DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 87 (May 4, 2018)

Page Range19750-19750
FR Document2018-09452

Federal Register, Volume 83 Issue 87 (Friday, May 4, 2018)
[Federal Register Volume 83, Number 87 (Friday, May 4, 2018)]
[Notices]
[Page 19750]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-09452]


-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Docket No. EL18-138-000]


Midcontinent Independent System Operator, Inc., ALLETE, Inc., 
Montana-Dakota Utilities Co., Northern Indiana Public Service Company, 
Otter Tail Power Company, Southern Indiana Gas & Electric Company; 
Notice of Institution of Section 206 Proceeding and Refund Effective 
Date

    On April 27, 2018, the Commission issued an order in Docket No. 
EL18-138-000 pursuant to section 206 of the Federal Power Act (FPA), 16 
U.S.C. 824e (2012), instituting an investigation into whether the 
transmission formula rate templates of ALLETE, Inc., Montana-Dakota 
Utilities Co., Northern Indiana Public Service Company, Otter Tail 
Power Company, and Southern Indiana Gas & Electric Company under 
Attachment O of the Midcontinent Independent System Operator, Inc. Open 
Access Transmission, Energy and Operating Reserve Markets Tariff may be 
unjust, unreasonable, or unduly discriminatory or preferential. 
Midcontinent Independent System Operator, Inc., et al., 163 FERC 61, 
061 (2018).
    The refund effective date in Docket Nos. EL18-138-000, established 
pursuant to section 206(b) of the FPA, will be the date of publication 
of this notice in the Federal Register.
    Any interested person desiring to be heard in Docket Nos. EL18-138-
000 must file a notice of intervention or motion to intervene, as 
appropriate, with the Federal Energy Regulatory Commission, 888 First 
Street, NE, Washington, DC 20426, in accordance with Rule 214 of the 
Commission's Rules of Practice and Procedure, 18 CFR 385.214 (2017), 
within 21 days of the date of issuance of the order.

    Dated: April 27, 2018.
Kimberly D. Bose,
Secretary.
[FR Doc. 2018-09452 Filed 5-3-18; 8:45 am]
 BILLING CODE 6717-01-P



