83_FR_18169 83 FR 18089 - Mitigation Strategies for Beyond-Design-Basis External Events

83 FR 18089 - Mitigation Strategies for Beyond-Design-Basis External Events

NUCLEAR REGULATORY COMMISSION

Federal Register Volume 83, Issue 80 (April 25, 2018)

Page Range18089-18090
FR Document2018-08601

The U.S. Nuclear Regulatory Commission (NRC) is issuing the final Revision 2 to Japan Lessons-Learned Division Interim Staff Guidance (JLD-ISG), JLD-ISG-2012-01, ``Compliance with Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.'' This ISG provides guidance and clarification to assist nuclear power reactor licensees with the identification of measures needed to comply with requirements to mitigate challenges to key safety functions. These requirements are contained in Order EA-12-049, ``Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events.''

Federal Register, Volume 83 Issue 80 (Wednesday, April 25, 2018)
[Federal Register Volume 83, Number 80 (Wednesday, April 25, 2018)]
[Notices]
[Pages 18089-18090]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-08601]


=======================================================================
-----------------------------------------------------------------------

NUCLEAR REGULATORY COMMISSION

[NRC-2012-0068]


Mitigation Strategies for Beyond-Design-Basis External Events

AGENCY: Nuclear Regulatory Commission.

ACTION: Interim staff guidance; issuance.

-----------------------------------------------------------------------

SUMMARY: The U.S. Nuclear Regulatory Commission (NRC) is issuing the 
final Revision 2 to Japan Lessons-Learned Division Interim Staff 
Guidance (JLD-ISG), JLD-ISG-2012-01, ``Compliance with Order EA-12-049, 
Order Modifying Licenses with Regard to Requirements for Mitigation 
Strategies for Beyond-Design-Basis External Events.'' This ISG provides 
guidance and clarification to assist nuclear power reactor licensees 
with the identification of measures needed to comply with requirements 
to mitigate challenges to key safety functions. These requirements are 
contained in Order EA-12-049, ``Order Modifying Licenses with Regard to 
Requirements for Mitigation Strategies for Beyond-Design-Basis External 
Events.''

DATES: This guidance is effective on April 25, 2018.

ADDRESSES: Please refer to Docket ID NRC-2012-0068 when contacting the 
NRC about the availability of information regarding this document. You 
may obtain publicly-available information related to this document 
using any of the following methods:
     Federal Rulemaking Website: Go to http://www.regulations.gov and search for Docket ID NRC-2012-0068. Address 
questions about NRC dockets to Jennifer Borges; telephone: 301-287-
9127; email: [email protected]. For technical questions, contact 
the individual listed in the FOR FURTHER INFORMATION CONTACT section of 
this document.
     NRC's Agencywide Documents Access and Management System 
(ADAMS): You may obtain publicly-available documents online in the 
ADAMS Public Documents collection at http://www.nrc.gov/reading-rm/adams.html. To begin the search, select ``ADAMS Public Documents'' and 
then select ``Begin Web-based ADAMS Search.'' For problems with ADAMS, 
please contact the NRC's Public Document Room (PDR) reference staff at 
1-800-397-4209, 301-415-4737, or by email to [email protected]. The 
ADAMS accession number for each document referenced (if it is available 
in ADAMS) is provided the first time that it is mentioned in this 
document. Revision 2 to JLD-ISG-2012-01 is available in ADAMS under 
Accession No. ML17005A188.
     NRC's PDR: You may examine and purchase copies of public 
documents at the NRC's PDR, Room O1-F21, One White Flint North, 11555 
Rockville Pike, Rockville, Maryland 20852.
     NRC's Interim Staff Guidance Website: http://www.nrc.gov/reading-rm/doc-collections/isg/japan-lessons-learned.html.

FOR FURTHER INFORMATION CONTACT: Eric Bowman, Office of Nuclear Reactor 
Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555-
0001; telephone: 301-415-2963, email: [email protected].

