82_FR_5575 82 FR 5564 - Eastern Shore Natural Gas Company; Notice of Application for Certificate of Public Convenience and Necessity

82 FR 5564 - Eastern Shore Natural Gas Company; Notice of Application for Certificate of Public Convenience and Necessity

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 82, Issue 11 (January 18, 2017)

Page Range5564-5565
FR Document2017-00986

Federal Register, Volume 82 Issue 11 (Wednesday, January 18, 2017)
[Federal Register Volume 82, Number 11 (Wednesday, January 18, 2017)]
[Notices]
[Pages 5564-5565]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-00986]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket Nos. CP17-28-000; PF16-7-000]


Eastern Shore Natural Gas Company; Notice of Application for 
Certificate of Public Convenience and Necessity

    Take notice that on December 30, 2016 Eastern Shore Natural Gas 
Company (Eastern Shore), 1110 Forrest Avenue, Dover, Delaware 19904, 
filed in the above referenced docket an application pursuant to section 
7(c) of the Natural Gas Act (NGA) and part 157 of the Commission's 
regulations, requesting a certificate of public convenience and 
necessity authorizing Eastern Shore to construct, own, operate and 
maintain the 2017 Expansion Project. The Project is designed to provide 
61,162 dekatherms per day of additional firm transportation service to 
seven of Eastern Shore's existing customers. Eastern Shore proposes to 
construct seven segments of buried natural gas pipeline totaling 
approximately 39.6 miles with miscellaneous appurtenances in Chester 
County, Pennsylvania, Cecil County, Maryland, as well as New Castle and 
Sussex Counties, Delaware and install additional 3,750 horsepower at 
the existing Daleville Compressor Station in Chester County, 
Pennsylvania. Eastern Shore proposes incremental recourse rate, as more 
fully set forth in the application which is on file with the Commission 
and open to public inspection.
    The filing may also be viewed on the web at http://www.ferc.gov 
using the ``eLibrary'' link. Enter the docket number excluding the last 
three digits in the docket number field to access the document. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or TTY, 
contact (202) 502-8659.
    Any questions concerning this application may be directed to Mark 
Parker P.E., Engineering Manager, Eastern Shore Natural Gas Company 
1110 Forrest Avenue, Dover, DE 19904 by phone 1-844-366-3764 use or by 
email [email protected].
    Specifically, Eastern Shore proposes (1) six 10-, 16-, and 24-inch-
diameter pipeline loop segments totaling 22.7 miles, (2) 10-inch-
diameter 16.9-mile-long mainline extension, (3) upgrades to an existing 
Meter and Regulator station and lateral piping at the existing 
interconnect with Texas Eastern in Lancaster County, Pennsylvania, and 
(4) the addition of two pressure control stations in Sussex County, 
Delaware. Eastern Shore requests that the Commission issue the 
requested authorizations by May 2017 in order to meet November 1, 2017 
in-service date requested by the project shippers who are local 
utility, power, and industrial manufacturing companies. The total cost 
of the Project is estimated to be approximately $98,578,673.
    On May 17, 2016, the Commission staff granted Eastern Shore's 
request to utilize the Pre-Filing Process and assigned Docket No. PF16-
7-000 to staff activities involved in the above referenced project. 
Now, as of the filing of the December 30, 2016 application, the Pre-
Filing Process for this project has ended. From this time forward, this 
proceeding will be conducted in Docket No. CP17-28-000, as noted in the 
caption of this Notice.
    Pursuant to section 157.9 of the Commission's rules, 18 CFR 157.9, 
within 90 days of this Notice the Commission staff will either: 
Complete its environmental assessment (EA) and place it into the 
Commission's public record (eLibrary) for this proceeding; or issue a 
Notice of Schedule for Environmental Review. If a Notice of Schedule 
for Environmental Review is issued, it will indicate, among other 
milestones, the anticipated date for the Commission staff's issuance of 
the EA for this proposal. The filing of the EA in the Commission's 
public record for this proceeding or the issuance of a Notice of 
Schedule for Environmental Review will serve to notify federal and 
state agencies of the timing for the completion of all necessary 
reviews, and the subsequent need to complete all federal authorizations 
within 90 days of the date of issuance of the Commission staff's EA.
    There are two ways to become involved in the Commission's review of 
this project. First, any person wishing to obtain legal status by 
becoming a party to the proceedings for this project should, on or 
before the comment date stated below, file with the Federal Energy 
Regulatory Commission, 888 First Street NE., Washington, DC 20426, a 
motion to intervene in accordance with the requirements of the 
Commission's Rules of Practice and Procedure (18 CFR 385.214 or 
385.211) and the Regulations under the NGA (18 CFR 157.10). A person 
obtaining party status will be placed on the service list maintained by 
the Secretary of the Commission and will receive copies of all 
documents filed by the applicant and by all other parties. A party must 
submit five copies of filings made with the Commission and must mail a 
copy to the applicant and to every other party in the proceeding. Only 
parties to the proceeding can ask for court review of Commission orders 
in the proceeding.
    However, a person does not have to intervene in order to have 
comments considered. The second way to participate is by filing with 
the Secretary of the Commission, as soon as possible, an original and 
two copies of comments in support of or in opposition to this project. 
The Commission will consider these comments in determining the 
appropriate action to be taken, but the filing of a comment alone will 
not serve to make the filer a party

