Federal Register, Volume 83 Issue 75 (Wednesday, April 18, 2018)
[Federal Register Volume 83, Number 75 (Wednesday, April 18, 2018)]
[Notices]
[Page 17174]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-08078]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 14870-000]


Notice of Preliminary Permit Application Accepted for Filing and 
Soliciting Comments, Motions To Intervene, and Competing Applications; 
Flat Canyon Hydro, LLC

    On March 7, 2018, the Flat Canyon Hydro, LLC, filed an application 
for a preliminary permit, pursuant to section 4(f) of the Federal Power 
Act (FPA), proposing to study the feasibility of the Flat Canyon Pumped 
Storage Project (Flat Canyon Project or project) to be located in Flat 
Canyon, near the City of Elsinore, Sevier County, Utah. The sole 
purpose of a preliminary permit, if issued, is to grant the permit 
holder priority to file a license application during the permit term. A 
preliminary permit does not authorize the permit holder to perform any 
land-disturbing activities or otherwise enter upon lands or waters 
owned by others without the owners' express permission.
    The proposed project would be a closed-loop pumped storage 
hydropower facility that consists of the following: (1) A 37-acre upper 
reservoir having a total storage capacity of 1,800 acre-feet at a 
normal maximum operating elevation of 6,930 feet mean sea level (msl); 
(2) a 55-foot-high, 550-foot-long zoned earth/rockfill or concrete-
faced upper reservoir dam; (3) a 55-foot-high, 525-foot-long zoned 
earth/rockfill or concrete-faced second upper reservoir dam; (4) a 
1,350-foot-long, 15-foot-diameter low-pressure headrace tunnel either 
unlined or lined concrete-lined; (5) a 6,850-foot-long, 15-foot-
diameter high-pressure headrace tunnel lined with either concrete or 
steel; (6) a 220-foot-long, 60-foot-wide, 120-foot-high powerhouse 
housed in an underground cavern and accessed via a 2,600-foot-long, 18-
foot-diameter access tunnel, housing two variable-speed reversible 
pump/turbine-motor/generator units rated for 150 megawatts each at 
1,370 feet maximum gross head; (7) a 2,400-foot-long, 17.5-foot-
diameter tailrace tunnel lined with concrete; (8) a 37-acre lower 
reservoir having a total storage capacity 1,800 acre-feet at a normal 
maximum operating elevation of 5,630 feet msl; (9) a 75-foot-high, 850-
foot-long zoned earth/rockfill or concrete-faced lower reservoir dam; 
(10) a 13-mile-long, 230-kilovolt (kV) transmission line extending from 
the powerhouse that would follow an existing transmission corridor to 
the Sigurd Substation owned by Rocky Mountain Power, or, if possible, a 
direct connection to Rocky Mountain Power's Sigurd-Red Butte No. 2 345-
kV line adjacent to the project (the point of interconnection); and 
(11) appurtenant facilities. The estimated annual generation of the 
Flat Canyon Project would be 525.6 gigawatt-hours.
    Applicant Contact: Matthew Shapiro, CEO, Gridflex Energy, LLC, 1210 
W Franklin St, Ste. 2, Boise, Idaho 83702; phone: (208) 246-9925.
    FERC Contact: Kyle Olcott; phone: (202) 502-8963.
    Deadline for filing comments, motions to intervene, competing 
applications (without notices of intent), or notices of intent to file 
competing applications: 60 days from the issuance of this notice. 
Competing applications and notices of intent must meet the requirements 
of 18 CFR 4.36.
    The Commission strongly encourages electronic filing. Please file 
comments, motions to intervene, notices of intent, and competing 
applications using the Commission's eFiling system at http://www.ferc.gov/docs-filing/efiling.asp. Commenters can submit brief 
comments up to 6,000 characters, without prior registration, using the 
eComment system at http://www.ferc.gov/docs-filing/ecomment.asp. You 
must include your name and contact information at the end of your 
comments. For assistance, please contact FERC Online Support at 
[email protected], (866) 208-3676 (toll free), or (202) 502-
8659 (TTY). In lieu of electronic filing, please send a paper copy to: 
Secretary, Federal Energy Regulatory Commission, 888 First Street NE, 
Washington, DC 20426. The first page of any filing should include 
docket number P-14870-000.
    More information about this project, including a copy of the 
application, can be viewed or printed on the eLibrary link of 
Commission's website at http://www.ferc.gov/docs-filing/elibrary.asp. 
Enter the docket number (P-14870) in the docket number field to access 
the document. For assistance, contact FERC Online Support.

    Dated: April 12, 2018. .
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-08078 Filed 4-17-18; 8:45 am]
 BILLING CODE 6717-01-P



                                             17174                        Federal Register / Vol. 83, No. 75 / Wednesday, April 18, 2018 / Notices

                                             Commission in determining the                           priority to file a license application                   The Commission strongly encourages
                                             appropriate action to be taken, but will                during the permit term. A preliminary                 electronic filing. Please file comments,
                                             not serve to make protestants parties to                permit does not authorize the permit                  motions to intervene, notices of intent,
                                             the proceeding. Any person wishing to                   holder to perform any land-disturbing                 and competing applications using the
                                             become a party must file a notice of                    activities or otherwise enter upon lands              Commission’s eFiling system at http://
                                             intervention or motion to intervene, as                 or waters owned by others without the                 www.ferc.gov/docs-filing/efiling.asp.
                                             appropriate. Such notices, motions, or                  owners’ express permission.                           Commenters can submit brief comments
                                             protests must be filed on or before the                    The proposed project would be a                    up to 6,000 characters, without prior
                                             comment date. On or before the                          closed-loop pumped storage                            registration, using the eComment system
                                             comment date, it is not necessary to                    hydropower facility that consists of the              at http://www.ferc.gov/docs-filing/
                                             serve motions to intervene or protests                  following: (1) A 37-acre upper reservoir              ecomment.asp. You must include your
                                             on persons other than the Applicant.                    having a total storage capacity of 1,800              name and contact information at the end
                                                The Commission encourages                            acre-feet at a normal maximum                         of your comments. For assistance,
                                             electronic submission of protests and                   operating elevation of 6,930 feet mean                please contact FERC Online Support at
                                             interventions in lieu of paper using the                sea level (msl); (2) a 55-foot-high, 550-             FERCOnlineSupport@ferc.gov, (866)
                                             ‘‘eFiling’’ link at http://www.ferc.gov.                foot-long zoned earth/rockfill or                     208–3676 (toll free), or (202) 502–8659
                                             Persons unable to file electronically                   concrete-faced upper reservoir dam; (3)               (TTY). In lieu of electronic filing, please
                                             should submit an original and 5 copies                  a 55-foot-high, 525-foot-long zoned                   send a paper copy to: Secretary, Federal
                                             of the protest or intervention to the                   earth/rockfill or concrete-faced second               Energy Regulatory Commission, 888
                                             Federal Energy Regulatory Commission,                   upper reservoir dam; (4) a 1,350-foot-                First Street NE, Washington, DC 20426.
                                             888 First Street NE, Washington, DC                     long, 15-foot-diameter low-pressure                   The first page of any filing should
                                             20426.                                                  headrace tunnel either unlined or lined               include docket number P–14870–000.
                                                This filing is accessible on-line at                 concrete-lined; (5) a 6,850-foot-long, 15-               More information about this project,
                                             http://www.ferc.gov, using the                          foot-diameter high-pressure headrace                  including a copy of the application, can
                                             ‘‘eLibrary’’ link and is available for                  tunnel lined with either concrete or                  be viewed or printed on the eLibrary
                                             review in the Commission’s Public                       steel; (6) a 220-foot-long, 60-foot-wide,             link of Commission’s website at http://
                                             Reference Room in Washington, DC.                       120-foot-high powerhouse housed in an                 www.ferc.gov/docs-filing/elibrary.asp.
                                             There is an ‘‘eSubscription’’ link on the               underground cavern and accessed via a                 Enter the docket number (P–14870) in
                                             website that enables subscribers to                     2,600-foot-long, 18-foot-diameter access              the docket number field to access the
                                             receive email notification when a                       tunnel, housing two variable-speed                    document. For assistance, contact FERC
                                             document is added to a subscribed                       reversible pump/turbine-motor/                        Online Support.
                                             docket(s). For assistance with any FERC                 generator units rated for 150 megawatts                 Dated: April 12, 2018. .
                                             Online service, please email                            each at 1,370 feet maximum gross head;                Nathaniel J. Davis, Sr.,
                                             FERCOnlineSupport@ferc.gov, or call                     (7) a 2,400-foot-long, 17.5-foot-diameter             Deputy Secretary.
                                             (866) 208–3676 (toll free). For TTY, call               tailrace tunnel lined with concrete; (8)              [FR Doc. 2018–08078 Filed 4–17–18; 8:45 am]
                                             (202) 502–8659.                                         a 37-acre lower reservoir having a total              BILLING CODE 6717–01–P
                                                Comment Date: 5:00 p.m. Eastern                      storage capacity 1,800 acre-feet at a
                                             Time on May 1, 2018.                                    normal maximum operating elevation of
                                               Dated: April 11, 2018.                                5,630 feet msl; (9) a 75-foot-high, 850-              DEPARTMENT OF ENERGY
                                             Kimberly D. Bose,                                       foot-long zoned earth/rockfill or
                                                                                                     concrete-faced lower reservoir dam; (10)              Federal Energy Regulatory
                                             Secretary.
                                                                                                     a 13-mile-long, 230-kilovolt (kV)                     Commission
                                             [FR Doc. 2018–08058 Filed 4–17–18; 8:45 am]
                                                                                                     transmission line extending from the                  [Project No. 7987–014]
                                             BILLING CODE 6717–01–P
                                                                                                     powerhouse that would follow an
                                                                                                     existing transmission corridor to the                 Notice of Transfer of Exemption;
                                                                                                     Sigurd Substation owned by Rocky                      Hydrodyne Industries, LLC, UP
                                             DEPARTMENT OF ENERGY
                                                                                                     Mountain Power, or, if possible, a direct             Property 2, LLC
                                             Federal Energy Regulatory                               connection to Rocky Mountain Power’s
                                                                                                     Sigurd-Red Butte No. 2 345-kV line                      1. By letter filed March 8, 2018,
                                             Commission                                                                                                    Charles T. Hagan, III, Manager,
                                                                                                     adjacent to the project (the point of
                                             [Project No. 14870–000]                                 interconnection); and (11) appurtenant                Hydrodyne Industries, LLC, exemptee
                                                                                                     facilities. The estimated annual                      informed the Commission that the
                                             Notice of Preliminary Permit                            generation of the Flat Canyon Project                 exemption from licensing for the High
                                             Application Accepted for Filing and                     would be 525.6 gigawatt-hours.                        Falls Hydroelectric Project No. 7987,
                                             Soliciting Comments, Motions To                                                                               originally issued September 12, 1984 1
                                                                                                        Applicant Contact: Matthew Shapiro,
                                             Intervene, and Competing                                                                                      has been transferred to UP Property 2,
                                                                                                     CEO, Gridflex Energy, LLC, 1210 W
                                             Applications; Flat Canyon Hydro, LLC                                                                          LLC. The project is located on the Deep
                                                                                                     Franklin St, Ste. 2, Boise, Idaho 83702;
                                                                                                     phone: (208) 246–9925.                                River in Moore County, North Carolina.
                                                On March 7, 2018, the Flat Canyon
                                                                                                        FERC Contact: Kyle Olcott; phone:                  The transfer of an exemption does not
                                             Hydro, LLC, filed an application for a
                                                                                                     (202) 502–8963.                                       require Commission approval.
                                             preliminary permit, pursuant to section                                                                         2. UP Property 2, LLC is now the
                                             4(f) of the Federal Power Act (FPA),                       Deadline for filing comments, motions
                                                                                                                                                           exemptee of the High Falls
amozie on DSK30RV082PROD with NOTICES




                                             proposing to study the feasibility of the               to intervene, competing applications
                                                                                                                                                           Hydroelectric Project No. 7987. All
                                             Flat Canyon Pumped Storage Project                      (without notices of intent), or notices of
                                                                                                                                                           correspondence should be forwarded to:
                                             (Flat Canyon Project or project) to be                  intent to file competing applications: 60
                                                                                                                                                           Mr. Aaron Aho, Land and Resource
                                             located in Flat Canyon, near the City of                days from the issuance of this notice.
                                             Elsinore, Sevier County, Utah. The sole                 Competing applications and notices of                   1 Order Granting Exemption From Licensing of a
                                             purpose of a preliminary permit, if                     intent must meet the requirements of 18               Small Hydroelectric Project of 5 Megawatts or Less.
                                             issued, is to grant the permit holder                   CFR 4.36.                                             Cook Industries, Inc., 28 FERC 62,352 (1984).



                                        VerDate Sep<11>2014   17:31 Apr 17, 2018   Jkt 244001   PO 00000   Frm 00037   Fmt 4703   Sfmt 4703   E:\FR\FM\18APN1.SGM   18APN1



Document Created: 2018-04-18 02:59:13
Document Modified: 2018-04-18 02:59:13
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 17174 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR