82_FR_57468 82 FR 57237 - Notice of Intent To Prepare a Joint Environmental Impact Statement/Environmental Impact Report for the San Francisco Bay to Stockton General Reevaluation Report, San Francisco Bay, California

82 FR 57237 - Notice of Intent To Prepare a Joint Environmental Impact Statement/Environmental Impact Report for the San Francisco Bay to Stockton General Reevaluation Report, San Francisco Bay, California

DEPARTMENT OF DEFENSE
Department of the Army, Corps of Engineers

Federal Register Volume 82, Issue 231 (December 4, 2017)

Page Range57237-57238
FR Document2017-26051

In accordance with the National Environmental Policy Act (NEPA), the U.S. Army Corps of Engineers (USACE) South Atlantic Division and the Port of Stockton are preparing an Environmental Impact Statement and Environmental Impact Report (EIS/EIR) to evaluate the efficiency of the movement of goods along the existing deep-draft navigation route extending from the Golden Gate, through San Pablo Bay and Carquinez Strait, to deep draft facilities at Avon, California. This Notice of Intent (NOI) represents a supplemental notice to the March 4, 2016, NOI released for the San Francisco Bay to Stockton Navigation Improvement Study. This supplemental NOI is being released to notify the public that the study scope has been reduced to only consider improvements within the portion of the navigation project extending from San Francisco Bay to Avon. Work is now being conducted on an EIS/EIR with a reduced scope and project footprint, which is anticipated to be issued for public review in 2018. This NOI also re- opens the public scoping period. The 2016 NOI proposed to deepen the John F. Baldwin channel from the West Richmond Channel through the Pinole Shoal Channel, Bulls Head Reach and Suisun Bay Channel to New York Slough Channel to a maximum depth of 45 feet mean lower low water (MLLW) and the Stockton Deep Water Ship Channel to a maximum depth of 40 feet MLLW. As of September, 2017, the portion of the authorized navigation project to the east of Avon is no longer under consideration for formulation of navigation improvements. The revised study area extends from Central San Francisco Bay to Avon only and includes the West Richmond Channel, Pinole Shoal Channel, and Bulls Head Reach portion of the Suisun Bay Channel (west of Avon). The current authorized depth of this study area is 45 feet mean lower low water (MLLW), but is currently maintained at 35 feet MLLW. The forthcoming EIS/EIR is a single purpose navigation improvement project to evaluate incremental deepening to a maximum depth of 38 feet MLLW within the channel reaches of the revised study area only.

Federal Register, Volume 82 Issue 231 (Monday, December 4, 2017)
[Federal Register Volume 82, Number 231 (Monday, December 4, 2017)]
[Notices]
[Pages 57237-57238]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2017-26051]


-----------------------------------------------------------------------

DEPARTMENT OF DEFENSE

Department of the Army, Corps of Engineers


Notice of Intent To Prepare a Joint Environmental Impact 
Statement/Environmental Impact Report for the San Francisco Bay to 
Stockton General Reevaluation Report, San Francisco Bay, California

AGENCY: Department of the Army, U.S. Army Corps of Engineers, DoD.

ACTION: Notice of intent.

-----------------------------------------------------------------------

SUMMARY: In accordance with the National Environmental Policy Act 
(NEPA), the U.S. Army Corps of Engineers (USACE) South Atlantic 
Division and the Port of Stockton are preparing an Environmental Impact 
Statement and Environmental Impact Report (EIS/EIR) to evaluate the 
efficiency of the movement of goods along the existing deep-draft 
navigation route extending from the Golden Gate, through San Pablo Bay 
and Carquinez Strait, to deep draft facilities at Avon, California. 
This Notice of Intent (NOI) represents a supplemental notice to the 
March 4, 2016, NOI released for the San Francisco Bay to Stockton 
Navigation Improvement Study. This supplemental NOI is being released 
to notify the public that the study scope has been reduced to only 
consider improvements within the portion of the navigation project 
extending from San Francisco Bay to Avon. Work is now being conducted 
on an EIS/EIR with a reduced scope and project footprint, which is 
anticipated to be issued for public review in 2018. This NOI also re-
opens the public scoping period.
    The 2016 NOI proposed to deepen the John F. Baldwin channel from 
the West Richmond Channel through the Pinole Shoal Channel, Bulls Head 
Reach and Suisun Bay Channel to New York Slough Channel to a maximum 
depth of 45 feet mean lower low water (MLLW) and the Stockton Deep 
Water Ship Channel to a maximum depth of 40 feet MLLW. As of September, 
2017, the portion of the authorized navigation project to the east of 
Avon is no longer under consideration for formulation of navigation 
improvements.
    The revised study area extends from Central San Francisco Bay to 
Avon only and includes the West Richmond Channel, Pinole Shoal Channel, 
and Bulls Head Reach portion of the Suisun Bay Channel (west of Avon). 
The current authorized depth of this study area is 45 feet mean lower 
low water (MLLW), but is currently maintained at 35 feet MLLW.
    The forthcoming EIS/EIR is a single purpose navigation improvement 
project to evaluate incremental deepening to a maximum depth of 38 feet 
MLLW within the channel reaches of the revised study area only.

DATES: Submit comments concerning this notice on or before thirty days 
after this posting. There will be no additional public meeting in 
conjunction with this scoping period.

ADDRESSES: Mail written comments concerning this notice to: U.S. Army 
Corps of Engineers, Jacksonville District, Planning and Policy 
Division, Environmental Branch, P.O. Box 4970, Jacksonville, FL 32232-
0019. Comment letters should include the commenter's physical mailing 
address and the project title.

FOR FURTHER INFORMATION CONTACT: Stacie Auvenshine, 904-314-6714 or 
email at [email protected].

SUPPLEMENTARY INFORMATION: This EIS/EIR is intended to be sufficient in 
scope to address the federal, state, and local requirements and 
environmental issues concerning the proposed activities and permit 
approvals.
    Project Area and Background Information: The authorized San 
Francisco Bay to Stockton, California, navigation project includes the 
John F. Baldwin and Stockton Ship Channels, which extend 75 nautical 
miles from the Pacific Ocean, just outside the Golden Gate, to the Port 
of Stockton. Modern vessels transiting the channels can require up to 
55 feet of draft when fully laden. Given that these channels are 
maintained at 35 feet MLLW, most vessels utilizing the navigation 
channels between San Francisco Bay and Avon must be ``light-loaded'' 
(i.e., less than fully loaded with cargo) to navigate the channels with 
sufficient under-keel clearance. Light-loading is inefficient and 
increases the transportation cost and overall cost of shipped products 
because more trips must be made to carry the same volume of cargo.
    The revised study area includes the West Richmond Channel, Pinole 
Shoal Channel, Carquinez Strait, and the Bulls Head Reach portion of 
the Suisun Bay Channel, ending at Avon. These channels are currently 
maintained at 35 feet MLLW, although the channels have an authorized 
depth of 45 feet MLLW.
    The Draft EIS/EIR will analyze the project alternatives described 
below:
    No Action, in which dredging would not occur and all construction-
related activities would be avoided. Maintenance dredging would 
continue annually or on an as-needed basis and the federal standard 
placement sites would continue to be used.
    Deepening to 37 feet MLLW, which would deepen the study area to a 
depth of 37 feet MLLW with an additional 2 feet of overdepth for a 
maximum depth of 39 feet MLLW. To account for rapid shoaling, a 
sediment trap would be constructed at Bulls Head Reach by dredging an 
additional 6 feet (including 2 feet of overdepth) to 43 feet MLLW.
    Deepening to 38 feet MLLW, which would deepen the study area to a 
depth of 38 feet MLLW with an additional 2 feet of overdepth for a 
maximum depth of 40 feet MLLW. Under this alternative, a sediment trap 
at Bulls Head Reach would be constructed by dredging an additional 6 
feet (including 2 feet of overdepth) to 44 feet MLLW.
    Under both deepening alternatives, the dredged material will be 
placed at one or more permitted and economically feasible beneficial 
reuse sites.
    Purpose and Need: The purpose of the project is to provide more 
efficient deep-draft navigation operations in a manner that minimizes 
adverse environmental effects. The need for the project is to address 
vessel restrictions imposed by the existing channel depths, which are 
inadequate to accommodate

[[Page 57238]]

vessels with drafts exceeding 35 feet MLLW.
    Issues: The environmental analysis will consider the effects of 
deepening navigation channels in the study area on biological 
resources, sediments, air quality, greenhouse gas emissions, climate 
change, water quality, geology, sediments, hydraulics and hydrology, 
hazards, noise, utilities, navigation, transportation, land use, 
cultural and historic resources, aesthetics, recreation, and 
socioeconomics. The EIS/EIR will evaluate environmental justice and 
cumulative impacts and potentially other environmental issues.
    Scoping Process: The USACE is seeking participation of all 
interested federal, state, and local agencies, Native American groups, 
and other concerned private organizations or individuals through this 
public notice. The purpose of the public scoping period is to solicit 
comments regarding the potential impacts, environmental issues, and 
alternatives associated with the proposed action to be considered in 
the Draft EIS/EIR; identify other significant issues; and provide other 
relevant information.
    The public will have an additional opportunity to comment once the 
Draft EIS/EIR is released, which is anticipated to be in the summer of 
2018. The U.S. Environmental Protection Agency will provide notice of 
the availability of the Draft EIS/EIR in the Federal Register and the 
USACE and Port of Stockton will provide a 45-day review period for the 
public, organizations, and agencies to review and comment on the Draft 
EIS/EIR. All interested parties should respond to this notice and 
provide a current address if they wish to be notified about circulation 
of the Draft EIS/EIR.

Brenda S. Bowen,
Army Federal Register Liaison Officer.
[FR Doc. 2017-26051 Filed 12-1-17; 8:45 am]
BILLING CODE 3720-58-P



                                                                            Federal Register / Vol. 82, No. 231 / Monday, December 4, 2017 / Notices                                           57237

                                                technology lead over any other Air and                  Improvement Study. This supplemental                  Francisco Bay to Stockton, California,
                                                Missile Defense (AMD) Command and                       NOI is being released to notify the                   navigation project includes the John F.
                                                Control (C2) system existing today.                     public that the study scope has been                  Baldwin and Stockton Ship Channels,
                                                   4. The IBCS sensitive/critical                       reduced to only consider improvements                 which extend 75 nautical miles from the
                                                technology is primarily in software. And                within the portion of the navigation                  Pacific Ocean, just outside the Golden
                                                also resides in the design,                             project extending from San Francisco                  Gate, to the Port of Stockton. Modern
                                                developments, and manufacturing of                      Bay to Avon. Work is now being                        vessels transiting the channels can
                                                certain components. The list of                         conducted on an EIS/EIR with a reduced                require up to 55 feet of draft when fully
                                                components containing sensitive/                        scope and project footprint, which is                 laden. Given that these channels are
                                                critical technology is classified SECRET.               anticipated to be issued for public                   maintained at 35 feet MLLW, most
                                                   5. The loss of this hardware, software,              review in 2018. This NOI also re-opens                vessels utilizing the navigation channels
                                                documentation and/or data could                         the public scoping period.                            between San Francisco Bay and Avon
                                                permit development of information                          The 2016 NOI proposed to deepen the                must be ‘‘light-loaded’’ (i.e., less than
                                                which may lead to a significant threat to               John F. Baldwin channel from the West                 fully loaded with cargo) to navigate the
                                                future U.S. military operations. If an                  Richmond Channel through the Pinole                   channels with sufficient under-keel
                                                adversary were to obtain this sensitive                 Shoal Channel, Bulls Head Reach and                   clearance. Light-loading is inefficient
                                                technology, the missile system                          Suisun Bay Channel to New York                        and increases the transportation cost
                                                effectiveness could be compromised                      Slough Channel to a maximum depth of                  and overall cost of shipped products
                                                through reverse engineering techniques.                 45 feet mean lower low water (MLLW)                   because more trips must be made to
                                                   6. A determination has been made                     and the Stockton Deep Water Ship                      carry the same volume of cargo.
                                                that Poland can provide substantially                   Channel to a maximum depth of 40 feet                    The revised study area includes the
                                                the same degree of protection for the                   MLLW. As of September, 2017, the                      West Richmond Channel, Pinole Shoal
                                                sensitive technology being released as                  portion of the authorized navigation                  Channel, Carquinez Strait, and the Bulls
                                                the U.S. Government. This proposed                      project to the east of Avon is no longer              Head Reach portion of the Suisun Bay
                                                sale is necessary in furtherance of the                 under consideration for formulation of                Channel, ending at Avon. These
                                                U.S. foreign policy and national security               navigation improvements.                              channels are currently maintained at 35
                                                objectives outlined in the Policy                          The revised study area extends from                feet MLLW, although the channels have
                                                Justification.                                          Central San Francisco Bay to Avon only                an authorized depth of 45 feet MLLW.
                                                   7. All defense articles and services                 and includes the West Richmond                           The Draft EIS/EIR will analyze the
                                                listed in this transmittal have been                    Channel, Pinole Shoal Channel, and                    project alternatives described below:
                                                authorized for release and export to the                Bulls Head Reach portion of the Suisun                   No Action, in which dredging would
                                                Government of Poland.                                   Bay Channel (west of Avon). The                       not occur and all construction-related
                                                                                                        current authorized depth of this study                activities would be avoided.
                                                [FR Doc. 2017–25996 Filed 12–1–17; 8:45 am]
                                                                                                        area is 45 feet mean lower low water                  Maintenance dredging would continue
                                                BILLING CODE 5001–06–P
                                                                                                        (MLLW), but is currently maintained at                annually or on an as-needed basis and
                                                                                                        35 feet MLLW.                                         the federal standard placement sites
                                                                                                           The forthcoming EIS/EIR is a single
                                                DEPARTMENT OF DEFENSE                                                                                         would continue to be used.
                                                                                                        purpose navigation improvement
                                                                                                                                                                 Deepening to 37 feet MLLW, which
                                                Department of the Army, Corps of                        project to evaluate incremental
                                                                                                                                                              would deepen the study area to a depth
                                                Engineers                                               deepening to a maximum depth of 38
                                                                                                                                                              of 37 feet MLLW with an additional 2
                                                                                                        feet MLLW within the channel reaches
                                                                                                                                                              feet of overdepth for a maximum depth
                                                Notice of Intent To Prepare a Joint                     of the revised study area only.
                                                                                                                                                              of 39 feet MLLW. To account for rapid
                                                Environmental Impact Statement/                         DATES: Submit comments concerning
                                                                                                                                                              shoaling, a sediment trap would be
                                                Environmental Impact Report for the                     this notice on or before thirty days after            constructed at Bulls Head Reach by
                                                San Francisco Bay to Stockton                           this posting. There will be no additional             dredging an additional 6 feet (including
                                                General Reevaluation Report, San                        public meeting in conjunction with this               2 feet of overdepth) to 43 feet MLLW.
                                                Francisco Bay, California                               scoping period.                                          Deepening to 38 feet MLLW, which
                                                                                                        ADDRESSES: Mail written comments                      would deepen the study area to a depth
                                                AGENCY: Department of the Army, U.S.
                                                Army Corps of Engineers, DoD.                           concerning this notice to: U.S. Army                  of 38 feet MLLW with an additional 2
                                                                                                        Corps of Engineers, Jacksonville District,            feet of overdepth for a maximum depth
                                                ACTION: Notice of intent.                               Planning and Policy Division,                         of 40 feet MLLW. Under this alternative,
                                                SUMMARY:    In accordance with the                      Environmental Branch, P.O. Box 4970,                  a sediment trap at Bulls Head Reach
                                                National Environmental Policy Act                       Jacksonville, FL 32232–0019. Comment                  would be constructed by dredging an
                                                (NEPA), the U.S. Army Corps of                          letters should include the commenter’s                additional 6 feet (including 2 feet of
                                                Engineers (USACE) South Atlantic                        physical mailing address and the project              overdepth) to 44 feet MLLW.
                                                Division and the Port of Stockton are                   title.                                                   Under both deepening alternatives,
                                                preparing an Environmental Impact                       FOR FURTHER INFORMATION CONTACT:                      the dredged material will be placed at
                                                Statement and Environmental Impact                      Stacie Auvenshine, 904–314–6714 or                    one or more permitted and
                                                Report (EIS/EIR) to evaluate the                        email at Stacie.j.auvenshine@                         economically feasible beneficial reuse
                                                efficiency of the movement of goods                     usace.army.mil.                                       sites.
                                                along the existing deep-draft navigation                                                                         Purpose and Need: The purpose of the
sradovich on DSK3GMQ082PROD with NOTICES




                                                                                                        SUPPLEMENTARY INFORMATION: This EIS/
                                                route extending from the Golden Gate,                   EIR is intended to be sufficient in scope             project is to provide more efficient
                                                through San Pablo Bay and Carquinez                     to address the federal, state, and local              deep-draft navigation operations in a
                                                Strait, to deep draft facilities at Avon,               requirements and environmental issues                 manner that minimizes adverse
                                                California. This Notice of Intent (NOI)                 concerning the proposed activities and                environmental effects. The need for the
                                                represents a supplemental notice to the                 permit approvals.                                     project is to address vessel restrictions
                                                March 4, 2016, NOI released for the San                    Project Area and Background                        imposed by the existing channel depths,
                                                Francisco Bay to Stockton Navigation                    Information: The authorized San                       which are inadequate to accommodate


                                           VerDate Sep<11>2014   18:22 Dec 01, 2017   Jkt 244001   PO 00000   Frm 00043   Fmt 4703   Sfmt 4703   E:\FR\FM\04DEN1.SGM   04DEN1


                                                57238                       Federal Register / Vol. 82, No. 231 / Monday, December 4, 2017 / Notices

                                                vessels with drafts exceeding 35 feet                   proposing a reinstatement of a                        response to this notice will be
                                                MLLW.                                                   previously approved information                       considered public records.
                                                   Issues: The environmental analysis                   collection.                                             Title of Collection: Survey on the Use
                                                will consider the effects of deepening                                                                        of Funds Under Title II, Part A:
                                                                                                        DATES:   Interested persons are invited to
                                                navigation channels in the study area on                                                                      Supporting Effective Instruction
                                                                                                        submit comments on or before February
                                                biological resources, sediments, air                                                                          Grants—Subgrants to LEAs.
                                                                                                        2, 2018.                                                OMB Control Number: 1810–0618.
                                                quality, greenhouse gas emissions,
                                                climate change, water quality, geology,                 ADDRESSES: To access and review all the                 Type of Review: A reinstatement of a
                                                sediments, hydraulics and hydrology,                    documents related to the information                  previously approved information
                                                hazards, noise, utilities, navigation,                  collection listed in this notice, please              collection.
                                                transportation, land use, cultural and                  use http://www.regulations.gov by                       Respondents/Affected Public: State,
                                                historic resources, aesthetics, recreation,             searching the Docket ID number ED–                    Local, and Tribal Governments.
                                                and socioeconomics. The EIS/EIR will                    2017–ICCD–0149. Comments submitted                      Total Estimated Number of Annual
                                                evaluate environmental justice and                      in response to this notice should be                  Responses: 6,050.
                                                cumulative impacts and potentially                      submitted electronically through the                    Total Estimated Number of Annual
                                                other environmental issues.                             Federal eRulemaking Portal at http://                 Burden Hours: 36,300.
                                                   Scoping Process: The USACE is                        www.regulations.gov by selecting the                    Abstract: The Elementary and
                                                seeking participation of all interested                 Docket ID number or via postal mail,                  Secondary Education Act of 1965, as
                                                federal, state, and local agencies, Native              commercial delivery, or hand delivery.                reauthorized by the Every Student
                                                American groups, and other concerned                    Please note that comments submitted by                Succeeds Act of 2015 (ESSA), provides
                                                private organizations or individuals                    fax or email and those submitted after                funds to States to prepare, train, and
                                                through this public notice. The purpose                 the comment period will not be                        recruit high-quality teachers, principals,
                                                of the public scoping period is to solicit              accepted. Written requests for                        and other school leaders. These funds
                                                comments regarding the potential                        information or comments submitted by                  are provided to districts through Title II,
                                                impacts, environmental issues, and                      postal mail or delivery should be                     Part A (Supporting Effective Instruction
                                                alternatives associated with the                        addressed to the Director of the                      Grants). The purpose of these surveys is
                                                proposed action to be considered in the                 Information Collection Clearance                      to provide the U.S. Department of
                                                Draft EIS/EIR; identify other significant               Division, U.S. Department of Education,               Education with a better understanding
                                                issues; and provide other relevant                      400 Maryland Avenue SW., LBJ, Room                    of how local educational agencies
                                                information.                                            216–44, Washington, DC 20202–4537.                    (LEAs) utilize these funds. This survey
                                                   The public will have an additional                                                                         also collects data on teacher salaries
                                                                                                        FOR FURTHER INFORMATION CONTACT: For
                                                opportunity to comment once the Draft                                                                         funded by Title II, Part A, and
                                                                                                        specific questions related to collection
                                                EIS/EIR is released, which is anticipated                                                                     professional development provided by
                                                                                                        activities, please contact Tawanda
                                                to be in the summer of 2018. The U.S.                                                                         LEAs to their teachers.
                                                                                                        Avery, 202–453–6471.                                    Similar data have been collected
                                                Environmental Protection Agency will                    SUPPLEMENTARY INFORMATION: The
                                                provide notice of the availability of the                                                                     under the Survey on the Use of Funds
                                                                                                        Department of Education (ED), in                      Under Title II, Part A prior to
                                                Draft EIS/EIR in the Federal Register                   accordance with the Paperwork
                                                and the USACE and Port of Stockton                                                                            reauthorization of ESEA. This OMB
                                                                                                        Reduction Act of 1995 (PRA) (44 U.S.C.                clearance request is to continue these
                                                will provide a 45-day review period for                 3506(c)(2)(A)), provides the general
                                                the public, organizations, and agencies                                                                       types of analyses, but using new data
                                                                                                        public and Federal agencies with an                   collection instruments updated to
                                                to review and comment on the Draft                      opportunity to comment on proposed,
                                                EIS/EIR. All interested parties should                                                                        reflect changes due to the
                                                                                                        revised, and continuing collections of                reauthorization of ESEA by the ESSA.
                                                respond to this notice and provide a                    information. This helps the Department
                                                current address if they wish to be                                                                            The request is to begin data collection
                                                                                                        assess the impact of its information                  and analyses for the 2017–18 school
                                                notified about circulation of the Draft                 collection requirements and minimize
                                                EIS/EIR.                                                                                                      year and subsequent years.
                                                                                                        the public’s reporting burden. It also
                                                                                                                                                                Dated: November 28, 2017.
                                                Brenda S. Bowen,                                        helps the public understand the
                                                                                                                                                              Tomakie Washington,
                                                Army Federal Register Liaison Officer.                  Department’s information collection
                                                                                                        requirements and provide the requested                Acting Director, Information Collection
                                                [FR Doc. 2017–26051 Filed 12–1–17; 8:45 am]                                                                   Clearance Division, Office of the Chief Privacy
                                                BILLING CODE 3720–58–P
                                                                                                        data in the desired format. ED is                     Officer, Office of Management.
                                                                                                        soliciting comments on the proposed
                                                                                                                                                              [FR Doc. 2017–25970 Filed 12–1–17; 8:45 am]
                                                                                                        information collection request (ICR) that
                                                                                                                                                              BILLING CODE 4000–01–P
                                                                                                        is described below. The Department of
                                                DEPARTMENT OF EDUCATION
                                                                                                        Education is especially interested in
                                                [Docket No.: ED–2017–ICCD–0149]                         public comment addressing the
                                                                                                                                                              DEPARTMENT OF EDUCATION
                                                                                                        following issues: (1) Is this collection
                                                Agency Information Collection                           necessary to the proper functions of the              [Docket No.: ED–2017–ICCD–0148]
                                                Activities; Comment Request; Survey                     Department; (2) will this information be
                                                on the Use of Funds Under Title II, Part                processed and used in a timely manner;                Agency Information Collection
                                                A: Supporting Effective Instruction                     (3) is the estimate of burden accurate;               Activities; Comment Request;
                                                Grants—Subgrants to LEAs                                (4) how might the Department enhance                  Quarterly Cumulative Caseload Report
sradovich on DSK3GMQ082PROD with NOTICES




                                                AGENCY: Office of Elementary and                        the quality, utility, and clarity of the              AGENCY:  Office of Special Education and
                                                Secondary Education (OESE),                             information to be collected; and (5) how              Rehabilitative Services (OSERS),
                                                Department of Education (ED).                           might the Department minimize the                     Department of Education (ED).
                                                ACTION: Notice.                                         burden of this collection on the                      ACTION: Notice.
                                                                                                        respondents, including through the use
                                                SUMMARY: In accordance with the                         of information technology. Please note                SUMMARY: In accordance with the
                                                Paperwork Reduction Act of 1995, ED is                  that written comments received in                     Paperwork Reduction Act of 1995, ED is


                                           VerDate Sep<11>2014   18:22 Dec 01, 2017   Jkt 244001   PO 00000   Frm 00044   Fmt 4703   Sfmt 4703   E:\FR\FM\04DEN1.SGM   04DEN1



Document Created: 2017-12-02 00:41:16
Document Modified: 2017-12-02 00:41:16
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of intent.
DatesSubmit comments concerning this notice on or before thirty days after this posting. There will be no additional public meeting in conjunction with this scoping period.
ContactStacie Auvenshine, 904-314-6714 or email at [email protected]
FR Citation82 FR 57237 

2025 Federal Register | Disclaimer | Privacy Policy