[[Page 5565]]

to the proceeding. The Commission's rules require that persons filing 
comments in opposition to the project provide copies of their protests 
only to the party or parties directly involved in the protest.
    Persons who wish to comment only on the environmental review of 
this project should submit an original and two copies of their comments 
to the Secretary of the Commission. Environmental commentors will be 
placed on the Commission's environmental mailing list, will receive 
copies of the environmental documents, and will be notified of meetings 
associated with the Commission's environmental review process. 
Environmental commentors will not be required to serve copies of filed 
documents on all other parties. However, the non-party commentors will 
not receive copies of all documents filed by other parties or issued by 
the Commission (except for the mailing of environmental documents 
issued by the Commission) and will not have the right to seek court 
review of the Commission's final order.
    The Commission strongly encourages electronic filings of comments, 
protests and interventions in lieu of paper using the ``eFiling'' link 
at http://www.ferc.gov. Persons unable to file electronically should 
submit original and five copies of the protest or intervention to the 
Federal Energy Regulatory Commission, 888 First Street NE., Washington, 
DC 20426.
    Comment Date: 5:00 p.m. Eastern Time on February 1, 2017.

    Dated: January 11, 2017.
Kimberly D. Bose,
Secretary.
[FR Doc. 2017-00986 Filed 1-17-17; 8:45 am]
 BILLING CODE 6717-01-P



                                                  5564                       Federal Register / Vol. 82, No. 11 / Wednesday, January 18, 2017 / Notices

                                                  notice that members of the                              application pursuant to section 7(c) of                referenced project. Now, as of the filing
                                                  Commission’s staff may attend the                       the Natural Gas Act (NGA) and part 157                 of the December 30, 2016 application,
                                                  following meetings related to the                       of the Commission’s regulations,                       the Pre-Filing Process for this project
                                                  transmission planning activities of                     requesting a certificate of public                     has ended. From this time forward, this
                                                  Tucson Electric Power Company, UNS                      convenience and necessity authorizing                  proceeding will be conducted in Docket
                                                  Electric, Inc., Public Service Company                  Eastern Shore to construct, own, operate               No. CP17–28–000, as noted in the
                                                  of New Mexico, Arizona Public Service                   and maintain the 2017 Expansion                        caption of this Notice.
                                                  Company, El Paso Electric Company,                      Project. The Project is designed to                       Pursuant to section 157.9 of the
                                                  Black Hills Power, Inc., Black Hills                    provide 61,162 dekatherms per day of                   Commission’s rules, 18 CFR 157.9,
                                                  Colorado Electric Utility Company, LP,                  additional firm transportation service to              within 90 days of this Notice the
                                                  Cheyenne Light, Fuel, & Power                           seven of Eastern Shore’s existing                      Commission staff will either: Complete
                                                  Company, NV Energy, Inc., and Xcel                      customers. Eastern Shore proposes to                   its environmental assessment (EA) and
                                                  Energy Services, Inc. on behalf of Public               construct seven segments of buried                     place it into the Commission’s public
                                                  Service Company of Colorado:                            natural gas pipeline totaling                          record (eLibrary) for this proceeding; or
                                                  Planning Management Committee                           approximately 39.6 miles with                          issue a Notice of Schedule for
                                                       Meeting                                            miscellaneous appurtenances in Chester                 Environmental Review. If a Notice of
                                                     January 18, 2017, 9 a.m.–3 p.m. (MST)                County, Pennsylvania, Cecil County,                    Schedule for Environmental Review is
                                                  Regional Stakeholder Meeting                            Maryland, as well as New Castle and                    issued, it will indicate, among other
                                                     February 16, 2017, 9 a.m.–4 p.m.                     Sussex Counties, Delaware and install                  milestones, the anticipated date for the
                                                       (MST)                                              additional 3,750 horsepower at the                     Commission staff’s issuance of the EA
                                                     The Planning Management Committee                    existing Daleville Compressor Station in               for this proposal. The filing of the EA
                                                  Meeting will be held at: Ocotillo                       Chester County, Pennsylvania. Eastern                  in the Commission’s public record for
                                                  Training Center, 1701 E. Rio Salado                     Shore proposes incremental recourse                    this proceeding or the issuance of a
                                                  Pkwy., Tempe, AZ 85281.                                 rate, as more fully set forth in the                   Notice of Schedule for Environmental
                                                     The Regional Stakeholder Meeting                     application which is on file with the                  Review will serve to notify federal and
                                                  will be held at: SRP PERA Club, 1 E.                    Commission and open to public                          state agencies of the timing for the
                                                  Continental Drive Tempe, Arizona                        inspection.                                            completion of all necessary reviews, and
                                                  85281.                                                     The filing may also be viewed on the                the subsequent need to complete all
                                                     The above-referenced meetings will                   web at http://www.ferc.gov using the                   federal authorizations within 90 days of
                                                  be available via web conference and                     ‘‘eLibrary’’ link. Enter the docket                    the date of issuance of the Commission
                                                  teleconference.                                         number excluding the last three digits in              staff’s EA.
                                                     The above-referenced meetings are                    the docket number field to access the                     There are two ways to become
                                                  open to stakeholders.                                   document. For assistance, please contact               involved in the Commission’s review of
                                                     Further information may be found at                  FERC Online Support at                                 this project. First, any person wishing to
                                                  http://www.westconnect.com/.                            FERCOnlineSupport@ferc.gov or toll                     obtain legal status by becoming a party
                                                     The discussions at the meetings                      free at (866) 208–3676, or TTY, contact                to the proceedings for this project
                                                  described above may address matters at                  (202) 502–8659.                                        should, on or before the comment date
                                                  issue in the following proceeding:                         Any questions concerning this                       stated below, file with the Federal
                                                                                                          application may be directed to Mark                    Energy Regulatory Commission, 888
                                                  ER13–75, Public Service Company of
                                                                                                          Parker P.E., Engineering Manager,                      First Street NE., Washington, DC 20426,
                                                       New Mexico; El Paso Electric
                                                                                                          Eastern Shore Natural Gas Company                      a motion to intervene in accordance
                                                       Company
                                                                                                          1110 Forrest Avenue, Dover, DE 19904                   with the requirements of the
                                                     For more information contact Nicole                  by phone 1–844–366–3764 use or by                      Commission’s Rules of Practice and
                                                  Cramer, Office of Energy Market                         email maparker@esng.com.                               Procedure (18 CFR 385.214 or 385.211)
                                                  Regulation, Federal Energy Regulatory                      Specifically, Eastern Shore proposes                and the Regulations under the NGA (18
                                                  Commission at (202) 502–6775 or                         (1) six 10-, 16-, and 24-inch-diameter                 CFR 157.10). A person obtaining party
                                                  nicole.cramer@ferc.gov.                                 pipeline loop segments totaling 22.7                   status will be placed on the service list
                                                    Dated: January 11, 2017.                              miles, (2) 10-inch-diameter 16.9-mile-                 maintained by the Secretary of the
                                                  Kimberly D. Bose,                                       long mainline extension, (3) upgrades to               Commission and will receive copies of
                                                  Secretary.                                              an existing Meter and Regulator station                all documents filed by the applicant and
                                                  [FR Doc. 2017–00996 Filed 1–17–17; 8:45 am]
                                                                                                          and lateral piping at the existing                     by all other parties. A party must submit
                                                                                                          interconnect with Texas Eastern in                     five copies of filings made with the
                                                  BILLING CODE 6717–01–P
                                                                                                          Lancaster County, Pennsylvania, and (4)                Commission and must mail a copy to
                                                                                                          the addition of two pressure control                   the applicant and to every other party in
                                                  DEPARTMENT OF ENERGY                                    stations in Sussex County, Delaware.                   the proceeding. Only parties to the
                                                                                                          Eastern Shore requests that the                        proceeding can ask for court review of
                                                  Federal Energy Regulatory                               Commission issue the requested                         Commission orders in the proceeding.
                                                  Commission                                              authorizations by May 2017 in order to                    However, a person does not have to
                                                                                                          meet November 1, 2017 in-service date                  intervene in order to have comments
                                                  [Docket Nos. CP17–28–000; PF16–7–000]                                                                          considered. The second way to
                                                                                                          requested by the project shippers who
                                                                                                          are local utility, power, and industrial               participate is by filing with the
                                                  Eastern Shore Natural Gas Company;
                                                                                                          manufacturing companies. The total                     Secretary of the Commission, as soon as
mstockstill on DSK3G9T082PROD with NOTICES




                                                  Notice of Application for Certificate of
                                                                                                          cost of the Project is estimated to be                 possible, an original and two copies of
                                                  Public Convenience and Necessity
                                                                                                          approximately $98,578,673.                             comments in support of or in opposition
                                                    Take notice that on December 30,                         On May 17, 2016, the Commission                     to this project. The Commission will
                                                  2016 Eastern Shore Natural Gas                          staff granted Eastern Shore’s request to               consider these comments in
                                                  Company (Eastern Shore), 1110 Forrest                   utilize the Pre-Filing Process and                     determining the appropriate action to be
                                                  Avenue, Dover, Delaware 19904, filed in                 assigned Docket No. PF16–7–000 to staff                taken, but the filing of a comment alone
                                                  the above referenced docket an                          activities involved in the above                       will not serve to make the filer a party


                                             VerDate Sep<11>2014   17:41 Jan 17, 2017   Jkt 241001   PO 00000   Frm 00043   Fmt 4703   Sfmt 4703   E:\FR\FM\18JAN1.SGM   18JAN1


                                                                             Federal Register / Vol. 82, No. 11 / Wednesday, January 18, 2017 / Notices                                                5565

                                                  to the proceeding. The Commission’s                     responsibilities of each of the parties                VA 22102–5090, (703) 883–4212, TTY
                                                  rules require that persons filing                       when the condition of a System bank                    (703) 883–4434,
                                                  comments in opposition to the project                   falls below pre-established financial                  or
                                                  provide copies of their protests only to                thresholds. In prior draft amended and                    Rebecca S. Orlich, Senior Counsel,
                                                  the party or parties directly involved in               restated MAAs, although not required,                  Office of General Counsel, Farm Credit
                                                  the protest.                                            the FCA published the draft document                   Administration, McLean, VA 22102–
                                                     Persons who wish to comment only                     for comment prior to its approval. The                 5090, (703) 883–4020, TTY (703) 883–
                                                  on the environmental review of this                     revisions in this draft are minor,                     4020.
                                                  project should submit an original and                   consisting primarily of replacing                      SUPPLEMENTARY INFORMATION: System
                                                  two copies of their comments to the                     references to the previous FCA                         banks and the Funding Corporation
                                                  Secretary of the Commission.                            regulatory capital standards with                      entered into the original Market Access
                                                  Environmental commentors will be                        references to the new FCA regulatory                   Agreement (original MAA) on
                                                  placed on the Commission’s                              capital standards that became effective                September 1, 1994, to help control the
                                                  environmental mailing list, will receive                on January 1, 2017, as well as updating                risk of each System bank by outlining
                                                  copies of the environmental documents,                  addresses. Therefore, the FCA has                      each party’s respective rights and
                                                  and will be notified of meetings                        determined to approve the Draft Third                  responsibilities in the event the
                                                  associated with the Commission’s                        Restated MAA without a request for                     condition of a System bank fell below
                                                  environmental review process.                           comments prior to approval; we will,                   certain financial thresholds. As part of
                                                  Environmental commentors will not be                    however, review and consider any                       the original MAA, System banks and the
                                                  required to serve copies of filed                       subsequent comments we may receive.                    Funding Corporation agreed to periodic
                                                  documents on all other parties.                         DATES: You may send comments on or                     reviews of the terms of the MAA to
                                                  However, the non-party commentors                       before February 17, 2017.                              consider whether any amendments were
                                                  will not receive copies of all documents                                                                       appropriate. The original MAA was
                                                                                                          ADDRESSES: For accuracy and efficiency
                                                  filed by other parties or issued by the                                                                        updated by the parties in 2003 in the
                                                                                                          reasons, commenters are encouraged to
                                                  Commission (except for the mailing of                                                                          Amended and Restated MAA and
                                                                                                          submit comments by e-mail or through                   received FCA approval following notice
                                                  environmental documents issued by the
                                                                                                          the FCA’s Web site. We are no longer                   and request for public comments in the
                                                  Commission) and will not have the right
                                                                                                          accepting comments submitted by                        Federal Register.1
                                                  to seek court review of the
                                                                                                          facsimile (fax). Please do not submit                     On December 3, 2010, the FCA Board
                                                  Commission’s final order.
                                                                                                          your comment multiple times via                        approved amendments to the Amended
                                                     The Commission strongly encourages
                                                                                                          different methods. You may submit                      and Restated MAA that would conform
                                                  electronic filings of comments, protests
                                                                                                          comments by any of the following                       its provisions to the System banks’
                                                  and interventions in lieu of paper using
                                                                                                          methods:                                               proposed Joint and Several Liability
                                                  the ‘‘eFiling’’ link at http://
                                                  www.ferc.gov. Persons unable to file                       • E-mail: Send us an e-mail at reg-                 Reallocation Agreement (Reallocation
                                                  electronically should submit original                   comm@fca.gov.                                          Agreement) to ensure that the MAA
                                                  and five copies of the protest or                          • FCA Web site: http://www.fca.gov.                 provisions did not impede operation of
                                                  intervention to the Federal Energy                      Select ‘‘Public Commenters,’’ then                     the Reallocation Agreement; the
                                                  Regulatory Commission, 888 First Street                 ‘‘Public Comments,’’ and follow the                    amendments also provided that the
                                                  NE., Washington, DC 20426.                              directions for ‘‘Submitting a Comment.’’               MAA and the Reallocation Agreement
                                                     Comment Date: 5:00 p.m. Eastern                         • Federal E-Rulemaking Web site:                    are separate agreements, and
                                                  Time on February 1, 2017.                               http://www.regulations.gov. Follow the                 invalidation of one does not affect the
                                                                                                          instructions for submitting comments.                  other. The FCA published these
                                                    Dated: January 11, 2017.                                 • Mail: Send mail to Barry F.                       amendments in the Federal Register.2
                                                  Kimberly D. Bose,                                       Mardock, Deputy Director, Office of                    The proposed Reallocation Agreement is
                                                  Secretary.                                              Regulatory Policy, Farm Credit                         an agreement among the banks and the
                                                  [FR Doc. 2017–00986 Filed 1–17–17; 8:45 am]             Administration, 1501 Farm Credit Drive,                Funding Corporation that establishes a
                                                  BILLING CODE 6717–01–P                                  McLean, VA 22102–5090.                                 procedure for non-defaulting banks to
                                                                                                             You may review copies of comments                   pay maturing System-wide debt on
                                                                                                          we receive at our office in McLean,                    behalf of defaulting banks prior to a
                                                  FARM CREDIT ADMINISTRATION                              Virginia, or on our Web site at http://                statutory joint and several call by the
                                                                                                          www.fca.gov. Once you are in the Web                   FCA under section 4.4 of the Farm
                                                  Market Access Agreement                                 site, select ‘‘Public Commenters,’’ then               Credit Act of 1971, as amended (Act).3
                                                                                                          ‘‘Public Comments,’’ and follow the                    The FCA Board approved the proposed
                                                  AGENCY: Farm Credit Administration.                     directions for ‘‘Reading Submitted                     Reallocation Agreement on October 14,
                                                  ACTION:Notice of approval of the Draft                  Public Comments.’’ We will show your                   2010, and notice of the approval was
                                                  Third Amended and Restated Market                       comments as submitted, but for                         published in the Federal Register.4
                                                  Access Agreement.                                       technical reasons we may omit items                       The MAA was updated again by the
                                                                                                          such as logos and special characters.                  parties in 2011 in the Second Amended
                                                  SUMMARY:   The Farm Credit                                                                                     and Restated MAA, as the first
                                                                                                          Identifying information that you
                                                  Administration (FCA) announces that it                                                                         Amended and Restated MAA was set to
                                                                                                          provide, such as phone numbers and
                                                  has approved the Draft Third Amended                                                                           expire at the end of 2011. The FCA
                                                                                                          addresses, will be publicly available.
                                                  and Restated Market Access Agreement
mstockstill on DSK3G9T082PROD with NOTICES




                                                                                                          However, we will attempt to remove e-                  approved the draft document on
                                                  (Draft Third Restated MAA) proposed to                                                                         December 9, 2011 following notice and
                                                                                                          mail addresses to help reduce Internet
                                                  be entered into by all of the banks of the                                                                     request for public comments, and notice
                                                                                                          spam.
                                                  Farm Credit System (System or FCS)
                                                  and the Federal Farm Credit Banks                       FOR FURTHER INFORMATION, CONTACT:                        1 68 FR 19539 (April 21, 2003).
                                                  Funding Corporation (Funding                              David J. Lewandrowski, Senior Policy                   2 75 FR 76729 (December 9, 2010).
                                                  Corporation). The Draft Third Restated                  Analyst, Office of Regulatory Policy,                    3 12 U.S.C. 2155.

                                                  MAA sets forth the rights and                           Farm Credit Administration, McLean,                      4 75 FR 64727 (October 20, 2010).




                                             VerDate Sep<11>2014   17:41 Jan 17, 2017   Jkt 241001   PO 00000   Frm 00044   Fmt 4703   Sfmt 4703   E:\FR\FM\18JAN1.SGM    18JAN1



Document Created: 2018-02-01 15:19:24
Document Modified: 2018-02-01 15:19:24
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
Dates5:00 p.m. Eastern Time on February 1, 2017.
FR Citation82 FR 5564 