DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 75 (April 18, 2018)

Page Range17170-17171
FR Document2018-08072

Federal Register, Volume 83 Issue 75 (Wednesday, April 18, 2018)
[Federal Register Volume 83, Number 75 (Wednesday, April 18, 2018)]
[Notices]
[Pages 17170-17171]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-08072]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. CP18-12-000]


Notice of Availability of the Environmental Assessment for the 
Proposed Natural Gas Pipeline Company of America, LLC Herscher 
Northwest Storage Field Abandonment Project

    The staff of the Federal Energy Regulatory Commission (FERC or 
Commission) has prepared an environmental assessment (EA) for the 
Herscher Northwest Storage Field Abandonment Project, proposed by 
Natural Gas Pipeline Company of America LLC (Natural) in the above-
referenced docket. Natural requests authorization to abandon the 
Herscher Northwest Storage Field facilities with its certificated 
maximum inventory of 18.5 billion cubic feet (Bcf) located in Kankakee 
County, Illinois.
    The EA assesses the potential environmental effects of the 
abandonment of the Herscher Northwest Storage Field Abandonment Project 
in accordance with the requirements of the National Environmental 
Policy Act (NEPA). The FERC staff concludes that approval of the 
proposed project, with appropriate mitigating measures, would not 
constitute a major federal action significantly affecting the quality 
of the human environment.
    Natural proposes to abandon:
     In place 19 injection/withdrawal wells by permanently 
plugging and capping;
     in place 16.15 miles of 4- to 16-inch-diameter associated 
pipeline laterals in the storage field by capping;
     in place 13 non-jurisdictional observation wells by 
plugging;
     in place one non-jurisdictional salt water disposal well 
by plugging;
     in place approximately 15.3 Bcf of non-recoverable cushion 
gas;
     by removal the 330-horsepower Compressor Station 202 
including its building, compressor unit, concrete piers, and concrete 
foundation; and
     by removal all aboveground and belowground storage field 
auxiliary surface facilities, including, but not limited to: Well head 
piping, slug catchers, water gathering system, and methanol 
distribution systems associated with the abandoned wells; seven tap 
valves; a pigging facility; and two corrosion monitors along with their 
associated rectifiers and ground beds.
    Natural also proposes to convert the P. Cook No. 1 injection/
withdrawal well to an observational well for its nearby Herscher Mount 
Simon Storage Field; and retain the P. Cook No. G-1 well as an 
observation well for its nearby Herscher Galesville Storage Field.
    The FERC staff mailed copies of the EA to federal, state, and local 
government representatives and agencies; elected officials; 
environmental and public interest groups; Native American tribes; 
potentially affected landowners and other interested individuals and 
groups; and newspapers and libraries in the project area. In addition, 
the EA is available for public viewing on the FERC's website 
(www.ferc.gov) using the eLibrary link. A limited number of copies of 
the EA are available for distribution and public inspection at: Federal 
Energy Regulatory Commission, Public Reference Room, 888 First Street 
NE, Room 2A, Washington, DC 20426, (202) 502-8371.
    Any person wishing to comment on the EA may do so. Your comments 
should focus on the potential environmental effects, reasonable 
alternatives, and measures to avoid or lessen environmental impacts. 
The more specific your comments, the more useful they will be. To 
ensure that the Commission has the opportunity to consider your 
comments prior to making its decision on this project, it is important 
that we receive your comments in Washington, DC on or before May 14, 
2018.
    For your convenience, there are three methods you can use to file 
your comments to the Commission. In all instances, please reference the 
project docket number (CP18-12-000) with your submission. The 
Commission encourages electronic filing of comments and has expert 
staff available to assist you at (202) 502-8258 or 
[email protected].
    (1) You can file your comments electronically using the eComment 
feature on the Commission's website (www.ferc.gov) under the link to 
Documents and Filings. This is an easy method for submitting brief, 
text-only comments on a project;
    (2) You can also file your comments electronically using the 
eFiling feature on the Commission's website (www.ferc.gov) under the 
link to Documents and Filings. With eFiling, you can provide comments 
in a variety of formats by attaching them as a file with your 
submission. New eFiling users must first create an account by clicking 
on eRegister. You must select the type of filing you are making. If you 
are filing a comment on a particular

