83_FR_22568 83 FR 22474 - FirstLight Hydro Generating Company; Notice of Authorization for Continued Project Operation

83 FR 22474 - FirstLight Hydro Generating Company; Notice of Authorization for Continued Project Operation

DEPARTMENT OF ENERGY
Federal Energy Regulatory Commission

Federal Register Volume 83, Issue 94 (May 15, 2018)

Page Range22474-22474
FR Document2018-10296

Federal Register, Volume 83 Issue 94 (Tuesday, May 15, 2018)
[Federal Register Volume 83, Number 94 (Tuesday, May 15, 2018)]
[Notices]
[Page 22474]
From the Federal Register Online  [www.thefederalregister.org]
[FR Doc No: 2018-10296]



[[Page 22474]]

-----------------------------------------------------------------------

DEPARTMENT OF ENERGY

Federal Energy Regulatory Commission

[Project No. 2485-000]


FirstLight Hydro Generating Company; Notice of Authorization for 
Continued Project Operation

    On April 29, 2016, FirstLight Hydro Generating Company, licensee 
for the Northfield Mountain Pumped Storage Project, filed an 
Application for a New License pursuant to the Federal Power Act (FPA) 
and the Commission's regulations thereunder. The Northfield Mountain 
Pumped Storage Project is located on the Connecticut River in Franklin 
County, Massachusetts; Windham County, Vermont; and Cheshire County, 
New Hampshire.
    The license for Project No. 2485 was issued for a period ending 
April 30, 2018. Section 15(a)(1) of the FPA, 16 U.S.C. 808(a)(1), 
requires the Commission, at the expiration of a license term, to issue 
from year-to-year an annual license to the then licensee under the 
terms and conditions of the prior license until a new license is 
issued, or the project is otherwise disposed of as provided in section 
15 or any other applicable section of the FPA. If the project's prior 
license waived the applicability of section 15 of the FPA, then, based 
on section 9(b) of the Administrative Procedure Act, 5 U.S.C. 558(c), 
and as set forth at 18 CFR 16.21(a), if the licensee of such project 
has filed an application for a subsequent license, the licensee may 
continue to operate the project in accordance with the terms and 
conditions of the license after the minor or minor part license 
expires, until the Commission acts on its application. If the licensee 
of such a project has not filed an application for a subsequent 
license, then it may be required, pursuant to 18 CFR 16.21(b), to 
continue project operations until the Commission issues someone else a 
license for the project or otherwise orders disposition of the project.
    If the project is subject to section 15 of the FPA, notice is 
hereby given that an annual license for Project No. 2485 is issued to 
the licensee for a period effective May 1, 2018 through April 30, 2019 
or until the issuance of a new license for the project or other 
disposition under the FPA, whichever comes first. If issuance of a new 
license (or other disposition) does not take place on or before April 
30, 2019, notice is hereby given that, pursuant to 18 CFR 16.18(c), an 
annual license under section 15(a)(1) of the FPA is renewed 
automatically without further order or notice by the Commission, unless 
the Commission orders otherwise.
    If the project is not subject to section 15 of the FPA, notice is 
hereby given that the licensee, FirstLight Hydro Generating Company, is 
authorized to continue operation of the Northfield Mountain Pumped 
Storage Project, until such time as the Commission acts on its 
application for a subsequent license.

    Dated: May 9, 2018.
Nathaniel J. Davis, Sr.,
Deputy Secretary.
[FR Doc. 2018-10296 Filed 5-14-18; 8:45 am]
 BILLING CODE 6717-01-P



                                               22474                          Federal Register / Vol. 83, No. 94 / Tuesday, May 15, 2018 / Notices

                                               DEPARTMENT OF ENERGY                                    notice by the Commission, unless the                  Commission issues someone else a
                                                                                                       Commission orders otherwise.                          license for the project or otherwise
                                               Federal Energy Regulatory                                 If the project is not subject to section            orders disposition of the project.
                                               Commission                                              15 of the FPA, notice is hereby given                    If the project is subject to section 15
                                               [Project No. 2485–000]                                  that the licensee, FirstLight Hydro                   of the FPA, notice is hereby given that
                                                                                                       Generating Company, is authorized to                  an annual license for Project No. 1889
                                               FirstLight Hydro Generating Company;                    continue operation of the Northfield                  is issued to the licensee for a period
                                               Notice of Authorization for Continued                   Mountain Pumped Storage Project, until                effective May 1, 2018 through April 30,
                                               Project Operation                                       such time as the Commission acts on its               2019 or until the issuance of a new
                                                                                                       application for a subsequent license.                 license for the project or other
                                                  On April 29, 2016, FirstLight Hydro                                                                        disposition under the FPA, whichever
                                               Generating Company, licensee for the                      Dated: May 9, 2018.
                                                                                                       Nathaniel J. Davis, Sr.,
                                                                                                                                                             comes first. If issuance of a new license
                                               Northfield Mountain Pumped Storage                                                                            (or other disposition) does not take
                                               Project, filed an Application for a New                 Deputy Secretary.
                                                                                                                                                             place on or before April 30, 2019, notice
                                               License pursuant to the Federal Power                   [FR Doc. 2018–10296 Filed 5–14–18; 8:45 am]
                                                                                                                                                             is hereby given that, pursuant to 18 CFR
                                               Act (FPA) and the Commission’s                          BILLING CODE 6717–01–P                                16.18(c), an annual license under
                                               regulations thereunder. The Northfield
                                                                                                                                                             section 15(a)(1) of the FPA is renewed
                                               Mountain Pumped Storage Project is
                                                                                                                                                             automatically without further order or
                                               located on the Connecticut River in                     DEPARTMENT OF ENERGY
                                                                                                                                                             notice by the Commission, unless the
                                               Franklin County, Massachusetts;
                                                                                                       Federal Energy Regulatory                             Commission orders otherwise.
                                               Windham County, Vermont; and
                                                                                                       Commission                                               If the project is not subject to section
                                               Cheshire County, New Hampshire.
                                                  The license for Project No. 2485 was                                                                       15 of the FPA, notice is hereby given
                                                                                                       [Project No. 1889–000]                                that the licensee, FirstLight Hydro
                                               issued for a period ending April 30,
                                               2018. Section 15(a)(1) of the FPA, 16                                                                         Generating Company, is authorized to
                                                                                                       FirstLight Hydro Generating Company;                  continue operation of the Turners Falls
                                               U.S.C. 808(a)(1), requires the                          Notice of Authorization for Continued
                                               Commission, at the expiration of a                                                                            Hydroelectric Project, until such time as
                                                                                                       Project Operation                                     the Commission acts on its application
                                               license term, to issue from year-to-year
                                               an annual license to the then licensee                     On April 29, 2016, FirstLight Hydro                for a subsequent license.
                                               under the terms and conditions of the                   Generating Company, licensee for the                    Dated: May 9, 2018.
                                               prior license until a new license is                    Turners Falls Hydroelectric Project,                  Nathaniel J. Davis, Sr.,
                                               issued, or the project is otherwise                     filed an Application for a New License                Deputy Secretary.
                                               disposed of as provided in section 15 or                pursuant to the Federal Power Act                     [FR Doc. 2018–10295 Filed 5–14–18; 8:45 am]
                                               any other applicable section of the FPA.                (FPA) and the Commission’s regulations
                                                                                                                                                             BILLING CODE 6717–01–P
                                               If the project’s prior license waived the               thereunder. The Turners Falls
                                               applicability of section 15 of the FPA,                 Hydroelectric Project is located on the
                                               then, based on section 9(b) of the                      Connecticut River in Franklin County,                 DEPARTMENT OF ENERGY
                                               Administrative Procedure Act, 5 U.S.C.                  Massachusetts; Windham County,
                                               558(c), and as set forth at 18 CFR                      Vermont; and Cheshire County, New                     Federal Energy Regulatory
                                               16.21(a), if the licensee of such project               Hampshire.                                            Commission
                                               has filed an application for a subsequent                  The license for Project No.1889 was
                                                                                                       issued for a period ending April 30,                  [Docket No. CP18–332–000]
                                               license, the licensee may continue to
                                               operate the project in accordance with                  2018. Section 15(a)(1) of the FPA, 16                 El Paso Natural Gas Company, L.L.C.;
                                               the terms and conditions of the license                 U.S.C. 808(a)(1), requires the                        Notice of Application
                                               after the minor or minor part license                   Commission, at the expiration of a
                                               expires, until the Commission acts on                   license term, to issue from year-to-year                 Take notice that on April 26, 2018, El
                                               its application. If the licensee of such a              an annual license to the then licensee                Paso Natural Gas Company, L.L.C.
                                               project has not filed an application for                under the terms and conditions of the                 (EPNG), PO Box 1087, Colorado Springs,
                                               a subsequent license, then it may be                    prior license until a new license is                  Colorado, 80944, filed in Docket No.
                                               required, pursuant to 18 CFR 16.21(b),                  issued, or the project is otherwise                   CP18–332–000 an application pursuant
                                               to continue project operations until the                disposed of as provided in section 15 or              to section 7(c) of the Natural Gas Act
                                               Commission issues someone else a                        any other applicable section of the FPA.              (NGA) and Part 157 of the Commission’s
                                               license for the project or otherwise                    If the project’s prior license waived the             regulations for authorization to
                                               orders disposition of the project.                      applicability of section 15 of the FPA,               construct, own, and operate the South
                                                  If the project is subject to section 15              then, based on section 9(b) of the                    Mainline Expansion Project comprising:
                                               of the FPA, notice is hereby given that                 Administrative Procedure Act, 5 U.S.C.                (i) About 17 miles of 30-inch-diameter
                                               an annual license for Project No. 2485                  558(c), and as set forth at 18 CFR                    loop line of EPNG’s existing Line Nos.
                                               is issued to the licensee for a period                  16.21(a), if the licensee of such project             1100 and 1103 located in Hudspeth and
                                               effective May 1, 2018 through April 30,                 has filed an application for a subsequent             El Paso Counties, Texas; (ii) a new
                                               2019 or until the issuance of a new                     license, the licensee may continue to                 13,220 horsepower (hp), turbine-driven
                                               license for the project or other                        operate the project in accordance with                Red Mountain Compressor Station
                                               disposition under the FPA, whichever                    the terms and conditions of the license               located in Luna County, New Mexico;
daltland on DSKBBV9HB2PROD with NOTICES




                                               comes first. If issuance of a new license               after the minor or minor part license                 and (iii) a new 13,220 hp turbine-driven
                                               (or other disposition) does not take                    expires, until the Commission acts on                 Dragoon Compressor Station located in
                                               place on or before April 30, 2019, notice               its application. If the licensee of such a            Cochise County, Arizona. EPNG states
                                               is hereby given that, pursuant to 18 CFR                project has not filed an application for              that the proposed facilities will result in
                                               16.18(c), an annual license under                       a subsequent license, then it may be                  an increase of 321,000 dekatherms per
                                               section 15(a)(1) of the FPA is renewed                  required, pursuant to 18 CFR 16.21(b),                day of contracted capacity and estimates
                                               automatically without further order or                  to continue project operations until the              the cost of the South Mainline


                                          VerDate Sep<11>2014   20:27 May 14, 2018   Jkt 244001   PO 00000   Frm 00034   Fmt 4703   Sfmt 4703   E:\FR\FM\15MYN1.SGM   15MYN1



Document Created: 2018-05-15 00:33:22
Document Modified: 2018-05-15 00:33:22
CategoryRegulatory Information
CollectionFederal Register
sudoc ClassAE 2.7:
GS 4.107:
AE 2.106:
PublisherOffice of the Federal Register, National Archives and Records Administration
SectionNotices
FR Citation83 FR 22474 

2024 Federal Register | Disclaimer | Privacy Policy