83_FR_19832 83 FR 19745 - Distributed Energy Resources-Technical Considerations for the Bulk Power System; Notice Inviting Post-Technical Conference Comments

83 FR 19745 - Distributed Energy Resources-Technical Considerations for the Bulk Power System; Notice Inviting Post-Technical Conference Comments

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 87 (May 4, 2018)

Page Range19745-19746
FR Document2018-09450

Federal Register, Volume 83 Issue 87 (Friday, May 4, 2018)
[Federal Register Volume 83, Number 87 (Friday, May 4, 2018)]
[Notices]
[Pages 19745-19746]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-09450]



[[Page 19745]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. AD18-10-000]


Distributed Energy Resources--Technical Considerations for the 
Bulk Power System; Notice Inviting Post-Technical Conference Comments

    On April 10 and April 11, 2018, Federal Energy Regulatory 
Commission (Commission) staff convened a technical conference to 
discuss the participation of distributed energy resource (DER) 
aggregations in Regional Transmission Organization (RTO) and 
Independent System Operator (ISO) markets and to more broadly discuss 
the potential effects of DERs on the bulk power system.
    All interested persons are invited to file post-technical 
conference comments on the topics relating to the potential effects of 
DERs on the bulk power system as discussed during the technical 
conference, including the questions listed in the Supplemental Notices 
issued in this proceeding on March 29, 2018 and April 9, 2018. In 
addition, Commission staff is interested in comments on several follow-
up topics and questions. Commenters need not respond to all topics or 
questions asked. Attached to this notice are the topics and questions 
related to Panels 4 and 5 from the two previous notices, as well as 
Commission staff's follow-up questions related to those panels. Please 
file comments relating to these areas in Docket No. AD18-10-000.
    A notice inviting post-technical conference comments on the topics 
and questions concerning the Commission's DER aggregation proposal 
related to Panels 1, 2, 3, 6, and 7 is being concurrently issued in 
Docket No. RM18-9-000. Please separately file comments relating to 
Panels 1, 2, 3, 6, and 7 in Docket No. RM18-9-000.
    Commenters may reference material previously filed in this docket 
but are encouraged to avoid repetition or replication of previous 
material. In addition, commenters are encouraged, when possible, to 
provide examples in support of their answers. Comments must be 
submitted on or before 60 days from the date of this notice.
    For further information about this notice, please contact:

Technical Information

    Louise Nutter, Office of Electric Reliability, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 
502-8175, [email protected].
    Joe Baumann, Office of Electric Reliability, Federal Energy 
Regulatory Commission, 888 First Street NE, Washington, DC 20426, (202) 
502-8373, [email protected].

    Dated: April 27, 2018.
Kimberly D. Bose,
Secretary.

Post-Technical Conference Questions for Comment

AD18-10-000

Collection and Availability of Data on DER Installations (Panel 4)

    To plan and operate the bulk power system, it is important for 
transmission planners, transmission operators, and distribution 
utilities to collect and share validated data across the transmission-
distribution interface. In September 2017, the North American Electric 
Reliability Corporation (NERC) published a Reliability Guideline on DER 
modeling (Guideline) that specified the minimum DER information needed 
by transmission planners and planning coordinators to assist in 
modeling and conducting assessments.\1\ The Guideline references the 
importance of static data (such as the capacity, technical 
capabilities, and location of a DER installation) for the entities 
involved in the planning of the bulk power system. The following 
questions focus on understanding the need for bulk power system 
planners and operators to have access to accurate data to plan and 
operate the bulk power system, explore the types of data that are 
needed, and assess the current state of DER data collection. The 
following questions also address regional DER penetration levels and 
any potential effects of inaccurate long-term DER forecasting. The 
Commission Staff DER Technical Report,\2\ issued on February 15, 2018, 
provides a common foundation for the topics raised in this panel.
---------------------------------------------------------------------------

    \1\ See NERC Distributed Energy Resource Modeling Reliability 
Guideline, at 5 (Sept. 2017), available at http://www.nerc.com/comm/PC_Reliability_Guidelines_DL/Reliability_Guideline_-_DER_Modeling_Parameters_-_2017-08-18_-_FINAL.pdf.
    \2\ The report is available at https://www.ferc.gov/legal/staff-reports/2018/der-report.pdf.
---------------------------------------------------------------------------

    Comments are requested on the following topics and questions that 
were included in previous supplemental notices:
    1. What type of information do bulk power system planners and 
operators need regarding DER installations within their footprint to 
plan and operate the bulk power system? Would it be sufficient for 
distribution utilities to provide aggregate information about the 
penetration of DERs below certain points on the transmission-
distribution interface? If greater granularity is needed, what level of 
detail would be sufficient? Is validation of the submitted data 
possible using data available?
    2. What, if any, data on DER installations is currently collected, 
and by whom is it collected? Do procedures and appropriate agreements 
exist to share this data with affected bulk power system entities 
(i.e., those entities responsible for the reliable operation of the 
bulk power system or for modeling and planning for a reliable bulk 
power system)? Is there variation by entity or region?
    3. At various DER penetration levels, what planning and operations 
impacts do you observe? Do balancing authorities with significant 
growth in DERs experience the need to address bulk power system 
reliability and operational considerations at certain DER penetration 
levels? What are they? Is the MW level of DER penetration the most 
important factor in whether DERs cause planning and operational 
impacts, or do certain characteristics of installed DERs affect the 
system operator's analysis? Is there a threshold that could trigger a 
need for distribution utilities to share information on DERs with the 
bulk power system operator, such as the point at which DER penetration 
causes bulk power system reliability and operational impacts, or some 
other, lower, level of penetration? How could the answer to these 
questions vary on a regional basis, and what factors may contribute to 
this variance?
    4. How are long-term projections for DER penetrations developed? 
Are these projections currently included in related forecasting 
efforts? Do system operators study the potential effects of future DER 
growth to assess changing infrastructure and planning needs at 
different penetration levels?
    5. What are the effects on the bulk power system if long-term 
forecasts of DER growth are inaccurate? Are these effects within 
current planning horizons? Are changes in the expected growth of DERs 
incorporated into ongoing planning efforts? Can these uncertainties be 
treated similarly to other uncertainties in the planning process?
    6. How are DERs incorporated into production cost modeling studies? 
Do current tools allow for assessment of forecasting variations and 
their effects?
    7. Noting that participation in the RTO/ISO markets by DER 
aggregators may provide more information to the RTOs/ISOs about DERs 
than would otherwise be available, should any specific information 
about DER aggregations or the individual DERs in

[[Page 19746]]

them be required from aggregators to ensure proper planning and 
operation of the bulk power system?
    8. Do the RTOs/ISOs need any directly metered data about the 
operations of DER aggregations to ensure proper planning and operation 
of the bulk power system?
    Based on the discussion at the April 10-11 Technical Conference, 
comments are also requested on the following additional questions:
    9. What can DERs offer to support or enhance bulk power system 
reliability? How can these benefits be quantified? Are these 
opportunities unique to DERs?
    10. With the recently approved IEEE 1547-2018 Standard, what 
coordination or collaboration is needed to leverage the Standard's 
technical requirements (e.g., ride-through settings, communication 
capabilities) in a manner that supports bulk power system reliability?
    11. Is a formal development of a grid architecture that includes 
distribution and transmission systems necessary to facilitate planning 
efforts to incorporate DERs?
    12. What specific real-time DER data is needed to manage bulk power 
system reliability? Why is that data needed? Is there a specific 
penetration-level of DERs above which real-time data is needed? Without 
real-time DER data to ensure visibility of DER installations, what, if 
any, potential challenges and mitigating actions exist for RTOs/ISOs 
and transmission operators (e.g., the potential need to procure 
additional contingency reserves)? Please give examples.
    13. What challenges exist for DER developers and owners to provide 
DER real-time data? Please give examples.