[[Page 17171]]

project, please select Comment on a Filing; or
    (3) You can file a paper copy of your comments by mailing them to 
the following address: Kimberly D. Bose, Secretary, Federal Energy 
Regulatory Commission, 888 First Street NE, Room 1A, Washington, DC 
20426.
    Any person seeking to become a party to the proceeding must file a 
motion to intervene pursuant to Rule 214 of the Commission's Rules of 
Practice and Procedures (18 CFR 385.214).\1\ Only intervenors have the 
right to seek rehearing of the Commission's decision. The Commission 
grants affected landowners and others with environmental concerns 
intervenor status upon showing good cause by stating that they have a 
clear and direct interest in this proceeding which no other party can 
adequately represent. Simply filing environmental comments will not 
give you intervenor status, but you do not need intervenor status to 
have your comments considered.
---------------------------------------------------------------------------

    \1\ See the previous discussion on the methods for filing 
comments.
---------------------------------------------------------------------------

    Additional information about the project is available from the 
Commission's Office of External Affairs, at (866) 208-FERC, or on the 
FERC website (www.ferc.gov) using the eLibrary link. Click on the 
eLibrary link, click on General Search, and enter the docket number 
excluding the last three digits in the Docket Number field (i.e., CP18-
12). Be sure you have selected an appropriate date range. For 
assistance, please contact FERC Online Support at 
[email protected] or toll free at (866) 208-3676, or for TTY, 
contact (202) 502-8659. The eLibrary link also provides access to the 
texts of formal documents issued by the Commission, such as orders, 
notices, and rulemakings.
    In addition, the Commission offers a free service called 
eSubscription which allows you to keep track of all formal issuances 
and submittals in specific dockets. This can reduce the amount of time 
you spend researching proceedings by automatically providing you with 
notification of these filings, document summaries, and direct links to 
the documents. Go to www.ferc.gov/docs-filing/esubscription.asp.

    Dated: April 12, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-08072 Filed 4-17-18; 8:45 am]
 BILLING CODE 6717-01-P



                                             17170                                 Federal Register / Vol. 83, No. 75 / Wednesday, April 18, 2018 / Notices

                                             reproduction at the Rowe Town Library,                                  related to this or other pending projects.                              requests that were filed in comments on
                                             located at 318 Zoar Road, Rowe, MA                                      For assistance, contact FERC Online                                     the draft license application. At this
                                             01367; or the North Adams Public                                        Support.                                                                time, the application is expected to be
                                             Library, located at 74 Church Street,                                      n. Procedural Schedule: Pursuant to                                  processed according to the following
                                             North Adams, MA 01247.                                                  section 5.19(d) of the Commission’s                                     preliminary Hydro Licensing Schedule.
                                               m. You may also register online at                                    regulations, the Director, Office of                                    Revisions to the schedule may be made
                                             http://www.ferc.gov/docs-filing/                                        Energy Projects will issue an order                                     following the Director’s determination
                                             esubscription.asp to be notified via                                    within 30 days of the filing date of the                                on the study requests, or as otherwise
                                             email of new filings and issuances                                      final license application to resolve study                              appropriate.

                                                                                                                                  Milestone                                                                                                Target date

                                             Notice of Acceptance/Notice of Ready for Environmental Analysis ................................................................................................                            October 2018.
                                             Filing of recommendations, preliminary terms and conditions, and fishway prescriptions ..............................................................                                       December 2018.
                                             Commission issues Draft Environmental Assessment (EA) ............................................................................................................                          June 2019.
                                             Comments on Draft EA ....................................................................................................................................................................   August 2019.
                                             Modified terms and conditions ..........................................................................................................................................................    October 2019.
                                             Commission issues Final EA ............................................................................................................................................................     January 2020.



                                               o. Final amendments to the                                            significantly affecting the quality of the                              copies of the EA are available for
                                             application must be filed with the                                      human environment.                                                      distribution and public inspection at:
                                             Commission no later than 30 days from                                      Natural proposes to abandon:                                         Federal Energy Regulatory Commission,
                                             the issuance date of the notice of ready                                   • In place 19 injection/withdrawal                                   Public Reference Room, 888 First Street
                                             for environmental analysis.                                             wells by permanently plugging and                                       NE, Room 2A, Washington, DC 20426,
                                               Dated: April 12, 2018.                                                capping;                                                                (202) 502–8371.
                                             Nathaniel J. Davis, Sr.,
                                                                                                                        • in place 16.15 miles of 4- to 16-                                     Any person wishing to comment on
                                                                                                                     inch-diameter associated pipeline                                       the EA may do so. Your comments
                                             Deputy Secretary.
                                                                                                                     laterals in the storage field by capping;                               should focus on the potential
                                             [FR Doc. 2018–08073 Filed 4–17–18; 8:45 am]
                                                                                                                        • in place 13 non-jurisdictional                                     environmental effects, reasonable
                                             BILLING CODE 6717–01–P
                                                                                                                     observation wells by plugging;                                          alternatives, and measures to avoid or
                                                                                                                        • in place one non-jurisdictional salt                               lessen environmental impacts. The more
                                                                                                                     water disposal well by plugging;                                        specific your comments, the more useful
                                             DEPARTMENT OF ENERGY
                                                                                                                        • in place approximately 15.3 Bcf of                                 they will be. To ensure that the
                                             Federal Energy Regulatory                                               non-recoverable cushion gas;                                            Commission has the opportunity to
                                             Commission                                                                 • by removal the 330-horsepower                                      consider your comments prior to
                                                                                                                     Compressor Station 202 including its                                    making its decision on this project, it is
                                             [Docket No. CP18–12–000]                                                building, compressor unit, concrete                                     important that we receive your
                                                                                                                     piers, and concrete foundation; and                                     comments in Washington, DC on or
                                             Notice of Availability of the                                              • by removal all aboveground and
                                             Environmental Assessment for the                                                                                                                before May 14, 2018.
                                                                                                                     belowground storage field auxiliary                                        For your convenience, there are three
                                             Proposed Natural Gas Pipeline
                                                                                                                     surface facilities, including, but not                                  methods you can use to file your
                                             Company of America, LLC Herscher
                                                                                                                     limited to: Well head piping, slug                                      comments to the Commission. In all
                                             Northwest Storage Field Abandonment
                                                                                                                     catchers, water gathering system, and                                   instances, please reference the project
                                             Project
                                                                                                                     methanol distribution systems                                           docket number (CP18–12–000) with
                                                The staff of the Federal Energy                                      associated with the abandoned wells;                                    your submission. The Commission
                                             Regulatory Commission (FERC or                                          seven tap valves; a pigging facility; and                               encourages electronic filing of
                                             Commission) has prepared an                                             two corrosion monitors along with their                                 comments and has expert staff available
                                             environmental assessment (EA) for the                                   associated rectifiers and ground beds.                                  to assist you at (202) 502–8258 or
                                             Herscher Northwest Storage Field                                           Natural also proposes to convert the                                 FercOnlineSupport@ferc.gov.
                                             Abandonment Project, proposed by                                        P. Cook No. 1 injection/withdrawal well                                    (1) You can file your comments
                                             Natural Gas Pipeline Company of                                         to an observational well for its nearby                                 electronically using the eComment
                                             America LLC (Natural) in the above-                                     Herscher Mount Simon Storage Field;                                     feature on the Commission’s website
                                             referenced docket. Natural requests                                     and retain the P. Cook No. G–1 well as                                  (www.ferc.gov) under the link to
                                             authorization to abandon the Herscher                                   an observation well for its nearby                                      Documents and Filings. This is an easy
                                             Northwest Storage Field facilities with                                 Herscher Galesville Storage Field.                                      method for submitting brief, text-only
                                             its certificated maximum inventory of                                      The FERC staff mailed copies of the                                  comments on a project;
                                             18.5 billion cubic feet (Bcf) located in                                EA to federal, state, and local                                            (2) You can also file your comments
                                             Kankakee County, Illinois.                                              government representatives and                                          electronically using the eFiling feature
                                                The EA assesses the potential                                        agencies; elected officials;                                            on the Commission’s website
                                             environmental effects of the                                            environmental and public interest                                       (www.ferc.gov) under the link to
                                             abandonment of the Herscher Northwest                                   groups; Native American tribes;                                         Documents and Filings. With eFiling,
amozie on DSK30RV082PROD with NOTICES




                                             Storage Field Abandonment Project in                                    potentially affected landowners and                                     you can provide comments in a variety
                                             accordance with the requirements of the                                 other interested individuals and groups;                                of formats by attaching them as a file
                                             National Environmental Policy Act                                       and newspapers and libraries in the                                     with your submission. New eFiling
                                             (NEPA). The FERC staff concludes that                                   project area. In addition, the EA is                                    users must first create an account by
                                             approval of the proposed project, with                                  available for public viewing on the                                     clicking on eRegister. You must select
                                             appropriate mitigating measures, would                                  FERC’s website (www.ferc.gov) using the                                 the type of filing you are making. If you
                                             not constitute a major federal action                                   eLibrary link. A limited number of                                      are filing a comment on a particular


                                        VerDate Sep<11>2014        17:31 Apr 17, 2018       Jkt 244001      PO 00000       Frm 00033       Fmt 4703      Sfmt 4703      E:\FR\FM\18APN1.SGM            18APN1


                                                                          Federal Register / Vol. 83, No. 75 / Wednesday, April 18, 2018 / Notices                                           17171

                                             project, please select Comment on a                     DEPARTMENT OF ENERGY                                  DEPARTMENT OF ENERGY
                                             Filing; or
                                                                                                     Federal Energy Regulatory                             Federal Energy Regulatory
                                                (3) You can file a paper copy of your
                                                                                                     Commission                                            Commission
                                             comments by mailing them to the
                                             following address: Kimberly D. Bose,                                                                          [Docket No. IC18–7–000]
                                             Secretary, Federal Energy Regulatory                    [Docket No. AD18–5–000]
                                             Commission, 888 First Street NE, Room                                                                         Commission Information Collection
                                             1A, Washington, DC 20426.                               Notice Requesting Questions and                       Activities (FERC–725L); Comment
                                                                                                     Comments on Fiscal Year 2017 Other                    Request
                                                Any person seeking to become a party                 Federal Agency Cost Submissions;
                                             to the proceeding must file a motion to                 Review of Cost Submittals by Other                    AGENCY:  Federal Energy Regulatory
                                             intervene pursuant to Rule 214 of the                   Federal Agencies for Administering                    Commission, DOE.
                                             Commission’s Rules of Practice and                      Part I of the Federal Power Act                       ACTION: Comment request.
                                             Procedures (18 CFR 385.214).1 Only
                                             intervenors have the right to seek                         In its Order On Rehearing                          SUMMARY:    In compliance with the
                                             rehearing of the Commission’s decision.                 Consolidating Administrative Annual                   requirements of the Paperwork
                                             The Commission grants affected                          Charges Bill Appeals And Modifying                    Reduction Act of 1995, the Federal
                                             landowners and others with                              Annual Charges Billing Procedures, 109                Energy Regulatory Commission
                                             environmental concerns intervenor                       FERC 61,040 (2004) (October 8 Order)                  (Commission or FERC) is submitting the
                                                                                                     the Commission set forth an annual                    FERC–725L (Mandatory Reliability
                                             status upon showing good cause by
                                                                                                     process for Other Federal Agencies                    Standards for the Bulk-Power System:
                                             stating that they have a clear and direct
                                                                                                     (OFAs) to submit their costs related to               MOD Reliability Standards) to the Office
                                             interest in this proceeding which no                                                                          of Management and Budget (OMB) for
                                             other party can adequately represent.                   Administering Part I of the Federal
                                                                                                     Power Act. Pursuant to the established                review of the information collection
                                             Simply filing environmental comments                                                                          requirements. Any interested person
                                             will not give you intervenor status, but                process the Chief of Revenue and
                                                                                                     Receivables, Financial Management                     may file comments directly with OMB
                                             you do not need intervenor status to                                                                          and should address a copy of those
                                             have your comments considered.                          Division, Office of the Executive
                                                                                                     Director, on October 5, 2017, issued a                comments to the Commission as
                                                Additional information about the                     letter requesting the OFAs to submit                  explained below. The Commission
                                             project is available from the                           their costs by December 31, 2017 using                previously issued a Notice in the
                                             Commission’s Office of External Affairs,                the OFA Cost Submission Form.                         Federal Register requesting public
                                             at (866) 208–FERC, or on the FERC                                                                             comments. The Commission received no
                                                                                                        Upon receipt of the agency                         comments on the FERC–725L and is
                                             website (www.ferc.gov) using the
                                                                                                     submissions, the Commission posted                    making this notation in its submittal to
                                             eLibrary link. Click on the eLibrary link,              the information in eLibrary, and issued,
                                             click on General Search, and enter the                                                                        OMB.
                                                                                                     on March 7, 2018, a notice announcing
                                             docket number excluding the last three                                                                        DATES: Comments on the collection of
                                                                                                     the date for a technical conference to
                                             digits in the Docket Number field (i.e.,                                                                      information are due by May 18, 2018.
                                                                                                     review the submitted costs. On March
                                             CP18–12). Be sure you have selected an                  27, 2018 the Commission held the                      ADDRESSES: Comments filed with OMB,
                                             appropriate date range. For assistance,                 technical conference. Technical                       identified by the OMB Control No.
                                             please contact FERC Online Support at                   conference transcripts, submitted cost                1902–0261, should be sent via email to
                                             FercOnlineSupport@ferc.gov or toll free                 forms, and detailed supporting                        the Office of Information and Regulatory
                                             at (866) 208–3676, or for TTY, contact                  documents are all available for review                Affairs: oira_submission@omb.gov.
                                             (202) 502–8659. The eLibrary link also                  under Docket No. AD18–5. These                        Attention: Federal Energy Regulatory
                                             provides access to the texts of formal                  documents are accessible on-line at                   Commission Desk Officer. The Desk
                                             documents issued by the Commission,                     http://www.ferc.gov, using the eLibrary               Officer may also be reached via
                                             such as orders, notices, and                            link and are available for review in the              telephone at 202–395–8528.
                                             rulemakings.                                            Commission’s Public Reference Room in                    A copy of the comments should also
                                                                                                     Washington, DC.                                       be sent to the Commission, in Docket
                                                In addition, the Commission offers a                                                                       No. IC18–7–000, by either of the
                                             free service called eSubscription which                    Interested parties may file specific               following methods:
                                             allows you to keep track of all formal                  questions and comments on the FY 2017                    • eFiling at Commission’s website:
                                             issuances and submittals in specific                    OFA cost submissions with the                         http://www.ferc.gov/docs-filing/
                                             dockets. This can reduce the amount of                  Commission under Docket No. AD18–5,                   efiling.asp.
                                             time you spend researching proceedings                  no later than April 26, 2018. Once filed,                • Mail/Hand Delivery/Courier:
                                             by automatically providing you with                     the Commission will forward the                       Federal Energy Regulatory Commission,
                                             notification of these filings, document                 questions and comments to the OFAs                    Secretary of the Commission, 888 First
                                             summaries, and direct links to the                      for response.                                         Street NE, Washington, DC 20426.
                                             documents. Go to www.ferc.gov/docs-                        Anyone with questions pertaining to                   Instructions: All submissions must be
                                             filing/esubscription.asp.                               the technical conference or this notice               formatted and filed in accordance with
                                                                                                     should contact Raven A. Rodriguez at                  submission guidelines at: http://
                                               Dated: April 12, 2018.
                                                                                                     (202) 502–6276 (via email at                          www.ferc.gov/help/submission-
                                             Nathaniel J. Davis, Sr.,
amozie on DSK30RV082PROD with NOTICES




                                                                                                     raven.rodriguez@ferc.gov).                            guide.asp. For user assistance contact
                                             Deputy Secretary.                                                                                             FERC Online Support by email at
                                                                                                       Dated: April 12, 2018. .
                                             [FR Doc. 2018–08072 Filed 4–17–18; 8:45 am]                                                                   ferconlinesupport@ferc.gov, or by phone
                                                                                                     Nathaniel J. Davis, Sr.,
                                             BILLING CODE 6717–01–P                                                                                        at: (866) 208–3676 (toll-free), or (202)
                                                                                                     Deputy Secretary.                                     502–8659 for TTY.
                                                1 See the previous discussion on the methods for     [FR Doc. 2018–08074 Filed 4–17–18; 8:45 am]              Docket: Users interested in receiving
                                             filing comments.                                        BILLING CODE 6717–01–P                                automatic notification of activity in this


                                        VerDate Sep<11>2014   17:31 Apr 17, 2018   Jkt 244001   PO 00000   Frm 00034   Fmt 4703   Sfmt 4703   E:\FR\FM\18APN1.SGM   18APN1



Document Created: 2018-04-18 02:58:29
Document Modified: 2018-04-18 02:58:29
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 17170 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR