83_FR_12810 83 FR 12753 - Clean Air Act Operating Permit Program; Petitions for Objection to State Operating Permit for ExxonMobil Corporation, ExxonMobil Baytown Olefins Plant, Harris County, Texas

83 FR 12753 - Clean Air Act Operating Permit Program; Petitions for Objection to State Operating Permit for ExxonMobil Corporation, ExxonMobil Baytown Olefins Plant, Harris County, Texas

ENVIRONMENTAL PROTECTION AGENCY

Federal Register Volume 83, Issue 57 (March 23, 2018)

Page Range12753-12753
FR Document2018-05970

The Environmental Protection Agency (EPA) Administrator signed an Order dated March 1, 2018, denying a Petition dated August 8, 2016 from the Environmental Integrity Project, Sierra Club, and Air Alliance Houston. The Petition requested that the EPA object to a Clean Air Act (CAA) title V operating permit issued by the Texas Commission on Environmental Quality (TCEQ) to ExxonMobil Corporation (ExxonMobil) for its Baytown Olefins Plant located in Harris County, Texas.

Federal Register, Volume 83 Issue 57 (Friday, March 23, 2018)
[Federal Register Volume 83, Number 57 (Friday, March 23, 2018)]
[Notices]
[Page 12753]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-05970]


=======================================================================
-----------------------------------------------------------------------

ENVIRONMENTAL PROTECTION AGENCY

[FRL-9975-26--Region 6]


Clean Air Act Operating Permit Program; Petitions for Objection 
to State Operating Permit for ExxonMobil Corporation, ExxonMobil 
Baytown Olefins Plant, Harris County, Texas

AGENCY: Environmental Protection Agency (EPA).

ACTION: Notice of final Order on Petition for objection to Clean Air 
Act title V operating permit.

-----------------------------------------------------------------------

SUMMARY: The Environmental Protection Agency (EPA) Administrator signed 
an Order dated March 1, 2018, denying a Petition dated August 8, 2016 
from the Environmental Integrity Project, Sierra Club, and Air Alliance 
Houston. The Petition requested that the EPA object to a Clean Air Act 
(CAA) title V operating permit issued by the Texas Commission on 
Environmental Quality (TCEQ) to ExxonMobil Corporation (ExxonMobil) for 
its Baytown Olefins Plant located in Harris County, Texas.

ADDRESSES: The EPA requests that you contact the individual listed in 
the FOR FURTHER INFORMATION CONTACT section to view copies of the final 
Order, the Petition, and other supporting information. You may review 
copies of the final Order, the Petition, and other supporting 
information at the EPA Region 6 Office, 1445 Ross Avenue, Dallas, Texas 
75202-2733. You may view the hard copies Monday through Friday, from 9 
a.m. to 3 p.m., excluding federal holidays. If you wish to examine 
these documents, you should make an appointment at least 24 hours 
before the visiting day. Additionally, the final Order and Petition are 
available electronically at: https://www.epa.gov/title-v-operating-permits/title-v-petition-database.

FOR FURTHER INFORMATION CONTACT: Aimee Wilson, EPA Region 6, (214) 665-
7596, [email protected].

SUPPLEMENTARY INFORMATION: The CAA affords EPA a 45-day period to 
review and object to, as appropriate, operating permits proposed by 
state permitting authorities under title V of the CAA. Section 
505(b)(2) of the CAA authorizes any person to petition the EPA 
Administrator to object to a title V operating permit within 60 days 
after the expiration of the EPA's 45-day review period if the EPA has 
not objected on its own initiative. Petitions must be based only on 
objections to the permit that were raised with reasonable specificity 
during the public comment period provided by the state, unless the 
petitioner demonstrates that it was impracticable to raise these issues 
during the comment period or unless the grounds for the issue arose 
after this period.
    The EPA received the Petition from the Environmental Integrity 
Project, Sierra Club, and Air Alliance Houston dated August 8, 2016, 
requesting that the EPA object to the issuance of operating permit no. 
O1553, issued by TCEQ to ExxonMobil Baytown Olefins Plant in Harris 
County, Texas. The Petition claims that: (1) TCEQ did not have the 
authority to create a federally-enforceable PAL permit at the time PAL6 
was issued, (2) the PAL6 permit is not federally enforceable because of 
alleged defects with how TCEQ calculated the facility's baseline 
emissions, and (3) PAL6 does not establish a PAL for PM2.5.
    On March 1, 2018, the EPA Administrator issued an Order denying the 
Petition. The Order explains the basis for EPA's decision.
    Sections 307(b) and 505(b)(2) of the CAA provide that a petitioner 
may request judicial review of those portions of an order that deny 
issues in a petition. Any petition for review shall be filed in the 
United States Court of Appeals for the appropriate circuit no later 
than May 22, 2018.

    Dated: March 16, 2018.
Anne Idsal,
Regional Administrator, Region 6.
[FR Doc. 2018-05970 Filed 3-22-18; 8:45 am]
 BILLING CODE 6560-50-P



                                                                             Federal Register / Vol. 83, No. 57 / Friday, March 23, 2018 / Notices                                                 12753

                                             docs-filing/efiling/filing-req.pdf. For                 ENVIRONMENTAL PROTECTION                              petitioner demonstrates that it was
                                             other information, call (866) 208–3676                  AGENCY                                                impracticable to raise these issues
                                             (toll free). For TTY, call (202) 502–8659.                                                                    during the comment period or unless
                                                                                                     [FRL–9975–26—Region 6]
                                                                                                                                                           the grounds for the issue arose after this
                                               Dated: March 19, 2018.
                                                                                                     Clean Air Act Operating Permit                        period.
                                             Nathaniel J. Davis, Sr.,                                                                                         The EPA received the Petition from
                                                                                                     Program; Petitions for Objection to
                                             Deputy Secretary.                                                                                             the Environmental Integrity Project,
                                                                                                     State Operating Permit for ExxonMobil
                                             [FR Doc. 2018–05953 Filed 3–22–18; 8:45 am]
                                                                                                     Corporation, ExxonMobil Baytown                       Sierra Club, and Air Alliance Houston
                                             BILLING CODE 6717–01–P                                  Olefins Plant, Harris County, Texas                   dated August 8, 2016, requesting that
                                                                                                                                                           the EPA object to the issuance of
                                                                                                     AGENCY:  Environmental Protection                     operating permit no. O1553, issued by
                                             DEPARTMENT OF ENERGY                                    Agency (EPA).                                         TCEQ to ExxonMobil Baytown Olefins
                                                                                                     ACTION: Notice of final Order on Petition             Plant in Harris County, Texas. The
                                             Federal Energy Regulatory                               for objection to Clean Air Act title V                Petition claims that: (1) TCEQ did not
                                             Commission                                              operating permit.                                     have the authority to create a federally-
                                                                                                                                                           enforceable PAL permit at the time
                                                                                                     SUMMARY:   The Environmental Protection               PAL6 was issued, (2) the PAL6 permit
                                             [Docket Nos. CP18–102–000; CP18–103–
                                                                                                     Agency (EPA) Administrator signed an                  is not federally enforceable because of
                                             000]
                                                                                                     Order dated March 1, 2018, denying a                  alleged defects with how TCEQ
                                             Cheyenne Connector, LLC; Rockies                        Petition dated August 8, 2016 from the                calculated the facility’s baseline
                                             Express Pipeline LLC; Notice of                         Environmental Integrity Project, Sierra               emissions, and (3) PAL6 does not
                                                                                                     Club, and Air Alliance Houston. The                   establish a PAL for PM2.5.
                                             Meeting Attendance
                                                                                                     Petition requested that the EPA object to                On March 1, 2018, the EPA
                                               The environmental staff of the Federal                a Clean Air Act (CAA) title V operating               Administrator issued an Order denying
                                             Energy Regulatory Commission                            permit issued by the Texas Commission                 the Petition. The Order explains the
                                                                                                     on Environmental Quality (TCEQ) to                    basis for EPA’s decision.
                                             (Commission) will attend three
                                                                                                     ExxonMobil Corporation (ExxonMobil)                      Sections 307(b) and 505(b)(2) of the
                                             informational public open house
                                                                                                     for its Baytown Olefins Plant located in              CAA provide that a petitioner may
                                             meetings sponsored by Cheyenne                          Harris County, Texas.
                                             Connector, LLC and Rockies Express                                                                            request judicial review of those portions
                                                                                                     ADDRESSES: The EPA requests that you                  of an order that deny issues in a
                                             Pipeline LLC. The project sponsor
                                                                                                     contact the individual listed in the FOR              petition. Any petition for review shall
                                             (Tallgrass Energy Partners, LP) will have               FURTHER INFORMATION CONTACT section to
                                             information on hand for two of its                                                                            be filed in the United States Court of
                                                                                                     view copies of the final Order, the                   Appeals for the appropriate circuit no
                                             related proposed projects in Weld                       Petition, and other supporting
                                             County, Colorado: The Cheyenne                                                                                later than May 22, 2018.
                                                                                                     information. You may review copies of
                                             Connector Pipeline (approximately 70                                                                            Dated: March 16, 2018.
                                                                                                     the final Order, the Petition, and other
                                             miles of new 36-inch-diameter pipeline                  supporting information at the EPA                     Anne Idsal,
                                             and five new meter and regulating                       Region 6 Office, 1445 Ross Avenue,                    Regional Administrator, Region 6.
                                             stations) and the REX Cheyenne Hub                      Dallas, Texas 75202–2733. You may                     [FR Doc. 2018–05970 Filed 3–22–18; 8:45 am]
                                             Enhancement (a new 32,100 horsepower                    view the hard copies Monday through                   BILLING CODE 6560–50–P
                                             compressor station as well as                           Friday, from 9 a.m. to 3 p.m., excluding
                                             modifications to the existing Cheyenne                  federal holidays. If you wish to examine
                                             Hub facility). The meetings will be on                  these documents, you should make an                   ENVIRONMENTAL PROTECTION
                                             April 3, 4, and 5, 2018, in Platteville,                appointment at least 24 hours before the              AGENCY
                                             Eaton, and Kersey, Colorado,                            visiting day. Additionally, the final
                                             respectively.                                           Order and Petition are available                      [ER–FRL–9038–3]
                                                                                                     electronically at: https://www.epa.gov/
                                               Commission staff will be present to                                                                         Environmental Impact Statements;
                                                                                                     title-v-operating-permits/title-v-petition-
                                             explain the Commission’s                                                                                      Notice of Availability
                                                                                                     database.
                                             environmental review process and
                                             answer related questions. For more                      FOR FURTHER INFORMATION CONTACT:                        Responsible Agency: Office of Federal
                                                                                                     Aimee Wilson, EPA Region 6, (214)                     Activities, General Information (202)
                                             information about the projects,
                                                                                                     665–7596, wilson.aimee@epa.gov.                       564–7156 or http://www2.epa.gov/nepa.
                                             including meeting details, visit Tallgrass
                                             Energy Partners, LP’s website at                        SUPPLEMENTARY INFORMATION: The CAA                    Weekly receipt of Environmental Impact
                                             www.tallgrassenergylp.com/                              affords EPA a 45-day period to review                   Statements
                                             Projects.aspx. Project-related questions                and object to, as appropriate, operating              Filed 03/12/2018 Through 03/16/2018
                                                                                                     permits proposed by state permitting                  Pursuant to 40 CFR 1506.9.
                                             can be directed to
                                             AskCheyenneConnector@                                   authorities under title V of the CAA.                 Notice
                                             tallgrassenergylp.com (or call 855–288–                 Section 505(b)(2) of the CAA authorizes
                                                                                                     any person to petition the EPA                          Section 309(a) of the Clean Air Act
                                             3997); or AskCheyenneHub@                                                                                     requires that EPA make public its
                                                                                                     Administrator to object to a title V
                                             tallgrassenergylp.com (or call 855–211–                                                                       comments on EISs issued by other
                                                                                                     operating permit within 60 days after
                                             1262).
amozie on DSK30RV082PROD with NOTICES




                                                                                                     the expiration of the EPA’s 45-day                    Federal agencies. EPA’s comment letters
                                               Dated: March 16, 2018.                                review period if the EPA has not                      on EISs are available at: https://
                                             Nathaniel J. Davis, Sr.,                                objected on its own initiative. Petitions             cdxnodengn.epa.gov/cdx-nepa-public/
                                                                                                     must be based only on objections to the               action/eis/search.
                                             Deputy Secretary.
                                             [FR Doc. 2018–05960 Filed 3–22–18; 8:45 am]
                                                                                                     permit that were raised with reasonable               EIS No. 20180043, Final, USACE, NC,
                                                                                                     specificity during the public comment                   Holden Beach East End Shore
                                             BILLING CODE 6717–01–P
                                                                                                     period provided by the state, unless the                Protection Project, Review Period


                                        VerDate Sep<11>2014   21:54 Mar 22, 2018   Jkt 244001   PO 00000   Frm 00040   Fmt 4703   Sfmt 4703   E:\FR\FM\23MRN1.SGM   23MRN1



Document Created: 2018-11-01 08:53:26
Document Modified: 2018-11-01 08:53:26
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionNotice of final Order on Petition for objection to Clean Air Act title V operating permit.
ContactAimee Wilson, EPA Region 6, (214) 665- 7596, [email protected]
FR Citation83 FR 12753 