 52-foot-long by 52-foot-wide brick masonry powerhouse 
protected by a trashrack structure with 2-inch clear bar spacing, 
located 120 feet downstream of the dam, containing one vertical Francis 
turbine generating unit that totals 1,000 kilowatt (kW); (5) a 180-
foot-long by 38-foot-wide tailrace; (6) a 263-foot-long, 600-volt 
transmission line connecting the powerhouse to the non-project 
substation; and (7) appurtenant facilities.
    Aquenergy operates the project in a run-of-river mode using 
automatic pond level control, with no useable storage or flood control 
capacity. A continuous minimum flow of 15 cubic feet per second (cfs) 
or inflow, whichever is less, is released into the bypassed area. The 
minimum flow is achieved via an 8-foot-wide by 1-foot-deep weir on the 
spillway crest. The project operates under an estimated average head of 
26 feet, including the 16-inch-high spillway flashboards. The 
impoundment water surface elevation is maintained at 774 feet. River 
flows between 159 cfs and 535 cfs are used for power generation, while 
flows in excess of 535 cfs are passed over the flashboards and 
spillway. The total installed capacity of the project is 1,000 kW from 
the single generating unit. The project generates approximately 5,369 
megawatt-hours annually, which are sold to a local utility.
    Aquenergy proposes to continue to operate and maintain the Piedmont 
Project as is required in the existing license, and to develop canoe 
portage facilities.
    m. A copy of the application is available for review at the 
Commission in the Public Reference Room, or may be viewed on the 
Commission's Web site at http://www.ferc.gov using the ``eLibrary'' 
link. Enter the docket number excluding the last three digits in the 
docket number field to access the document. For assistance, contact 
FERC Online Support. A copy is also available for inspection and 
reproduction at the address in item h above.
    All filings must: (1) Bear in all capital letters the title 
COMMENTS, REPLY COMMENTS, RECOMMENDATIONS, TERMS AND CONDITIONS, or 
``PRESCRIPTIONS;'' (2) set forth in the heading the name of the 
applicant and the project number of the application to which the filing 
responds; (3) furnish the name, address, and telephone number of the 
person submitting the filing; and (4) otherwise comply with the 
requirements of 18 CFR 385.2001 through 385.2005. All comments, 
recommendations, terms and conditions or prescriptions must set forth 
their evidentiary basis and otherwise comply with the requirements of 
18 CFR 4.34(b). Agencies may obtain copies of the application directly 
from the applicant. Each filing must be accompanied by proof of service 
on all persons listed on

[[Page 55602]]

the service list prepared by the Commission in this proceeding, in 
accordance with 18 CFR 4.34(b) and 385.2010.
    You may also register online at http://www.ferc.gov/docs-filing/esubscription.asp to be notified via email of new filings and issuances 
related to this or other pending projects. For assistance, contact FERC 
Online Support.
    n. A license applicant must file no later than 60 days following 
the date of issuance of this notice: (1) A copy of the water quality 
certification; (2) a copy of the request for certification, including 
proof of the date on which the certifying agency received the request; 
or (3) evidence of waiver of water quality certification.

    Dated: November 16, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-25318 Filed 11-21-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                                             Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices                                             55601

                                                    Agencies may obtain copies of the                       Power North America, Inc., One Tech                   unit that totals 1,000 kilowatt (kW); (5)
                                                    application directly from the applicant.                Drive, Suite 220, Andover, MA 01810;                  a 180-foot-long by 38-foot-wide tailrace;
                                                    Each filing must be accompanied by                      Telephone—(978) 681–1900; Email—                      (6) a 263-foot-long, 600-volt
                                                    proof of service on all persons listed on               kevin.webb@enel.com.                                  transmission line connecting the
                                                    the service list prepared by the                           i. FERC Contact: Navreet Deo, (202)                powerhouse to the non-project
                                                    Commission in this proceeding, in                       502–6304, or navreet.deo@ferc.gov.                    substation; and (7) appurtenant
                                                    accordance with 18 CFR 4.34(b) and                         j. Deadline for filing comments,                   facilities.
                                                    385.2010.                                               recommendations, terms and                               Aquenergy operates the project in a
                                                       You may also register online at http://              conditions, and prescriptions: 60 days                run-of-river mode using automatic pond
                                                    www.ferc.gov/docs-filing/                               from the issuance date of this notice;                level control, with no useable storage or
                                                    esubscription.asp to be notified via                    reply comments are due 105 days from                  flood control capacity. A continuous
                                                    email of new filings and issuances                      the issuance date of this notice.                     minimum flow of 15 cubic feet per
                                                    related to this or other pending projects.                 The Commission strongly encourages                 second (cfs) or inflow, whichever is less,
                                                    For assistance, contact FERC Online                     electronic filing. Please file comments,              is released into the bypassed area. The
                                                    Support.                                                recommendations, terms and                            minimum flow is achieved via an 8-foot-
                                                       n. A license applicant must file no                  conditions, and prescriptions using the               wide by 1-foot-deep weir on the
                                                    later than 60 days following the date of                Commission’s eFiling system at http://                spillway crest. The project operates
                                                    issuance of this notice: (1) A copy of the              www.ferc.gov/docs-filing/efiling.asp.                 under an estimated average head of 26
                                                    water quality certification; (2) a copy of              Commenters can submit brief comments                  feet, including the 16-inch-high
                                                    the request for certification, including                up to 6,000 characters, without prior                 spillway flashboards. The impoundment
                                                    proof of the date on which the certifying               registration, using the eComment system               water surface elevation is maintained at
                                                    agency received the request; or (3)                     at http://www.ferc.gov/docs-filing/                   774 feet. River flows between 159 cfs
                                                    evidence of waiver of water quality                     ecomment.asp. You must include your                   and 535 cfs are used for power
                                                    certification.                                          name and contact information at the end               generation, while flows in excess of 535
                                                                                                            of your comments. For assistance,                     cfs are passed over the flashboards and
                                                    Kimberly D. Bose,                                       please contact FERC Online Support at                 spillway. The total installed capacity of
                                                    Secretary.                                              FERCOnlineSupport@ferc.gov, (866)                     the project is 1,000 kW from the single
                                                    [FR Doc. 2017–25319 Filed 11–21–17; 8:45 am]            208–3676 (toll free), or (202) 502–8659               generating unit. The project generates
                                                    BILLING CODE 6717–01–P                                  (TTY). In lieu of electronic filing, please           approximately 5,369 megawatt-hours
                                                                                                            send a paper copy to: Secretary, Federal              annually, which are sold to a local
                                                                                                            Energy Regulatory Commission, 888                     utility.
                                                    DEPARTMENT OF ENERGY                                    First Street NE., Washington, DC 20426.                  Aquenergy proposes to continue to
                                                                                                            The first page of any filing should                   operate and maintain the Piedmont
                                                    Federal Energy Regulatory                               include docket number P–2428–007.                     Project as is required in the existing
                                                    Commission                                                 The Commission’s Rules of Practice                 license, and to develop canoe portage
                                                                                                            require all intervenors filing documents              facilities.
                                                    [Project No. 2428–007]
                                                                                                            with the Commission to serve a copy of                   m. A copy of the application is
                                                    Aquenergy Systems, LLC; Notice of                       that document on each person on the                   available for review at the Commission
                                                    Application Ready for Environmental                     official service list for the project.                in the Public Reference Room, or may be
                                                    Analysis and Soliciting Comments,                       Further, if an intervenor files comments              viewed on the Commission’s Web site at
                                                    Recommendations, Terms and                              or documents with the Commission                      http://www.ferc.gov using the
                                                    Conditions, and Prescriptions                           relating to the merits of an issue that               ‘‘eLibrary’’ link. Enter the docket
                                                                                                            may affect the responsibilities of a                  number excluding the last three digits in
                                                      Take notice that the following                        particular resource agency, they must                 the docket number field to access the
                                                    hydroelectric application has been filed                also serve a copy of the document on                  document. For assistance, contact FERC
                                                    with the Commission and is available                    that resource agency.                                 Online Support. A copy is also available
                                                    for public inspection.                                     k. This application has been accepted              for inspection and reproduction at the
                                                      a. Type of Application: Subsequent                    and is now ready for environmental                    address in item h above.
                                                    License.                                                analysis.                                                All filings must: (1) Bear in all capital
                                                      b. Project No.: 2428–007.                                l. The Piedmont Project consists of:               letters the title COMMENTS, REPLY
                                                      c. Date filed: December 30, 2015.                     (1) A 600-foot-long by 25-foot-high stone             COMMENTS, RECOMMENDATIONS,
                                                      d. Applicant: Aquenergy Systems,                      masonry dam, consisting of (i) a 200-                 TERMS AND CONDITIONS, or
                                                    LLC (Aquenergy).                                        foot-long non-overflow section, (ii) a                ‘‘PRESCRIPTIONS;’’ (2) set forth in the
                                                      e. Name of Project: Piedmont                          200-foot-long central overflow spillway               heading the name of the applicant and
                                                    Hydroelectric Project.                                  topped with 16-inch-high wooden                       the project number of the application to
                                                      f. Location: The existing project is                  flashboards, and (iii) a 200-foot-long                which the filing responds; (3) furnish
                                                    located on the Saluda River in the Town                 non-overflow spillway housing the                     the name, address, and telephone
                                                    of Piedmont, in Anderson and                            inoperable J.P. Stevens Canal intake; (2)             number of the person submitting the
                                                    Greenville Counties, South Carolina.                    a 22-acre impoundment at a normal                     filing; and (4) otherwise comply with
                                                    The project does not affect federal land.               pool elevation of 774 feet mean sea                   the requirements of 18 CFR 385.2001
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                      g. Filed Pursuant to: Federal Power                   level; (3) a 140-foot-long by 81-foot-wide            through 385.2005. All comments,
                                                    Act 16 U.S.C. 791 (a)—825(r).                           intake canal consisting of eight gates at             recommendations, terms and conditions
                                                      h. Applicant Contact: Beth E. Harris,                 the head of the canal controlling flow to             or prescriptions must set forth their
                                                    P.E., Regional Operations Manager, Enel                 the powerhouse; (4) a 52-foot-long by                 evidentiary basis and otherwise comply
                                                    Green Power North America, Inc., 11                     52-foot-wide brick masonry powerhouse                 with the requirements of 18 CFR 4.34(b).
                                                    Anderson Street, Piedmont, SC 29673;                    protected by a trashrack structure with               Agencies may obtain copies of the
                                                    Telephone—(864) 846–0042; Email—                        2-inch clear bar spacing, located 120                 application directly from the applicant.
                                                    beth.harris@enel.com, OR Kevin Webb,                    feet downstream of the dam, containing                Each filing must be accompanied by
                                                    Hydro Licensing Manager, Enel Green                     one vertical Francis turbine generating               proof of service on all persons listed on


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00049   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1


                                                    55602                    Federal Register / Vol. 82, No. 224 / Wednesday, November 22, 2017 / Notices

                                                    the service list prepared by the                          Description: § 205(d) Rate Filing:                  DEPARTMENT OF ENERGY
                                                    Commission in this proceeding, in                       Section 205 Requirements Depreciation
                                                    accordance with 18 CFR 4.34(b) and                      Rates—Polk 2 Buildout to be effective                 Federal Energy Regulatory
                                                    385.2010.                                               2/1/2017.                                             Commission
                                                       You may also register online at http://                Filed Date: 11/16/17.
                                                    www.ferc.gov/docs-filing/                                                                                     Combined Notice of Filings #1
                                                    esubscription.asp to be notified via                      Accession Number: 20171116–5060.
                                                                                                                                                                     Take notice that the Commission
                                                    email of new filings and issuances                        Comments Due: 5 p.m. ET 12/7/17.                    received the following electric rate
                                                    related to this or other pending projects.                 Docket Numbers: ER18–303–000.                      filings:
                                                    For assistance, contact FERC Online                                                                              Docket Numbers: ER10–3297–011.
                                                    Support.                                                   Applicants: South Jersey Energy ISO2,
                                                                                                            LLC.                                                     Applicants: Powerex Corp. .
                                                       n. A license applicant must file no                                                                           Description: Notice of Change in
                                                    later than 60 days following the date of                   Description: Tariff Cancellation:                  Status and Request for Confidential
                                                    issuance of this notice: (1) A copy of the              Cancel market-based rate tariff to be                 Treatment of Powerex Corp.
                                                    water quality certification; (2) a copy of              effective 11/17/2017.                                    Filed Date: 11/15/17.
                                                    the request for certification, including                   Filed Date: 11/16/17.                                 Accession Number: 20171115–5236.
                                                    proof of the date on which the certifying                                                                        Comments Due: 5 p.m. ET 12/6/17.
                                                                                                               Accession Number: 20171116–5061.
                                                    agency received the request; or (3)                                                                              Docket Numbers: ER11–3417–013;
                                                    evidence of waiver of water quality                        Comments Due: 5 p.m. ET 12/7/17.
                                                                                                                                                                  ER11–2292–019; ER11–3942–018;
                                                    certification.                                            Docket Numbers: ER18–304–000.                       ER11–2293–019; ER10–2917–018;
                                                      Dated: November 16, 2017.                               Applicants: Southern California                     ER11–2294–017; ER12–2447–017;
                                                    Kimberly D. Bose,                                       Edison Company.                                       ER13–1613–011 ER10–2918–019; ER10–
                                                    Secretary.                                                                                                    2920–018; ER11–3941–016; ER10–2921–
                                                                                                              Description: § 205(d) Rate Filing:
                                                    [FR Doc. 2017–25318 Filed 11–21–17; 8:45 am]                                                                  018; ER10–2922–018; ER13–1346–009;
                                                                                                            LGIA Sienna Solar Farm Project SA No.
                                                                                                                                                                  ER10–2966–018; ER11–2383–013;
                                                    BILLING CODE 6717–01–P                                  199 to be effective 11/17/2017.
                                                                                                                                                                  ER10–3178–010; ER12–161–018; ER12–
                                                                                                              Filed Date: 11/16/17.                               2068–014; ER12–645–019; ER10–2460–
                                                    DEPARTMENT OF ENERGY                                      Accession Number: 20171116–5063.                    014; ER10–2461–015; ER12–682–015;
                                                                                                              Comments Due: 5 p.m. ET 12/7/17.                    ER10–2463–014; ER11–2201–018;
                                                    Federal Energy Regulatory                                                                                     ER13–1139–017; ER13–17–012; ER14–
                                                    Commission                                                Docket Numbers: ER18–305–000.                       25–014; ER14–2630–010; ER12–1311–
                                                                                                              Applicants: Bishop Hill Energy LLC.                 014; ER10–2466–015; ER11–4029–014;
                                                    Combined Notice of Filings #2                                                                                 ER10–2895–018; ER14–1964–009;
                                                                                                              Description: § 205(d) Rate Filing:
                                                                                                            Revised Rate Schedule to be effective                 ER16–287–004; ER13–2143–011; ER10–
                                                       Take notice that the Commission
                                                                                                            10/15/2017.                                           3167–010; ER13–203–010; ER17–482–
                                                    received the following electric rate
                                                                                                                                                                  003.
                                                    filings:                                                  Filed Date: 11/16/17.                                  Applicants: Alta Wind VIII, LLC, Bear
                                                       Docket Numbers: ER10–1585–010;                         Accession Number: 20171116–5109.                    Swamp Power Company LLC, BIF II
                                                    ER10–1594–010; ER16–733–001; ER10–                                                                            Safe Harbor Holdings, LLC, BIF III
                                                    1617–010; ER16–1148–001; ER12–60–                         Comments Due: 5 p.m. ET 12/7/17.
                                                                                                                                                                  Holtwood LLC, Black Bear Development
                                                    012; ER10–1632–012; ER10–1626–007;                         The filings are accessible in the                  Holdings, LLC, Black Bear Hydro
                                                    ER10–1628–010.                                          Commission’s eLibrary system by                       Partners, LLC, Black Bear SO, LLC,
                                                       Applicants: Alabama Electric                         clicking on the links or querying the                 BREG Aggregator LLC, Brookfield
                                                    Marketing, LLC, California Electric                     docket number.                                        Energy Marketing Inc., Brookfield
                                                    Marketing, LLC, LQA, LLC, New Mexico                       Any person desiring to intervene or                Energy Marketing LP, Brookfield Energy
                                                    Electric Marketing, LLC, Tenaska                        protest in any of the above proceedings               Marketing US LLC, Brookfield Power
                                                    Energı́a de Mexico, S. de R. L. d,                      must file in accordance with Rules 211                Piney & Deep Creek LLC, Brookfield
                                                    Tenaska Power Management, LLC,                          and 214 of the Commission’s                           Renewable Energy Marketing US LLC,
                                                    Tenaska Power Services Co., Tenaska                     Regulations (18 CFR 385.211 and                       Brookfield Smoky Mountain
                                                    Virginia Partners, L.P., Texas Electric                 385.214) on or before 5:00 p.m. Eastern               Hydropower LLC, Brookfield White
                                                    Marketing, LLC.                                         time on the specified comment date.                   Pine Hydro LLC, Carr Street Generating
                                                       Description: Supplement to June 28,                  Protests may be considered, but                       Station, L.P., Erie Boulevard
                                                    2016 Updated Market Power Analysis of                   intervention is necessary to become a                 Hydropower, L.P., Granite Reliable
                                                    the Tenaska Northeast MBR Sellers.                      party to the proceeding.                              Power, LLC, Great Lakes Hydro
                                                       Filed Date: 11/16/17.                                                                                      America, LLC, Hawks Nest Hydro LLC,
                                                       Accession Number: 20171116–5099.                        eFiling is encouraged. More detailed
                                                                                                            information relating to filing                        Mesa Wind Power Corporation,
                                                       Comments Due: 5 p.m. ET 12/7/17.                                                                           Rumford Falls Hydro LLC, Safe Harbor
                                                                                                            requirements, interventions, protests,
                                                       Docket Numbers: ER18–295–001.                                                                              Water Power Corporation, Windstar
                                                                                                            service, and qualifying facilities filings
                                                       Applicants: Louisville Gas and                                                                             Energy, LLC, Bishop Hill Energy LLC,
                                                                                                            can be found at: http://www.ferc.gov/
                                                    Electric Company.
asabaliauskas on DSKBBXCHB2PROD with NOTICES




                                                                                                            docs-filing/efiling/filing-req.pdf. For               Blue Sky East, LLC, California Ridge
                                                       Description: Tariff Amendment:                                                                             Wind Energy LLC, Canandaigua Power
                                                                                                            other information, call (866) 208–3676
                                                    Refiling EKPC NITSA Under Correct                                                                             Partners, LLC, Canandaigua Power
                                                                                                            (toll free). For TTY, call (202) 502–8659.
                                                    Record ID to be effective 10/16/2017.                                                                         Partners II, LLC, Erie Wind, LLC,
                                                       Filed Date: 11/16/17.                                  Dated: November 16, 2017.                           Evergreen Wind Power, LLC, Evergreen
                                                       Accession Number: 20171116–5059.                     Kimberly D. Bose,                                     Wind Power III, LLC, Imperial Valley
                                                       Comments Due: 5 p.m. ET 12/7/17.                     Secretary.                                            Solar 1, LLC, Niagara Wind Power, LLC,
                                                       Docket Numbers: ER18–302–000.                        [FR Doc. 2017–25325 Filed 11–21–17; 8:45 am]          Prairie Breeze Wind Energy LLC,
                                                       Applicants: Tampa Electric Company.                  BILLING CODE 6717–01–P                                Regulus Solar, LLC, Stetson Holdings,


                                               VerDate Sep<11>2014   18:57 Nov 21, 2017   Jkt 244001   PO 00000   Frm 00050   Fmt 4703   Sfmt 4703   E:\FR\FM\22NON1.SGM   22NON1



Document Created: 2017-11-22 00:48:36
Document Modified: 2017-11-22 00:48:36
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation82 FR 55601 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR