NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 72 (April 13, 2018)

Page Range16134-16135
FR Document2018-07729

The U.S. Nuclear Regulatory Commission (NRC) invites public comment on the renewal of the Office of Management and Budget (OMB) approval for an existing collection of information. The information collection is entitled, ``Requirements for Renewal of Operating Licenses for Nuclear Power Plants.''

Federal Register, Volume 83 Issue 72 (Friday, April 13, 2018)
[Federal Register Volume 83, Number 72 (Friday, April 13, 2018)]
[Notices]
[Pages 16134-16135]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-07729]


-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2017-0213]


Information Collection: Requirements for Renewal of Operating 
Licenses for Nuclear Power Plants

AGENCY: Nuclear Regulatory Commission.

ACTION: Renewal of existing information collection; request for 
comment.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) invites public 
comment on the renewal of the Office of Management and Budget (OMB) 
approval for an existing collection of information. The information 
collection is entitled, ``Requirements for Renewal of Operating 
Licenses for Nuclear Power Plants.''

DATES: Submit comments by June 12, 2018. Comments received after this 
date will be considered if it is practical to do so, but the Commission 
is able to ensure consideration only for comments received on or before 
this date.

ADDRESSES: You may submit comments by any of the following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0213. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     Mail comments to: David Cullison, Office of the Chief 
Information Officer, Mail Stop: T-5 F53, U.S. Nuclear Regulatory 
Commission, Washington, DC 20555-0001.
    For additional direction on obtaining information and submitting 
comments, see ``Obtaining Information and Submitting Comments'' in the 
SUPPLEMENTARY INFORMATION section of this document.

FOR FURTHER INFORMATION CONTACT: David Cullison, Office of the Chief 
Information Officer, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2084; email: 
[email protected].

SUPPLEMENTARY INFORMATION: 

I. Obtaining Information and Submitting Comments

A. Obtaining Information

    Please refer to Docket ID NRC-2017-0213 when contacting the NRC 
about the availability of information for this action. You may obtain 
publicly-available information related to this action by any of the 
following methods:
     Federal Rulemaking website: Go to http://www.regulations.gov and search for Docket ID NRC-2017-0213.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
supporting statement for part 54 of title 10 of the Code of Federal 
Regulations (10 CFR), ``Requirements for Renewal of Operating Licenses 
for Nuclear Power Plants,'' is available in ADAMS under Package 
Accession No. ML17310A926.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.
     NRC's Clearance Officer: A copy of the collection of 
information and related instructions may be obtained without charge by 
contacting NRC's Clearance Officer, David Cullison, Office of the Chief 
Information Officer, U.S. Nuclear Regulatory Commission, Washington, DC 
20555-0001; telephone: 301-415-2084; email: 
[email protected].

B. Submitting Comments

    Please include Docket ID NRC-2017-0213 in the subject line of your 
comment submission in order to ensure that the NRC is able to make your

[[Page 16135]]

comment submission available to the public in this docket.
    The NRC cautions you not to include identifying or contact 
information in comment submissions that you do not want to be publicly 
disclosed in your comment submission. All comment submissions are 
posted at http://www.regulations.gov and entered into ADAMS. Comment 
submissions are not routinely edited to remove identifying or contact 
information.
    If you are requesting or aggregating comments from other persons 
for submission to the NRC, then you should inform those persons not to 
include identifying or contact information that they do not want to be 
publicly disclosed in their comment submission. Your request should 
state that the NRC does not routinely edit comment submissions to 
remove such information before making the comment submissions available 
to the public or entering the comment submissions into ADAMS.

II. Background

    In accordance with the Paperwork Reduction Act of 1995 (44 U.S.C. 
Chapter 35), the NRC is requesting public comment on its intention to 
request the OMB's approval for the information collection summarized 
below:
    1. The title of the information collection: 10 CFR part 54, 
``Requirements for Renewal of Operating Licenses for Nuclear Power 
Plants.''
    2. OMB approval number: 3150-0155.
    3. Type of submission: Extension.
    4. The form number, if applicable: Not applicable.
    5. How often the collection is required or requested: There is a 
one-time application for any licensee wishing to renew the operating 
license for its nuclear power plant. There is a one-time requirement 
for each licensee with a renewed operating license to submit a letter 
documenting the completion of inspection and testing activities. All 
holders of renewed licenses must perform yearly record keeping.
    6. Who will be required or asked to respond: Commercial nuclear 
power plant licensees who wish to renew their operating licenses and 
holders of renewed licenses.
    7. The estimated number of annual responses: 66 (8 reporting 
responses + 58 recordkeepers).
    8. The estimated number of annual respondents: 6.
    9. The estimated number of hours needed annually to comply with the 
information collection requirement or request: 226,320 (168,320 hours 
reporting + 58,000 hours recordkeeping).
    10. Abstract: Part 54 of 10 CFR establishes license renewal 
requirements for commercial nuclear power plants and describes the 
information that licensees must submit to the NRC when applying for a 
license renewal. The application must contain information on how the 
licensee will manage the detrimental effects of age-related degradation 
on certain plant systems, structures, and components so as to continue 
the plant's safe operation during the renewal term. The NRC needs this 
information to determine whether the licensee's actions will be 
effective in assuring the plants' continued safe operation during the 
period of extended operation. Holders of renewed licenses must retain 
in an auditable and retrievable form, for the term of the renewed 
operating license, all information and documentation required to 
document compliance with 10 CFR part 54. The NRC needs access to this 
information for continuing effective regulatory oversight.

III. Specific Requests for Comments

    The NRC is seeking comments that address the following questions:
    1. Is the proposed collection of information necessary for the NRC 
to properly perform its functions? Does the information have practical 
utility?
    2. Is the estimate of the burden of the information collection 
accurate?
    3. Is there a way to enhance the quality, utility, and clarity of 
the information to be collected?
    4. How can the burden of the information collection on respondents 
be minimized, including the use of automated collection techniques or 
other forms of information technology?

    Dated at Rockville, Maryland, this 10th day of April 2018.
    For the Nuclear Regulatory Commission.
David Cullison,
NRC Clearance Officer, Office of the Chief Information Officer.
[FR Doc. 2018-07729 Filed 4-12-18; 8:45 am]
 BILLING CODE 7590-01-P



                                               16134                            Federal Register / Vol. 83, No. 72 / Friday, April 13, 2018 / Notices

                                               license renewals in 2018, 2019, and                     at this time, NUREG–2221, ‘‘Technical                   For additional direction on obtaining
                                               2020. Subsequent License Renewal is a                   Bases for Changes in the Subsequent                   information and submitting comments,
                                               term referring to all license renewals                  License Renewal Guidance Documents                    see ‘‘Obtaining Information and
                                               allowing a plant to operate beyond the                  NUREG–2191 and NUREG–2192,’’ and                      Submitting Comments’’ in the
                                               60-year period (40-year period of an                    NUREG–2222, ‘‘Disposition of Public                   SUPPLEMENTARY INFORMATION section of
                                               initial operating license and a 20-year                 Comments on the Draft Subsequent                      this document.
                                               period of the first license renewal).                   License Renewal Guidance Documents                    FOR FURTHER INFORMATION CONTACT:
                                               Based on a survey conducted by the                      NUREG–2191 and NUREG–2192.’’ The                      David Cullison, Office of the Chief
                                               nuclear power industry, the NRC staff                   NRC’s resolution of these comments are                Information Officer, U.S. Nuclear
                                               believes that additional applications for               incorporated in the final SLR guidance                Regulatory Commission, Washington,
                                               subsequent license renewal will be                      documents, NUREG–2191 and NUREG–                      DC 20555–0001; telephone: 301–415–
                                               submitted in future years.                              2192.                                                 2084; email: INFOCOLLECTS.Resource@
                                                  The NRC has developed and                                                                                  NRC.GOV.
                                                                                                         Dated at Rockville, Maryland, this 10th day
                                               published final guidance for licensees                  of April 2018.                                        SUPPLEMENTARY INFORMATION:
                                               that intend to apply for subsequent
                                                                                                         For the Nuclear Regulatory Commission.
                                               license renewal. The guidance                                                                                 I. Obtaining Information and
                                               documents for subsequent license                        Eric R. Oesterle,                                     Submitting Comments
                                               renewal (i.e., for operation from 60 to 80              Chief, License Renewal Project Branch,
                                                                                                       Division of Materials and License Renewal,            A. Obtaining Information
                                               years), NUREG–2191, the ‘‘Generic
                                                                                                       Office of Nuclear Reactor Regulation.                    Please refer to Docket ID NRC–2017–
                                               Aging Lessons Learned for Subsequent
                                               License Renewal (GALL–SLR) Report,’’                    [FR Doc. 2018–07698 Filed 4–12–18; 8:45 am]           0213 when contacting the NRC about
                                               and NUREG–2192, the ‘‘Standard                          BILLING CODE 7590–01–P                                the availability of information for this
                                               Review Plan for Review of Subsequent                                                                          action. You may obtain publicly-
                                               License Renewal Applications for                                                                              available information related to this
                                               Nuclear Power Plants’’ (SRP–SLR),                       NUCLEAR REGULATORY                                    action by any of the following methods:
                                               address the issues for increased                        COMMISSION                                               • Federal Rulemaking website: Go to
                                               operating time from 60 to 80 years. The                 [NRC–2017–0213]                                       http://www.regulations.gov and search
                                               guidance also considers recent operating                                                                      for Docket ID NRC–2017–0213.
                                               experience identified since the release                 Information Collection: Requirements                     • NRC’s Agencywide Documents
                                               of GALL Report, Rev. 2. The GALL–SLR                    for Renewal of Operating Licenses for                 Access and Management System
                                               Report and SRP–SLR also include                         Nuclear Power Plants                                  (ADAMS): You may obtain publicly-
                                               changes that have been previously                                                                             available documents online in the
                                                                                                       AGENCY:  Nuclear Regulatory                           ADAMS Public Documents collection at
                                               issued for public comment as part of the
                                                                                                       Commission.                                           http://www.nrc.gov/reading-rm/
                                               staff’s license renewal Interim Staff
                                               Guidance (ISG) process. These ISGs can                  ACTION: Renewal of existing information               adams.html. To begin the search, select
                                               be found at http://www.nrc.gov/reading-                 collection; request for comment.                      ‘‘ADAMS Public Documents’’ and then
                                               rm/doc-collections/isg/license-                                                                               select ‘‘Begin Web-based ADAMS
                                                                                                       SUMMARY:   The U.S. Nuclear Regulatory
                                               renewal.html. These ISGs                                                                                      Search.’’ For problems with ADAMS,
                                                                                                       Commission (NRC) invites public
                                               (ML12286A275, ML11297A085,                                                                                    please contact the NRC’s Public
                                                                                                       comment on the renewal of the Office of
                                               ML12138A296, ML12270A436,                                                                                     Document Room (PDR) reference staff at
                                                                                                       Management and Budget (OMB)
                                               ML12044A215, ML12352A057,                                                                                     1–800–397–4209, 301–415–4737, or by
                                                                                                       approval for an existing collection of
                                               ML13227A361, ML15308A018, and                                                                                 email to pdr.resource@nrc.gov. The
                                                                                                       information. The information collection
                                               ML16237A383) have been incorporated                                                                           supporting statement for part 54 of title
                                                                                                       is entitled, ‘‘Requirements for Renewal
                                               into the GALL–SLR Report and the                                                                              10 of the Code of Federal Regulations
                                                                                                       of Operating Licenses for Nuclear Power
                                               associated sections of the SRP–SLR. The                                                                       (10 CFR), ‘‘Requirements for Renewal of
                                                                                                       Plants.’’
                                               NRC has previously received public                                                                            Operating Licenses for Nuclear Power
                                               comments on these ISGs, and is not                      DATES: Submit comments by June 12,                    Plants,’’ is available in ADAMS under
                                               requesting additional comments on the                   2018. Comments received after this date               Package Accession No. ML17310A926.
                                               ISGs.                                                   will be considered if it is practical to do              • NRC’s PDR: You may examine and
                                                  A notice of availability and request for             so, but the Commission is able to ensure              purchase copies of public documents at
                                               comments on draft NUREG–2191 and                        consideration only for comments                       the NRC’s PDR, Room O1–F21, One
                                               draft NUREG–2192 was published in the                   received on or before this date.                      White Flint North, 11555 Rockville
                                               Federal Register on December 23, 2015                   ADDRESSES: You may submit comments                    Pike, Rockville, Maryland 20852.
                                               (80 FR 79956). The public comment                       by any of the following methods:                         • NRC’s Clearance Officer: A copy of
                                               period ended on February 29, 2016. The                     • Federal Rulemaking website: Go to                the collection of information and related
                                               NRC received over 500 comments on                       http://www.regulations.gov and search                 instructions may be obtained without
                                               these draft guidance documents. The                     for Docket ID NRC–2017–0213. Address                  charge by contacting NRC’s Clearance
                                               NRC also published a supplement to the                  questions about NRC dockets to Jennifer               Officer, David Cullison, Office of the
                                               draft guidance documents in the                         Borges; telephone: 301–287–9127;                      Chief Information Officer, U.S. Nuclear
                                               Federal Register on March 29, 2016 (81                  email: Jennifer.Borges@nrc.gov. For                   Regulatory Commission, Washington,
                                               FR 17500). The public comment period                    technical questions, contact the                      DC 20555–0001; telephone: 301–415–
                                               on the supplements to draft NUREG–                      individual listed in the FOR FURTHER                  2084; email: INFOCOLLECTS.Resource@
daltland on DSKBBV9HB2PROD with NOTICES




                                               2191 and draft NUREG–2192 ended May                     INFORMATION CONTACT section of this                   NRC.GOV.
                                               31, 2016. The NRC reviewed and                          document.
                                               dispositioned all of the comments and                      • Mail comments to: David Cullison,                B. Submitting Comments
                                               published the disposition of the                        Office of the Chief Information Officer,                Please include Docket ID NRC–2017–
                                               comments and the technical bases for                    Mail Stop: T–5 F53, U.S. Nuclear                      0213 in the subject line of your
                                               their disposition in companion NUREG                    Regulatory Commission, Washington,                    comment submission in order to ensure
                                               documents, which are being published                    DC 20555–0001.                                        that the NRC is able to make your


                                          VerDate Sep<11>2014   17:41 Apr 12, 2018   Jkt 244001   PO 00000   Frm 00091   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1


                                                                                Federal Register / Vol. 83, No. 72 / Friday, April 13, 2018 / Notices                                              16135

                                               comment submission available to the                     reporting + 58,000 hours                              SECURITIES AND EXCHANGE
                                               public in this docket.                                  recordkeeping).                                       COMMISSION
                                                 The NRC cautions you not to include                     10. Abstract: Part 54 of 10 CFR                     [Release No. 34–83022; File No. SR–
                                               identifying or contact information in                   establishes license renewal                           CboeEDGX–2018–012]
                                               comment submissions that you do not                     requirements for commercial nuclear
                                               want to be publicly disclosed in your                   power plants and describes the                        Self-Regulatory Organizations; Cboe
                                               comment submission. All comment                                                                               EDGX Exchange, Inc.; Notice of Filing
                                                                                                       information that licensees must submit
                                               submissions are posted at http://                                                                             and Immediate Effectiveness of a
                                                                                                       to the NRC when applying for a license
                                               www.regulations.gov and entered into                                                                          Proposed Rule Change To Modify Rule
                                               ADAMS. Comment submissions are not                      renewal. The application must contain
                                                                                                       information on how the licensee will                  21.9 of the Exchange’s Rules and
                                               routinely edited to remove identifying                                                                        Related Functionality Applicable to the
                                               or contact information.                                 manage the detrimental effects of age-
                                                                                                                                                             Routing Options Made Available by the
                                                 If you are requesting or aggregating                  related degradation on certain plant
                                                                                                                                                             Exchange’s Equity Options Platform
                                               comments from other persons for                         systems, structures, and components so
                                               submission to the NRC, then you should                  as to continue the plant’s safe operation             April 9, 2018.
                                               inform those persons not to include                     during the renewal term. The NRC                         Pursuant to Section 19(b)(1) of the
                                               identifying or contact information that                 needs this information to determine                   Securities Exchange Act of 1934 (the
                                               they do not want to be publicly                         whether the licensee’s actions will be                ‘‘Act’’),1 and Rule 19b–4 thereunder,2
                                               disclosed in their comment submission.                  effective in assuring the plants’                     notice is hereby given that on April 9,
                                               Your request should state that the NRC                  continued safe operation during the                   2018, Cboe EDGX Exchange, Inc. (the
                                               does not routinely edit comment                         period of extended operation. Holders of              ‘‘Exchange’’) filed with the Securities
                                               submissions to remove such information                  renewed licenses must retain in an                    and Exchange Commission
                                               before making the comment                               auditable and retrievable form, for the               (‘‘Commission’’) the proposed rule
                                               submissions available to the public or                  term of the renewed operating license,                change as described in Items I and II
                                               entering the comment submissions into                   all information and documentation                     below, which Items have been prepared
                                               ADAMS.                                                  required to document compliance with                  by the Exchange. The Exchange has
                                                                                                       10 CFR part 54. The NRC needs access                  designated this proposal as a ‘‘non-
                                               II. Background                                                                                                controversial’’ proposed rule change
                                                                                                       to this information for continuing
                                                  In accordance with the Paperwork                                                                           pursuant to Section 19(b)(3)(A) of the
                                                                                                       effective regulatory oversight.
                                               Reduction Act of 1995 (44 U.S.C.                                                                              Act 3 and Rule 19b–4(f)(6)(iii)
                                               Chapter 35), the NRC is requesting                      III. Specific Requests for Comments                   thereunder,4 which renders it effective
                                               public comment on its intention to                                                                            upon filing with the Commission. The
                                               request the OMB’s approval for the                        The NRC is seeking comments that                    Commission is publishing this notice to
                                               information collection summarized                       address the following questions:                      solicit comments on the proposed rule
                                               below:                                                    1. Is the proposed collection of                    change from interested persons.
                                                  1. The title of the information                      information necessary for the NRC to                  I. Self-Regulatory Organization’s
                                               collection: 10 CFR part 54,                             properly perform its functions? Does the              Statement of the Terms of Substance of
                                               ‘‘Requirements for Renewal of Operating                 information have practical utility?                   the Proposed Rule Change
                                               Licenses for Nuclear Power Plants.’’                      2. Is the estimate of the burden of the
                                                  2. OMB approval number: 3150–0155.                                                                            The Exchange filed a proposal to
                                                                                                       information collection accurate?                      modify Rule 21.9 of Exchange’s rules
                                                  3. Type of submission: Extension.
                                                  4. The form number, if applicable:                     3. Is there a way to enhance the                    and related functionality applicable to
                                               Not applicable.                                         quality, utility, and clarity of the                  the routing options made available by
                                                  5. How often the collection is required              information to be collected?                          the Exchange’s equity options platform
                                               or requested: There is a one-time                                                                             (‘‘EDGX Options’’).
                                                                                                         4. How can the burden of the
                                               application for any licensee wishing to                                                                          The text of the proposed rule change
                                                                                                       information collection on respondents                 is available at the Exchange’s website at
                                               renew the operating license for its                     be minimized, including the use of
                                               nuclear power plant. There is a one-time                                                                      www.markets.cboe.com, at the principal
                                                                                                       automated collection techniques or                    office of the Exchange, and at the
                                               requirement for each licensee with a                    other forms of information technology?
                                               renewed operating license to submit a                                                                         Commission’s Public Reference Room.
                                               letter documenting the completion of                      Dated at Rockville, Maryland, this 10th day
                                                                                                                                                             II. Self-Regulatory Organization’s
                                               inspection and testing activities. All                  of April 2018.
                                                                                                                                                             Statement of the Purpose of, and
                                               holders of renewed licenses must                          For the Nuclear Regulatory Commission.
                                                                                                                                                             Statutory Basis for, the Proposed Rule
                                               perform yearly record keeping.                          David Cullison,                                       Change
                                                  6. Who will be required or asked to                  NRC Clearance Officer, Office of the Chief
                                                                                                                                                               In its filing with the Commission, the
                                               respond: Commercial nuclear power                       Information Officer.
                                                                                                                                                             Exchange included statements
                                               plant licensees who wish to renew their                 [FR Doc. 2018–07729 Filed 4–12–18; 8:45 am]
                                                                                                                                                             concerning the purpose of and basis for
                                               operating licenses and holders of                       BILLING CODE 7590–01–P                                the proposed rule change and discussed
                                               renewed licenses.                                                                                             any comments it received on the
                                                  7. The estimated number of annual                                                                          proposed rule change. The text of these
                                               responses: 66 (8 reporting responses +                                                                        statements may be examined at the
daltland on DSKBBV9HB2PROD with NOTICES




                                               58 recordkeepers).                                                                                            places specified in Item IV below. The
                                                  8. The estimated number of annual                                                                          Exchange has prepared summaries, set
                                               respondents: 6.
                                                  9. The estimated number of hours                                                                             1 15 U.S.C. 78s(b)(1).
                                               needed annually to comply with the                                                                              2 17 CFR 240.19b–4.
                                               information collection requirement or                                                                           3 15 U.S.C. 78s(b)(3)(A).

                                               request: 226,320 (168,320 hours                                                                                 4 17 CFR 240.19b–4(f)(6)(iii).




                                          VerDate Sep<11>2014   19:04 Apr 12, 2018   Jkt 244001   PO 00000   Frm 00092   Fmt 4703   Sfmt 4703   E:\FR\FM\13APN1.SGM   13APN1



Document Created: 2018-04-13 00:18:15
Document Modified: 2018-04-13 00:18:15
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionRenewal of existing information collection; request for comment.
DatesSubmit comments by June 12, 2018. Comments received after this date will be considered if it is practical to do so, but the Commission is able to ensure consideration only for comments received on or before this date.
ContactDavid Cullison, Office of the Chief Information Officer, U.S. Nuclear Regulatory Commission, Washington, DC 20555-0001; telephone: 301-415-2084; email: [email protected]
FR Citation83 FR 16134 