SUPPLEMENTARY INFORMATION:

I. Background Information

    The original Final Japan Lessons-Learned Project Directorate 
Interim Staff Guidance, JLD-ISG-2012-01 (ADAMS Accession No. 
ML12229A174) dated August 29, 2012, was issued to describe to the 
public methods acceptable to the NRC for complying with Order EA-12-049 
issued March 12, 2012 (ADAMS Package Accession No. ML12054A736). This 
ISG endorsed the methodologies described in the industry guidance 
document, Nuclear Energy Institute (NEI) 12-06, ``Diverse and Flexible 
Coping Strategies (FLEX) Implementation Guide,'' Revision 0, (ADAMS 
Accession No. ML12242A378), submitted on August 21, 2012. Revision 1 to 
JLD-ISG-2012-01 (ADAMS Accession No. ML15357A163) was issued on January 
22, 2016, and endorsed NEI 12-06, Revision 2 (ADAMS Accession No. 
ML16005A625), issued in December 2015. The NRC staff is now issuing 
Revision 2 to JLD-ISG-2012-01, which incorporates additional guidance 
related to reevaluated seismic hazard information and some additional 
changes based on lessons learned in the implementation of Order EA-12-
049. This revision endorses NEI 12-06, Revision 4 (ADAMS Accession No. 
ML16354B421), issued in December 2016.
    The NRC issued Order EA-12-049 following evaluation of the Japan 
earthquake and tsunami and resulting nuclear accident at the Fukushima 
Dai-

[[Page 18090]]

ichi Nuclear Power Plant in March 2011. Order EA-12-049 requires all 
licensees and construction permit holders to develop a three-phase 
approach for mitigating beyond-design-basis external events. The 
initial phase requires the use of installed equipment and resources to 
maintain or restore core cooling, containment, and spent fuel pool 
cooling. The transition phase requires providing sufficient, portable, 
onsite equipment and consumables to maintain or restore these functions 
until they can be accomplished with resources brought from off site. 
The final phase requires obtaining sufficient offsite resources to 
sustain those functions indefinitely. Order EA-12-049 also specified 
that the NRC would issue final interim staff guidance in August 2012, 
to provide additional details on an acceptable approach for complying 
with Order EA-12-049.
    The original version of this ISG, which endorsed the original NEI 
12-06, was issued on August 29, 2012. Revision 1 to JLD-ISG-2012-01 
incorporated acceptable alternative approaches to compliance proposed 
by licensees, as well as the NRC's review strategy described in 
COMSECY-14-0037, ``Integration of Mitigating Strategies for Beyond-
Design Basis External Events and the Reevaluation of Flooding Hazards'' 
(ADAMS Accession No. ML14238A616), which clarified the NRC's position 
on the interdependency of the mitigating strategies responses and the 
responses to the seismic and flooding reevaluations. The NRC has 
further revised this ISG in Revision 2 in order to include additional 
guidance regarding reevaluated seismic hazard information and changes 
based on lessons learned related to mitigating strategies 
implementation. This revised guidance will be publicly available and 
used by members of the industry to help develop their responses to 
Order EA-12-049, including impacts of the reevaluated seismic and 
flooding information, and by the NRC in its reviews of licensee 
strategies. On November 10, 2016 (81 FR 79056), the NRC requested 
public comments on draft Revision 2 to JLD-ISG-2012-01. The NRC 
received comments from seven stakeholders, which were considered in the 
development of the final Revision 2 to JLD-ISG-2012-01. The questions, 
comments, and NRC resolutions of those comments are contained in ``NRC 
Responses to Public Comments: Revision 2 to JLD-ISG-2012-01, Compliance 
with Order EA-12-049, `Order Modifying Licenses with Regard to 
Requirements for Mitigation Strategies for Beyond-Design-Basis External 
Events''' (ADAMS Accession No. ML17005A187).

II. Congressional Review Act

    This ISG revision is a rule as defined in the Congressional Review 
Act (5 U.S.C. 801-808). However, the Office of Management and Budget 
has not found it to be a major rule as defined in the Congressional 
Review Act.

III. Backfitting and Issue Finality

    This ISG provides guidance on an acceptable method for implementing 
the requirements contained in Order EA-12-049. Licensees may 
voluntarily use the guidance in Revision 2 to JLD-ISG-2012-01 to 
demonstrate compliance with Order EA-12-049. Methods or solutions that 
differ from those described in this ISG may be deemed acceptable if 
they provide sufficient basis and information for the NRC to verify 
that the proposed alternative demonstrates compliance with Order EA-12-
049.
    Issuance of this ISG does not constitute backfitting as defined in 
section 50.109 of title 10 of the Code of Federal Regulations (10 CFR), 
``Backfitting'' (the Backfit Rule), and is not otherwise inconsistent 
with the issue finality provisions in 10 CFR part 52, ``Licenses, 
Certifications, and Approvals for Nuclear Power Plants.''

    Dated at Rockville, Maryland, this 19th day of April, 2018.

    For the Nuclear Regulatory Commission.
Anita L. Lund,
Director, Division of Licensing Projects, Office of Nuclear Reactor 
Regulation.
[FR Doc. 2018-08601 Filed 4-24-18; 8:45 am]
 BILLING CODE 7590-01-P



                                                                             Federal Register / Vol. 83, No. 80 / Wednesday, April 25, 2018 / Notices                                           18089

                                                information or for a copy of this ICR and                 Comments submitted in response to                   select ‘‘Begin Web-based ADAMS
                                                applicable supporting documentation.                    this notice will become a matter of                   Search.’’ For problems with ADAMS,
                                                                                                        public record.                                        please contact the NRC’s Public
                                                SUPPLEMENTARY INFORMATION:       NEH first
                                                                                                                                                              Document Room (PDR) reference staff at
                                                published notice of its intent to seek                  Jon Parrish Peede,
                                                                                                                                                              1–800–397–4209, 301–415–4737, or by
                                                OMB approval for this ICR in the                        Senior Deputy Chairman.                               email to pdr.resource@nrc.gov. The
                                                Federal Register of February 14, 2018                   [FR Doc. 2018–08541 Filed 4–24–18; 8:45 am]           ADAMS accession number for each
                                                (83 FR 6615). This ICR requests OMB                     BILLING CODE 7536–01–P                                document referenced (if it is available in
                                                approval for a three-year extension of                                                                        ADAMS) is provided the first time that
                                                NEH’s currently approved generic                                                                              it is mentioned in this document.
                                                clearance authority for all NEH                         NUCLEAR REGULATORY                                    Revision 2 to JLD–ISG–2012–01 is
                                                information collections other than one-                 COMMISSION                                            available in ADAMS under Accession
                                                time evaluations, questionnaires, and                                                                         No. ML17005A188.
                                                                                                        [NRC–2012–0068]
                                                surveys. Generic clearance authority                                                                             • NRC’s PDR: You may examine and
                                                would cover forms and instructions for                                                                        purchase copies of public documents at
                                                                                                        Mitigation Strategies for Beyond-
                                                applications to NEH grant programs;                                                                           the NRC’s PDR, Room O1–F21, One
                                                                                                        Design-Basis External Events
                                                and reporting forms for NEH grantees,                                                                         White Flint North, 11555 Rockville
                                                panelists, and reviewers, and for                       AGENCY:  Nuclear Regulatory                           Pike, Rockville, Maryland 20852.
                                                program evaluation purposes. OMB is                     Commission.                                              • NRC’s Interim Staff Guidance
                                                particularly interested in comments                     ACTION: Interim staff guidance; issuance.             Website: http://www.nrc.gov/reading-
                                                about this ICR which help the agency to:                                                                      rm/doc-collections/isg/japan-lessons-
                                                (1) Evaluate whether the proposed                       SUMMARY:   The U.S. Nuclear Regulatory                learned.html.
                                                collection of information is necessary                  Commission (NRC) is issuing the final
                                                                                                                                                              FOR FURTHER INFORMATION CONTACT:   Eric
                                                for the proper performance of the                       Revision 2 to Japan Lessons-Learned
                                                                                                                                                              Bowman, Office of Nuclear Reactor
                                                functions of the agency, including                      Division Interim Staff Guidance (JLD–
                                                                                                                                                              Regulation, U.S. Nuclear Regulatory
                                                whether the information will have                       ISG), JLD–ISG–2012–01, ‘‘Compliance
                                                                                                                                                              Commission, Washington, DC 20555–
                                                practical utility; (2) evaluate the                     with Order EA–12–049, Order
                                                                                                                                                              0001; telephone: 301–415–2963, email:
                                                accuracy of the agency’s estimate of the                Modifying Licenses with Regard to
                                                                                                                                                              Eric.Bowman@nrc.gov.
                                                burden of the proposed collection of                    Requirements for Mitigation Strategies
                                                                                                                                                              SUPPLEMENTARY INFORMATION:
                                                information, including the validity of                  for Beyond-Design-Basis External
                                                the methodology and assumptions used;                   Events.’’ This ISG provides guidance                  I. Background Information
                                                (3) enhance the quality, utility, and                   and clarification to assist nuclear power
                                                                                                                                                                 The original Final Japan Lessons-
                                                clarity of the information to be                        reactor licensees with the identification
                                                                                                                                                              Learned Project Directorate Interim Staff
                                                collected; and (4) minimize the burden                  of measures needed to comply with
                                                                                                                                                              Guidance, JLD–ISG–2012–01 (ADAMS
                                                of the collection of information on those               requirements to mitigate challenges to
                                                                                                                                                              Accession No. ML12229A174) dated
                                                who are to respond, including through                   key safety functions. These
                                                                                                                                                              August 29, 2012, was issued to describe
                                                the use of appropriate information                      requirements are contained in Order
                                                                                                                                                              to the public methods acceptable to the
                                                technology (e.g., permitting electronic                 EA–12–049, ‘‘Order Modifying Licenses
                                                                                                                                                              NRC for complying with Order EA–12–
                                                submission of responses).                               with Regard to Requirements for
                                                                                                                                                              049 issued March 12, 2012 (ADAMS
                                                                                                        Mitigation Strategies for Beyond-Design-
                                                  This Notice also lists the following                                                                        Package Accession No. ML12054A736).
                                                                                                        Basis External Events.’’
                                                information:                                                                                                  This ISG endorsed the methodologies
                                                                                                        DATES: This guidance is effective on                  described in the industry guidance
                                                  Agency: National Endowment for the                    April 25, 2018.                                       document, Nuclear Energy Institute
                                                Humanities.                                             ADDRESSES: Please refer to Docket ID                  (NEI) 12–06, ‘‘Diverse and Flexible
                                                  Title of Proposal: Generic Clearance                  NRC–2012–0068 when contacting the                     Coping Strategies (FLEX)
                                                Authority for the National Endowment                    NRC about the availability of                         Implementation Guide,’’ Revision 0,
                                                for the Humanities.                                     information regarding this document.                  (ADAMS Accession No. ML12242A378),
                                                  Type of Review: Extension of a                        You may obtain publicly-available                     submitted on August 21, 2012. Revision
                                                currently approved collection.                          information related to this document                  1 to JLD–ISG–2012–01 (ADAMS
                                                                                                        using any of the following methods:                   Accession No. ML15357A163) was
                                                  OMB Number: 3136–0134.                                   • Federal Rulemaking Website: Go to                issued on January 22, 2016, and
                                                  Affected Public: Applicants to NEH                    http://www.regulations.gov and search                 endorsed NEI 12–06, Revision 2
                                                grant programs, reviewers of NEH grant                  for Docket ID NRC–2012–0068. Address                  (ADAMS Accession No. ML16005A625),
                                                applications, and NEH award recipients.                 questions about NRC dockets to Jennifer               issued in December 2015. The NRC staff
                                                  Total Respondents: 7,815.                             Borges; telephone: 301–287–9127;                      is now issuing Revision 2 to JLD–ISG–
                                                                                                        email: Jennifer.Borges@nrc.gov. For                   2012–01, which incorporates additional
                                                  Frequency of Collection: On occasion.                 technical questions, contact the                      guidance related to reevaluated seismic
                                                  Average Time per Response: Varies                     individual listed in the FOR FURTHER                  hazard information and some additional
                                                according to type of information                        INFORMATION CONTACT section of this                   changes based on lessons learned in the
                                                collection.                                             document.                                             implementation of Order EA–12–049.
                                                                                                           • NRC’s Agencywide Documents
sradovich on DSK3GMQ082PROD with NOTICES