                                             19750                              Federal Register / Vol. 83, No. 87 / Friday, May 4, 2018 / Notices

                                             system with high DER penetration                          in real time? Are new systems or                      (DMS) for efficient operational
                                             where those resources do not participate                  approaches needed? Does DER                           coordination?
                                             in the RTO/ISO markets? Would these                       aggregation require separate or                       [FR Doc. 2018–09455 Filed 5–3–18; 8:45 am]
                                             measures also help manage the safety                      additional capabilities and                           BILLING CODE 6717–01–P
                                             and reliability of a distribution system                  infrastructure for communication and
                                             where these resources do participate in                   control?
                                             the RTO/ISO markets? Would additional                        2. What processes/protocols do                     DEPARTMENT OF ENERGY
                                             safety and reliability measures be                        distribution utilities, transmission
                                             necessary if DERs participate in the                                                                            Federal Energy Regulatory
                                                                                                       operators, and DERs or DER aggregators
                                             RTO/ISO markets, or would the current                                                                           Commission
                                                                                                       use to coordinate with each other? Are
                                             safeguards against backflows, islanding,
                                                                                                       these processes/protocols capable of                  [Docket No. EL18–138–000]
                                             or other concerns adequately ensure
                                                                                                       providing needed real-time
                                             safety and reliability? If additional
                                                                                                       communications and coordination?                      Midcontinent Independent System
                                             measures are necessary, what are they?
                                                                                                       What new processes, resources, and                    Operator, Inc., ALLETE, Inc., Montana-
                                             Ongoing Operational Coordination                          efforts will be required to achieve                   Dakota Utilities Co., Northern Indiana
                                             (Panel 7)                                                 effective real-time coordination?                     Public Service Company, Otter Tail
                                                                                                         3. What are the minimum set of                      Power Company, Southern Indiana
                                                In the NOPR, the Commission
                                                                                                       specific RTO/ISO operational protocols,               Gas & Electric Company; Notice of
                                             acknowledged that ongoing
                                                                                                       performance standards, and market                     Institution of Section 206 Proceeding
                                             coordination between the RTO/ISO, a
                                                                                                       rules that should be adopted now to                   and Refund Effective Date
                                             DER aggregator, and the relevant
                                             distribution utility or utilities may be                  ensure operational coordination for DER                  On April 27, 2018, the Commission
                                             necessary to ensure that the DER                          aggregation participating in the RTO/                 issued an order in Docket No. EL18–
                                             aggregator is dispatching individual                      ISO markets? What additional protocols                138–000 pursuant to section 206 of the
                                             resources in a DER aggregation                            may be important for the future? Should               Federal Power Act (FPA), 16 U.S.C.
                                             consistent with the limitations of the                    the Commission adopt more                             824e (2012), instituting an investigation
                                             distribution system.9 The Commission                      prescriptive requirements with respect                into whether the transmission formula
                                             proposed that each RTO/ISO revise its                     to coordination than those proposed in                rate templates of ALLETE, Inc.,
                                             tariff to establish a process for ongoing                 the NOPR? If so, what should the                      Montana-Dakota Utilities Co., Northern
                                             coordination, including operational                       Commission require?                                   Indiana Public Service Company, Otter
                                             coordination, among itself, the DER                         4. Should distribution utilities be able            Tail Power Company, and Southern
                                             aggregator, and the distribution utility to               to override RTO/ISO decisions                         Indiana Gas & Electric Company under
                                             maximize the availability of the DER                      regarding day-ahead and real-time                     Attachment O of the Midcontinent
                                             aggregation consistent with the safe and                  dispatch of DER aggregations to resolve               Independent System Operator, Inc.
                                             reliable operation of the distribution                    local distribution reliability issues? If             Open Access Transmission, Energy and
                                             system. To help effectuate this proposal,                                                                       Operating Reserve Markets Tariff may
                                                                                                       so, should DER aggregations nonetheless
                                             the Commission also proposed to                                                                                 be unjust, unreasonable, or unduly
                                                                                                       be subject to non-deliverability
                                             require each RTO/ISO to revise its tariff                                                                       discriminatory or preferential.
                                                                                                       penalties under such circumstances?
                                             to require the DER aggregator to report                                                                         Midcontinent Independent System
                                             to the RTO/ISO any changes to its                           5. Is it possible for DERs or DER                   Operator, Inc., et al., 163 FERC 61, 061
                                             offered quantity and related distribution                 aggregations participating in the RTO/                (2018).
                                             factors that result from distribution line                ISO markets to also be used to improve                   The refund effective date in Docket
                                             faults or outages. The Commission also                    distribution system operations and                    Nos. EL18–138–000, established
                                             sought comment on the level of detail                     reliability? If so, please provide                    pursuant to section 206(b) of the FPA,
                                             necessary in the RTO/ISO tariffs to                       examples of how this could be                         will be the date of publication of this
                                             establish a framework for ongoing                         accomplished.                                         notice in the Federal Register.
                                             coordination between the RTO/ISO, a                         6. Can real-time dispatch of                           Any interested person desiring to be
                                             DER aggregator, and the relevant                          aggregated DERs address distribution                  heard in Docket Nos. EL18–138–000
                                             distribution utility or utilities.                        constraints? If not, can tools be                     must file a notice of intervention or
                                                Comments are requested on the                          developed to accomplish this?                         motion to intervene, as appropriate,
                                             following topics and questions that were                                                                        with the Federal Energy Regulatory
                                             included in previous supplemental                           7. Should individual DERs be
                                                                                                       required to have communications                       Commission, 888 First Street, NE,
                                             notices:                                                                                                        Washington, DC 20426, in accordance
                                                                                                       capabilities to comply with control
                                                1. What real-time data acquisition and                                                                       with Rule 214 of the Commission’s
                                                                                                       center obligations? What level of
                                             communication technologies are                                                                                  Rules of Practice and Procedure, 18 CFR
                                                                                                       communications security should be
                                             currently in use to provide bulk power                                                                          385.214 (2017), within 21 days of the
                                                                                                       employed for these communications?
                                             system operators with visibility into the                                                                       date of issuance of the order.
                                             distribution system? Are they adequate                      8. How might recent and expected
                                                                                                                                                               Dated: April 27, 2018.
                                             to convey the information necessary for                   technical advancements be used to
                                                                                                       enhance the coordination of DER                       Kimberly D. Bose,
                                             transmission and distribution operators
amozie on DSK3GDR082PROD with NOTICES




                                             to assess distribution system conditions                  aggregations, for example, integrating                Secretary.
                                                                                                       Energy Management Systems (EMS) and                   [FR Doc. 2018–09452 Filed 5–3–18; 8:45 am]
                                               9 NOPR,   FERC Stats. & Regs. ¶ 32,718 at P 155.        Distribution Management Systems                       BILLING CODE 6717–01–P




                                        VerDate Sep<11>2014    18:16 May 03, 2018   Jkt 244001    PO 00000   Frm 00071   Fmt 4703   Sfmt 4703   E:\FR\FM\04MYN1.SGM   04MYN1



Document Created: 2018-11-02 09:52:00
Document Modified: 2018-11-02 09:52:00
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106: