[Federal Register Volume 83, Number 50 (Wednesday, March 14, 2018)]
[Notices]
[Pages 11197-11198]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-05100]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 1773-000]


Yellowstone Hydroelectric Project; Notice of Existing Licensee's 
Notice of Intent To Not File a Subsequent License Application, and 
Soliciting Pre-Application Documents and Notices of Intent To File a 
License Application

    At least five years before the expiration of a license for a minor 
water power project not subject to sections 14 and 15 of the Federal 
Power Act (i.e., a project having an installed capacity of 1.5 
megawatts or less), the licensee must file with the Commission a letter 
that contains an unequivocal statement of the licensee's intent to file 
or not to file an application for a subsequent license.\1\
---------------------------------------------------------------------------

    \1\ 18 CFR 16.19(b) (2017) (citing 18 CFR 16.6(b)). Section 
16.19(b) applies to licenses not subject to Parts 14 and 15 of the 
Federal Power Act.
---------------------------------------------------------------------------

    If such a licensee informs the Commission that it does not intend 
to file an application for a subsequent license, nonpower license, or 
exemption for the project, the licensee may not file an application for 
a subsequent license, nonpower license, or exemption for the project, 
either individually or in conjunction with an entity or entities that 
are not currently licensees of the project.\2\
---------------------------------------------------------------------------

    \2\ 18 CFR 16.24(b)(1) (2017).
---------------------------------------------------------------------------

    On September 26, 2017, Moon Lake Electric Association, the existing 
licensee for the Yellowstone Hydroelectric Project No. 1773, filed 
notice of its intent to not file an application for a subsequent 
license. Therefore, pursuant to section 16.24(b)(1) of the Commission's 
regulations, Moon Lake may not file an application for a subsequent 
license for the project, either individually or in conjunction with an 
entity or entities that are not currently licensees of the project.
    The 900-kilowatt (kW) Yellowstone Hydroelectric Project is located 
on the Yellowstone River, in Duchesne County, Utah. The diversion dam, 
and portions of the penstock, are located within the Ashley National 
Forest. The existing minor license for the project expires on October 
15, 2022.
    The principal project works consist of: (1) A 15-foot-high, 313-
foot-long rock filled, timber-crib dam that impounds a small reservoir 
covering approximately 3.8 acres; (2) a concrete intake structure with 
a gate valve; (3) a 14,126-foot-long, 44-inch-diameter and 42-inch-
diameter steel penstock; (4) a powerhouse with three turbine-generators 
rated at 300 kW each; (5) a substation; (6) a 14.27-mile-long, 7.2-
kilovolt overhead transmission line and underlain telephone line; and 
(7) and appurtenant facilities.
    Any party interested in filing a license application (i.e., 
potential applicant) for the Yellowstone Hydroelectric Project No. 1773 
must file a Notice of Intent (NOI) \3\ and pre-application document 
(PAD).\4\ Additionally, while the integrated licensing process (ILP) is 
the default process for preparing an application for a subsequent 
license, a potential applicant may request to use alternative licensing 
procedures when it files its NOI.\5\
---------------------------------------------------------------------------

    \3\ 18 CFR 5.5 (2017).
    \4\ 18 CFR 5.6 (2017).
    \5\ 18 CFR 5.3(b) (2017).
---------------------------------------------------------------------------

    The deadline for potential applicants, other than the existing 
licensee, to file NOIs, PADs, and requests to use an alternative 
licensing process is 120 days from the issuance date of this notice.
    Applications for a subsequent license from potential applicants, 
other than the existing licensee, must be filed with the Commission at 
least 24 months prior to the expiration of the existing license.\6\ 
Because the existing license expires on October 15, 2022, applications 
for

[[Page 11198]]

license for this project must be filed by October 15, 2020.\7\
---------------------------------------------------------------------------

    \6\ 18 CFR 16.20 (2017).
    \7\ To the extent an interested applicant files an NOI and PAD 
and elects or is required to use the Commission's ILP, a process 
plan will be issued within 180 days of this notice, which 
accelerates the steps of the ILP to allow for filing a subsequent 
license application by the October 15, 2020, deadline.
---------------------------------------------------------------------------

    Questions concerning this notice should be directed to Evan 
Williams (202) 502-8462 or [email protected].

    Dated: March 8, 2018.
Kimberly D. Bose,
 Secretary.
[FR Doc. 2018-05100 Filed 3-13-18; 8:45 am]
BILLING CODE 6717-01-P



                                                                                        Federal Register / Vol. 83, No. 50 / Wednesday, March 14, 2018 / Notices                                                                                                                 11197

                                                                                                                              FERC–725Y IN DOCKET NO. IC18–2–000
                                                                                                                                                        Annual                                                                                     Total annual burden
                                                                                                             Number and type of                        number of                Total number                Avg. burden & cost                        hours & total           Cost per
                                                                                                               respondents 2                        responses per               of responses                  per response 3                           annual cost           respondent
                                                                                                                                                      respondent

                                                                                                                           (1)                               (2)                (1) * (2) = (3)                          (4)                          (3) * (4) = (5)           (5) ÷ (1)

                                               Annual Evaluation and Update of                             TO (331), GOP (890) ...                                        1                4 1,064        6 hrs.; $408.72 hr ......              6,384 hrs.; $434,878 ....           $68.12
                                                 Training Program and Task List.
                                               Retention of Records ...........................            TO (331), GOP (890) ...                                        1                4 1,064        10 hrs.; $408.90 hr ....               10,640 hrs.; $435,070 ..              40.89
                                               Verification and Retention of Evidence                      TO (331) ......................                                1                      331      10 hrs.; $408.90 hr ....               3,310 hrs.; $135,346 ....             40.89
                                                 of capabilities of personnel [R3, M3,
                                                 C1.2], and Creation and Retention
                                                 of Records on Simulation Training.

                                                    Total ..............................................   ......................................   ........................   ........................   ....................................   20,334 hrs.; $1,005,294     ....................



                                                 Comments: Comments are invited on:                                               DEPARTMENT OF ENERGY                                                                    that are not currently licensees of the
                                               (1) Whether the collection of                                                                                                                                              project.
                                               information is necessary for the proper                                            Federal Energy Regulatory                                                                  The 900-kilowatt (kW) Yellowstone
                                               performance of the functions of the                                                Commission                                                                              Hydroelectric Project is located on the
                                               Commission, including whether the                                                                                                                                          Yellowstone River, in Duchesne County,
                                               information will have practical utility;                                           [Project No. 1773–000]                                                                  Utah. The diversion dam, and portions
                                               (2) the accuracy of the agency’s estimate                                                                                                                                  of the penstock, are located within the
                                                                                                                                  Yellowstone Hydroelectric Project;                                                      Ashley National Forest. The existing
                                               of the burden and cost of the collection                                           Notice of Existing Licensee’s Notice of
                                               of information, including the validity of                                                                                                                                  minor license for the project expires on
                                                                                                                                  Intent To Not File a Subsequent                                                         October 15, 2022.
                                               the methodology and assumptions used;                                              License Application, and Soliciting
                                               (3) ways to enhance the quality, utility                                                                                                                                      The principal project works consist
                                                                                                                                  Pre-Application Documents and                                                           of: (1) A 15-foot-high, 313-foot-long rock
                                               and clarity of the information collection;                                         Notices of Intent To File a License                                                     filled, timber-crib dam that impounds a
                                               and (4) ways to minimize the burden of                                             Application                                                                             small reservoir covering approximately
                                               the collection of information on those
                                                                                                                                     At least five years before the                                                       3.8 acres; (2) a concrete intake structure
                                               who are to respond, including the use
                                                                                                                                  expiration of a license for a minor water                                               with a gate valve; (3) a 14,126-foot-long,
                                               of automated collection techniques or                                                                                                                                      44-inch-diameter and 42-inch-diameter
                                               other forms of information technology.                                             power project not subject to sections 14
                                                                                                                                  and 15 of the Federal Power Act (i.e., a                                                steel penstock; (4) a powerhouse with
                                                 Dated: March 6, 2018.                                                            project having an installed capacity of                                                 three turbine-generators rated at 300 kW
                                               Kimberly D. Bose,                                                                  1.5 megawatts or less), the licensee must                                               each; (5) a substation; (6) a 14.27-mile-
                                               Secretary.                                                                         file with the Commission a letter that                                                  long, 7.2-kilovolt overhead transmission
                                                                                                                                  contains an unequivocal statement of                                                    line and underlain telephone line; and
                                               [FR Doc. 2018–05102 Filed 3–13–18; 8:45 am]
                                                                                                                                  the licensee’s intent to file or not to file                                            (7) and appurtenant facilities.
                                               BILLING CODE 6717–01–P
                                                                                                                                  an application for a subsequent license.1                                                  Any party interested in filing a license
                                                                                                                                     If such a licensee informs the                                                       application (i.e., potential applicant) for
                                                                                                                                  Commission that it does not intend to                                                   the Yellowstone Hydroelectric Project
                                                                                                                                  file an application for a subsequent                                                    No. 1773 must file a Notice of Intent
                                                                                                                                  license, nonpower license, or exemption                                                 (NOI) 3 and pre-application document
                                                                                                                                  for the project, the licensee may not file                                              (PAD).4 Additionally, while the
                                                                                                                                  an application for a subsequent license,                                                integrated licensing process (ILP) is the
                                                                                                                                  nonpower license, or exemption for the                                                  default process for preparing an
                                                                                                                                  project, either individually or in                                                      application for a subsequent license, a
                                                                                                                                  conjunction with an entity or entities                                                  potential applicant may request to use
                                                                                                                                  that are not currently licensees of the                                                 alternative licensing procedures when it
                                                                                                                                  project.2                                                                               files its NOI.5
                                                                                                                                     On September 26, 2017, Moon Lake                                                        The deadline for potential applicants,
                                                                                                                                  Electric Association, the existing                                                      other than the existing licensee, to file
                                                                                                                                  licensee for the Yellowstone                                                            NOIs, PADs, and requests to use an
                                                 2 TO = Transmission Owner; GOP = Generator                                       Hydroelectric Project No. 1773, filed                                                   alternative licensing process is 120 days
                                               Operator.                                                                          notice of its intent to not file an                                                     from the issuance date of this notice.
                                                 3 The estimates for cost per response are loaded
                                                                                                                                  application for a subsequent license.                                                      Applications for a subsequent license
                                               hourly wage figure (includes benefits) is based on                                 Therefore, pursuant to section                                                          from potential applicants, other than the
                                               the average of three occupational categories for                                   16.24(b)(1) of the Commission’s                                                         existing licensee, must be filed with the
                                               2016 found on the Bureau of Labor Statistics                                                                                                                               Commission at least 24 months prior to
                                                                                                                                  regulations, Moon Lake may not file an
                                               website (http://www.bls.gov/oes/current/naics2_                                                                                                                            the expiration of the existing license.6
                                                                                                                                  application for a subsequent license for
daltland on DSKBBV9HB2PROD with NOTICES




                                               22.htm): Electrical Engineer (Occupation Code: 17–
                                               2071): $68.12; Office and Administrative Support                                   the project, either individually or in                                                  Because the existing license expires on
                                               (Occupation Code: 43–0000): $40.89.                                                conjunction with an entity or entities                                                  October 15, 2022, applications for
                                                 4 Some transmission owners are also generator
                                                                                                                                                                                                                             3 18 CFR 5.5 (2017).
                                               operators. To eliminate double counting some                                         1 18 CFR 16.19(b) (2017) (citing 18 CFR 16.6(b)).

                                               entities, this figure reflects the number of unique                                                                                                                           4 18 CFR 5.6 (2017).
                                                                                                                                  Section 16.19(b) applies to licenses not subject to
                                               entities (1064) within the group of TOs and GOPs.                                  Parts 14 and 15 of the Federal Power Act.                                                  5 18 CFR 5.3(b) (2017).

                                               That approach is used throughout the table.                                          2 18 CFR 16.24(b)(1) (2017).                                                             6 18 CFR 16.20 (2017).




                                          VerDate Sep<11>2014          19:50 Mar 13, 2018            Jkt 244001         PO 00000          Frm 00030          Fmt 4703          Sfmt 4703         E:\FR\FM\14MRN1.SGM                    14MRN1


                                               11198                        Federal Register / Vol. 83, No. 50 / Wednesday, March 14, 2018 / Notices

                                               license for this project must be filed by                DEPARTMENT OF ENERGY                                  with any FERC Online service, please
                                               October 15, 2020.7                                                                                             email FERCOnlineSupport@ferc.gov, or
                                                  Questions concerning this notice                      Federal Energy Regulatory                             call (866) 208–3676 (toll free). For TTY,
                                               should be directed to Evan Williams                      Commission                                            call (202) 502–8659.
                                               (202) 502–8462 or evan.williams@                         [Docket No. EL18–124–000]                               Comment Date: 5:00 p.m. Eastern time
                                               ferc.gov.                                                                                                      on April 4, 2018.
                                                 Dated: March 8, 2018.                                  T.E.S. Filer City Station Limited                       Dated: March 6, 2018.
                                               Kimberly D. Bose,                                        Partnership; Consumers Energy                         Kimberly D. Bose,
                                               Secretary.                                               Company; Notice of Petition for                       Secretary.
                                               [FR Doc. 2018–05100 Filed 3–13–18; 8:45 am]
                                                                                                        Declaratory Order
                                                                                                                                                              [FR Doc. 2018–05101 Filed 3–13–18; 8:45 am]
                                               BILLING CODE 6717–01–P                                      Take notice that on March 5, 2018,                 BILLING CODE 6717–01–P
                                                                                                        pursuant to Rule 207(a)(2) of the Federal
                                                                                                        Energy Regulatory Commission’s
                                               DEPARTMENT OF ENERGY                                     (Commission) Rules of Practice and                    DEPARTMENT OF ENERGY
                                                                                                        Procedure, 18 CFR 385.207(a)(2), T.E.S.
                                               Federal Energy Regulatory                                Filer City Station Limited Partnership                Federal Energy Regulatory
                                               Commission                                               (Filer City) and Consumers Energy                     Commission
                                               [Docket No. CP17–178–000]                                Company (Consumers) (jointly                          [Docket No. CP18–90–000]
                                                                                                        Petitioners) submitted a Petition for
                                               Alaska Gasline Development                               Declaratory Order requesting                          Transcontinental Gas Pipe Line
                                               Corporation; Notice of Technical                         confirmation that, pursuant to 18 CFR                 Company, LLC; Notice of Application
                                               Conference                                               292.601(c), sales of energy and capacity
                                                                                                        from the T.E.S. Filer City Station Plant                 Take notice that on February 22, 2018,
                                                  Take notice that a technical                                                                                Transcontinental Gas Pipe Line
                                                                                                        (Facility), pursuant to a 1988 power
                                               conference will be held on Thursday,                                                                           Company, LLC (Transco), P.O. Box
                                                                                                        purchase agreement between Filer City
                                               March 22, 2018 at 9:00 a.m., in Room                                                                           1396, Houston, Texas 77251, filed an
                                                                                                        and Consumers (PPA), will continue to
                                               3M–4 A and B at the Federal Energy                                                                             application in Docket No. CP18–90–000
                                                                                                        be exempt from Federal Power Act
                                               Regulatory Commission, 888 First Street                                                                        an application pursuant to section 7(b)
                                                                                                        sections 205 and 206, 16 U.S.C. 824d,
                                               NE, Washington, DC 20426.                                                                                      of the Natural Gas Act (NGA) requesting
                                                  The technical conference will provide                 824e, after the PPA is amended in
                                                                                                        connection with a plan to repower and                 authorization to amend its certificate
                                               an opportunity for Commission staff and                                                                        authority granted in Docket No. CP15–
                                               representatives from Alaska Gasline                      modernize the Facility, as more fully
                                                                                                        explained in the petition.                            536–000 to abandon by sale to Tana
                                               Development Corporation to discuss                                                                             Exploration Company LLC (Tana)
                                                                                                           Any person desiring to intervene or to
                                               clarifications on the Commission staff’s                                                                       approximately 26.55 miles of 20-inch-
                                                                                                        protest this filing must file in
                                               February 15, 2018 environmental data                                                                           diameter gathering pipeline extending
                                                                                                        accordance with Rules 211 and 214 of
                                               request for the Alaska LNG Project.                                                                            from Matagorda Island Block 669 to
                                                                                                        the Commission’s Rules of Practice and
                                               While all interested persons and                                                                               Brazos Block 133 Platform A, offshore
                                                                                                        Procedure (18 CFR 385.211, 385.214).
                                               Commission staff are permitted to                                                                              Texas. Transco now seeks to abandon
                                                                                                        Protests will be considered by the
                                               attend, no comments or statements                                                                              these facilities in place, rather than by
                                                                                                        Commission in determining the
                                               during the conference will be permitted.                                                                       sale to Tana, all as more fully set forth
                                                                                                        appropriate action to be taken, but will
                                               Further, there will be no discussion of                                                                        in the application which is on file with
                                                                                                        not serve to make protestants parties to
                                               Critical Energy Infrastructure                                                                                 the Commission and open to public
                                                                                                        the proceeding. Any person wishing to
                                               Information or privileged materials. For                                                                       inspection. The filing is available for
                                                                                                        become a party must file a notice of
                                               further information please contact                                                                             review at the Commission in the Public
                                                                                                        intervention or motion to intervene, as
                                               Jennifer Zielinski at (202) 502–6259 or                                                                        Reference Room or may be viewed on
                                                                                                        appropriate. Such notices, motions, or
                                               email jennifer.zielinski@ferc.gov.                                                                             the Commission’s website web at http://
                                                  Federal Energy Regulatory                             protests must be filed on or before the
                                                                                                        comment date. Anyone filing a motion                  www.ferc.gov using the eLibrary link.
                                               Commission conferences are accessible                                                                          Enter the docket number excluding the
                                               under section 508 of the Rehabilitation                  to intervene or protest must serve a copy
                                                                                                        of that document on the Petitioner.                   last three digits in the docket number
                                               Act of 1973. For accessibility                                                                                 field to access the document. For
                                                                                                           The Commission encourages
                                               accommodations please send an email                                                                            assistance, contact FERC at
                                                                                                        electronic submission of protests and
                                               to accessibility@ferc.gov or call toll free                                                                    FERCOnlineSupport@ferc.gov or call
                                                                                                        interventions in lieu of paper using the
                                               (866) 208–3372 (voice) or (202) 502–                                                                           toll-free, (886) 208–3676 or TYY, (202)
                                                                                                        eFiling link at http://www.ferc.gov.
                                               8659 (TTY), or send a fax to (202) 208–                                                                        502–8659.
                                                                                                        Persons unable to file electronically
                                               2106 with the required                                                                                            Any questions concerning this
                                                                                                        should submit an original and 5 copies
                                               accommodations.                                                                                                application may be directed to Marg
                                                                                                        of the protest or intervention to the
                                                 Dated: March 8, 2018.                                  Federal Energy Regulatory Commission,                 Camardello, Regulatory Analyst, Lead,
                                               Nathaniel J. Davis, Sr.,                                 888 First Street NE, Washington, DC                   Rates & Regulatory, Transcontinental
                                               Deputy Secretary.                                        20426.                                                Gas Pipe Line Company, LLC, P.O. Box
                                               [FR Doc. 2018–05095 Filed 3–13–18; 8:45 am]                 This filing is accessible on-line at               1396, Houston, Texas 77251, or by
                                                                                                        http://www.ferc.gov, using the eLibrary               telephone at (713) 215–3380.
daltland on DSKBBV9HB2PROD with NOTICES




                                               BILLING CODE 6717–01–P
                                                                                                        link and is available for review in the                  Pursuant to section 157.9 of the
                                                  7 To the extent an interested applicant files an      Commission’s Public Reference Room in                 Commission’s rules, 18 CFR 157.9,
                                               NOI and PAD and elects or is required to use the         Washington, DC. There is an                           within 90 days of this Notice the
                                               Commission’s ILP, a process plan will be issued          eSubscription link on the website that                Commission staff will either: Complete
                                               within 180 days of this notice, which accelerates
                                               the steps of the ILP to allow for filing a subsequent
                                                                                                        enables subscribers to receive email                  its environmental assessment (EA) and
                                               license application by the October 15, 2020,             notification when a document is added                 place it into the Commission’s public
                                               deadline.                                                to a subscribed docket(s). For assistance             record (eLibrary) for this proceeding; or


                                          VerDate Sep<11>2014    18:17 Mar 13, 2018   Jkt 244001   PO 00000   Frm 00031   Fmt 4703   Sfmt 4703   E:\FR\FM\14MRN1.SGM   14MRN1



Document Created: 2018-03-14 01:06:59
Document Modified: 2018-03-14 01:06:59
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 11197 

2025 Federal Register | Disclaimer | Privacy Policy