                                                  Estimated Total Burden Hours: 88,885                                                                        This revision endorses NEI 12–06,
                                                hours.                                                  Access and Management System                          Revision 4 (ADAMS Accession No.
                                                                                                        (ADAMS): You may obtain publicly-                     ML16354B421), issued in December
                                                  Total Annualized Capital/Startup                      available documents online in the                     2016.
                                                Costs: 0.                                               ADAMS Public Documents collection at                     The NRC issued Order EA–12–049
                                                  Total Annual Costs (operating/                        http://www.nrc.gov/reading-rm/                        following evaluation of the Japan
                                                maintaining systems or purchasing                       adams.html. To begin the search, select               earthquake and tsunami and resulting
                                                services): 0.                                           ‘‘ADAMS Public Documents’’ and then                   nuclear accident at the Fukushima Dai-


                                           VerDate Sep<11>2014   19:12 Apr 24, 2018   Jkt 244001   PO 00000   Frm 00097   Fmt 4703   Sfmt 4703   E:\FR\FM\25APN1.SGM   25APN1


                                                18090                        Federal Register / Vol. 83, No. 80 / Wednesday, April 25, 2018 / Notices

                                                ichi Nuclear Power Plant in March                       External Events’’’ (ADAMS Accession                   general form is necessary to
                                                2011. Order EA–12–049 requires all                      No. ML17005A187).                                     accommodate the unique timing
                                                licensees and construction permit                                                                             provisions of a combined license (COL).
                                                                                                        II. Congressional Review Act
                                                holders to develop a three-phase                                                                              DATES: On April 5, 2018, the
                                                approach for mitigating beyond-design-                     This ISG revision is a rule as defined             Commission authorized the Director of
                                                basis external events. The initial phase                in the Congressional Review Act (5                    the Office of New Reactors to issue
                                                requires the use of installed equipment                 U.S.C. 801–808). However, the Office of               COLs to FPL to construct and operate
                                                and resources to maintain or restore                    Management and Budget has not found                   Turkey Point Units 6 and 7. The
                                                core cooling, containment, and spent                    it to be a major rule as defined in the               modified indemnity agreement would
                                                fuel pool cooling. The transition phase                 Congressional Review Act.                             be effective upon issuance of the COLs.
                                                requires providing sufficient, portable,                III. Backfitting and Issue Finality                   ADDRESSES: Please refer to Docket ID
                                                onsite equipment and consumables to                                                                           NRC–2009–0337 when contacting the
                                                maintain or restore these functions until                  This ISG provides guidance on an
                                                                                                        acceptable method for implementing the                NRC about the availability of
                                                they can be accomplished with                                                                                 information regarding this document.
                                                resources brought from off site. The                    requirements contained in Order EA–
                                                                                                        12–049. Licensees may voluntarily use                 You may obtain publicly-available
                                                final phase requires obtaining sufficient                                                                     information related to this document
                                                offsite resources to sustain those                      the guidance in Revision 2 to JLD–ISG–
                                                                                                        2012–01 to demonstrate compliance                     using any of the following methods:
                                                functions indefinitely. Order EA–12–                                                                             • Federal Rulemaking website: Go to
                                                049 also specified that the NRC would                   with Order EA–12–049. Methods or
                                                                                                                                                              http://www.regulations.gov and search
                                                issue final interim staff guidance in                   solutions that differ from those
                                                                                                                                                              for Docket ID NRC–2009–0337. Address
                                                August 2012, to provide additional                      described in this ISG may be deemed
                                                                                                                                                              questions about NRC dockets to Jennifer
                                                details on an acceptable approach for                   acceptable if they provide sufficient
                                                                                                                                                              Borges; telephone: 301–287–9127;
                                                complying with Order EA–12–049.                         basis and information for the NRC to
                                                                                                                                                              email: Jennifer.Borges@nrc.gov. For
                                                                                                        verify that the proposed alternative
                                                   The original version of this ISG,                                                                          technical questions, contact the
                                                                                                        demonstrates compliance with Order
                                                which endorsed the original NEI 12–06,                                                                        individual listed in the FOR FURTHER
                                                                                                        EA–12–049.
                                                was issued on August 29, 2012.                                                                                INFORMATION CONTACT section of this
                                                                                                           Issuance of this ISG does not
                                                Revision 1 to JLD–ISG–2012–01                           constitute backfitting as defined in                  document.
                                                incorporated acceptable alternative                                                                              • NRC’s Agencywide Documents
                                                                                                        section 50.109 of title 10 of the Code of
                                                approaches to compliance proposed by                                                                          Access and Management System
                                                                                                        Federal Regulations (10 CFR),
                                                licensees, as well as the NRC’s review                                                                        (ADAMS): You may obtain publicly-
                                                                                                        ‘‘Backfitting’’ (the Backfit Rule), and is
                                                strategy described in COMSECY–14–                                                                             available documents online in the
                                                                                                        not otherwise inconsistent with the
                                                0037, ‘‘Integration of Mitigating                                                                             ADAMS Public Documents collection at
                                                                                                        issue finality provisions in 10 CFR part
                                                Strategies for Beyond-Design Basis                                                                            http://www.nrc.gov/reading-rm/
                                                                                                        52, ‘‘Licenses, Certifications, and
                                                External Events and the Reevaluation of                                                                       adams.html. To begin the search, select
                                                                                                        Approvals for Nuclear Power Plants.’’
                                                Flooding Hazards’’ (ADAMS Accession                                                                           ‘‘ADAMS Public Documents’’ and then
                                                No. ML14238A616), which clarified the                      Dated at Rockville, Maryland, this 19th day        select ‘‘Begin Web-based ADAMS
                                                                                                        of April, 2018.                                       Search.’’ For problems with ADAMS,
                                                NRC’s position on the interdependency
                                                                                                           For the Nuclear Regulatory Commission.             please contact the NRC’s Public
                                                of the mitigating strategies responses
                                                and the responses to the seismic and                    Anita L. Lund,                                        Document Room (PDR) reference staff at
                                                flooding reevaluations. The NRC has                     Director, Division of Licensing Projects, Office      1–800–397–4209, 301–415–4737, or by
                                                further revised this ISG in Revision 2 in               of Nuclear Reactor Regulation.                        email to pdr.resource@nrc.gov.
                                                order to include additional guidance                    [FR Doc. 2018–08601 Filed 4–24–18; 8:45 am]              • NRC’s PDR: You may examine and
                                                regarding reevaluated seismic hazard                    BILLING CODE 7590–01–P                                purchase copies of public documents at
                                                information and changes based on                                                                              the NRC’s PDR, Room O1–F21, One
                                                lessons learned related to mitigating                                                                         White Flint North, 11555 Rockville
                                                strategies implementation. This revised                 NUCLEAR REGULATORY                                    Pike, Rockville, Maryland 20852.
                                                guidance will be publicly available and                 COMMISSION                                            FOR FURTHER INFORMATION CONTACT:
                                                used by members of the industry to help                 [Docket Nos. 52–040 and 52–041; NRC–                  Manny Comar, Office of New Reactors,
                                                develop their responses to Order EA–                    2009–0337]                                            U.S. Nuclear Regulatory Commission,
                                                12–049, including impacts of the                                                                              Washington DC 20555–0001; telephone:
                                                reevaluated seismic and flooding                        Florida Power & Light Company;                        301–415–3863, email: Manny.Comar@
                                                information, and by the NRC in its                      Turkey Point Units 6 and 7                            nrc.gov.
                                                reviews of licensee strategies. On                      AGENCY: Nuclear Regulatory                            SUPPLEMENTARY INFORMATION:
                                                November 10, 2016 (81 FR 79056), the                    Commission
                                                NRC requested public comments on                                                                              I. Background
                                                                                                        ACTION: Notice of intent to enter into a
                                                draft Revision 2 to JLD–ISG–2012–01.                    modified indemnity agreement.                            On April 5, 2018, the Commission
                                                The NRC received comments from seven                                                                          authorized issuance of COLs to FPL for
                                                stakeholders, which were considered in                  SUMMARY:   The U.S. Nuclear Regulatory                Turkey Point Units 6 and 7. These COLs
                                                the development of the final Revision 2                 Commission (NRC) is issuing a notice of               would include a license pursuant to part
                                                to JLD–ISG–2012–01. The questions,                      intent to enter into a modified                       70 of title 10 of the Code of Federal
                                                comments, and NRC resolutions of those                  indemnity agreement with Florida                      Regulations (10 CFR), ‘‘Domestic
sradovich on DSK3GMQ082PROD with NOTICES




                                                comments are contained in ‘‘NRC                         Power & Light Company (FPL) to                        Licensing of Special Nuclear Material.’’
                                                Responses to Public Comments:                           operate Turkey Point Units 6 and 7. The               Pursuant to 10 CFR 140.20(a)(1)(iii), the
                                                Revision 2 to JLD–ISG–2012–01,                          NRC is publishing notice of its intent to             NRC will execute and issue agreements
                                                Compliance with Order EA–12–049,                        enter into an indemnity agreement                     of indemnity, effective on the date of a
                                                ‘Order Modifying Licenses with Regard                   which contains provisions different                   license under 10 CFR part 70,
                                                to Requirements for Mitigation                          from the general form found in the                    authorizing the licensee to possess and
                                                Strategies for Beyond-Design-Basis                      NRC’s regulations. A modification to the              store special nuclear material at the site


                                           VerDate Sep<11>2014   19:12 Apr 24, 2018   Jkt 244001   PO 00000   Frm 00098   Fmt 4703   Sfmt 4703   E:\FR\FM\25APN1.SGM   25APN1



Document Created: 2018-11-02 08:17:58
Document Modified: 2018-11-02 08:17:58
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
ActionInterim staff guidance; issuance.
DatesThis guidance is effective on April 25, 2018.
ContactEric Bowman, Office of Nuclear Reactor Regulation, U.S. Nuclear Regulatory Commission, Washington, DC 20555- 0001; telephone: 301-415-2963, email: [email protected]
FR Citation83 FR 18089 