Incorporating DERs in Modeling, Planning, and Operations Studies (Panel 
5)

    Bulk power system planners and operators must select methods to 
feasibly model DERs at the bulk power system level with sufficient 
granularity to ensure accurate results. The chosen methodology for 
grouping DERs at the bulk power system level could affect planners' 
ability to predict system behavior following events, or to identify a 
need for different operating procedures under changing system 
conditions. Further, the operation of DERs can affect both bulk power 
systems and distribution facilities in unintended ways, suggesting that 
new tools to model the transmission and distribution interface may be 
needed. Staff is also aware of ongoing work in this area, for example 
efforts at NERC, national labs, and other groups, to evaluate options 
for studies in these areas, which could also inform future work. The 
following questions focus on the incorporation of DERs into different 
types of planning and operational studies, including options for 
modeling DERs and the methodology for the inclusion of DERs in larger 
regional models. The Commission Staff DER Technical Report, issued on 
February 15, 2018, provides a common foundation for the topics raised 
in this panel.
    Comments are requested on the following topics and questions that 
were included in previous supplemental notices:
    1. What are current and best practices for modeling DERs in 
different types of planning, operations, and production cost studies? 
Are options available for modeling the interactions between the 
transmission and distribution systems?
    2. To what extent are capabilities and performance of DERs 
currently modeled? Do current modeling tools provide features needed to 
model these capabilities?
    3. What methods, such as net load, composite load models, detailed 
models or others, are currently used in power flow and dynamic models 
to represent groups of DERs at the bulk power system level? Would more 
detailed models of DERs at the bulk power system level provide better 
visibility and enable more accurate assessment of their impacts on 
system conditions? Does the appropriate method for grouping DERs vary 
by penetration level?
    4. Do current contingency studies include the outage of DER 
facilities, and if they are considered, how is the contingency size 
chosen? At what penetration levels or under what system conditions 
could including DER outages be beneficial? Are DERs accounted for in 
calculations for Under Frequency Load Shedding and related studies?
    5. What methods are used to calculate capacity needed for balancing 
supply and demand with large amount of solar DER (ramping and frequency 
control) and determining which resources can provide an appropriate 
response?
    Based on the discussion at the April 10-11 Technical Conference, 
comments are also requested on the following additional questions:
    6. For planning efforts, how are model parameters determined and 
incorporated into existing models using currently available data on DER 
capabilities? What types of validation techniques are used for the data 
in these models and how often are they applied?
    7. Given the discussion on interactions between distribution and 
transmission operators, are further requirements for distributed 
controls, interoperability and/or cybersecurity protections being 
evaluated? Would advanced techniques and methods to simulate real-time 
systems, distributed controls and demand response or additional risk-
based planning methods, forecasting techniques and data analytics 
provide a benefit in this area? Which of these methods would provide 
the most value to operators and why?

[FR Doc. 2018-09450 Filed 5-3-18; 8:45 am]
 BILLING CODE 6717-01-P



                                                                               Federal Register / Vol. 83, No. 87 / Friday, May 4, 2018 / Notices                                               19745

                                             DEPARTMENT OF ENERGY                                      Joe Baumann, Office of Electric                      points on the transmission-distribution
                                                                                                     Reliability, Federal Energy Regulatory                 interface? If greater granularity is
                                             Federal Energy Regulatory                               Commission, 888 First Street NE,                       needed, what level of detail would be
                                             Commission                                              Washington, DC 20426, (202) 502–8373,                  sufficient? Is validation of the submitted
                                             [Docket No. AD18–10–000]                                joseph.baumann@ferc.gov.                               data possible using data available?
                                                                                                       Dated: April 27, 2018.                                  2. What, if any, data on DER
                                             Distributed Energy Resources—                                                                                  installations is currently collected, and
                                                                                                     Kimberly D. Bose,
                                             Technical Considerations for the Bulk                                                                          by whom is it collected? Do procedures
                                                                                                     Secretary.
                                             Power System; Notice Inviting Post-                                                                            and appropriate agreements exist to
                                             Technical Conference Comments                           Post-Technical Conference Questions                    share this data with affected bulk power
                                                                                                     for Comment                                            system entities (i.e., those entities
                                                On April 10 and April 11, 2018,                                                                             responsible for the reliable operation of
                                             Federal Energy Regulatory Commission                    AD18–10–000
                                                                                                                                                            the bulk power system or for modeling
                                             (Commission) staff convened a technical                 Collection and Availability of Data on                 and planning for a reliable bulk power
                                             conference to discuss the participation                 DER Installations (Panel 4)                            system)? Is there variation by entity or
                                             of distributed energy resource (DER)                      To plan and operate the bulk power                   region?
                                             aggregations in Regional Transmission                   system, it is important for transmission                  3. At various DER penetration levels,
                                             Organization (RTO) and Independent                      planners, transmission operators, and                  what planning and operations impacts
                                             System Operator (ISO) markets and to                    distribution utilities to collect and share            do you observe? Do balancing
                                             more broadly discuss the potential                      validated data across the transmission-                authorities with significant growth in
                                             effects of DERs on the bulk power                       distribution interface. In September                   DERs experience the need to address
                                             system.                                                 2017, the North American Electric                      bulk power system reliability and
                                                All interested persons are invited to                Reliability Corporation (NERC)                         operational considerations at certain
                                             file post-technical conference comments                 published a Reliability Guideline on                   DER penetration levels? What are they?
                                             on the topics relating to the potential                 DER modeling (Guideline) that specified                Is the MW level of DER penetration the
                                             effects of DERs on the bulk power                       the minimum DER information needed                     most important factor in whether DERs
                                             system as discussed during the                          by transmission planners and planning                  cause planning and operational impacts,
                                             technical conference, including the                     coordinators to assist in modeling and                 or do certain characteristics of installed
                                             questions listed in the Supplemental                    conducting assessments.1 The Guideline                 DERs affect the system operator’s
                                             Notices issued in this proceeding on                    references the importance of static data               analysis? Is there a threshold that could
                                             March 29, 2018 and April 9, 2018. In                    (such as the capacity, technical                       trigger a need for distribution utilities to
                                             addition, Commission staff is interested                capabilities, and location of a DER                    share information on DERs with the
                                             in comments on several follow-up                        installation) for the entities involved in             bulk power system operator, such as the
                                             topics and questions. Commenters need                   the planning of the bulk power system.                 point at which DER penetration causes
                                             not respond to all topics or questions                  The following questions focus on                       bulk power system reliability and
                                             asked. Attached to this notice are the                  understanding the need for bulk power                  operational impacts, or some other,
                                             topics and questions related to Panels 4                system planners and operators to have                  lower, level of penetration? How could
                                             and 5 from the two previous notices, as                 access to accurate data to plan and                    the answer to these questions vary on a
                                             well as Commission staff’s follow-up                    operate the bulk power system, explore                 regional basis, and what factors may
                                             questions related to those panels. Please               the types of data that are needed, and                 contribute to this variance?
                                             file comments relating to these areas in                assess the current state of DER data                      4. How are long-term projections for
                                             Docket No. AD18–10–000.                                 collection. The following questions also               DER penetrations developed? Are these
                                                A notice inviting post-technical                     address regional DER penetration levels                projections currently included in related
                                             conference comments on the topics and                   and any potential effects of inaccurate                forecasting efforts? Do system operators
                                             questions concerning the Commission’s                   long-term DER forecasting. The                         study the potential effects of future DER
                                             DER aggregation proposal related to                     Commission Staff DER Technical                         growth to assess changing infrastructure
                                             Panels 1, 2, 3, 6, and 7 is being                       Report,2 issued on February 15, 2018,                  and planning needs at different
                                             concurrently issued in Docket No.                       provides a common foundation for the                   penetration levels?
                                             RM18–9–000. Please separately file                      topics raised in this panel.                              5. What are the effects on the bulk
                                             comments relating to Panels 1, 2, 3, 6,                   Comments are requested on the                        power system if long-term forecasts of
                                             and 7 in Docket No. RM18–9–000.                         following topics and questions that were               DER growth are inaccurate? Are these
                                                Commenters may reference material                    included in previous supplemental                      effects within current planning
                                             previously filed in this docket but are                 notices:                                               horizons? Are changes in the expected
                                             encouraged to avoid repetition or                         1. What type of information do bulk                  growth of DERs incorporated into
                                             replication of previous material. In                    power system planners and operators                    ongoing planning efforts? Can these
                                             addition, commenters are encouraged,                    need regarding DER installations within                uncertainties be treated similarly to
                                             when possible, to provide examples in                   their footprint to plan and operate the                other uncertainties in the planning
                                             support of their answers. Comments                      bulk power system? Would it be                         process?
                                             must be submitted on or before 60 days                  sufficient for distribution utilities to                  6. How are DERs incorporated into
                                             from the date of this notice.                           provide aggregate information about the                production cost modeling studies? Do
                                                For further information about this                   penetration of DERs below certain                      current tools allow for assessment of
                                             notice, please contact:                                                                                        forecasting variations and their effects?
amozie on DSK3GDR082PROD with NOTICES




                                                                                                       1 See NERC Distributed Energy Resource                  7. Noting that participation in the
                                             Technical Information                                   Modeling Reliability Guideline, at 5 (Sept. 2017),     RTO/ISO markets by DER aggregators
                                               Louise Nutter, Office of Electric                     available at http://www.nerc.com/comm/PC_              may provide more information to the
                                             Reliability, Federal Energy Regulatory                  Reliability_Guidelines_DL/Reliability_Guideline_-_     RTOs/ISOs about DERs than would
                                                                                                     DER_Modeling_Parameters_-_2017-08-18_-_
                                             Commission, 888 First Street NE,                        FINAL.pdf.                                             otherwise be available, should any
                                             Washington, DC 20426, (202) 502–8175,                     2 The report is available at https://www.ferc.gov/   specific information about DER
                                             louise.nutter@ferc.gov.                                 legal/staff-reports/2018/der-report.pdf.               aggregations or the individual DERs in


                                        VerDate Sep<11>2014   18:16 May 03, 2018   Jkt 244001   PO 00000   Frm 00066   Fmt 4703   Sfmt 4703   E:\FR\FM\04MYN1.SGM   04MYN1


                                             19746                             Federal Register / Vol. 83, No. 87 / Friday, May 4, 2018 / Notices

                                             them be required from aggregators to                    evaluate options for studies in these                 transmission operators, are further
                                             ensure proper planning and operation of                 areas, which could also inform future                 requirements for distributed controls,
                                             the bulk power system?                                  work. The following questions focus on                interoperability and/or cybersecurity
                                                8. Do the RTOs/ISOs need any                         the incorporation of DERs into different              protections being evaluated? Would
                                             directly metered data about the                         types of planning and operational                     advanced techniques and methods to
                                             operations of DER aggregations to                       studies, including options for modeling               simulate real-time systems, distributed
                                             ensure proper planning and operation of                 DERs and the methodology for the                      controls and demand response or
                                             the bulk power system?                                  inclusion of DERs in larger regional                  additional risk-based planning methods,
                                                Based on the discussion at the April                 models. The Commission Staff DER                      forecasting techniques and data
                                             10–11 Technical Conference, comments                    Technical Report, issued on February                  analytics provide a benefit in this area?
                                             are also requested on the following                     15, 2018, provides a common                           Which of these methods would provide
                                             additional questions:                                   foundation for the topics raised in this              the most value to operators and why?
                                                9. What can DERs offer to support or                 panel.                                                [FR Doc. 2018–09450 Filed 5–3–18; 8:45 am]
                                             enhance bulk power system reliability?                     Comments are requested on the
                                                                                                                                                           BILLING CODE 6717–01–P
                                             How can these benefits be quantified?                   following topics and questions that were
                                             Are these opportunities unique to DERs?                 included in previous supplemental
                                                10. With the recently approved IEEE                  notices:                                              DEPARTMENT OF ENERGY
                                             1547–2018 Standard, what coordination                      1. What are current and best practices
                                             or collaboration is needed to leverage                  for modeling DERs in different types of               Federal Energy Regulatory
                                             the Standard’s technical requirements                   planning, operations, and production                  Commission
                                             (e.g., ride-through settings,                           cost studies? Are options available for
                                             communication capabilities) in a                        modeling the interactions between the                 [Docket No. RM18–9–000]
                                             manner that supports bulk power                         transmission and distribution systems?
                                             system reliability?                                        2. To what extent are capabilities and             Participation of Distributed Energy
                                                11. Is a formal development of a grid                performance of DERs currently                         Resource Aggregations in Markets
                                             architecture that includes distribution                 modeled? Do current modeling tools                    Operated by Regional Transmission
                                             and transmission systems necessary to                   provide features needed to model these                Organizations and Independent
                                             facilitate planning efforts to incorporate              capabilities?                                         System Operators; Notice Inviting
                                             DERs?                                                      3. What methods, such as net load,                 Post-Technical Conference Comments
                                                12. What specific real-time DER data                 composite load models, detailed models
                                             is needed to manage bulk power system                   or others, are currently used in power                   On April 10 and April 11, 2018,
                                             reliability? Why is that data needed? Is                flow and dynamic models to represent                  Federal Energy Regulatory Commission
                                             there a specific penetration-level of                   groups of DERs at the bulk power                      (Commission) staff convened a technical
                                             DERs above which real-time data is                      system level? Would more detailed                     conference to discuss the participation
                                             needed? Without real-time DER data to                   models of DERs at the bulk power                      of distributed energy resource (DER)
                                             ensure visibility of DER installations,                 system level provide better visibility                aggregations in Regional Transmission
                                             what, if any, potential challenges and                  and enable more accurate assessment of                Organization (RTO) and Independent
                                             mitigating actions exist for RTOs/ISOs                  their impacts on system conditions?                   System Operator (ISO) markets and to
                                             and transmission operators (e.g., the                   Does the appropriate method for                       more broadly discuss the potential
                                             potential need to procure additional                    grouping DERs vary by penetration                     effects of DERs on the bulk power
                                             contingency reserves)? Please give                      level?                                                system.
                                             examples.                                                  4. Do current contingency studies                     All interested persons are invited to
                                                13. What challenges exist for DER                    include the outage of DER facilities, and             file post-technical conference comments
                                             developers and owners to provide DER                    if they are considered, how is the                    on the topics concerning the
                                             real-time data? Please give examples.                   contingency size chosen? At what                      Commission’s DER aggregation proposal
                                                                                                     penetration levels or under what system               discussed during the technical
                                             Incorporating DERs in Modeling,                                                                               conference, including the questions
                                             Planning, and Operations Studies                        conditions could including DER outages
                                                                                                     be beneficial? Are DERs accounted for                 listed in the Supplemental Notices
                                             (Panel 5)                                                                                                     issued in this proceeding on March 29,
                                                                                                     in calculations for Under Frequency
                                               Bulk power system planners and                        Load Shedding and related studies?                    2018 and April 9, 2018. In addition,
                                             operators must select methods to                           5. What methods are used to calculate              Commission staff is interested in
                                             feasibly model DERs at the bulk power                   capacity needed for balancing supply                  comments on several follow-up topics
                                             system level with sufficient granularity                and demand with large amount of solar                 and questions. Commenters need not
                                             to ensure accurate results. The chosen                  DER (ramping and frequency control)                   respond to all topics or questions asked.
                                             methodology for grouping DERs at the                    and determining which resources can                   Attached to this notice are the DER
                                             bulk power system level could affect                    provide an appropriate response?                      aggregation topics and questions related
                                             planners’ ability to predict system                        Based on the discussion at the April               to Panels 1, 2, 3, 6, and 7 from the two
                                             behavior following events, or to identify               10–11 Technical Conference, comments                  previous notices, as well as Commission
                                             a need for different operating                          are also requested on the following                   staff’s follow-up questions related to
                                             procedures under changing system                        additional questions:                                 those panels. Please file comments
                                             conditions. Further, the operation of                      6. For planning efforts, how are model             relating to these issues in Docket No.
                                             DERs can affect both bulk power                         parameters determined and                             RM18–9–000.
amozie on DSK3GDR082PROD with NOTICES




                                             systems and distribution facilities in                  incorporated into existing models using                  A notice inviting post-technical
                                             unintended ways, suggesting that new                    currently available data on DER                       conference comments on the topics and
                                             tools to model the transmission and                     capabilities? What types of validation                questions relating to the potential effects
                                             distribution interface may be needed.                   techniques are used for the data in these             of DERs on the bulk power system
                                             Staff is also aware of ongoing work in                  models and how often are they applied?                related to Panels 4 and 5 is being
                                             this area, for example efforts at NERC,                    7. Given the discussion on                         concurrently issued in Docket No.
                                             national labs, and other groups, to                     interactions between distribution and                 AD18–10–000. Please separately file


                                        VerDate Sep<11>2014   18:16 May 03, 2018   Jkt 244001   PO 00000   Frm 00067   Fmt 4703   Sfmt 4703   E:\FR\FM\04MYN1.SGM   04MYN1



Document Created: 2018-11-02 09:52:01
Document Modified: 2018-11-02 09:52:01
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 19745 

2025 Federal Register | Disclaimer | Privacy Policy
USC | CFR | eCFR